Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
File Note
Page 1 of 41
Traffic Survey Data Used for Reference A number of traffic surveys had been carried out in the Docklands by DCC, either as part of the Blood Stoney Bridge project, The Point Roundabout project, or periodical traffic counts. The following sets of data have been used to inform this traffic modelling exercise.
Location Date Type of Count Samuel Beckett Bridge
2017.12.07 Thursday
Junction Turning Counts + Pedestrian Crossing Counts Link Count
Samuel Beckett Bridge
2019.05.14 Tuesday
Junction Turning Counts + Pedestrian Crossing Counts Link Count
New Wapping Street
2017.12.07 Thursday
Pedestrian and cyclist OD counts at junctions.
Blood Stoney Bridge
2017.12.07 Thursday
Pedestrian and cyclist OD counts at junctions.
Tom Clarke Bridge
2012 Link traffic volumes (pcu) extracted from ARUP Technical Note for The Point Roundabout Improvement Scheme 2018.04.04.
Tom Clarke Bridge
2017.11.21-22 Tuesday, Wednesday
Link Count
East Link Bridge
2018.02.06 Tuesday
Junction Turning Counts + Pedestrian Crossing Counts
East Link Bridge
2018.04.10 Tuesday
Junction Turning Counts + Pedestrian Crossing Counts
East Link Bridge
2019.05.14 Tuesday
Junction Turning Counts + Pedestrian Crossing Counts Pedestrian and Cyclist Link Count
Table 1.1: Traffic Survey Data For reference, on Samuel Beckett Bridge, survey of December 2017 recorded 2,841 pedestrians and 823 cyclists, and survey of May 2019 recorded 3,427 pedestrians and 1,302 cyclists, in the AM peak hour. This is an increase of 20.6% in pedestrian volumes and 58.2% in cyclist volumes over 15 months. Summary of pedestrian and cyclist numbers recorded at Samuel Beckett Bridge and Tom Clarke Bridge during peak hours of Thursday 14th May 2019 is shown in Appendix D of this document.
Study Area The NTA’s Eastern Regional Model (ERM) was used in its entirety. The area of interest is the Docklands - specifically Liffey crossings, including and east of, Samuel Beckett Bridge. Figure 2-1 shows potential crossing locations at Forbes Street – Park Lane, Blood Stoney Road – New Wapping Street, and Castleforbes Road – Benson Street. The traffic modelling will compare the potential walking/ cycling demand along these crossings, in conjunction with new pedestrian/ cyclist infrastructure along the future Dodder Bridge and alongside Tom Clarke Bridge. The location of future Southern Port Access Route (SPAR) is also shown; however it should be noted that this link will not be open to public for walking and cycling.
Project: Docklands Bridge Traffic Modelling File No: FN-18-002-001 Subject: Network Modelling Results Date: 09 July 2019
File Note
Page 2 of 41
Figure 2-1: Study Area
Existing Samuel Beckett Bridge
Tom Clarke Bridge & Future Footbridge
Future Dodder Bridge
Potential Blood Stoney Bridge
Future Southern Port Access Route
(SPAR)
Potential Castleforbes Road Bridge
Potential Forbes Street Bridge
File Note
Page 3 of 41
Modelling Using NTA Eastern Regional Model The NTA’s Eastern Regional Model’s Active Mode Model (AMM) was used to predict walking and cycling volumes; and the Road Model was used to predict motorised vehicular volumes. Summarily, the modelling process involves running iterations between demand, mode choice, and assignment; with generalised costs being returned after each iteration, to inform the next iteration. For active modes, only the AM peak hour has been modelled, as the May 2019 surveys along Samuel Beckett Bridge and Tom Clarke Bridge recorded the highest numbers of pedestrians and cyclists crossing the Liffey in the AM (5,420 in the AM peak hour vs. 4,610 in the PM peak hour), and therefore represents the critical case.
3.1 Scenarios
Scenario Year Model Description Base 2012 NTA Eastern
Regional Model (ERM) Base Model, 2012
The 2012 ERM Base Model network reflects existing infrastructure.
2035 Do-Minimum 2035 NTA ERM Do-Strategy Model, 2035
The NTA’s Strategy Model includes measures that have been outlined in the Transport Strategy for the Greater Dublin Area 2016-2035.
Demand in Poolbeg and Docklands have been updated (see Section 2.2).
The Dodder Bridge is already included in this scenario.
Southern Port Access Road is also included; however there is no public access for walking and cycling.
2035 Do-Option 1: Forbes Street Bridge
2035 Do-Minimum + Option 1 Proposed Measures
Option 1 proposed measures include:
Pedestrian/ cycle bridge at Forbes Street;
Separate pedestrian and cycle bridge adjacent to the Tom Clarke Bridge (East Link Bridge);
Replacing The Point roundabout with a signalised junction.
2035 Do-Option 2: Blood Stoney Bridge
2035 Do-Minimum + Option 2 Proposed Measures
Option 2 proposed measures include:
Blood Stoney Bridge, with signalised junctions on both ends;
Separate pedestrian and cycle bridge adjacent to the Tom Clarke Bridge (East Link Bridge);
Replacing The Point roundabout with a signalised junction.
