    LOS ANGELES UNIFIED SCHOOL DISTRICT

    SCHOOL CONSTRUCTION BOND CITIZENS OVERSIGHT COMMITTEE

    David Crippens, ChairL.A. Area Chamber of Commerce

    Elizabeth Bar-El, Vice ChairLAUSD Student Parent(Primary Member)

    John Naimo, SecretaryCounty of Los Angeles(Primary Member)

    Scott FolsomTenth District PTSA

    Constance Rice

    L.A. City Controllers Office

    Joseph P. Buchman Legal CounselBurke, Williams & Sorensen, LLP

    Maria CabildoLAUSD Student Parent(Primary Member)

    Sylvia CunninghamAARP

    Adrian GarcaL.A. Mayors Office

    John HakelAssociated General Contractors ofCalifornia (Alternate Member)

    David Jenkins

    Associated General Contractors ofCalifornia (Primary Member)

    Lynda LevitanThirty-First District PTSA

    Anastacio MedinaBREATHE California

    Thomas A. RubinOversight Committee Consultant

    Richard SlawsonL.A. Co. Federation of Labor,

    AFL-CIOWendy Watanabe

    County of Los Angeles(Alternate Member)

    Chester WidomAmerican Institute of Architects

    Barry WaiteLAUSD Student Parent(Alternate Member)

    (Vacant)California Taxpayers

    Association(Vacant)

    Environmental Justice/CivilRights Group

    Gary C. AndersonDirector

    Frank PadillaAdministrator

    School Construction Bond Citizens Oversight CommitteeRegular Meeting

    LAUSD HQ Board Room333 S. Beaudry AvenueLos Angeles, CA 90017

    Wednesday, October 20, 2010

    10:00 a.m.

    Item

    Presentation/Discussion

    TimePresenter

    1. Call To Order D. Crippens

    2. Chairs Remarks D. Crippens

    3. Consent Calendar August 18, 2010 Minutes

    BOC Quarterly Report (April June 2010)............................Action Item

    2 Minutes D. Crippens

    4.Facilities Services Division Update.....................................................Report

    (New Construction, Existing Facilities, and Planning and Development)10 Minutes J. Sohn

    Existing Facilities SEP AmendmentJ Sohn

  • 8/8/2019 Final BOC Agenda October 20 2010

    2/200

    J Sohn

    LOS ANGELES UNIFIED SCHOOL DISTRICTSCHOOL CONSTRUCTION BOND CITIZENS OVERSIGHT COMMITTEE

    Regular MeetingWednesday, October 20, 2010

    7.Existing Facilities SEP Amendment

    Alteration and Improvement and Board Member Funded Projects atVarious Schools.....................................................................Action Item

    10 MinutesJ. SohnA. Lasso

    8.Existing Facilities SEP Amendment

    Fund Four Additional Modified Consent Decree (MCD) On-DemandAccessibility Projects.............................................................Action Item

    10 MinutesJ. SohnG. Garcia

    9.New Construction SEP Amendment

    Central Los Angeles High School No. 12 Funding Strategy andAuthorization to Enter into a Development Agreement..........Action Item

    10 MinutesJ. SohnJ. Sun

    10. Bond Oversight Committee School Garden Task Force..............Action Item 10 Minutes A. Medina

    11. Bond Oversight Committee Measure Q Task Force....................Action Item 10 Minutes E. Bar-El

    12.Board of Education / Bond Oversight Committee Task Force to Study BOCMembership........................................................................................Report

    10 Minutes T. Rubin

    13.Construction Cost Analysis: Conventional School vs. CharterSchool.................................................................................................Report

    10 Minutes T. Rubin

    14. Design/Build Competition Update.......................................................Report 10 MinutesJ. SohnR. Brykalski

    15. Career Technical Education Review...................................................Report 10 Minutes E. Morris

    16. Public Comment

    Information Items

    ITD Quarterly Program Status Report

    Bond Oversight Committee Upcoming Meeting Schedule: November 17, 2010 December 17, 2010 January 19, 2011

    Bond Oversight Committee meetings are aired on KLCS-TV (channel 58) on the Sunday following the meeting date.Broadcast time of the Bond Oversight Committee meetings may change due to the volume of broadcasts scheduled forthe day. Please call (213) 241-4036 the Friday prior to the Sunday Broadcast to verify the time.

  • 8/8/2019 Final BOC Agenda October 20 2010

    3/200

    Agenda

    Item # 3

  • 8/8/2019 Final BOC Agenda October 20 2010

    4/200

    LOS ANGELES UNIFIED SCHOOL DISTRICT

    SCHOOL CONSTRUCTION BOND CITIZENS OVERSIGHT COMMITTEE

    David Crippens, ChairL.A. Area Chamber of Commerce

    Elizabeth Bar-El, Vice ChairLAUSD Student Parent(Primary Member)

    John Naimo, SecretaryL.A. County Auditor-Controllers

    Office (Primary Member)Scott FolsomTenth District PTSA

    Constance RiceL.A. City Controllers Office

    Joseph P. Buchman Legal Counsel

    Burke, Williams & Sorensen, LLP

    Maria CabildoLAUSD Student Parent(Primary Member)

    Sylvia CunninghamAARP

    Adrian GarcaL.A. Mayors Office

    John HakelAssociated General Contractors ofCalifornia (Alternate Member)

    David JenkinsAssociated General Contractors ofCalifornia (Primary Member)

    Lynda LevitanThirty-First District PTSA

    Anastacio MedinaBREATHE California

    Thomas A. Rubin

    Oversight Committee Consultant

    Richard SlawsonL.A. Co. Federation of Labor,

    AFL-CIOWendy WatanabeL.A. County Auditor-Controllers

    Office (Alternate Member)Chester WidomAmerican Institute of Architects

    Barry WaiteLAUSD Student Parent

    (Alternate Member)(Vacant)California Taxpayers

    Association(Vacant)Environmental Justice/CivilRights Group

    Gary C. Anderson

    DirectorFrank PadillaAdministrator

    Citizens Bond Oversight CommitteeRegular Meeting

    333 S. Beaudry AvenueLos Angeles, CA 90017

    Wednesday, August 18, 2010

    Committee Members Present: D. Crippens; E. Bar-El; J. Naimo; S. Folsom; S. Cunningham; A. Medina; M. Cabildo;L. Levitan; C. Widom; C. Rice

    Committee Members Absent: A. Garcia; D. Jenkins; R. Slawson

    Agenda Item 1. Call to Order

    Mr. Crippens called the meeting to order at 10:06 a.m.

    Agenda Item 2.Chairs Remarks

    Mr. Crippens read the BOCs mission statement:

    The mission of the strong and independent Oversight Committee is to oversee the expenditure of moneyfor the construction, repair, and modernization of schools by the Los Angeles Unified School District. The

  • 8/8/2019 Final BOC Agenda October 20 2010

    5/200

    BOC Meeting, August 18, 2010Page 2

    Agenda Item 3. Consent Calendar

    Mr. Crippens introduced the consent calendar consisting of the May 19, 2010 BOC minutes and June 16, 2010 BOCminutes.

    There was a Motion, Second, and vote.

    Aye: 10Nay: 0Absent:Abstain:

    The Consent Calendar Passed Unanimously

    Agenda Item 4.4A. Contract Audit Work Plan 2010/20114B. Follow-Up Report on Rational Audit Plan 08/09Presenter: Jess Womack, Interim Inspector General

    Contract Audit Work Plan

    Resolution 2010-26

    Mr. Womack discussed the proposed OIG budget ($2.9 million) for 2010/2011. He also discussed the OIGs overallbudget. In a worst case scenario, Mr. Womack reported that OIG will be short of funds by 2015.

    Mr. Naimo requested to hear OIG updates throughout the fiscal year instead of once a year. With regard to budget, Mr.Naimo asked if last years budget was fully expended. Mr. Onwualu responded that all funds were expended. Mr. Naimoasked when the OIG Annual Report would be released. Mr. Womack responded that it would be released today.

    Since Mr. Womack is filling the Inspector General position as an interim, Ms Rice stated that one of the best services hecould provide would be to help the OIG office and the Board of Education (BOE) identify rules that insulate the OIG officefrom political use. In the past, not the current BOE, the BOE has done so. Ms. Rice asked if the OIG had sufficientresources to conduct the range of audits needed under the Rational Audit Plan. Mr. Womack responded that he has beenworking with senior management, BOE, and senior staff to let them know and urge them to make themselves accessibleto those that they are serving. Regarding participating in finding a new Inspector General, Mr. Womack reported that inhis research about the inspector general position he found a statement from another inspector general that identifies howan inspector general has to operate inside a public institution. He will forward the information to the BOC. Mr. Womackinvited Mr. Onwualu to respond to the staffing question. He responded that current staff and bench contracts provideadequate staffing to perform the required work.

    With regard to staffing, Mr. Widom asked if the OIG had an adequate amount of design construction professionals onstaff. Mr. Onwualu responded that in house staff includes an architect and an electrical engineer and that it is notadequate. He added that there are bench contracts that provide the necessary expertise. Mr. Widom expressed concernabout relying heavily on bench contracts and cautioned about finding bench firms that have direct in house constructionand design experience. Mr. Onwualu responded that the bench firms have auditors with experience auditing constructioncontracts but do not have in house staffs that are engineers, architects, or designers but they can hire those skills. Mr.

  • 8/8/2019 Final BOC Agenda October 20 2010

    6/200

    BOC Meeting, August 18, 2010Page 3

    Aye: 10Nay: 0

    Absent: 4Abstain: 0

    Resolution 2010-26 Passed Unanimously

    Follow-Up Report on the Rational Audit Plan 08/09

    Mr. Womack reported that he spoke to the Superintendent and Mr. Sohn about the issues addressed in the report. Mr.Sohn indicated to Mr. Womack that they would be addressed.

    Mr. Widom reported that he was the architect of record for two previous projects. One was occupied in 2005 and one in2006 and Mr. Widom reported that there are 12 outstanding change orders from the project that was completed in 2006.The project completed in 2005 is still sitting on an addendum from the initial bidding process. Mr. Widom stated that thereis a problem and something has to be done.

    Agenda Item 5.Facilities Services Division UpdatePresenter: James Sohn, Chief Facilities Executive

    Mr. Sohn provided a Facilities Services Division update. He reported on the 21 schools that are scheduled to open this

    school year. Ninety six of 131 planned new schools have been completed. Mr. Sohn reported that involuntary busing hasbeen nearly eliminated.

    Mr. Sohn discussed FSD reorganization and consolidation. The number of departments and branches has been reduced.There are now five operating units and they incude: asset management, project execution, maintenance and operations,support services, and contracts.

    Mr. Sohn discussed several allocation models for use of future funds, including Measure Q. The allocation models arestrategies to provide guidance on the allocation of future funds by complex and program.

    Mr. Sohn discussed the FSD sustainability program. Two green ombudspersons were hired to assist with gardening andgreening projects. There is a new website with information on green species, native plants, and gardening/plantingguidelines. There are over 100 teaching and edible gardens in schools. Smart irrigation projects will be located at 173sites. Mr. Sohn reported that 1.2 megawatts of solar projects have been completed. Four projects are under constructionfor 1.6 megawatts. Three large projects are in design that will result will be four megawatts and there are projects in theplanning stages for 17 megawatts.

