  • Geary Community Advisory Committee

    July 21, 2020

  • Order of Business

    1. Call to Order

    2. Virtual meeting etiquette

    3. Roll call

    4. Ice breaker activity

    5. Approval of minutes – May 19, 2020

    6. Public comment

    7. Temporary Emergency Transit-Only Lane proposal for Geary Boulevard Improvement Project limits

    8. Geary Rapid – Project update

    9. Geary Rapid – Implementation update

    10. Geary Rapid – Outreach update

    11. Adjourn

    2

    https://www.sfmta.com/sites/default/files/reports-and-documents/2020/05/geary_community_advisory_committee_meeting_minutes_200519_0.pdf

  • 2. Virtual Meeting Etiquette

    • Microsoft Teams – download for desktop or mobile at: www.microsoft.com/en-us/microsoft-365/microsoft-teams/download-app

    • Key functions: mute/unmute, raise hand, chat • Please stay on mute unless called on to speak by Chair

    3

    https://www.microsoft.com/en-us/microsoft-365/microsoft-teams/download-app

  • 3. Roll Call

    4

  • 4. Ice breaker

    What was the first job you’ve ever had?

    5

  • 5. Approval of Minutes

    • May 19, 2020

    6

    https://www.sfmta.com/sites/default/files/reports-and-documents/2020/05/geary_community_advisory_committee_meeting_minutes_200519_0.pdf

  • 6. Public Comment

    • See Public Comment Policy on back of agenda. • Public comment for matters within the Geary

    Community Advisory Committee jurisdiction and are not on today’s calendar.

    • Public comment is limited to two minutes each.

    7

  • 7. Temporary Emergency Transit-Only Lanes proposal for Geary Boulevard Improvement Project limits

    8

  • 9

    Time Savings During Shelter in Place

  • • Install on corridors that normallyexperience congestion to keepbuses moving and reducecrowding

    • Allow buses to complete trips inless time and return into servicemore quickly

    • Provide more frequent servicewith same number of buses,mitigating service reductions

    • Are automatically removedwithin 120 days after emergencyorder is lifted, unless there is apublic process to make a lanepermanent

    10

    Temporary Emergency Transit Lanes

  • 11

    Program Benefits

    • Equity: Transit lanes reduce the riskof exposure for people who havethe fewest travel choices andensures there is enough capacity onboard, especially for lower-incomeand people of color

    • Public Health: Reducing crowdingon transit is imperative topreventing the spread of COVID-19

    • Economic Recovery: A strongeconomic recovery is dependent onan efficient transit system

  • 7. Temporary Emergency Transit-Only Lanesproposal for Geary Boulevard ImprovementProject limits

    • While pursuing Geary TETL, Geary BoulevardImprovement Project (GBIP) work is on hold

    • Geary TETL will be evaluated and lessonslearned applied to next stages of GBIP work

    12

  • 7. Temporary Emergency Transit-Only Lanesproposal for Geary Boulevard ImprovementProject limits

    Toolkit of emergency transit priority treatments

    Leading Transit Temporary bus bulbs Intervals Transit-Only Lanes

    13

  • 7. Temporary Emergency Transit-Only Lanes proposal for Geary Boulevard Improvement Project limits

    Proposed Geary TETL Scope (proposed for both inbound and outbound)

    14

  • 7. Temporary Emergency Transit-Only Lanes proposal for Geary Boulevard Improvement Project limits

    Transit-Only Lane (TOL) Proposal

    • Proposed for locations with existing parallel parking and three travel lanes per direction.

    • Parallel parking + 1 TOL + 2 general purpose travel lanes/direction

    15

  • 7. Temporary Emergency Transit-Only Lanes proposal for Geary Boulevard Improvement Project limits

    Focus Area 1: 15th Avenue Outbound Aerial

    16

  • 7. Temporary Emergency Transit-Only Lanes proposal for Geary Boulevard Improvement Project limits

    Focus Area 1: 15th Avenue Outbound Street view

    17

  • 7. Temporary Emergency Transit-Only Lanes proposal for Geary Boulevard Improvement Project limits

    Focus Area 1: 15th Avenue Outbound

    Proposal: install transit queue jump and right turn-pocket

    18

  • 7. Temporary Emergency Transit-Only Lanes proposal for Geary Boulevard Improvement Project limits

    Focus Area 1: 15th Avenue Outbound

    Benefits

    Bus travel time and reliability

    • Transit travel time data from Shelter in Place showed fewer buses got stopped here than in pre-COVID conditions

    • During PM peak, about 2 vehicles/signal-cycle turn right

    Impacts

    On-street parking loss

    • 4-6 metered spaces

    19

  • 7. Temporary Emergency Transit-Only Lanes proposal for Geary Boulevard Improvement Project limits

    Focus Area 2: 16th-15th Avenue Inbound Aerial

    20

  • 7. Temporary Emergency Transit-Only Lanes proposal for Geary Boulevard Improvement Project limits

    Focus Area 2: 16th-15th Avenue Inbound Street view

    21

  • 7. Temporary Emergency Transit-Only Lanes proposal for Geary Boulevard Improvement Project limits

    Focus Area 2: 16th-15th Avenue Inbound

    Proposal: Convert angled parking to parallel parking on this block to make room for TOL and right-turn lane

    22

  • 7. Temporary Emergency Transit-Only Lanes proposal for Geary Boulevard Improvement Project limits