2035 Do-Option 3: Forbes Street Bridge + Castleforbes Road Bridge
2035 Do-Minimum + Option 3 Proposed Measures
Option 3 proposed measures include:
Pedestrian/ cycle bridges at Forbes Street and Castleforbes Road;
Separate pedestrian and cycle bridge adjacent to the Tom Clarke Bridge (East Link Bridge);
Replacing The Point roundabout with a signalised junction.
Table 3.1: Scenarios
File Note
Page 4 of 41
3.2 Demand In 2016, DCC and the NTA had carried out a similar modelling exercise for Poolbeg SDZ. As part of that, land use proposals associated with Poolbeg SDZ and Docklands SDZ had been updated based on more precise planning data which has emerged since the NTA’s 2035 Do-Strategy model was set up. These updated demands and trip-ends developed as part of that modelling exercise has also been used in this case.
Poolbeg SDZ Docklands SDZ Population 7,278 17,507
Jobs (Non-Retail) 6,824 52,522
Jobs (Retail) 342 900
Education 500 59
Trip Ends Production 12,518 48,825
Trip Ends Attraction 12,489 68,955 Table 3.2: Demands and Trip Ends
Walking & Cycling Modelling Results 4.1 Initial Modelling Results
Table 4.1: 2012 Base Model Initial Modelling Results, Active Modes
Peak Period Direction Samuel Beckett Bridge Tom Clarke Bridge
PT-Walk1 Other-Walk All Walk Cycle PT-Walk Other-Walk All Walk Cycle
AM2 NB3 / EB4 40 280 320 210 70 140 210 90
SB5 / WB6 250 500 750 430 90 190 280 60
Table 4.2: 2035 Do-Minimum Initial Modelling Results, Active Modes
Peak Period Direction
Samuel Beckett Bridge Tom Clarke Bridge Dodder Bridge PT-
Walk Other-Walk
All Walk Cycle PT-
Walk Other-Walk
All Walk Cycle PT-
Walk Other-Walk
All Walk Cycle
AM NB / EB 90 440 530 230 50 430 480 120 40 170 210 60
SB / WB 980 780 1,760 420 160 310 470 90 160 280 440 110
1 PT-Walk = Walking trips that are taken in combination with public transport trips. 2 AM peak period is 1 hour, usually assumed as between 08:00-09:00am. 3 NB = Northbound for Samuel Becket Bridge, Tom Clarke Bridge, Blood Stoney Bridge. 4 EB = Eastbound for Dodder Bridge. 5 SB = Southbound for Samuel Becket Bridge, Tom Clarke Bridge, Blood Stoney Bridge. 6 WB = Westbound for Dodder Bridge.
File Note
Page 5 of 41
Table 4.3: 2035 Do-Option 1: Forbes St Bridge, Initial Modelling Results, Active Modes
Peak Period Direction Samuel Beckett Bridge Forbes Street Bridge
PT-Walk Other-Walk All Walk Cycle PT-Walk Other-Walk All Walk Cycle
AM NB / EB 30 300 330 90 160 220 380 170
SB / WB 360 270 630 130 990 660 1,650 400
East Link Footbridge Dodder Bridge
PT-Walk Other-Walk All Walk Cycle PT-Walk Other-Walk All Walk Cycle
AM NB / EB 30 410 440 120 60 180 240 60
SB / WB 100 300 400 90 60 300 360 110
Table 4.4: 2035 Do-Option 2: Blood Stoney Bridge, Initial Modelling Results, Active Modes
Peak Period Direction Samuel Beckett Bridge Blood Stoney Bridge
PT-Walk Other-Walk All Walk Cycle PT-Walk Other-Walk All Walk Cycle
AM NB / EB 50 320 370 120 120 250 370 180
SB / WB 370 380 750 260 980 650 1,630 240
East Link Footbridge Dodder Bridge
PT-Walk Other-Walk All Walk Cycle PT-Walk Other-Walk All Walk Cycle
AM NB / EB 30 370 400 90 70 160 230 60
SB / WB 90 200 290 60 50 240 290 100
Table 4.5: 2035 Do-Option 3: Forbes St Bridge + Castleforbes Rd Bridge, Initial Modelling Results, Active Modes
Peak Period Direction
Samuel Beckett Bridge Forbes Street Bridge Castleforbes Road Bridge
PT-Walk
Other-Walk
All Walk Cycle PT-
Walk Other-Walk
All Walk Cycle PT-
Walk Other-Walk
All Walk Cycle
AM NB / EB 30 300 330 90 160 170 330 90 10 90 100 100
SB / WB 350 270 620 130 980 540 1,520 250 50 200 250 180
East Link Footbridge Dodder Bridge
PT-Walk Other-Walk All Walk Cycle PT-Walk Other-Walk All Walk Cycle
AM NB / EB 30 370 400 100 60 140 200 20
SB / WB 60 220 280 60 30 240 270 50
Screenshots showing the initial modelling results are attached in Appendix B of this document.