    Mr. Sohn reported that DSA closeout and change order issues are a huge priority for FSD. He participated in the state-wide DSA reform and streamlining effort but there hasnt been appreciable improvement in the results. The San Diego

    and Sacramento DSA offices are receptive to LAUSD recommendation to create a focused pilot program that addressesDSA certification issues.

    Mr. Sohn reported on the LAUSD budget crisis. It has been challenging and many staff members will be taking furloughdays. Mr. Sohn has been granted flexibility with scheduling furlough days to minimize impact to the operations of schools.

    Mr. Sohn reported that the team cleaning approach has been piloted at 15 schools and in the results are mixed. In some

  • 8/8/2019 Final BOC Agenda October 20 2010

    7/200

    BOC Meeting, August 18, 2010Page 4

    available, either a positive $100 million or negative $200 million, depending on how liberal or conservative FSD wants tobe in the assumptions for risk. One of the greatest assumptions for risk is the $660 million owed to the bond program

    through State match.

    Mr. Sohn reported that senior management has responded enormously well during this time of change in FSD andLAUSD. Management positions have been downgraded and/or eliminated for accountability and performance as well asdownsizing. Where possible, FSD has looked at well qualified district staff and provided them the opportunity forpromotion.

    Mr. Medina commented on a finding in the OIG report regarding DSA closeout and certification. The finding was that thecloseout and commissioning team was more interested in finishing schools rather than closing out the projects. Mr.Medina asked if the 22 schools scheduled to open this year were completely finished. Mr. Medina also commented on

    school gardens and reported that he visited three schools with gardens. He added that a few months ago the BOCapproved building teaching gardens. After what Mr. Medina saw, he was wondering whether the approved money wouldbe wisely used. Mr. Medina reported on his garden tours.

    Ms. Bar-El requested an update on the portable replacement program. Mr. Sohn responded that based on participationthe program is successful. Approximately 262 portable buildings have been removed or will be removed by the end of thesummer. Mr. Crippens requested Mr. Sohn provide a more detailed report. Regarding the school garden program, Ms.Bar-El noted that last year many of the garden staffing was reduced. Mr. Sohn stated that the green ombudsmen arevolunteers and will be provided a stipend for travel expenses. He added that gardening staff positions dedicated to

    secondary schools were eliminated. Team gardeners were implemented and they visit each school on a regularschedule. Ms. Bar-El asked if there were gardening staff working with the students on gardening programs. Mr. Sohnresponded that characteristics of a successful garden are one that has deep community engagement, support by principaland faculty, and that transcends individual student matriculation. He added that a successful garden is one that complieswith safety and OEHS concerns and is readily accessible and maintainable and supported by the local users. FSDs roleis to provide resources for the installation of the garden. Ms. Bar-El noted that the gardens are set up although there is nostaff to champion the efforts. Mr. Crippens stated that garden staffing is not a FSD function. Ms. Bar-El expressedconcern that good money is being put into projects that are going to be perceived by the schools as a waste when nobodyis taking care of them. Mr. Sohn responded that FSD does not build a garden unless there is deep support by the school

    and community.

    Regarding maintenance and new staffing hours, Ms. Levitan noted that elementary schools often have limitedmaintenance staff and asked if staffing decisions were discussed with the schools principal and administration. Mr. Sohnresponded that they work with the principal to assess needs and provide the necessary coverage.

    For the next BOC meeting, Mr. Widom requested reports on Design/Build and New Maintenance Company.

    Agenda Item 12.Change Order ProcessPresenter: James Sohn, Chief Facilities Executive

    Item postponed to September 15, 2010 BOC meeting.

    Agenda Item 6. New Construction SEP Amendment Capital Improvement Program Reserve Funding for SixProjects Previously To Be Funded By Certificates of ParticipationPresenter: James Sohn, Chief Facilities Executive

  • 8/8/2019 Final BOC Agenda October 20 2010

    8/200

    BOC Meeting, August 18, 2010Page 5

    Abstain: 0

    Resolution 2010-27 Passed Unanimously

    Agenda Item 7. New Construction SEP Amendment Capital Improvement Program Reserve Funding for 29Projects in Board District 3Presenter: Edwin Van Ginkel, Asset Manager

    BOC Resolution 2010-28

    This SEP Amendment is to allocate funds related to the Capital Improvement Program Reserve (CIPR). CIPR allocated$25 million to Board District 3. Through work with principals and the Local District Facilities Director, 29 projects have

    been identified as high priority. These projects are valued at $8.5 million.

    There was a Motion, Second, and vote.

    Aye: 9Nay: 0Absent: 4Abstain: 0

    Resolution 2010-28 Passed Unanimously

    Agenda Item 8. Existing Facilities SEP Amendment Air Conditioning to Currently Non-Air ConditionedGymnasiums at Chatsworth High School and Frost Middle SchoolPresenter: James Sohn, Chief Facilities Executive

    BOC Resolution 2010-29

    This SEP Amendment is for gymnasium air conditioning projects at Frost MS and Chatsworth HS.

    There was a Motion, Second, and vote.

    Aye: 9Nay: 0Absent: 4Abstain: 0

    Resolution 2010-29 Passed Unanimously

    Agenda Item 9.Existing Facilities SEP Amendment Add Eight Alteration and Improvement Projects and BoardMember Priority Projects at Various SchoolsPresenter: Richard Luke, Deputy Director, Asset Management

    Resolution 2010-30

    This SEP Amendment is for eight projects valued at approximately $1 million.

  • 8/8/2019 Final BOC Agenda October 20 2010

    9/200

    BOC Meeting, August 18, 2010Page 6

    Agenda Item 10.Existing Facilities SEP Amendment Funding For Priority Exterior Paint and Refinishing Projectat Fremont High School

    Presenter: Roger Finstad, Acting Direction, Maintenance and Operations

    Resolution 2010-31

    This SEP Amendment is for an exterior painting project at Fremont High School valued at $347,000.

    There was a Motion, Second, and vote.

    Aye: 9Nay: 0

    Absent: 4Abstain: 0

    Resolution 2010-31 Passed Unanimously

    Agenda Item 11. Existing Facilities SEP Amendment Replace Portable Classroom Buildings at LiggettElementary School with One Permanent Two-Story Modular Classroom BuildingPresenter: Edwin Van Ginkel, Asset Manager

    Resolution 2010-32

    This SEP Amendment is to remove 14 portable classrooms at Liggett ES and replace them with an eight classroom twostory modular building. The improvements are estimated to cost $3,991,307.

    There was a Motion, Second, and vote.

    Aye: 9Nay: 0

    Absent: 4Abstain: 0

    Resolution 2010-32 Passed Unanimously

    Agenda Item 13.City of Los Angeles Joint Use UpdatePresenter: Christopher Espinosa, Office of the Mayor, City of Los Angeles

    Item was deleted from the agenda.

    Mr. Crippens invited the BOC members to comment on anything they felt important.

    Regarding the upcoming fiscal year 2010 audit, Mr. Naimo requested Mr. Rubin work with FSD and the outsideauditor to make sure lessons learned in the past two audits are incorporated into the upcoming audit.

    Mr. Medina requested a list of all school gardens.

  • 8/8/2019 Final BOC Agenda October 20 2010

    10/200

    Los Angeles Unified School District

    SCHOOL CONSTRUCTION BOND

    CITIZENS OVERSIGHT

    COMMITTEE

    QUARTERLY REPORT

    JULY - SEPTEMBER 2010

  • 8/8/2019 Final BOC Agenda October 20 2010

    11/200

    LOS ANGELES UNIFIED SCHOOL DISTRICT

    SCHOOL CONSTRUCTION BOND CITIZENS OVERSIGHT COMMITTEE

    David Crippens, ChairL.A. Area Chamber of Commerce

    Elizabeth Bar-El, Vice ChairLAUSD Student Parent(Primary Member)

    John Naimo, SecretaryL.A. County Auditor-ControllersOffice (Primary Member)

    Scott FolsomTenth District PTSAConstance RiceL.A. City Controllers Office

    Joseph P. Buchman Legal CounselBurke, Williams & Sorensen, LLP

    Maria CabildoLAUSD Student Parent(Primary Member)

    Sylvia CunninghamAARP

    Adrian GarciaL.A. Mayors Office

    John Hakel

    Associated General Contractors California (Alternate Member)David JenkinsAssociated General Contractors -California (Primary Member)

    Lynda LevitanThirty-First District PTSA

    Anastacio MedinaBREATHE California

    Thomas A. RubinOversight Committee Consultant

    Richard SlawsonL.A. Co. Federation of Labor,AFL-CIO

    Wendy WatanabeL.A. County Auditor ControllersOffice (Alternate Member)

    Chester WidomAmerican Institute of Architects

    Barry WaiteLAUSD Student Parent(Alternate Member)

    (Vacant)California Taxpayers Association

    (Vacant)Environmental Justice/CivilRights Group

    Gary C. AndersonDirector

    Frank PadillaAdministrator

    Quarterly Report for April June 2010

    I. Overview

    The mission of the School Construction Bond Citizens Oversight Committee (BOC) is to oversee theexpenditure of money for the construction, repair and modernization of schools by the LAUSD and tocommunicate its findings to the Board and the public so that school bond funds are invested as the voters

    intended and that projects are completed wisely and efficiently.

    The shared vision between the BOC and the LAUSD is to build and maintain schools that promote the fulldevelopment of the child, are educationally and environmentally sound, enhance their neighborhoodsthrough design and programming as centers of community, and reflect the wise and efficient use of limitedland and public resources.

  • 8/8/2019 Final BOC Agenda October 20 2010

    12/200

    BOC Quarterly Report for AprilJune 2010Page 2

    2010-15 A Resolution of the School Construction Bond Citizens Oversight Committee

    Supporting LAUSD and its partnership with the Division of the State Architect toStreamline the Close-Out and Certification Process (April 21, 2010).

    2010-17 Existing Facilities Strategic Execution Plan Amendment for 17 Projects in Districts1, 3, 4, 5, 6, 7 and 8 (April 21, 2010).

    2010-18 Planning and Development Branch Strategic Execution Plan Amendment to Authorize

    Use of Measure Y Innovation Funds for School-Based Clinics and Wellness Centers atGarfield, Hollywood, Jefferson, Jordan, Manual Arts and Washington Prep High Schools(April 21, 2010).

    2010-16 Existing Facilities Strategic Execution Plan Amendment Reallocation of Funds ForPortables Projects (May 19, 2010).

    2010-19 Existing Facilities Strategic Execution Plan Amendment for 13 Projects in Districts 1, 3,

    4, 6 and 7 (May 19, 2010).

    2010-20 Planning and Development Strategic Execution Plan Amendment to Authorize Use ofMeasure Y Innovation Funds for a Wellness Center at Locke Early Education Center(May 19, 2010).

    2010-21 Planning and Development Strategic Execution Plan Amendment to Add 18 Proposition39 Charter Renovation Project (May 19, 2010).

    2010-22 Existing Facilities Strategic Execution Plan Amendment for 1 Project in District 1(June 16, 2010).

    2010-23 Existing Facilities Strategic Execution Plan Amendment to Fund Two New ModifiedConsent Decree On-Demand Accessibility Projects (June 16, 2010) .

