Holbrook Campground Road at Midway Road Intersection Improvement Project FINAL PRESENTATION JULY 27, 2016

Final Presentation (Intersection Improvement Project)

Embed Size (px)

Citation preview

Page 1: Final Presentation (Intersection Improvement Project)

Holbrook Campground Road at Midway RoadIntersection Improvement Project

FINAL PRESENTATION

JULY 27, 2016

Page 2: Final Presentation (Intersection Improvement Project)

PROJECT LOCATION

Source: GIS Cherokee County

Page 3: Final Presentation (Intersection Improvement Project)

EXISTING CONDITIONS

Page 4: Final Presentation (Intersection Improvement Project)

BACKGROUND

• Sight distance

• Midway Road stopped traffic looking left

• Safety• Accident reports

• Congestion

Page 5: Final Presentation (Intersection Improvement Project)

STOP SIGN ALTERNATIVE (1)

Page 6: Final Presentation (Intersection Improvement Project)

STOP SIGN ALTERNATIVE (2)

• Advantages• Solves sight distance issue• Safer approach

• Disadvantages• Little to no benefit for traffic

Page 7: Final Presentation (Intersection Improvement Project)

ROUNDABOUT ALTERNATIVE (1)

• Geometric Design• Inscribed circle

• Lane widths

• Entry, exit, circulatory

Page 8: Final Presentation (Intersection Improvement Project)

ROUNDABOUT ALTERNATIVE (2)

• Geometric Design• Horizontal curves

• 346’

• 362’

Page 9: Final Presentation (Intersection Improvement Project)

ROUNDABOUT ALTERNATIVE (3)

• Advantages• Solves sight distance issue• Safer approach speed• Improved intersection traffic flow and capacity• Cheaper alternative

• Disadvantages• Mainline traffic

Page 10: Final Presentation (Intersection Improvement Project)

TRAFFIC

Northbound Southbound Westbound

2016 AM A B A

2016 PM A A A

2036 AM C A A

2036 PM A A B

Page 11: Final Presentation (Intersection Improvement Project)

DRAINAGE

Page 12: Final Presentation (Intersection Improvement Project)

TYPICAL SECTION

Page 13: Final Presentation (Intersection Improvement Project)

UTILITIES

Page 14: Final Presentation (Intersection Improvement Project)

COST ESTIMATES

• Total Project Costs

• T Intersection: $ 543,748.00

• Roundabout: $ 513,585.00

Page 15: Final Presentation (Intersection Improvement Project)

FUTURE RECOMMENDATIONS

• Fastest Path Analysis

• Speed Control

• Traffic Predictions and Trend

Page 16: Final Presentation (Intersection Improvement Project)

CONCLUSION

• Safety• Sight Distance

• Speed

• Congestion• Traffic Flow

• Traffic Capacity

• Cost Effective

Page 17: Final Presentation (Intersection Improvement Project)

Thank You