File Note
Page 6 of 41
4.2 Adjustments to 2035 Modelling Results The Base Model volumes shown in Table 4 were compared with pedestrian and cyclist volumes recorded in surveys of May 2019 (see Section 1). There were significant discrepancies, especially in terms of pedestrian volumes. These are due to the fact that the NTA’s Active Modes Model only includes certain defined walking trips, namely employers-business trips, work commuting trips, education trips, and “other journey purposes”. Trips that are irregular, i.e. not recorded by a census or travel survey, e.g. shopping or “going to get a coffee”, are not included. During consultations with the NTA, it was agreed that suitable scaling factors can be applied locally to adjust the outputs so that they are in line with what was recorded in the traffic surveys. The methodology used to determine and apply suitable scaling factors have been summarised below:
Figure 4-1: Methodology for Adjusting 2035 Initial Model Outputs
(1) 2012 Base Model Outputs•Results from NTA's 2012 Base Model is collated (shown in Table 4).
(2) 2019 NTA Active Modes Model (AMM) Volumes•The NTA model's growth factor is roughly 35% over 23 years. On that basis, growth rate for the 7 years between 2012 and 2019
was calculated and applied to the 2012 Base Model Outputs.•This approximates what might be the NTA model's outputs for 2019.
(3) 2019 Actual (Survey) Volumes•Pedestrian and cyclist volumes from 2019 surveys were collated.
(4) Compare 2019 NTA Active Modes Model (AMM) and Actual Volumes•Compare (2) the number of pedestrians and cyclists crossing the Liffey in 2019 NTA Active Modes Model and (3) actual number
of pedestrians and cyclists recorded crossing the Liffey in survey of 2019, at Samuel Beckett Bridge and Tom Clarke Bridge.•Comparison ratios between model and actual volumes are calculated for each direction (NB/SB), peak period (AM/ PM), and
mode (Walk/ Cycle).
(5) Determine Scaling Factors to be Applied•The calculated ratios comparing 2019 NTA AMM and 2019 actual volumes were evaluated.•Scaling factors (to be applied to 2035 outputs) are then determined for each direction (NB/SB), peak period (AM/ PM), and
mode (Walk/ Cycle).• As a conservative measure, these scaling factors to be applied are generally less than the calculated comparison ratios.
(6) Apply Scaling Factors to 2035 Outputs•The scaling factors determined in (5) are applied to 2035 Do-Minimum and 2035 Do-Options initial modelling results.•This gives "Adjusted results for 2035 Do-Minimum and 2035 Do-Something.
File Note
Page 7 of 41
Table 4.6 shows the calculations involved in determining the scaling factors to be applied to 2035 outputs. Note that the “Walk” and “Cycle” volumes are total numbers crossing the Liffey using Samuel Beckett Bridge and Tom Clarke Bridge.
Table 4.6: Determining Scaling Factors to be Applied to 2035 Outputs
Walk Cycle (1) 2012 Base Model AM Northbound 530 300
Southbound 1,030 490
(2) 2019 NTA Active Modes Model Volumes Estimated by applying 1.01313^7 growth rate between
2012 and 2019.
AM Northbound 581 329
Southbound 1,128 537
(3) 2019 Actual (Survey) Volumes AM Northbound 1,250 553
Southbound 2,627 990
(4) Ratio from comparison of (2) 2019 Model Volumes vs. (3) 2019 Actual Survey Volumes
AM Northbound 2.15 1.68
Southbound 2.33 1.84
(5) Scaling Factors to be applied to 2035 outputs AM Northbound 2.0 1.5
Southbound 2.2 1.7
Com
pare
(2) a
nd (3
) to
cal
cula
te (4
) In
form
ed b
y (4
)
File Note
Page 8 of 41
Adjusted results for pedestrian and cyclist across the Liffey (on Samuel Beckett Bridge, Tom Clarke Bridge, Dodder Bridge, Forbes Street Bridge/ Blood Stoney Bridge/ Castleforbes Road Bridge) in 2035 Do-Minimum and 2035 Do-Options scenarios are shown in Table 10 – Table 13. These are also illustrated in Appendix A of this document.