    Focus Area 2: 16th-15th Avenue Inbound

    Benefits Impacts

    Bus travel time and reliability On-street parking loss

    • Transit travel time data • 1 space by converting 5 from Shelter-in-Place angled spaces to 4 parallel showed fewer buses got spaces stopped here than in pre-COVID conditions

    • During PM peak, less than 1 vehicle/signal-cycle turns right

    23

  • 7. Temporary Emergency Transit-Only Lanesproposal for Geary Boulevard ImprovementProject limits

    July 21:

    Geary CAC Meeting

    TBD fall: Public Hearing

    TBD fall/winter: implementation

    Resume work on GBIP and ongoing

    monitoring and evaluation

    24

  • 7. Temporary Emergency Transit-Only Lanes proposal for Geary Boulevard Improvement Project limits

    Areas for CAC Input

    • Proposal for Geary at 15th Avenue Outbound

    • Proposal for 16th to 15th Avenue Inbound

    • Evaluation approach

    25

  • 8. Geary Rapid Project updates Geary Rapid Project - Project Report SFMTA only

    Design Construction Budget $ 5.0M $ 31.0M Expenditures* $ 4.7M $ 7.6M % expended 94% 25% Budget Status Closing out On track Est. Completion Summer '19 Sept '21 Schedule Status Complete On track

    *financial data as of 7/6/2020

    Geary Rapid Project - All Construction Contracts includes MTA, PUC Sewer and Water, DT, Paving and Curb Ramps Contract/Work Estimated Price Status (% paid) MTA Near-Term $ 1.0M $ 1.0M Complete PUC Sewer/Water $ 16.0M $ 16.2M Underway (72%) PW Geary East $ 6.2M $ 8.7M Underway (41%) PW Steiner Demo $ 1.0M $ 0.8M Punchlist (86%) PW Geary West $ 16.6M $ 16.0M Underway (0%)

    $ 40.8M $ 42.7M Underway (40%)

    26

  • 9. Geary Rapid – Implementation update

    Overview

    27

  • 9. Geary Rapid – Implementation updateBi-weekly Gantt Charts/Bar Schedules

    28

  • 9. Geary Rapid – Implementation update

    “Geary Blvd Water/Sewer” contract: Masonic to Van Ness

    • “Segment A” work is complete (Masonic to Fillmore).• “Segment B” is underway between Fillmore and Franklin.

    “Geary East” contract: Van Ness to Market Street

    • Water main work is underway: Polk-Jones and Powell-Stockton.Pedestrian countdown signals were added at O’Farrell/Leavenworth

    29

  • 9. Geary Rapid – Implementation update

    “West Surface” contract: Stanyan to Van Ness

    • “Segment A” work between Stanyan-Fillmore is underway. • Focusing on traffic signals/streetlights and base repair Masonic-Scott • First segment of final paving scheduled this Saturday, July 25th

    30

  • 9. Geary Rapid – Implementation update

    Geary/Steiner Bridge Demolition

    • Bridge removed over Memorial Day weekend (5/23-24). Finishing punchlist and transferring site to Surface contractor.

    31

  • 10. Geary Rapid – Outreach update

    Business support: First Union Square signs posted for Powell to Stockton southside

    32

  • 10. Geary Rapid – Outreach update

    Recent Events/Meetings

    • Business support meeting with Tenderloin Community Benefit District (TLCBD) • June 15, 2020

    Other Outreach

    • Geary Rapid Project Newsletter • Summer 2020 issue coming

    soon, print and digital version

    33

  • 11. Adjourn

    Thank you!

    Next meeting:

    • September 15, 2020, 6:00 p.m.

    • Most likely still virtual on Microsoft Teams, else: 1 South Van Ness Avenue, 7th Floor, Union Square Conference Room

    34

  • Appendix: 9. Implementation update Baseline and Bi-weekly Gantt Charts/Bar Schedules

    35

    Bo: Biweekly Gantt ChartsBar Schedules: Esquivel Grading Paving: ftatwork comersatldaH work Bus shetter foundation: Geary 1nd Lyon St intersection NW SE SW: Geary o1nd BMff St interuction NW: Bker St to Broderick St South side: fbtwoA comesBAUMAN work Bus shelter fooricution: fLltworkccmer5work Bus shelter foundation: Scott St to SteinK St North and South side: flatwork comers: Geary and Steintt St interuction NW NE islands West: GeMY and Filmore St intersection NW: GeMY and Filmore St intersection Bus Pad: Row1: Masonic Ave to Presidio Ave North South side: GeMY and Lyon St interwction: Su: BSR: undefined: ID: MRow1: T w T FRow1: 3: MRow2: T w T FRow2: MRow3: T w T FRow3: 5: MRow4: T w T FRow4: 6: MRow5: T w T FRow5: MRow6: T w T FRow6: undefined_2: Row1_2: Row1_3: Row1_4: Row1_5: Row1_6: Row1_7: Row2: Row2_2: Row2_3: Row2_4: Row2_5: Row1_8: Row1_9: Row1_10: Row1_11: Row1_12: Row1_13: Row1_14: Row1_15: Row1_16: Row1_17: Row2_6: Row2_7: Row2_8: Row2_9: Row2_10: Row2_11: Row2_12: Row2_13: Row2_14: Row2_15: Row2_16: