47
Harald Lück for the Ruthe Team GEO600 during S5 9th ILIAS WG1 meeting, Potsdam, 2006

GEO600 during S5

Embed Size (px)

DESCRIPTION

GEO600 during S5. Harald Lück for the Ruthe Team. 9th ILIAS WG1 meeting, Potsdam, 2006. 2.2 W. 2 kW. 2.5 kW. 5 W. GEO600 Optical Layout. 5 W. 0.09. 7 kW. 4 kW. 5 kW. 10 W. GEO in S5 ON &WE mode. Started participating in S5 on Jan. 20th Comissioning during daytime - PowerPoint PPT Presentation

Citation preview

Page 1: GEO600 during S5

Harald Lück for the Ruthe Team

GEO600 during S5

9th ILIAS WG1 meeting, Potsdam, 2006

Page 2: GEO600 during S5

GEO600 Optical Layout

4 kW

0.09

10 W

5 W

5 kW

7 kW

5 W

2.2 W

2.5

kW

2 kW

Page 3: GEO600 during S5

GEO in S5 ON &WE mode

• Started participating in S5 on Jan. 20th

• Comissioning during daytime

• Data taking during nights, weekends and holidays.

• Moderate efforts to keep detector locked during data taking times, i.e. no operator shifts.

Page 4: GEO600 during S5

GEO in S5 24/7 mode

• Commissioning stopped on May 1st 2006• Full time data taking with operators on site in 2

shifts during working days• SMS – alarm system calls operator on duty if

predefined problem occurs– Lock-loss > 30min., h_rms > reference, data

acquisition faults, ...• Operator calls 'expert' if he cannot solve a problem

by predefined procedure• Maintenance times for measuring loop gains,

transfer functions, noise projections etc.

Page 5: GEO600 during S5

SMS Alarm System

Page 6: GEO600 during S5

GEO600 S5 Science Duty Cycle

0 10 20 30 40 50 60 70 80 90 1000

10

20

30

40

50

60

70

80

90

100Total science time: 46.5 days, Overall Duty Cycle: 46.5 %

Scie

nce

duty

cyc

le (

%)

0 10 20 30 40 50 60 70 80 90 1000

10

20

30

40

50

Acc

umul

ated

scie

nce

tim

e [d

ays]

Time from 2006-01-20 23:59:47 (821836800) [days]

ON&WE Mode (Jan. 20th – April 30th) 24/7 Mode (May 1st - …)

Page 7: GEO600 during S5

S5: Duty Cycle

• 1. May-17. July, 78 days– Instrumental duty cycle: 95.4%– Science time duty cycle: 90.3%

• Longest lock: 102 hours

Time [days]

Inst

. dut

y cy

cle

[%]

Page 8: GEO600 during S5

S5: unlocked times

• Typical relock-time ~ 5 minutes

• Longest unlocked time: 19 hours

Unlocked time [minutes]

Num

ber

of u

nloc

ked

tim

es

Histogram of unlocked times < 1 hour

Page 9: GEO600 during S5

Tuning (from 350 Hz) to 550 Hz

• On April 3rd we changed the tuning from 350 Hz to 550 Hz to improve SNR @ fs above 400 Hz.

• Optimized all parameters and combining filters for 550 Hz.

• This did not compromise much sensitivity @ low fs as we had a lot of excess noise there anyway.

Page 10: GEO600 during S5

Sensitivity in Science Runs

102

103

10-23

10-22

10-21

10-20

10-19

10-18

10-17

10-16

Typical Sensitivity: Science Runs

Freq. [Hz]

AS

D [ h

/H

z]

S1 Aug 26 `02S3I Nov 5 `03S3II Dec 31 `03S4 Feb 22 `05S5 N&W Mar 23 `06S5 24/7 July '06

Page 11: GEO600 during S5

Sensitivity in Science Runs

102

103

10-23

10-22

10-21

10-20

10-19

10-18

10-17

10-16

Typical Sensitivity: Science Runs

Freq. [Hz]

AS

D [ h

/H

z]