    2010-25 Recommendation to Approve the 2010 Information Technology Infrastructure StrategicExecution Plan (June 16, 2010).

    III. Resolutions Not Adopted

  • 8/8/2019 Final BOC Agenda October 20 2010

    13/200

    BOC Quarterly Report for AprilJune 2010Page 3

    V. Joint Use Activities

    Funding ($11,100,000) for school based clinics and wellness centers at Garfield, Hollywood,Jefferson, Jordan, Manual Arts and Washington Prep High Schools were approved by the BOC. Thescope of work for Garfield consists of 2,200 square feet of tenant improvements to be constructed inthe schools existing shop building. The area will be converted into a new school based clinic. Thepartner for this project is Bienvenidos Clinic. The scope of work for Hollywood consists of 2,900square feet of tenant improvements to be constructed in the schools existing shop classroom. Thearea will be converted into a new school based clinic. The partner for this project is the Saban Free

    Clinic. The scope of work for Jefferson consists of the purchase and installation of a new 2,000square foot modular building that will be designed as a clinic. The partner for this project is SouthCentral Family Health Center. The scope of work for Jordan consists of purchasing and installing anew 2,000 square foot modular building designed as a clinic. The partner for this project is WattsHealth Care Corporation. The scope of work for Manual Arts consists of the removal and relocationof the counseling and attendance offices to an existing school building to make room for a newmodular. It also includes the purchase and installation of a 1,920 square foot modular buildingdesigned as a clinic. The partner for this project is St. Johns Well Child. The scope of work for

    Washington Prep consists of purchasing and installing of 2,880 square foot modular buildingdesigned as a health clinic. The partner for this project is St. Johns Well Child.

    Funding ($2,150,000) for a Wellness Center at Locke Early Childhood Education Center wasapproved by the BOC. The scope of work includes tenant improvements to 9,211 square feet on thesecond floor of the Locke Early Education Center. The partner for this project is Watts Health CareCorporation.

    VI. Board of Education Presentations

    David Crippens, BOC Chair, addressed the Board of Education at their April 20, 2010 and June 15,2010 meetings and spoke to the following topics:

    April 20, 2010

    Office of Inspector General Bring Back Facilities Committee

    June 15, 2010

  • 8/8/2019 Final BOC Agenda October 20 2010

    14/200

    BOC Quarterly Report for AprilJune 2010Page 4

    The Board of Education (BOE) and Bond Oversight Committee (BOC) have partnered together to

    create a joint taskforce to study BOC membership. The taskforce will examine BOC membership todetermine:

    If the nominating authority for any current BOC member should be changed. If any of the current entities represented on the BOC should be eliminated. If any representative of any additional entities should be added to the BOC. The desirable number of BOC members.

    The Task Force met and interviewed organizations that submitted letters of interest in becoming to become BOC nominating authorities. The Task Force will continue to meet and is scheduled toissue their report at the August 18, 2010 BOC meeting.

    The BOC Measure Q Planning Task Force. This Task Force will issue a report that details an actionplan for oversight in the planning of Measure Q expenditures for modernization programs. The TaskForce will develop an action plan with strategic steps for improvement in stakeholder participation,

    examining related reports and reviewing alternative program models and trends, hearing various presenters on issues in the Measure Q modernization program, and discussing preliminary actionplans.

    The BOC Lessons Learned Task Force. This Task Force is chaired by Scott Folsom and will includeinput from various District departments (e.g. Office of Instruction, Community Outreach, etc.). ThisTask Force will be looking at the lessons learned process. The first meeting was held June 25, 2010.

    VIII. New Construction

    131new school projects: 92 new school projects have been completed. 36 new school projects are currently under construction. 98,900 seats have been delivered. 28 schools remain on a Concept 6 Calendar.

    87 schools remain on a Multi-Track Calendar. 5 schools remain on involuntary busing.

    The following new schools are scheduled to open in September 2010: Central LA New Learning Center #1 MS/HS; Central Region ES #13; Central Region ES #15;

    C l R i ES #16 d EEC #1

  • 8/8/2019 Final BOC Agenda October 20 2010

    15/200

    BOC Quarterly Report for AprilJune 2010Page 5

    South Region ES #7; South Region MS #2; South Region MS #6; Valley Region ES #10; Valley Region ES #6; Valley Region ES #7; Valley Region ES #8; Valley Region ES #9; Valley Region ES #12.

    IX. Modernization

    The Capital Improvement Program includes 22,099 projects valued at $4.704 billion; 19,467 projectshave been completed.

    Current change order rate is 8.9%; existing facilities has a change order goal of 5%; the industrystandard for existing facilities is 10%.

    BB Bond Program is 97% complete with regard to project value and 99% complete with regard toproject count.

    Measure K Program is 61% complete with regard to project value and 87% complete with regard toproject count.

    Measure R Program is 44% complete with regard to project value and 68% percent complete withregard to project count.

    Measure Y Program is 31% complete with regard to project value and 52% complete with regard toproject count.

    X. Committee MemberAppointments/Resignations/Elections

    The annual election for BOC officers was held at the June 16, 2010 BOC meeting. David Crippens waselected Chair, Elizabeth Bar-El was elected Vice Chair, and John Naimo was elected Secretary. The two

    at large Executive Committee positions went unchanged. These positions are currently filled by ScottFolsom and Constance Rice.

    There are currently two vacancies on the BOC, a California Taxpayers Association representative andEnvironmental Justice/Civil Rights Group representative.

  • 8/8/2019 Final BOC Agenda October 20 2010

    16/200

    BOC Quarterly Report for AprilJune 2010Page 6

    Services Division and reflects the status as of June 15, 2010. The monthly status report for ExistingFacilities (Exhibit 3) was provided to the BOC by the LAUSD Facilities Services Division and reflects the

    status as of June 1, 2010.

    XII. BOC Budget

    The BOCs Annual Budget for the July 1, 2009-June 30, 2010 Fiscal Year is $540,712.00. Actualexpenditures through June 2010 were $491,427.00 or 91% of the budget.

    Third Quarter* (FY) YTD Budget

    Legal 14,399.00 70,203.00 110,146.00

    Consultant 39,318.00 163,000.00 163,000.00

    Office 83,980.00 258,224.00 267,566.00Totals $137,697.00 $491,427.00 $540,712.00

    *Fourth quarter fiscal expenses occurred during the second quarter of calendar year 2010

    XIII. BOC Member Requests

    The following requests were made by BOC members during the quarter:

    Ms. Bar-El requested a report on why Small Learning Community and Joint Use change orders were

    so high. (Done; May 2010) Mr. Folsom requested a flow chart of how the new Clean Schools Initiative would be implemented.

    (Done; June 2010)

    Mr. Naimo requested a report on change orders. (Done; September 2010)

    Mr. Naimo requested an update on assessed valuation from Beacon Economics. (Scheduled forOctober 2010)

    Regarding the portable removal program, the BOC requested a regular monthly update. (Done;September 2010)

    Mr. Crippens requested a Proposition 39 presentation at the October 2010 Regular BOC Meeting.(Scheduled for future BOC meeting)

    Mr. Widom requested a copy of the RFQ for the Dorsey HS Redevelopment Project. (Done; June

  • 8/8/2019 Final BOC Agenda October 20 2010

    17/200

    BOC Quarterly Report for AprilJune 2010Page 7

    Agenda Item #10 Planning and Development SEP Amendment Joint Use Clinic at LockeECEC

    Sandra N. Jones, Watts Healthcare CorporationSandy Escobedo, California Community FoundationMelina Sanchez, California Community FoundationIdaht Gonzalez, Proyecto Pastoral

    Agenda Item #12 Public Comment

    Tommy Chang, California Charter Schools Association

    BOC Meeting June 16, 2010

    The following person addressed the BOC:

    Agenda Item #11 Public Comment

    Gary Mitten, Community MemberBill Ring, Community MemberYolanda Beckles, ParentMud Baron, Board Member LaMottes Office

    XV. Public Meetings

    For the matters contained in the Quarterly Report, the BOC held four public meetings. These meetingswere held on April 21, 2010, May 19, 2010, and June 16, 2010. The record of the BOC membersattendance for these meetings and all other meetings during the 12-month prior ending June 2010 can befound in Exhibit 1.

    XVI. Public Access

    Agendas, resolutions, approved minutes, as well as information regarding BOC committee members maybe accessed at: http://www.laschools.org/bond.

  • 8/8/2019 Final BOC Agenda October 20 2010

    18/200

    Index Of Exhibits For Quarterly Report For April - June 2010

    Exhibit No. Description

    1 BOC Meeting Attendance Record For 12 Months Ending June 2010

    2LAUSD Facilities Services Division Monthly Status Report For NewConstruction Reflecting Status Of Program As Of July 15, 2010

    3LAUSD Facilities Services Division Monthly Status Report For ExistingFacilities Reflecting Status Of Program As Of July 1, 2010

    4Office of Inspector General Follow-Up Report on Simpson & Simpson

    CPAs Agreed Upon Procedures Reports for Fiscal Years 2008 and 2009

  • 8/8/2019 Final BOC Agenda October 20 2010

    19/200

    Exhibit 1

  • 8/8/2019 Final BOC Agenda October 20 2010

    20/200

    Bond Oversight Committee Meeting AttendanceFor 12 Months Ending June 2010

    LA #4838-7901-8496 v1

    Name 07/08/09(Regular)

    08/19/09(Regular)

    09/16/09(Regular)

    09/30/09(Regular)

    10/21/09(Regular)

    11/18/09(Regular)

    12/16/09(Regular)

    01/20/10(Regular)

    02/17/10(Regular)

    03/17/10(Regular)

    04/21/10(Regular)

    05/19/10(Regular)

    06/16/10(Regular)

    Bar-El, Elizabeth(LAUSD Student Parent) -- Bergson, Charles(LAUSD Student Parent) -- -- -- -- -- -- -- -- -- -- --Cabildo, Maria (LAUSD Student Parent) -- -- -- -- -- -- -- -- Crippens, David(L.A. Chamber of Commerce) Cunningham, Sylvia(AARP) Espinosa, Christopher(L.A. Mayors Office) -- -- -- -- -- --Folsom, Scott (Tenth District PTSA) Garcia, Adrian (L.A. Mayors Office) -- -- -- -- -- -- -- -- -- Hakel, John* (Associated General Contractors Ca)

    Jenkins, David** (Associated General Contractors Ca) Levitan, Lynda(Thirty-First District PTSA) Medina, Anastacio (BREATHE California) Naimo, John* (LA County Auditor/Controllers Office) Rice, Constance (L.A. City Controllers Office) Slawson, Richard (L.A. County Fedn of Labor, AFL-CIO) Tanzmann, Virginia(American Institute of Architects) -- -- -- -- -- -- -- -- -- -- -- --Valles, Betty (AARP) -- -- -- -- -- -- -- -- --Waite, Barry** (LAUSD Student Parent) -- -- -- -- -- -- -- --

    Watanabe, Wendy**(LA County Auditor/Controllers Office) Widom, Chester(American Institute of Architects) -- -- -- -- -- --

    = Present = Absent

    -- = Non-Committee Member at time of Meeting*Primary Member **Alternate Member

  • 8/8/2019 Final BOC Agenda October 20 2010

    21/200

    Exhibit 2

  • 8/8/2019 Final BOC Agenda October 20 2010

    22/200

    F AC I L I T I E S S ERV I C E S D I V I S I ON

    Monthly Program Status Report

    NEW CONSTRUCTION

  • 8/8/2019 Final BOC Agenda October 20 2010

    23/200

    Los Angeles Unified School District

    F A C I L I T I E S S E R V I C E S D I V I S I O N , N E W C O N S T R U C T I O N

    Monthly Program Status ReportNEW CONSTRUCTION

    TABLE OF CONTENTS

    Program Status Key Deliverables ......................................................................2

    K-12 Program Status ............................................................................................3

    Event Status .......................................................................................................14

    Appendix

    Bid Results ...............................................................................................16

    Projects Under Construction.....................................................................17

    Completed Projects ..................................................................................20

    Federal Stimulus Bond Status ..................................................................22

    Project Milestone Listing by Board Member District .................................23

  • 8/8/2019 Final BOC Agenda October 20 2010

    24/200

    Los An eles Unified School District

    F AC I L I T I E S S ERV I C E S D I V I S I ON , NEW CON ST RUC T I ON

    Key Deliverables

    0

    25

    50

    75

    100

    125

    150

    175

    200

    225

    250

    03 04 05 06 07 08 09 10 11 12 13

    Schools on Multi-Track Calendar

    33

    134

    0

    20

    40

    60

    80

    100

    120

    140

    160

    04 05 06 07 08 09 10 11 12 13 14

    Anticipated Seat Delivery (Thousands)

    100.7

    109.1

    NEW CONSTRUCTION PROGRAM STATUS

    0

    20

    40

    60

    80

    100

    120

    140

    160

    2003

    -200

    4

    2004

    -200

    5

    2005

    -200

    6

    2006

    -2007

    2007

    -200

    8

    2008

    -200

    9

    2009

    -201

    0

    2010

    -201

    1

    2011

    -201

    2

    Schools With Involuntary Busing

    5

    17 Pre-Norm DayEstimate

    0

    20

    40

    60

    80

    100

    120

    140

    160

    2003

    -200

    4

    2004

    -200

    5

    2005

    -200

    6

    2006

    -2007

    2007

    -200

    8

    2008

    -200

    9

    2009

    -201

    0

    2010

    -201

    1

    2011

    -201

    2

    2012

    -201

    3

    Schools on Concept 6 Calendar

    8

    47

  • 8/8/2019 Final BOC Agenda October 20 2010

    25/200

    Los An eles Unified School District

    F AC I L I T I E S S ERV I C E S D I V I S I ON , NEW CON ST RUC T I ON

    3

    DesignatedSites

    PendingAcquisitionor Vacancy

    1

    SitesPendingBoard

    Designation

    SitesOwned orControlled

    andVacant

    Real Estate

    35

    UnderConstruction

    11

    Pre-Construction

    176

    ConstructionComplete

    Construction

    DSA Approved

    In DesignProcess

    PendingStart ofDesign

    Design

    33

    216

    NEW CONSTRUCTION K-12 PROGRAM STATUS REPORTS

    $0.5

    Future StateMatch (2)

    $11.4

    Funding

    On-Hand(1)

    Funding($ Billions)

    222 Projects

    (1) Total funding from all sources. Excludes $675 million of localbonds that cannot be issued due to LAUSD's debt limit.

    (2) Based on current eligibility rules.

    No changes since last report.

  • 8/8/2019 Final BOC Agenda October 20 2010

    26/200

    Los An eles Unified School District

    F AC I L I T I E S S ERV I C E S D I V I S I ON , NEW CON ST RUC T I ON

    PROGRAM RESERVE STATUS REPORT

    Program reserve funds are required to cover costs related to unforeseen site conditions, unanticipated scopechanges and cost escalation above anticipated amounts. All changes in sources of funds or uses of fundsaffect the Program Reserve balance.

    The assessed value of real property within the Districts boundaries is anticipated to decrease for the next

    $0

    $200

    $400

    $600

    $800

    $1,000

    $1,200

    $1,400

    $1,600

    $303 $321 $310$352

    $703

    $568 $582 $592 $603

    $340 $320 $320

    $1,043 $1,061 $1,050$1,092

    $1,443

    July-

    09

    Aug-09

    Sep-09

    Oct-0

    9

    Nov-09

    Dec-09

    Jan-10

    Feb-

    10

    Mar

    -10

    Apr-1

    0

    May

    -10

    Jun-10

    $inMillions

    Program Reserve

    Program Reserve not available due toLAUSD's Debt Limit

    Available Program Reserve

    $740$740

    $740

    $740$740

    $77

    Unallocated CIPR

    $35 $77

  • 8/8/2019 Final BOC Agenda October 20 2010

    27/200

    Los An eles Unified School District

    F AC I L I T I E S S ERV I C E S D I V I S I ON , NEW CON ST RUC T I ON

    PROGRAM EXECUTIVE NOTES

    REAL ESTATE

    Recent Board Actions

    The following items were approved by the Board of Education on June 22, 2010:

    o CEQA certification and project approval for CHIME Charter

    o 17250 project delivery method for Dorsey HS Redevelopment

    The following items were approved by the Board of Education on July 13, 2010:

    o Addendum to the Final Environmental Impact Report, Revised Findings of Fact and Statement of OverridingConsiderations for South Region HS #8

    o Authorization to enter into a Memorandum of Understanding (MOU) and Cooperative Development Agreementwith the City of Los Angeles related to site improvements and interactions between Angels Gate Park and South

    Region HS #15

    o Establishment of a Citizens Advisory Committee, as the first step in the disposition of surplus property, to conductreview meetings and advise the District on properties which may not be needed for school purposes and could beidentified for sale

    Pending Board Items

    The following items are planned for presentation to the Board of Education in September 2010:

    o CEQA certification and project approval for 9th St. Span K-8 Redevelopment

    o Joint use school-based clinic for Dorsey HS Redevelopment

    o Authorization for staff to enter into a development agreement for the delivery of Valley Region MS #3 pursuant tothe requirements of Education Code Section 17406

    o Resolutions of intention to dedicate easements for:

    Central Region HS #13

    Central Region MS #7

    Valley Region ES #13

    Site Acquisition Activities

  • 8/8/2019 Final BOC Agenda October 20 2010

    28/200

    Los An eles Unified School District

    F AC I L I T I E S S ERV I C E S D I V I S I ON , NEW CON ST RUC T I ON

    PROGRAM EXECUTIVE NOTES

    REAL ESTATE - cont'd

    Program Activities

    The Real Estate Department is currently managing 10 New Construction projects through the preconstruction phaseand has transitioned a total of 61 projects to the Construction Department as of July 15, 2010. After projects arehanded over, we continue working to resolve project issues such as finalizing pending eminent domain cases,

    relocating remaining occupants on the site, and completing offsite improvements, dedications/easements, and streetand alley vacations. In addition, we file state funding applications and provide responses to the states review as wellas provide information during the states annual and final audits.

  • 8/8/2019 Final BOC Agenda October 20 2010

    29/200

    Los An eles Unified School District

    F AC I L I T I E S S ERV I C E S D I V I S I ON , NEW CON ST RUC T I ON

    PROGRAM EXECUTIVE NOTES

    DESIGN MANAGEMENT

    Current Design Activities

    Recent Activities:

    o DSA continues to have resource challenges due to staff reductions and furloughs, and have eliminated the

    use of consultant plan reviewers. These resource challenges have caused DSA to rescind the partnering

    agreement with LAUSD. Plan review durations are expected to extend 8 weeks beyond the durations

    indicated in the partnering agreement.

    o Design Management is currently managing the 100% construction document phase for South Region HS #8,which is scheduled for an August 2010 submittal to the DSA.

    o Design Management is currently managing the 50% construction document phase for 9th St. Span K-8Redevelopment.

    o Design Management is managing A/E contracts through completion of construction on all remaining Phase

    2, 3 and 4 projects.

    o Design Management is implementing a program to monitor the effectiveness of the high performance

    features of our newly constructed schools including:

    Indoor environmental quality

    Energy use

    Water use Student API

    Student and staff absenteeism

    A lump sum proposal is under review to provide these services.

    Currently at the DSA under review:

    o South Region HS #15 - Pool and Pool Building

    o Bell Education Centero South Region HS #6 (Middle College HS)

    Future DSA Submittals:

    o South Region HS #8 has been accelerated and will be submitted in August 2010

    9th St Span K 8 Redevelopment will be submitted in September 2010

  • 8/8/2019 Final BOC Agenda October 20 2010

    30/200

    Los An eles Unified School District

    F AC I L I T I E S S ERV I C E S D I V I S I ON , NEW CON ST RUC T I ON

    PROGRAM EXECUTIVE NOTES

    Design Management Priorities

    A/E technical support for construction in the field.

    Savings by Design program participation with Southern California Edison; this effort to receive grant money forimplementing energy-saving features applies to both new and modernization projects.

    High Performance Incentive Grant Program, access supplemental state funding through Proposition 1D.

    CHPS verification during construction.

    LEED certification for four select projects.

    DESIGN MANAGEMENT - cont'd

  • 8/8/2019 Final BOC Agenda October 20 2010

    31/200

    Los An eles Unified School District

    F AC I L I T I E S S ERV I C E S D I V I S I ON , NEW CON ST RUC T I ON

    Construction Summary

    With 94 new K-12 schools completed, construction continues on 32 new K-12 schools, 1 EEC, and 3 additions.Procurement activities continue for the selection of contractors under the 17406 bid and award process. In the past month,a Request for Qualifications was released for Valley Region MS #3 and three contractors were short-listed for ValleyRegion ES #13.

    The Board approved two new 17406 contracts for construction at the July 13, 2010 Board meeting: Central Region ES #21and Valley Region Span K-8 #1.

    Substantial completion was achieved on two new schools opening in 2010: South Region ES #4 and South Region ES #7.

    Qualified Construction Management (Agency CM) firms are competing to provide construction management services forselected construction projects. Priced proposals from these Agency CM firms selected during the first procurement cyclefor nine projects were received on July 13, 2010. Review of cost proposals and contract negotiations will extend throughthe end of July.

    Proposals have been solicited from Agency CM firms for the remaining projects. Proposals are due July 20th, firms will beshort-listed July 27th, and interviews will take place August 5th.

    The following twenty-one new schools are currently scheduled to open in September 2010:

    Central Region

    Central LA New Learning Center #1 MS/HS

    Central Region ES #13

    Central Region ES #15

    Central Region ES #16 & EEC #1

    Central Region ES #17

    Central Region ES #18

    East LA HS #2

    Gratts New PC and Central Region Gratts EEC

    South Region

    South Region ES #1 South Region ES #2

    South Region ES #3 & EEC #1

    South Region ES #4 & EEC #2

    South Region ES #7

    South Region MS #2

    PROGRAM EXECUTIVE NOTES

    CONSTRUCTION

  • 8/8/2019 Final BOC Agenda October 20 2010

    32/200

    Los An eles Unified School District

    F AC I L I T I E S S ERV I C E S D I V I S I ON , NEW CON ST RUC T I ON

    120

    140

    160

    180

    200

    220

    9 9 0 0

    Projects

    Legal Possession of Property

    218 projectsas of July 15, 2010

    120

    140

    160

    180

    200

    220

    Q4-20

    08

    Q1-20

    09

    Q2-20

    09

    Q3-

    2009

    Q4-20

    09

    Q1-20

    10

    Q2-20

    10

    Q3-

    2010

    Q4-20

    10

    Projects

    Board Designation of Preferred Sites

    221 projects

    as of July 15, 2010

    REAL ESTATE

    PRE-CONSTRUCTION

    On schedule.