Table 4.7: 2035 Do-Minimum Adjusted Results, Active Modes
Peak Period Direction
Samuel Beckett Bridge East Link Bridge Dodder Bridge
PT-Walk
Other-Walk
All Walk Cycle PT-
Walk Other-Walk
All Walk Cycle PT-
Walk Other-Walk
All Walk Cycle
AM NB / EB 180 880 1,060 345 100 860 960 180 80 340 420 90
SB / WB 2,156 1,716 3,872 714 352 682 1,034 153 352 616 968 187
Table 4.8: 2035 Do-Option 1 (Forbes St Bridge) Adjusted Results, Active Modes
Peak Period Direction Samuel Beckett Bridge Forbes St Bridge
PT-Walk Other-Walk All Walk Cycle PT-Walk Other-Walk All Walk Cycle
AM NB / EB 60 600 660 135 320 440 760 255
SB / WB 792 594 1,386 221 2,178 1,452 3,630 680
East Link Footbridge Dodder Bridge
PT-Walk Other-Walk All Walk Cycle PT-Walk Other-Walk All Walk Cycle
AM NB / EB 60 820 880 180 120 360 480 90
SB / WB 220 660 880 153 132 660 792 187
Table 4.9: 2035 Do-Option 2: Blood Stoney Bridge, Adjusted Results, Active Modes
Peak Period Direction Samuel Beckett Bridge Blood Stoney Bridge
PT-Walk Other-Walk All Walk Cycle PT-Walk Other-Walk All Walk Cycle
AM NB / EB 100 640 740 180 240 500 740 270
SB / WB 814 836 1,650 442 2,156 1,430 3,586 408
East Link Footbridge Dodder Bridge
PT-Walk Other-Walk All Walk Cycle PT-Walk Other-Walk All Walk Cycle
AM NB / EB 60 740 800 135 140 320 460 90
SB / WB 198 440 638 102 110 528 638 170
Table 4.10: 2035 Do-Option 3: Forbes St Bridge + Castleforbes Rd Bridge, Adjusted Results, Active Modes
Peak Period Direction
Samuel Beckett Bridge Forbes Street Bridge Castleforbes Road Bridge PT-
Walk Other-Walk All Walk Cycle PT-
Walk Other-Walk
All Walk Cycle PT-
Walk Other-Walk
All Walk Cycle
AM NB / EB 60 600 660 135 320 340 660 135 20 180 200 150
SB / WB 770 594 1,364 221 2,156 1,188 3,344 425 110 440 550 306
East Link Footbridge Dodder Bridge
PT-Walk Other-Walk All Walk Cycle PT-Walk Other-Walk All Walk Cycle
AM NB / EB 60 740 800 150 120 280 400 30
SB / WB 132 484 616 102 66 528 594 85
File Note
Page 9 of 41
Level of Service for Footpaths The American Highway Capacity Manual (HCM) concept of Level of Service (LOS) for pedestrian traffic is widely used as a qualitative measure to describe operational conditions of footpaths and walkways, based on measurement of bi-directional pedestrian flow rates and available footpath widths. In the case of the Liffey crossings described in this report, pedestrian would be expected to often travel together as a group, voluntarily or involuntarily (e.g. due to signal control), hence the impact of platooning is also taken into account.
LOS Flow Rate (pedestrians/
minute /meter)
Description
A <= 1.6 Free flow
B >1.6 – 9.8 Pedestrians will respond to the presence of other pedestrians by electing a walking path.
C >9.8 – 19.7 Space is sufficient for normal walking speeds, and for bypassing other pedestrians in primarily unidirectional streams. Opposing or crossing movements can cause minor conflicts, and speeds and flow rates are somewhat lower.
D >19.7 – 36.1 Freedom to select individual walking speed and to bypass other pedestrians is restricted. Opposing or crossing movements face high probability of conflict. Friction and interaction between pedestrians is likely.
E >36.1 – 59.1 Virtually all pedestrians restrict their normal walking speed. Insufficient space for passing slower pedestrians. Extreme difficulties for bi-directional or crossing movements.
F >59.1 Forward progress only by shuffling. Frequent unavoidable contact with other pedestrians. Space is more characteristic of queueing rather than of moving pedestrian streams.
Table 5.1: HCM 2010 Platoon-Adjusted LOS Criteria for Walkways and Sidewalks LOS Level C is generally considered acceptable, and a minimum for design purposes. The AM Peak LOS calculated for Samuel Beckett Bridge and Forbes Street Bridge/ Blood Stoney Bridge/ Castleforbes Road Bridge are shown below (AM peak hour has higher bi-directional pedestrians volumes than PM peak). On the day of survey in May 2019, 62% of northbound pedestrians and 66% of southbound pedestrians were recorded walking on the eastern side of Samuel Beckett Bridge during AM peak hour. An earlier Pedestrian Study commissioned by Dublin City Council in 2015 had also noted that a higher proportion of pedestrians (75%) tend to walk on the eastern side of Samuel Beckett Bridge. In the calculations and assessments of potential Level of Service for pedestrian in 2035 AM peak, two different cases of pedestrian splits, listed in Table 15, have been considered.
Western Pavement Eastern Pavement
Northbound Pedestrians Southbound Pedestrians Northbound Pedestrians Southbound Pedestrians
Case 1 38% 34% 62% 66%
Case 2 50% 50% 50% 50%
Table 5.2: Western & Eastern Pavements Pedestrian Splits Considered for Assessment In the Do-Options scenarios, footpath widths of 2.5m and 3.0m have both been assessed for potential LOS.
File Note
Page 10 of 41
Table 5.3: Calculated LOS for Footpaths using HCM Criteria
Scenario Location (Bridge) Pedestrian volumes Assumed footpath usage ratio Available minimum footpath width (m) Flow Rate (ped/min/m) LOS
Northbound Southbound Case West Side East Side West Side East Side West Side East Side
NB SB NB SB
AM 2019 Survey Samuel Beckett Bridge 948 2,479 Survey 0.38 0.34 0.62 0.66 2.2 1.5 9.2 24.6 D
AM 2035 Do-Minimum Samuel Beckett Bridge 1,060 3,872 Case 1 0.38 0.34 0.62 0.66 2.2 1.5 13.1 35.6 D
Case 2 0.5 0.5 0.5 0.5 2.2 1.5 18.7 27.4 D
AM 2035 Do-Option 1 Samuel Beckett Bridge 660 1,386 Case 1 0.38 0.34 0.62 0.66 2.2 1.5 5.5 14.7 C
Case 2 0.5 0.5 0.5 0.5 2.2 1.5 7.8 11.4 C
Forbes St Bridge 760 3,630 Case 1 0.38 0.34 0.62 0.66 3.0 3.0 8.5 15.9 C
Case 2 0.5 0.5 0.5 0.5 3.0 3.0 12.2 12.2 C
Case 1 0.38 0.34 0.62 0.66 2.5 2.5 10.2 19.1 C
Case 2 0.5 0.5 0.5 0.5 2.5 2.5 14.6 14.6 C
AM 2035 Do-Option 2 Samuel Beckett Bridge 740 1,650 Case 1 0.38 0.34 0.62 0.66 2.2 1.5 6.4 17.1 C
Case 2 0.5 0.5 0.5 0.5 2.2 1.5 9.1 13.3 C
Blood Stoney Bridge 740 3,586 Case 1 0.38 0.34 0.62 0.66 3.0 3.0 8.4 15.7 C
Case 2 0.5 0.5 0.5 0.5 3.0 3.0 12.0 12.0 C
Case 1 0.38 0.34 0.62 0.66 2.5 2.5 10.1 18.8 C
Case 2 0.5 0.5 0.5 0.5 2.5 2.5 14.4 14.4 C
AM 2035 Do-Option 3 Samuel Beckett Bridge 660 1,364 Case 1 0.38 0.34 0.62 0.66 2.2 1.5 5.4 14.5 C
Case 2 0.5 0.5 0.5 0.5 2.2 1.5 7.7 11.2 C
Forbes St Bridge 660 3,344 Case 1 0.38 0.34 0.62 0.66 3.0 3.0 7.8 14.5 C
Case 2 0.5 0.5 0.5 0.5 3.0 3.0 11.1 11.1 C
Case 1 0.38 0.34 0.62 0.66 2.5 2.5 9.3 17.4 C
Case 2 0.5 0.5 0.5 0.5 2.5 2.5 13.3 13.3 C
Castleforbes Rd Bridge 200 550 Case 1 0.38 0.34 0.62 0.66 3.0 3.0 1.5 2.7 B
Case 2 0.5 0.5 0.5 0.5 3.0 3.0 2.1 2.1 B
Case 1 0.38 0.34 0.62 0.66 2.5 2.5 1.8 3.2 B
Case 2 0.5 0.5 0.5 0.5 2.5 2.5 2.5 2.5 B
File Note
Page 11 of 41
Using pedestrian volumes recorded during AM peak in survey of May 2019, the overall LOS assessed for pedestrians on Samuel Beckett Bridge is Level D. Along the western pavement, the pedestrian flow rate is 9.2 pedestrians/ minute/ meter (peds/min/m); and along the eastern pavement it is busier, 24.6 peds/min/m. In the 2035 Do-Minimum scenario, the AM peak LOS for pedestrians on Samuel Beckett Bridge is Level D. This suggests that pedestrians will be experiencing congestion on the footpaths in this scenario. In the 2035 Do-Option 1 scenario, assessments suggest that both Samuel Beckett Bridge and Forbes Street Bridge will be able to cater to the predicted volume of pedestrians. Minimum footpath widths of 3.0m would be recommended for Forbes Street Bridge, as the LOS on the eastern footpath would be approaching Level D with 2.5m width. Similarly in the 2035 Do-Option 2 scenario, assessments suggest that both Samuel Beckett Bridge and Blood Stoney Bridge will be able to cater to the predicted volume of pedestrians. Minimum footpath widths of 3.0m would be recommended for Blood Stoney Bridge, as the LOS on the eastern footpath would be approaching Level D with 2.5m width. Modelling and pedestrian LOS assessment for Do-Option 1 (Forbes Street Bridge) and Do-Option 2 (Blood Stoney Bridge) scenarios produced very similar results in terms of demand on the new bridge(s) and the relief/ reduction of demand on Samuel Beckett Bridge (see Table 5.4). Compared to Blood Stoney Bridge, Forbes Street Bridge is expected to have 6% more active mode users, and is expected to have a greater relief for walking/ cycling demand on Samuel Beckett Bridge (-34% with Forbes Street Bridge vs. -18% with Blood Stoney Bridge). However, the Level of Service on all bridges are at Level C in both scenarios, assuming 2x3.0m footpath widths on new bridges - which is a notable improvement from the Do-Minimum scenario where Samuel Beckett Bridge would be at Level D.
Do-Option 1 (Forbes St Bridge)
Samuel Beckett Bridge Forbes St Bridge
All Walk Cycle All Active Modes Level of
Service for Pedestrians
All Walk Cycle
All Active Modes
Level of Service for Pedestrians
2,046 356 2,402 C 4,390 935 5,325 C
Do-Option 2 (Blood Stoney Bridge)
Samuel Beckett Bridge Blood Stoney Bridge
All Walk Cycle All Active Modes Level of
Service for Pedestrians
All Walk Cycle
All Active Modes
Level of Service for Pedestrians
2,390 622 3,012 C 4,326 678 5,004 C
Table 5.4 Summary Comparison of Do-Option 1 (Forbes St Bridge) and Do-Option 2 (Blood Stoney Bridge) In the 2035 Do-Option 3 scenario, assessments suggest that Samuel Beckett Bridge, Forbes Street Bridge, and Castleforbes Road Bridge will all be able to cater to the predicated volume of pedestrians. Minimum footpath widths of 3.0 would be recommended for Forbes Street Bridge, as the LOS on the eastern footpath would be approaching Level D with 2.5m width. On Castleforbes Road Bridge, demand is expected to be lower than the other two bridges, hence footpath widths of 2.5m, or even 1.8m should suffice.