  • 8/8/2019 Final BOC Agenda October 20 2010

    33/200

    Los An eles Unified School District

    F AC I L I T I E S S ERV I C E S D I V I S I ON , NEW CON ST RUC T I ON

    ENVIRONMENTAL

    120

    140

    160

    180

    200

    220

    4-2008

    1-2009

    2-2009

    3-2009

    4-2009

    1-2010

    2-2010

    3-2010

    4-2010

    Projects

    Property Cleared and Environmental Clearance Achieved for Construction

    211 projectsas of July 15, 2010

    120

    140

    160

    180

    200

    220

    Q4-20

    08

    Q1-20

    09

    Q2-20

    09

    Q3-

    2009

    Q4-20

    09

    Q1-20

    10

    Q2-20

    10

    Q3-

    2010

    Q4-20

    10

    Projects

    CEQA Approval

    218 projects

    as of July 15, 2010

    PRE-CONSTRUCTION

    On schedule.

  • 8/8/2019 Final BOC Agenda October 20 2010

    34/200

    Los An eles Unified School District

    F AC I L I T I E S S ERV I C E S D I V I S I ON , NEW CON ST RUC T I ON

    DESIGN

    120

    140

    160

    180

    200

    220

    Q4-20

    08

    Q1-20

    09

    Q2-20

    09

    Q3-

    2009

    Q4-20

    09

    Q1-20

    10

    Q2-20

    10

    Q3-

    2010

    Q4-20

    10

    Projects

    A/E Contract Award

    219 projects

    as of July 15, 2010

    120

    140

    160

    180

    200

    220

    Q4-20

    08

    Q1-20

    09

    Q2-20

    09

    Q3-20

    09

    Q4-20

    09

    Q1-20

    10

    Q2-20

    10

    Q3-20

    10

    Q4-20

    10

    Projects

    DSA Approval

    216 projectsas of July 15, 2010

    PRE-CONSTRUCTION

    On schedule.

  • 8/8/2019 Final BOC Agenda October 20 2010

    35/200

    Los An eles Unified School District

    F AC I L I T I E S S ERV I C E S D I V I S I ON , NEW CON ST RUC T I ON

    120

    140

    160

    180

    200

    220

    Q4-20

    08

    Q1-20

    09

    Q2-20

    09

    Q3-

    2009

    Q4-20

    09

    Q1-20

    10

    Q2-20

    10

    Q3-

    2010

    Q4-20

    10

    Projects

    Project Completion

    176 projectsas of July 15, 2010

    120

    140

    160

    180

    200

    220

    Q4-20

    08

    Q1-20

    09

    Q2-20

    09

    Q3-

    2009

    Q4-20

    09

    Q1-20

    10

    Q2-20

    10

    Q3-

    2010

    Q4-20

    10

    Projects

    Construction Contract Awards

    211 projects

    as of July 15, 2010

    CONSTRUCTION

    Ahead of schedule by 7 projects.

  • 8/8/2019 Final BOC Agenda October 20 2010

    36/200

    Los An eles Unified School District

    F AC I L I T I E S S ERV I C E S D I V I S I ON , NEW CON ST RUC T I ON

    Events Since Last Report

    Ribbon-Cutting Ceremony - Ramona Opportunity HS06/17/10

    Construction Update / Meet the Principal - Central Region ES #16 and Central Region EEC #106/24/10

    Anticipated Future Events (30-Day Lookahead)

    Construction Update / Meet the Principal - Valley Region ES #908/03/10

    Construction Update / Meet the Principal - South Region ES #108/03/10

    Construction Update / Meet the Principal - South Region MS #608/12/10

    Bid Openings

    Central Region Glassell Park EECJul-10

    East LA Star HS AcademyJul-10

    Construction Contract Awards

    Central Region ES #21Jul-10

    Valley Region Span K-8 #1Jul-10

  • 8/8/2019 Final BOC Agenda October 20 2010

    37/200

    Los An eles Unified School District

    F AC I L I T I E S S ERV I C E S D I V I S I ON , NEW CON ST RUC T I ON

    Bid Results

    Projects Under Construction

    Completed Projects

    Federal Stimulus Bond Status (BAB and QSCB)

    Project Milestone Listing by Board Member District

    APPENDIX

  • 8/8/2019 Final BOC Agenda October 20 2010

    38/200

  • 8/8/2019 Final BOC Agenda October 20 2010

    39/200

    Los An eles Unified School District

    F AC I L I T I E S S ERV I C E S D I V I S I ON , NEW CON ST RUC T I ON

    TotalCompleted

    Completedthis

    MonthUnder

    ConstructionSchool Type

    New School

    0 5Continuation High School 0

    1 4Early Education Center 1

    2 39Elementary School 13

    0 17High School 13

    0 9Middle School 20 0MS/HS 1

    0 23Primary Center 1

    0 1Span K-8 School 2

    Addition

    0 31Early Education Center 0

    0 51Elementary School 3

    0 8High School 0

    0 1Middle School 0

    Others0 0Early Education Center 0

    0 1Elementary School 0

    0 1High School 0

    0 2Other 0

    0 17Playground Expansion 0

    0 1Span 6-12 School 0

    3 21136

    PROJECTS UNDER CONSTRUCTION

    Project Name SeatsStartDate

    AnticipatedCompletion

    OriginalContractAmount

    CurrentContractAmount

    TotalChangeOrder %

    UserChangeOrder % Contractor

    Clark ConstructionGroup, LLC

    $144,801,180 $145,027,560 %0.162010-Q311/27/07 %0.14East LA HS #2 2,322

    Hensel PhelpsConstruction Co.

    $322,722,155 $322,722,155 %0.002010-Q312/13/07 %0.00Central LA New Learning Center #1MS/HS

    3,440

    Summit Builders$31,630,000 $32,854,470 %3.872010-Q301/03/08 %0.14Central Region ES #13 875

    Summit Builders$34,140,000 $38,001,893 %11.312010-Q303/10/08 %0.57Gratts New PC 400

    Summit Builders%0.002010-Q303/10/08 %0.00Central Region Gratts EEC (ii) N/A N/A175

    Turner Construction Co$107 548 350 $107 548 350 %0 002010 Q405/07/08 %0 00Valley Region HS #5 2 160

  • 8/8/2019 Final BOC Agenda October 20 2010

    40/200

    Los An eles Unified School District

    F AC I L I T I E S S ERV I C E S D I V I S I ON , NEW CON ST RUC T I ON

    PROJECTS UNDER CONSTRUCTION

    Project Name SeatsStartDate

    AnticipatedCompletion

    OriginalContractAmount

    CurrentContractAmount

    TotalChangeOrder %

    UserChangeOrder % Contractor

    Turner Construction Co.$122,173,800 $123,808,246 %1.342011-Q206/12/08 %1.00Central Region HS #13 2,295

    Clark ConstructionGroup, LLC

    $81,149,250 $82,822,426 %2.062011-Q206/30/08 %0.01Central Region MS #7 1,350

    Sinanian Development$26,777,000 $28,208,304 %5.352010-Q307/29/08 %0.00Valley Region ES #12 650

    McCarthy BuildingCompanies, Inc.

    $95,571,087 $96,207,195 %0.672011-Q209/08/08 %0.00South Region HS #2 2,025

    Turner Construction Co.$48,379,800 $48,514,800 %0.282011-Q209/08/08 %0.00Valley Region HS #9 810

    Turner Construction Co.$94,676,344 $95,231,981 %0.592011-Q312/10/08 %0.00Central Region HS #16 2,025

    2H Construction$5,648,000 $5,850,017 %3.582011-Q203/24/09 %0.88Valley Region Blythe ES Addition 400

    Clark ConstructionGroup, LLC

    $86,299,500 $86,299,500 %0.002012-Q206/11/09 %0.00South LA Area New HS #3 2,025

    Swinerton Builders$29,378,042 $29,378,042 %0.002011-Q207/15/09 %0.00Central Region ES #14 875

    Suffolk Construction Co.,Inc.

    $28,201,885 $28,201,885 %0.002011-Q207/20/09 %0.00South Region ES #6 950

    Suffolk Construction Co.,Inc.

    $75,529,233 $76,274,326 %0.992012-Q209/08/09 %0.00South Region HS #12 2,025

    McCarthy BuildingCompanies, Inc.

    $66,465,087 $66,465,087 %0.002012-Q211/24/09 %0.00South Region HS #7 1,620

    Tilden-Coil Constructors,Inc.

    $37,588,950 $37,588,950 %0.002012-Q212/02/09 %0.00South Region Span K-8 #1 1,278

    Turner Construction Co.$58,741,718 $58,912,287 %0.292012-Q201/12/10 %0.00South Region HS #9 1,431

    Pinner Construction, Inc.$62,640,567 $62,881,429 %0.382012-Q201/12/10 %0.00South Region HS #15 810

    Suffolk Construction Co.,Inc.

    $37,174,029 $37,174,029 %0.002012-Q203/09/10 %0.00South Region MS #3 1,026

  • 8/8/2019 Final BOC Agenda October 20 2010

    41/200

    Los An eles Unified School District

    F AC I L I T I E S S ERV I C E S D I V I S I ON , NEW CON ST RUC T I ON

    PROJECTS UNDER CONSTRUCTION

    Project Name SeatsStartDate

    AnticipatedCompletion

    OriginalContractAmount

    CurrentContractAmount

    TotalChangeOrder %

    UserChangeOrder % Contractor

    Kemp Bros., Inc.$23,551,841 $23,551,841 %0.002012-Q205/11/10 %0.00South Region ES #12 800

    Sinanian Development$17,765,475 $17,765,475 %0.002012-Q205/26/10 %0.00Central Region MacArthur Park ESAddition

    350

    Taisei ConstructionCorporation

    $19,768,847 $19,768,847 %0.002012-Q206/08/10 %0.00South Region ES #10 650

    Sundt ConstructionCompany

    $21,517,443 $21,517,443 %0.002012-Q206/08/10 %0.00South Region ES #9 650

    Summit Builders$25,307,540 $25,307,540 %0.002012-Q206/09/10 %0.00South Region ES #5 950