File Note
Page 12 of 41
Highway Network Modelling The focus of the highway network modelling exercise is on Tom Clarke Bridge. Following mode choice selection, motorised vehicular trips are assigned routes in the highway network. Given that the scale of interventions under consideration are relatively contained, it was decided to focus our assessment on a cordon of the ERM (shown in Figure 6-1), around the city centre.
Figure 6-1: Highway Model Cordon
6.1 2012 Base Model Table 12 compares traffic volumes recorded during a 2012 traffic survey on Tom Clarke Bridge (extracted from ARUP Technical Note for The Point Roundabout Improvement Scheme 2018.04.04) and traffic volumes in the NTA’s 2012 ERM Base Model at the same location.
Peak Hour Direction Traffic on Tom Clarke Bridge, including cyclists 2012 Survey 2012 ERM Base Model
AM Northbound 716 778
Southbound 953 982
PM Northbound 831 522
Southbound 680 248 Table 6.1: Comparison of 2012 Surveyed Traffic Volumes vs. 2012 ERM Base Model Volumes
While the 2012 ERM Base Model AM peak flows on Tom Clarke Bridge are comparable with 2012 surveyed traffic, the PM peak comparison is poor. Hence when doing assessment work for the PM peak, it should be noted that potential effects might be under represented. However, at this stage of the project, the AM peak hour is considered the more critical, particularly in the southbound direction, as this would have a direct impact on the viability of allowing a right-turning movement for vehicles from Tom Clarke Bridge onto the proposed Dodder Bridge.
File Note
Page 13 of 41
6.2 Amendments to 2035 Do-Minimum ERM Highway Network A few adjustments were made to the NTA’s 2035 Strategy Network:
Junction between Dodder Bridge and Tom Clarke Bridge is signalised, with right-turning allowed for public transport from Tom Clarke Bridge to Dodder Bridge.
The Southern Port Access Road (SPAR) is amended to function as a private road instead of a public road. Three links have been used to model the SPAR, allowing the following traffic movements:
i. Originating from the north port, wanting to access South Dublin (southbound); and
Originating from somewhere in South Dublin, wanting to access the north port (northbound).
ii. Travelling to/from (between) north port and south port.
iii. Originating somewhere in North Dublin (e.g. the Port Tunnel), and wanting to access the south port (southbound); and
Originating from the south port, and wanting to access North Dublin (northbound)
Figure 6-2 Modified Links for Southern Port Access Road (Private Road)
(i) North Port ⇔ South Dublin
(ii) North Port ⇔
South Port
(iii) South Port ⇔ North Dublin
File Note
Page 14 of 41
6.3 2035 Do-Something For the purpose of this road-based assessment, a Do-Something scenario similar to the Do-Option 2 (Blood Stoney Bridge) has been used. The following were included as new measures:
The Point roundabout is amended to a signalised junction. Signal plans are as per LinSig model received from ARUP in April 2018.
Figure 6-3: Proposed Signal Sequencing for The Point Junction
New signalised junction south of proposed Blood Stoney Bridge; and revised signalised junction north of proposed Blood Stoney Bridge, with additional phase for cyclists coming from Blood Stoney Bridge. These are shown in Figure 5.
File Note
Page 15 of 41
Figure 6-4: Proposed Junction Arrangements North and South of Proposed Blood Stoney Bridge
File Note
Page 16 of 41
6.4 Highway Network Modelling Results Table 6.2: 2035 Do-Minimum, Highway Demand
Peak Period Direction Tom Clarke Bridge Dodder Bridge Southern Port Access Road (SPAR)
AM NB / EB 805 110 358
SB / WB 542 2 405
PM NB / EB 651 113 150
SB / WB 130 1 269
Figure 6-5: AM 2035 Do-Minimum Highway Demand SATURN Output
Figure 6-6: PM 2035 Do-Minimum Highway Demand SATURN Output
Tom Clarke Bridge
Proposed Southern Port Access Road Proposed Dodder
Bridge
Tom Clarke Bridge
Proposed Southern Port Access Road Proposed Dodder
Bridge
File Note
Page 17 of 41
Table 6.3: 2035 Do-Something, Highway Demand
Peak Period Direction Tom Clarke Bridge Dodder Bridge Southern Port Access Road (SPAR)
AM NB / EB 802 77 368
SB / WB 538 22 420
PM NB / EB 981 117 141
SB / WB 107 3 358
Figure 6-7: AM 2035 Do-Something Highway Demand SATURN Output
Figure 6-8: AM 2035 Do-Something Highway Demand SATURN Output
Screenshots showing the highway network modelling results are included in Appendix C of this document.