    $2,092,577,542Grand Totals $2,108,933,851 %0.78 %0.11

    (ii) Included with another project

    36 Projects

    (i) New since last report

    42,613 $2,092,577,542 $2,108,933,851

  • 8/8/2019 Final BOC Agenda October 20 2010

    42/200

    Los An eles Unified School District

    F AC I L I T I E S S ERV I C E S D I V I S I ON , NEW CON ST RUC T I ON

    FinalContractAmount

    UserChangeOrder %

    TotalChangeOrder %

    PROJECT COMPLETION

    PROJECTS COMPLETED PRIOR TO 2010

    Seats

    OriginalContractAmount

    Total Number of ProjectsCompleted Prior to 2010

    Renovation 4 1,841 $71,185,500 $90,037,132 %26.48 %2.69

    All Other Projects 193 90,901 $2,410,808,425 $2,622,564,193 %8.78 %0.39

    197 %0.46$2,712,601,325$2,481,993,92592,742Total %9.29Projects

    PROJECT COMPLETION

    PROJECTS COMPLETED FROM 2010 FORWARD

    Project Name

    Original

    ContractAmountSeats

    Total

    ChangeOrder %

    User

    ChangeOrder %

    Date

    Complete

    Final

    ContractAmount

    %0.00800 2010-Q1 %0.00Valley Region ES #9 $36,493,528 $36,493,528

    %4.59575 2010-Q1 %0.53Central Region ES #15 $33,998,000 $35,557,611

    %0.00175 2010-Q1 %0.00South Region EEC #1 (ii) N/A N/A

    %10.31775 2010-Q1 %0.09South Region ES #3 $43,472,000 $47,952,024

    %0.00175 2010-Q1 %0.00Central Region EEC #1 (ii) N/A N/A

    %1.33675 2010-Q1 %0.74Central Region ES #16 $33,373,000 $33,816,069

    %0.00950 2010-Q2 %0.00Valley Region ES #6 $40,597,283 $40,597,283

    %5.861,050 2010-Q2 %0.64South Region ES #2 $43,978,000 $46,555,801

    %4 181 404 2010-Q2 %0 11South Region MS #6 $74 985 000 $78 118 601

  • 8/8/2019 Final BOC Agenda October 20 2010

    43/200

    Los An eles Unified School District

    F AC I L I T I E S S ERV I C E S D I V I S I ON , NEW CON ST RUC T I ON

    PROJECT COMPLETION

    PROJECTS COMPLETED FROM 2010 FORWARD

    Project Name

    OriginalContractAmountSeats

    TotalChangeOrder %

    UserChangeOrder %

    DateComplete

    FinalContractAmount

    %0.00175 2010-Q3 %0.00South Region EEC #2 (i) (ii) N/A N/A

    %6.78775 2010-Q3 %0.13South Region ES #4 (i) $42,242,000 $45,107,888

    %4.46Completion Totals 10,458

    Projects

    $476,956,911 %0.27

    (i) New this month(ii) Included with another project

    $498,205,471

    14

    Summary Totals

    TotalChangeOrder %

    OriginalContractAmountSeats

    UserChangeOrder %

    FinalContractAmount

    GRAND TOTAL - PROJECT COMPLETION

    RenovationProjects $90,037,132$71,185,5004 1,841 %26.48 %2.69

    All Other ProjectsProjects $3,120,769,664$2,887,765,336207 101,359 %8.07 %0.37

    Projects $3,210,806,796$2,958,950,836Grand Total

    211 %8.51103,200 %0.43

  • 8/8/2019 Final BOC Agenda October 20 2010

    44/200

    Los An eles Unified School District

    F AC I L I T I E S S ERV I C E S D I V I S I ON , NEW CON ST RUC T I ON

    FEDERAL STIMULUS BOND STATUS BAB AND QSCB

    Remainingto Spend

    %Expended

    Expenditures asof 7/15/10

    AmountIssued*

    Local BondMeasure Bond Type

    $199,898,054Build America BondsMeasure K $199,783,489%0.1$114,565

    $840,218,663Build America BondsMeasure R $840,218,663%0.0$0

    $1,579,005,124Build America BondsMeasure Y $1,578,240,939%0.0$764,184$608,594,112Qualified School Construction BondMeasure Y $477,837,155%21.5$130,756,957

    $3,227,715,953 $131,635,706 $3,096,080,247%4.08

    *net cost of issuance

    In October 2009, LAUSD sold $1.97 billion in Measure K, Measure R and Measure Y General Obligation Bonds (GO Bonds). Anadditonal $1.84 billion was sold in February 2010, and another $449 million in April 2010.

    The GO Bonds included traditional tax exempt bonds as well as Build America Bonds (BABs) and Qualified School ConstructionBonds (QSCBs). BABs and QSCBs are special bond structures authorized by the federal government through the AmericanRecovery and Reinvestment Act of 2009 (Federal stimulus). BABs are taxable municipal bonds where the federal government paysstate or local government issuers a payment equal to 35% of the interest payments on those bonds, intended to lower the issuerscost of borrowing. QSCBs provide federal tax credits for bondholders in lieu of interest in order to reduce an issuers cost ofborrowing. QSCBs must be spent within three years of issuance.

    The table above shows the amount of BABs and QSCBs issued by LAUSD, how much has been spent and how much is remainingto spend.

    l ifi d h l i i

  • 8/8/2019 Final BOC Agenda October 20 2010

    45/200

    Los An eles Unified School District

    F AC I L I T I E S S ERV I C E S D I V I S I ON , NEW CON ST RUC T I ON

    PROJECT MILESTONE LISTING BY BOARD MEMBER DISTRICT

    Project SchoolOccupancy

    Notice toProceed

    Construction

    PreferredSite

    SelectedProject/CEQA

    ApprovalDSA

    Approval

    Board District: 1 Board Member: Marguerite Poindexter LaMotte

    05/09/2007 09/13/201056.40001 - Central Region ES #13 11/09/2004 01/24/2006 01/03/2008

    12/31/2011 09/03/201356.40097 - Dorsey HS Redevelopment 04/13/2010 03/31/2011 12/31/2011

    10/14/2008 09/04/201255.98047 - South LA Area New HS #3 11/28/2006 02/26/2008 06/11/2009

    01/12/2007 09/13/201056.40014 - South Region ES #1 07/22/2004 10/11/2005 12/03/2007

    10/15/2009 09/04/201256.40078 - South Region ES #10 05/27/2008 02/10/2009 06/08/2010

    10/14/2009 09/04/201256.40079 - South Region ES #11 03/11/2008 12/09/2008 05/11/2010

    10/14/2008 09/06/201156.40062 - South Region ES #6 11/28/2006 01/08/2008 07/20/2009

    08/28/2008 09/04/201256.40066 - South Region HS #12 02/14/2006 02/26/2008 09/08/2009

    09/30/2010 03/31/201256.40021 - South Region HS #6 02/12/2008 11/30/2009 09/30/2010

    03/27/2007 09/13/201056.40025 - South Region MS #6 02/08/2005 01/24/2006 12/24/2007

    L A l U ifi d S h l Di i

  • 8/8/2019 Final BOC Agenda October 20 2010

    46/200

    Los An eles Unified School District

    F AC I L I T I E S S ERV I C E S D I V I S I ON , NEW CON ST RUC T I ON

    PROJECT MILESTONE LISTING BY BOARD MEMBER DISTRICT

    Project

    Notice toProceed

    ConstructionSchool

    Occupancy

    PreferredSite

    SelectedProject/CEQA

    ApprovalDSA

    Approval

    Board District: 2 Board Member: Mnica Garca

    06/30/2011 09/03/201356.40095 - 9th St. Span K-8 Redevelopment 09/08/2009 09/30/2010 09/30/2011

    10/15/2007 09/13/201055.98046 - Central LA New Learning Center #1 MS/HS 12/10/2002 10/12/2004 12/13/2007

    12/21/2006 09/13/201056.40003 - Central Region ES #15 11/02/2004 10/11/2005 12/24/2007

    05/01/2007 09/13/201056.40005 - Central Region ES #17 07/22/2004 02/28/2006 11/29/2007

    11/27/2006 09/13/201056.40006 - Central Region ES #18 11/02/2004 02/28/2006 03/12/2008

    10/07/2009 09/03/201356.40074 - Central Region ES #20 04/22/2008 12/09/2008 04/14/2010

    04/10/2006 09/13/201047.03902A - Central Region Gratts EEC 03/11/2003 02/08/2005 03/10/2008

    10/15/2009 09/04/201256.40076 - Central Region MacArthur Park ES Addition 01/08/2008 11/25/2008 05/26/2010

    09/20/2007 09/06/201156.40010 - Central Region MS #7 09/21/2004 01/24/2006 06/30/2008

    04/10/2006 09/13/201047.03902 - Gratts New PC 03/11/2003 02/08/2005 03/10/2008

    L A l U ifi d S h l Di t i t

  • 8/8/2019 Final BOC Agenda October 20 2010

    47/200

    Los An eles Unified School District

    F AC I L I T I E S S ERV I C E S D I V I S I ON , NEW CON ST RUC T I ON

    PROJECT MILESTONE LISTING BY BOARD MEMBER DISTRICT

    Project

    Notice toProceed

    ConstructionSchool

    Occupancy

    PreferredSite

    SelectedProject/CEQA

    ApprovalDSA

    Approval

    Board District: 3 Board Member: Tamar Galatzan

    09/25/2009 09/04/201256.40087 - Valley Region Bellingham ES Addition 01/22/2008 10/14/2008 03/25/2010

    09/24/2008 09/06/201156.40041 - Valley Region Blythe ES Addition 06/21/2005 09/09/2008 03/24/2009

    08/14/2007 09/06/201156.40031 - Valley Region HS #4 06/22/2004 11/28/2006 05/19/2008

    10/19/2009 09/04/201256.40091 - Valley Region Span K-8 #2 04/24/2007 01/27/2009 03/15/2010

    L A l U ifi d S h l Di t i t

  • 8/8/2019 Final BOC Agenda October 20 2010

    48/200

    Los An eles Unified School District

    F AC I L I T I E S S ERV I C E S D I V I S I ON , NEW CON ST RUC T I ON

    PROJECT MILESTONE LISTING BY BOARD MEMBER DISTRICT

    Project

    Notice toProceed

    ConstructionSchool

    Occupancy

    PreferredSite

    SelectedProject/CEQA

    ApprovalDSA

    Approval

    Board District: 4 Board Member: Steve Zimmer

    09/30/2009 09/04/201256.40077 - Central Region ES #22 04/24/2007 02/10/2009 05/07/2010

    08/09/2007 09/13/201056.40046 - Valley Region ES #10 06/21/2005 06/26/2007 05/21/2008

    Los An eles Unified School District

  • 8/8/2019 Final BOC Agenda October 20 2010

    49/200

    Los An eles Unified School District

    F AC I L I T I E S S ERV I C E S D I V I S I ON , NEW CON ST RUC T I ON

    PROJECT MILESTONE LISTING BY BOARD MEMBER DISTRICT

    Project

    Notice toProceed

    ConstructionSchool

    Occupancy

    PreferredSite

    SelectedProject/CEQA

    ApprovalDSA

    Approval

    Board District: 5 Board Member: Yolie Flores

    09/02/2009 07/31/201156.40052 - Central Region EEC #2 02/26/2008 02/10/2009 12/31/2010

    12/14/2006 09/06/201156.40002 - Central Region ES #14 09/21/2004 06/26/2007 07/15/2009

    10/20/2009 11/01/201156.40035 - Central Region Glassell Park EEC 01/20/2004 09/02/2008 09/15/2010

    09/19/2007 09/06/201156.40007 - Central Region HS #13 12/14/2004 01/24/2006 06/12/2008

    05/22/2007 09/13/201056.40011 - East LA HS #2 06/22/2004 10/11/2005 11/27/2007

    10/06/2009 09/06/201156.40099 - East LA Star HS Academy 10/11/2005 07/11/2006 09/16/2010

    06/08/2007 08/16/201056.40016A - South Region EEC #1 01/11/2005 05/23/2006 01/15/2008