Tom Clarke Bridge
Proposed Southern Port Access Road Proposed Dodder
Bridge
Tom Clarke Bridge
Proposed Southern Port Access Road Proposed Dodder
Bridge
File Note
Page 18 of 41
In general, results for the 2035 Do-Minimum and 2035 Do-Something scenarios are similar - with the exception of PM northbound traffic on Tom Clarke Bridge, where the 2035 Do-Something scenario had 981no. going northbound compared to 651no. in the 2035 Do-Minimum scenario. In the 2035 Do-Minimum scenario, vehicles exiting the port from just north of the Point roundabout are able to do u-turns at the roundabout in order to go north (e.g. towards the Port Tunnel). However in the 2035 Do-Something scenario, these same vehicles cannot make the same manoeuvre as the Point junction is signalised. Instead they are exiting the Port further north (at Alexandra Road), which releases capacity at the Point junction. As a result, northbound traffic from other bridges are being attracted onto the Tom Clarke Bridge, rather than take the longer distance route further west (e.g. Butt Bridge). This is illustrated in Figure 6-9, which shows a difference plot between 2035 Do-Minimum and 2035 Do-Something in the PM Peak. Blue lines represent a reduction in traffic flow between the Do-Minimum and Do-Something; and green lines represent traffic flow increase.
Figure 6-9: Difference Plot between 2035 Do-Minimum and 2035 Do-Something
The same isn’t having such a pronounced effect in the AM, as there isn’t as much traffic heading north in the AM.
File Note
Page 19 of 41
Appendix A: 2035 Do-Minimum and 2035 Do-Something Adjusted Outputs, Active Modes
AM 2035 Do-MinimumWalk & Cycle Mode
1,060
345 ù 3,872
714 ù
960
180 ù
1,034
153 ù
420
90 ù
968
187 ù
AM 2035 Do-Option 1 (Forbes St Bridge)
660
135 ù 1,386
221 ù
880
180 ù
880
153 ù
480
90 ù
792
187 ù
760
255 ù
3,630
680 ù
AM 2035 Do-Option 2 (Blood Stoney Bridge)
740
180 ù 1,650
442 ù
800
135 ù
638
102 ù
460
90 ù
638
170 ù
740
270 ù
3,586
408 ù
AM 2035 Do-Option 3(Forbes St Bridge + Castleforbes Rd Bridge)
660
135 ù 1,364
221 ù
800
150 ù
616
102 ù
400
30 ù
594
85 ù
660
135 ù
3,344
425 ù
200
150 ù 550
306 ù
File Note
Page 20 of 41
Appendix B: Initial Modelling Results, Active Modes The following figures are screenshots from CUBE, provided by the NTA. Figure 0-1: AM 2012 Base, PT-Walk-Access
Figure 0-2: AM 2012 Base, Walk-Mode
Figure 0-3: AM 2012 Base, Cycle-Mode
Figure 0-4: AM 2035 Do Minimum, PT-Walk-Access
Figure 0-5: AM 2035 Do Minimum, Walk-Mode
Figure 0-6: AM 2035 Do Minimum, Cycle-Mode
Figure 0-7: AM 2035 Do-Option 1 (Forbes St Bridge) PT-Walk-Access
Figure 0-8: AM 2035 Do-Option 1 (Forbes St Bridge) Walk-Mode
Figure 0-9: AM 2035 Do-Option 1 (Forbes St Bridge) Cycle-Mode
Figure 0-10: AM 2035 Do-Option 2 (Blood Stoney Bridge) PT-Walk-Access
Figure 0-11: AM 2035 Do-Option 2 (Blood Stoney Bridge) Walk-Mode
Figure 0-12: AM 2035 Do-Option 2 (Blood Stoney Bridge) Cycle-Mode
Figure 0-13: AM 2035 Do-Option 3 (Forbes St Bridge + Castleforbes Rd Bridge) PT-Walk-Access
Figure 0-14: AM 2035 Do-Option 3 (Forbes St Bridge + Castleforbes Rd Bridge) Walk-Mode
Figure 0-15: AM 2035 Do-Option 3 (Forbes St Bridge + Castleforbes Rd Bridge) Cycle-Mode
File Note
Page 21 of 41
Figure 0-1: AM 2012 Base, PT-Walk-Access
File Note
Page 22 of 41
Figure 0-2: AM 2012 Base, Walk-Mode
File Note
Page 23 of 41
Figure 0-3: AM 2012 Base, Cycle-Mode
File Note
Page 24 of 41
Figure 0-4: AM 2035 Do Minimum, PT-Walk-Access
File Note
Page 25 of 41
Figure 0-5: AM 2035 Do Minimum, Walk-Mode
File Note
Page 26 of 41
Figure 0-6: AM 2035 Do Minimum, Cycle-Mode
File Note
Page 27 of 41
Figure 0-7: AM 2035 Do-Option 1 (Forbes St Bridge) PT-Walk-Access
File Note
Page 28 of 41
Figure 0-8: AM 2035 Do-Option 1 (Forbes St Bridge) Walk-Mode
File Note
Page 29 of 41
Figure 0-9: AM 2035 Do-Option 1 (Forbes St Bridge) Cycle-Mode
File Note
Page 30 of 41
Figure 0-10: AM 2035 Do-Option 2 (Blood Stoney Bridge) PT-Walk-Access
File Note
Page 31 of 41
Figure 0-11: AM 2035 Do-Option 2 (Blood Stoney Bridge) Walk-Mode