    06/25/2007 08/11/201056.40017A - South Region EEC #2 11/02/2004 03/28/2006 06/06/2008

    06/08/2007 08/16/201056.40016 - South Region ES #3 01/11/2005 05/23/2006 01/15/2008

    06/25/2007 08/11/201056.40017 - South Region ES #4 11/02/2004 03/28/2006 06/06/2008

    10/19/2009 09/04/201256.40057 - South Region ES #5 11/28/2006 03/25/2008 06/09/2010

    10/14/2009 09/04/201256.40083 - South Region ES #9 05/27/2008 02/10/2009 06/08/2010

    06/12/2009 09/04/201256.40036 - South Region HS #7 11/25/2008 12/09/2008 11/24/2009

    09/30/2011 09/02/201456.40058 - South Region HS #8 05/28/2009 03/09/2010 12/31/2011

    09/16/2009 09/04/201256.40059 - South Region HS #9 06/21/2005 08/25/2009 01/12/2010

    08/03/2007 09/13/201056.40022 - South Region MS #2 07/22/2004 03/07/2006 01/02/2008

    10/07/2009 09/04/201256.40060 - South Region MS #3 04/22/2008 12/09/2008 03/09/2010

    Los An eles Unified School District

  • 8/8/2019 Final BOC Agenda October 20 2010

    50/200

    Los An eles Unified School District

    F AC I L I T I E S S ERV I C E S D I V I S I ON , NEW CON ST RUC T I ON

    PROJECT MILESTONE LISTING BY BOARD MEMBER DISTRICT

    Project

    Notice toProceed

    ConstructionSchool

    Occupancy

    PreferredSite

    SelectedProject/CEQA

    ApprovalDSA

    Approval

    Board District: 6 Board Member: Nury Martinez

    10/17/2007 09/13/201056.40047 - Valley Region ES #12 06/21/2005 08/28/2007 07/29/2008

    10/15/2009 09/04/201256.40088 - Valley Region ES #13 03/25/2008 12/09/2008 09/30/2010

    08/31/2007 09/13/201056.40027 - Valley Region ES #6 03/08/2005 06/27/2006 03/27/2008

    05/11/2007 09/13/201056.40028 - Valley Region ES #7 12/14/2004 04/25/2006 12/18/2007

    10/11/2007 09/13/201056.40029 - Valley Region ES #8 12/14/2004 05/09/2006 05/13/2008

    05/11/2007 09/13/201056.40030 - Valley Region ES #9 01/11/2005 04/25/2006 12/18/2007

    09/14/2007 09/06/201156.40032 - Valley Region HS #5 07/22/2004 01/23/2007 05/07/2008

    09/14/2007 09/06/201156.40037 - Valley Region HS #9 06/21/2005 09/11/2007 09/08/2008

    10/11/2007 03/31/201356.40034 - Valley Region MS #3 01/20/2004 05/24/2005 09/30/2010

    09/09/2009 09/04/201256.40051 - Valley Region Span K-8 #1 04/24/2007 09/09/2008 09/30/2010

    Los An eles Unified School District

  • 8/8/2019 Final BOC Agenda October 20 2010

    51/200

    Los An eles Unified School District

    F AC I L I T I E S S ERV I C E S D I V I S I ON , NEW CON ST RUC T I ON

    PROJECT MILESTONE LISTING BY BOARD MEMBER DISTRICT

    Project

    Notice toProceed

    ConstructionSchool

    Occupancy

    PreferredSite

    SelectedProject/CEQA

    ApprovalDSA

    Approval

    Board District: 7 Board Member: Richard Vladovic

    01/18/2007 09/13/201056.40004A - Central Region EEC #1 07/22/2004 11/22/2005 01/22/2008

    01/18/2007 09/13/201056.40004 - Central Region ES #16 07/22/2004 11/22/2005 01/22/2008

    10/15/2009 09/04/201256.40075 - Central Region ES #21 01/22/2008 11/25/2008 07/19/2010

    07/24/2008 08/15/201156.40055 - Central Region HS #16 03/07/2006 09/25/2007 12/10/2008

    03/31/2012 09/02/201456.40098 - Harbor Teacher Preparation Academy Redevelopment 04/13/2010 06/30/2011 06/30/2012

    10/20/2009 09/04/201256.40080 - South Region ES #12 01/22/2008 11/25/2008 05/11/2010

    03/12/2007 09/13/201056.40015 - South Region ES #2 11/02/2004 03/07/2006 12/24/2007

    03/21/2008 09/13/201056.40063 - South Region ES #7 03/28/2006 04/24/2007 09/30/2008

    03/31/2013 09/08/201556.40084 - South Region ES Addition #1 03/31/2011 12/31/2011 06/30/2013

    09/29/2009 09/04/201256.40092 - South Region HS #15 05/22/2007 12/09/2008 01/12/2010

    09/05/2007 09/06/201156.40018 - South Region HS #2 07/22/2004 05/23/2006 09/08/2008

    08/24/2007 09/06/201156.40019 - South Region HS #4 02/08/2005 04/24/2007 06/10/2008

    07/30/2008 09/04/201256.40024 - South Region Span K-8 #1 07/11/2006 01/22/2008 12/02/2009

  • 8/8/2019 Final BOC Agenda October 20 2010

    52/200

  • 8/8/2019 Final BOC Agenda October 20 2010

    53/200

    Exhibit 3

  • 8/8/2019 Final BOC Agenda October 20 2010

    54/200

    Los Angeles Unified School District

    Facilities Services Division

    E X I S T I N G F A C I L I T I E S

    UNIVERSITY HIGH SCHOOLNEW GYMNASIUM

    Monthly Program Status Report

  • 8/8/2019 Final BOC Agenda October 20 2010

    55/200

    TABLE OF CONTENTS

    Program Overview ............................................................................................... 2

    Construction Starts and Completions ................................................................... 7

    Change Order Rates ............................................................................................ 9

    Board Member and Local District Discretionary Funds ...................................... 11

    Program Highlights ............................................................................................ 13

  • 8/8/2019 Final BOC Agenda October 20 2010

    56/200

    August 2010Monthly Program Status Report

    PROGRAM OVERVIEW

  • 8/8/2019 Final BOC Agenda October 20 2010

    57/200

    August 2010

    The following figures provide a highlight on the status of the various bond programs:

    BB Bond Program StatusProgram is 97% complete with regards to project value of $2.418 billionProgram is 99% complete with regards to project count of 12,782Please note that 2% of the program is in construction and another 1% is in thedesign phase, leaving less than 1% to planning and contracting.

    Measure K Program StatusProgram is 60% complete with regards to project value of $505.0 million

    Program is 88% complete with regards to project count of 3,497

    Measure R Program StatusProgram is 46% complete with regards to project value of $622.2 millionProgram is 69% complete with regards to project count of 3,199

    Measure Y Program StatusProgram is 34% complete with regards to project value of $448.9 million

    Program is 55% complete with regards to project count of 1,335

  • 8/8/2019 Final BOC Agenda October 20 2010

    58/200

  • 8/8/2019 Final BOC Agenda October 20 2010

    59/200

  • 8/8/2019 Final BOC Agenda October 20 2010

    60/200

  • 8/8/2019 Final BOC Agenda October 20 2010

    61/200

    August 2010Monthly Program Status Report

    CONSTRUCTION

  • 8/8/2019 Final BOC Agenda October 20 2010

    62/200

  • 8/8/2019 Final BOC Agenda October 20 2010

    63/200

    August 2010Monthly Program Status Report

    CHANGE ORDER RATES

  • 8/8/2019 Final BOC Agenda October 20 2010

    64/200

  • 8/8/2019 Final BOC Agenda October 20 2010

    65/200

    August 2010Monthly Program Status Report

    BOARD MEMBER AND LOCAL

  • 8/8/2019 Final BOC Agenda October 20 2010

    66/200

  • 8/8/2019 Final BOC Agenda October 20 2010

    67/200

    August 2010Monthly Program Status Report

    PROGRAM HIGHLIGHTS

  • 8/8/2019 Final BOC Agenda October 20 2010

    68/200

    Project Before Facts:12/22/2004 5/20/2010

    1/1/2005 1/1/2006 1/1/2007 1/1/2008 1/1/2009 1/1/2010

    12/22/2004

    Design

    1/17/2007 - 5/12/2010

    Construction

    5/11/2010

    Close-Out

    The existing fire alarm system used a manual pull station. This required someone to spot the fire and pull the pull station handle.

    The problem with this system is that a fire can smolder for hours unseen and erupt into flames hours after everyone has gone

    home.

    Install Fully Automatic Fire Alarm SystemBoard Member: Steve Zimmer District 4 Region 3

    Project Budget: $ 1,759.129

    LOCATION FOR PURPOSED

    ADA DRINKING FOUNTAIN

    After

    After

    After

    After

    The new fire alarm system is fully automaticand provides 24/7 monitoring service todispatch the fire department in the event anyof the smoke and/or heat detectors areactivated

    The annunciator panel indicates the exactlocation of the activated device

    The new fire alarm system is interfaced withthe following for fire life safety purposes:

    - lighting system in the auditorium- HVAC system for automatic shut-off- fire sprinkler system- public address system

    The notification devices; horns and lightstrobes, are activated to alert student bodyin the event of a fire

    Project After Facts: After

    The Main PA Rack Interfaced WithFire Alarm System Main Fire Alarm Control PanelAfter

  • 8/8/2019 Final BOC Agenda October 20 2010

    69/200

    Project Before Facts

    8/12/2009 9/13/2010

    1/1/2010

    8/12/2009

    Planning

    4/19/2010 - 5/14/2010

    Construction

    5/17/2010

    Close-Out

    The main play yard, kindergarten play yard, and existing areas with play bars were unsafe, useless and unsightly. Both play bars were set in grass. The main play yard received plenty of water from the new irrigation system. The area

    under the kindergarten yard play bars became bare, uneven, hard and sometimes very slippery and muddy.