File Note
Page 32 of 41
Figure 0-12: AM 2035 Do-Option 2 (Blood Stoney Bridge) Cycle-Mode
File Note
Page 33 of 41
Figure 0-13: AM 2035 Do-Option 3 (Forbes St Bridge + Castleforbes Rd Bridge) PT-Walk-Access
File Note
Page 34 of 41
Figure 0-14: AM 2035 Do-Option 3 (Forbes St Bridge + Castleforbes Rd Bridge) Walk-Mode
File Note
Page 35 of 41
Figure 0-15: AM 2035 Do-Option 3 (Forbes St Bridge + Castleforbes Rd Bridge) Cycle-Mode
File Note
Page 36 of 41
Appendix C: Highway Network Modelling Results (Demand)
80
270
118
88
604
138
00
446174
6
9
262
237
166
633
35
104
247
379
245
14
142413
154
252
187
146
1556 542751
1690
564
696 711
1165
1561
1165
604
635
805
700
153
227
453
324
227
153
572
457
385
702
0
0
522
977
0
0
20440
40
204
696
564 154
591
1560
727
614
1879
544
698
2
110
805
542
129
1561
472
42
185
487
727
1561
577
979
587
1052
464
274
27080
464
3120
290
372
354
174
446
606
584
138
604
0
2
760
909
909
760
211
34
12066
15
245
14245
457
572
388
727
1293
7
904
760
5
35786
5
579
598
606
805
9
6
357
5
1560
727
0
0
110
2
10435
251
164
5
117
1
5
117
327
139
262
236
237
262
1
1117
603
782
73
960
907
762
919
634
233
1077
534
439
1132
697
701
698
286
379
247
654
557
751
768
252
154
413
142
633
166
262
11
11
262
20
4
420
139327
AM 2035 Do-Minimum Demand Flows
80
270
118
88
496
136
780
425173
6
9
263
240
168
654
30
106
247
371
241
28
141413
155
252
188
146
508
350 365
521
957
1064
1064
957
389
626
677
509
107
66
481
253
66218
567
474
363
531
0
111
540
914
0
78
212
145
107
207
350
508 205
331
1063
831
681
1402
518
726
22
77
802
538
557
69
182
442
831
1064
424
1029
464
274
27080
464
2880
277
328
303
173
425
551
420
136
496
0
2
725
897
897
725
176
44
11433
30
241
28241
474
567
379
660
538
802
7
892
725
6
30684
4
551
433
551
9
6
306
6
1063
831
0
78
77
22
10630
250
152
7
128
1
7
128
333
153
263
239
240
263
1
1160
614
746
75
954
910
737
928
649
271
1057
529
439
1139
702
666
686
282
371
247
621
562
763
773
252
155
413
141
654
168
263
12
12
263
23
4
423
153333
AM 2035 Do-Something Demand Flows
181
75
68
122
277
367
00
315207
16
27
226
125
232
211
281
9
282
158
72
66
344144
179
122
132
114
2107 1301456
1863
656
404 421
1555
1833
1555
530
454
556
725
196
104
544
356
104
196
430
645
378
259
0
0
506
753
0
0
116
445
445
116
404
656 150
1393
1832
312
186
2134
133
543
1
113
651
130
31
1833
462
35
240
480
312
1833
665
1442
695
1026
214
320
75181
214
46
0
287
310
130
207
315
504
697
367
277
0
3
580
1117
1117
579
92
252
18620
69
72
6672
645
430
351
813
1585
4
1116
579
20
13965
5
677
713
504
651
27
16
139
20
1832
312
0
0
113
1
9
281
133
272
49
15
6
49
15
120
199
226
119
125
226
6
638
774
653
48
687
766
989
634
876
108
389
700
736
963
537
985
231
418
158
282
893
504
684
645
122
179
144
344
211
232
10
25
25 10
5
60
60
5199120
PM 2035 Do-Minimum Demand Flows
178
75
67
122
275
355
11
316198
16
27
232
125
232
206
289
11
286
158
72
67
350142
179
122
133
115
558
239 256
566
592
1156
1156
592
361
454
456
516
181
55
494
472
55260
525
584
487
244
0
79
557
978
1
1
177
411
332
177
239
558 173
488
1155
277
422
1400
105
864
3
117
981
107
449
351
324
400
277
1156
560
976
215
319
75178
215
50
287
266
97
198
316
535
557
355
275
0
3
574
1080
1080
574
97
260
19325
70
72
6772
584
525
380
861
107
981
4
1079
574
21
10766
7
743
573
535
27
16
107
21
1155
277
1
1
117
3
11289
143
222
37
71
6
37
71
112
286
232
119
125
232
6
644
714
598
48
654
605
976
644
808
98
388
711
704
887
483
1069
231
425
158
286
1001
476
614
660
122
179
142
350
206
232
10
24
24 10
5
62
62
5286112
PM 2035 Do-Something Demand Flows
File Note
Page 37 of 41
Appendix D: Pedestrian and Cycle Count Survey Results – Monday 14th of May 2019
File Note
Page 38 of 41
Samuel Beckett Bridge – AM Peak Hour
Samuel Beckett Bridge – PM Peak Hour
File Note
Page 39 of 41
Samuel Beckett Bridge – Total AM and PM Peak Periods
File Note
Page 40 of 41
East Link Toll Bridge – AM Peak Hour
East Link Toll Bridge – PM Peak Hour
File Note
Page 41 of 41
East Link Toll Bridge – Total AM and PM Periods