    Purchase and Install Safety MattingBoard Member: Yolie Flores Aguilar District 5 Region 6

    Project Budget: $ 20,026

    LOCATION FOR PURPOSED

    ADA DRINKING FOUNTAIN Installed new, safety interlocking matting under the play bars on the main and kindergarten yards, making the areas safer

    for the students The new interlocking matting offers protection for the students, keeps the ground from eroding beneath the bars and is

    easier to maintain The new interlocking matting is age appropriate, durable, colorful and creates a better appearance for students, faculty

    and visitors

    After

    Before

    Project After Facts

    Before

    After

    KINDERGARTEN PLAY YARDMAIN PLAY YARD

  • 8/8/2019 Final BOC Agenda October 20 2010

    70/200

    Project Before Facts3/1/2010 8/30/2010

    4/1/2010 7/1/2010

    3/1/2010

    Planning

    3/20/2010 - 5/1/2010

    Construction

    5/3/2010

    Close-Out

    Asphalt Paving Repair & ResealingBoard Member: Richard Vladovic District 7 Region 7

    Project Budget: $ 100,358

    LOCATION FOR PURPOSED

    ADA DRINKING FOUNTAIN

    After

    After

    After

    Before

    Before

    After

    Project After FactsAfter

    After

    After

    AfterBefore

  • 8/8/2019 Final BOC Agenda October 20 2010

    71/200

    Exhibit 4

  • 8/8/2019 Final BOC Agenda October 20 2010

    72/200

  • 8/8/2019 Final BOC Agenda October 20 2010

    73/200

  • 8/8/2019 Final BOC Agenda October 20 2010

    74/200

  • 8/8/2019 Final BOC Agenda October 20 2010

    75/200

  • 8/8/2019 Final BOC Agenda October 20 2010

    76/200

  • 8/8/2019 Final BOC Agenda October 20 2010

    77/200

  • 8/8/2019 Final BOC Agenda October 20 2010

    78/200

  • 8/8/2019 Final BOC Agenda October 20 2010

    79/200

  • 8/8/2019 Final BOC Agenda October 20 2010

    80/200

  • 8/8/2019 Final BOC Agenda October 20 2010

    81/200

  • 8/8/2019 Final BOC Agenda October 20 2010

    82/200

  • 8/8/2019 Final BOC Agenda October 20 2010

    83/200

  • 8/8/2019 Final BOC Agenda October 20 2010

    84/200

  • 8/8/2019 Final BOC Agenda October 20 2010

    85/200

  • 8/8/2019 Final BOC Agenda October 20 2010

    86/200

  • 8/8/2019 Final BOC Agenda October 20 2010

    87/200

    AgendaItem # 4

  • 8/8/2019 Final BOC Agenda October 20 2010

    88/200

    Los Angeles Unified School District

    Facilities Services Division

    E X I S T I N G F A C I L I T I E S

    LIMERICK ELEMENTARYNEW LIBRARY AND MODULAR CLASSROOM BUILDING

    Monthly Program Status Report

    October 2010

  • 8/8/2019 Final BOC Agenda October 20 2010

    89/200

  • 8/8/2019 Final BOC Agenda October 20 2010

    90/200

    October 2010Monthly Program Status Report

    PROGRAM OVERVIEW

    October 2010

  • 8/8/2019 Final BOC Agenda October 20 2010

    91/200

    The following figures provide a highlight on the status of the various bond programs:

    BB Bond Program StatusProgram is 98% complete with regards to project value of $2.428 billionProgram is 99% complete with regards to project count of 12,783Please note that 1% of the program is in construction and another 1% is in thedesign phase, leaving less than 1% to planning and contracting.

    Measure K Program StatusProgram is 62% complete with regards to project value of $506.0 million

    Program is 89% complete with regards to project count of 3,513

    Measure R Program StatusProgram is 48% complete with regards to project value of $625.1 millionProgram is 71% complete with regards to project count of 3,244

    Measure Y Program StatusProgram is 35% complete with regards to project value of $445.2 million

    Program is 59% complete with regards to project count of 1,312

  • 8/8/2019 Final BOC Agenda October 20 2010

    92/200

  • 8/8/2019 Final BOC Agenda October 20 2010

    93/200

  • 8/8/2019 Final BOC Agenda October 20 2010

    94/200

  • 8/8/2019 Final BOC Agenda October 20 2010

    95/200

  • 8/8/2019 Final BOC Agenda October 20 2010

    96/200

  • 8/8/2019 Final BOC Agenda October 20 2010

    97/200

    October 2010Monthly Program Status Report

    CHANGE ORDER RATES

  • 8/8/2019 Final BOC Agenda October 20 2010

    98/200

  • 8/8/2019 Final BOC Agenda October 20 2010

    99/200

    October 2010Monthly Program Status Report

    BOARD MEMBER AND LOCAL

  • 8/8/2019 Final BOC Agenda October 20 2010

    100/200

  • 8/8/2019 Final BOC Agenda October 20 2010

    101/200

    October 2010Monthly Program Status Report

    PROGRAM HIGHLIGHTS

    P t bl R l P U d t

  • 8/8/2019 Final BOC Agenda October 20 2010

    102/200

    Portable Removal Program Update

    Portable Removals by Funding Source Benchmark2010 total

    Actual to Dateas of 9-28-10

    PRP Measure Y 34 15PRP RHU 42 56ORG 38 45Escutia 152 72Other (Interim housing, FDK, RPMD, various lease

    terminations) 0 30Total 266 218

  • 8/8/2019 Final BOC Agenda October 20 2010

    103/200

    DSA Fire Alarm OAR: Louis Ramos

  • 8/8/2019 Final BOC Agenda October 20 2010

    104/200

    DSA Fire Alarm OAR: Louis RamosBoard Member: Marguerite Poindexter LaMotte District 1, Region 3

    Project Budget: $ 2,636,812

    Project Before Facts:3/21/2005 11/28/2010

    1/1/2006 1/1/2007 1/1/2008 1/1/2009 1/1/2010

    Project After Facts:

    ELECTRONIC THERMOSTAT

    CHILLER

    VENTILATOR

    3/21/2005Design

    5/14/2007 - 7/23/2010

    Construction

    7/24/2010Close-Out

    NEW STROBE/HORN COMBINATION

    After

    AfterAfter

    After

  • 8/8/2019 Final BOC Agenda October 20 2010

    105/200

    Replace 13 HVAC Units OAR: Ross Plasencia

  • 8/8/2019 Final BOC Agenda October 20 2010

    106/200

    Replace 13 HVAC Units OAR: Ross PlasenciaBoard Member: Yolie Flores Aguilar District 5, Region 4

    Project Budget: $ 468,288

    Project Before Facts:The existing HVAC system was 25 years old and required constant maintenance and repairs.

    Inconsistent heating and air conditioning affected students attention, performance and learningThe existing system in the main building is comprised of 12 classrooms and the library

    The existing thermostats and roof-top chiller were outdated and in need of replacement

    2/14/2008 12/25/2010

    1/1/2009 1/1/2010

    After

    CHILLER

    Installed a new, efficientchiller and pump. The air andheat supply to classroomsand library will be moreconsistent.

    3/2/2008Design

    8/28/2010Close-Out

    6/23/2009 - 8/27/2010

    Construction

    Project After Facts:

    ELECTRONIC THERMOSTAT

    CHILLER

    VENTILATOR

  • 8/8/2019 Final BOC Agenda October 20 2010

    107/200

    LOS ANGELES UNIFIED SCHOOL DISTRICT

    SCHOOL CONSTRUCTION BOND CITIZENS OVERSIGHT COMMITTEE

  • 8/8/2019 Final BOC Agenda October 20 2010

    108/200

    David Crippens, ChairL.A. Area Chamber of Commerce

    Elizabeth Bar-El

    LAUSD Student Parent(Primary Member)

    John Naimo, SecretaryL.A. County Auditor-Controllers

    Office (Primary Member)Scott Folsom

    Tenth District PTSAConstance Rice

    L.A. City Controllers Office

    Joseph P. Buchman Legal CounselBurke, Williams & Sorensen, LLP

    Maria CabildoLAUSD Student Parent(Primary Member)

    Sylvia CunninghamAARP

    Adrian GarcaL.A. Mayors Office

    John HakelAssociated General Contractors ofCalifornia (Alternate Member)

    David JenkinsAssociated General Contractors of

    California (Primary Member)Lynda LevitanThirty-First District PTSA

    Anastacio MedinaBREATHE California

    Thomas A. RubinOversight Committee Consultant

    Richard SlawsonL.A. Co. Federation of Labor,

    AFL-CIO

    Barry WaiteLAUSD Student Parent(Alternate Member)

    Wendy WatanabeL.A. County Auditor-Controllers

    Office (Alternate Member)Chester Widom

    American Institute of Architects(Vacant)

    California TaxpayersAssociation(Vacant)

    Environmental Justice/CivilRights Group

    Gary C. AndersonDirector

    Frank PadillaAdministrator

    RESOLUTION 2010-36

    BOARD REPORT NO. _-10/11

    EXISTING FACILITIES STRATEGIC EXECUTION PLAN AMENDMENT TO DEFINE

    THE REMAINING SCOPE AND ASSOCIATED FUNDING OF THE CURRENT REPAIR

    AND MODERNIZATION PROGRAM

    WHEREAS, the Districts current 13-year Bond Program, valued at $19.5 Billion, is making up for 34years of neglect of our students school facilities; and

    WHEREAS, $7.3 Billion of Program funds have been dedicated to repair and modernize existingschool facilities; and

    WHEREAS, approximately 20,000 school improvement projects valued at $6 Billion, which is nearly$1.2 Billion greater than the total allocation of local bond funds to the program, have been invested inschools throughout the District; and

    WHEREAS, as a result of the long term neglect of the Districts school facilities and the pressure to

  • 8/8/2019 Final BOC Agenda October 20 2010

    109/200

    Resolution 2010-36

    Existing Facilities Strategic Execution Plan Amendment to Define the Remaining Scope and Associated

    Funding of the Current Modernization and Repair Program

    P 3

  • 8/8/2019 Final BOC Agenda October 20 2010

    110/200

    Page -3-

    ADOPTED on August 18, 2010, by the following vote:

    AYES: ABSTAIN:

    NAYS: ABSENT:

    ____________________ ____________________David Crippens Elizabeth Bar-ElChair Vice Chair

  • 8/8/2019 Final BOC Agenda October 20 2010

    111/200

  • 8/8/2019 Final BOC Agenda October 20 2010

    112/200

  • 8/8/2019 Final BOC Agenda October 20 2010

    113/200

  • 8/8/2019 Final BOC Agenda October 20 2010

    114/200

  • 8/8/2019 Final BOC Agenda October 20 2010

    115/200

  • 8/8/2019 Final BOC Agenda October 20 2010

    116/200

  • 8/8/2019 Final BOC Agenda October 20 2010

    117/200

    LOS ANGELES UNIFIED SCHOOL DISTRICT

    SCHOOL CONSTRUCTION BOND CITIZENS OVERSIGHT COMMITTEE

    David Crippens Chair Maria Cabildo Richard Slawson

  • 8/8/2019 Final BOC Agenda October 20 2010

    118/200

    David Crippens, ChairL.A. Area Chamber of Commerce

    Elizabeth Bar-El

    LAUSD Student Parent(Primary Member)

    John Naimo, SecretaryL.A. County Auditor-Controllers

    Office (Primary Member)Scott Folsom

    Tenth District PTSAConstance Rice

    L.A. City Controllers Office

    Joseph P. Buchman Legal CounselBurke, Williams & Sorensen, LLP

    Maria CabildoLAUSD Student Parent(Primary Member)

    Sylvia CunninghamAARP

    Adrian GarcaL.A. Mayors Office

    John HakelAssociated General Contractors ofCalifornia (Alternate Member)

    David JenkinsAssociated General Contractors of

    California (Primary Member)Lynda LevitanThirty-First District PTSA

    Anastacio MedinaBREATHE California

    Thomas A. RubinOversight Committee Consultant

    Richard SlawsonL.A. Co. Federation of Labor,

    AFL-CIO

    Barry WaiteLAUSD Student Parent(Alternate Member)

    Wendy WatanabeL.A. County Auditor-Controllers

    Office (Alternate Member)Chester Widom

    American Institute of Architects(Vacant)

    California TaxpayersAssociation(Vacant)

    Environmental Justice/CivilRights Group

    Gary C. AndersonDirector

    Frank PadillaAdministrator

    RESOLUTION 2010-37

    BOARD REPORT NO. _-10/11

    EXISTING FACILITIES STRATEGIC EXECUTION PLAN AMENDMENT TO RE-DEFINE