S1 Aug 26 `02S3I Nov 5 `03S3II Dec 31 `03S4 Feb 22 `05S5 N&W Mar 23 `06LHO4k Mar ' 06LLO 4k Jan '06LHO 2k Jan '06GEO Design 550HzS5 24/7 July '06

Page 12: GEO600 during S5

Sensitivity in Science Runs

102

103

10-23

10-22

10-21

10-20

10-19

10-18

10-17

10-16

Typical Sensitivity: Science Runs

Freq. [Hz]

AS

D [ h

/H

z]

S1 Aug 26 `02S3I Nov 5 `03S3II Dec 31 `03S4 Feb 22 `05S5 N&W Mar 23 `06LHO4k Mar ' 06LLO 4k Jan '06LHO 2k Jan '06GEO Design 550HzS5 24/7 July '06

x4

Page 13: GEO600 during S5

GW-IFO network (USA & Europe)

4x

Page 14: GEO600 during S5

Cal. Lines removal from h(t)

102

103

10-21

10-20

10-19

10-18

10-17

nfft/fs = 2.00 : navs = 50 : enbw = 0.75 : nsecs = 100

Am

plit

ud

e (

Vrm

s /

Hz1

/2)

Frequency (Hz)

G1:DER_DATA_Hfs = 16384 : 2006-03-22 22:05:06 -

Page 15: GEO600 during S5

Locking procedure with add. 2f signal

• PR error signal always available due to asymmetry in BS (~48/52)

• MI lock to dark fringe• SR lock with three different signals in detuned

state (~2kHz)

• Tuning to desired frequency (changing parameters in the process)

• Switching MI lock to Single element diode• Switching Servo parameters to lower noise &

lower tolerance ones• Ramping up power to ‚final‘ value• In Total: ~ 3min

Page 16: GEO600 during S5

Locking on 2f-SR sequence

At second 4.2 SR control is switched from SR-2f to MI-2f. (only visible by more noise in SR feedback)at second 5.5 the SR freq. is set back to tuning start frequency.

For this purpose the SR mod. freq. is set automatically to the value chosen in the front panel,which is 9.018070MHz right now. Also the SR-2f signal is routed in hardware by cmos switch to the SR module.

Then 2 sec. after acquisition the 2f-lock is switched to MI-2f signal and then the SR freq. is changed to nominal for tuning start.Then tuning starts as usual…and tunes down to any f > 200 Hz. Straight from the labbook

Page 17: GEO600 during S5

Sensitivity; tuned vs. 550Hz detuned

Page 18: GEO600 during S5

Sensitivity; tuned vs. 550Hz detuned (normalized to 550Hz)

Page 19: GEO600 during S5

BS Violin Modes

Page 20: GEO600 during S5

BS Violin Modes

660 670 680 690 700 710 720

10-23

10-22

10-21

10-20

10-19

10-18

10-17

nfft/fs = 100.00 : navs = 1 : enbw = 0.02 : nsecs = 100

Am

pli

tud

e (V

rms)

Frequency (Hz)

G1:DER_DATA_Hfs = 16384 : 2006-06-22 16:58:20 -

data2

G1:DER_DATA_Hfs = 16384 : 2006-06-20 16:58:20 -

data4

Page 21: GEO600 during S5

BS Violin Modes

0 1 2 3 4 5 6

x 105

10-22

10-21

10-20

10-19

10-18

10-17

10-16

time [s]

Vio

lin

mod

e am

pli

tud

e in

h [

rms]

688.7100

689.0500

710.2000711.0300

713.7500

685.9300

Qs f

0.66x108 688.71

0.58x108 689.05

0.65x108 710.20

0.58x108 711.03

0.69x108 713.75

0.88x108 685.93

0 1 2 3 4 5 6 7 8

x 104

10-21

10-20

10-19

10-18

10-17

10-16

time [s]

Vio

lin

mod

e am

pli

tud

e in

h [

rms]

688.7100

689.0500

710.2000711.0300

713.7500

685.9300

Page 22: GEO600 during S5

Glitches (MIC-VIS, Sine gaussians, Magnetic, Power ups, Seismic etc.)

(see Josh‘s glitch talk)

100

101

102

103

104

10-24

10-22

10-20

10-18

10-16

10-14

10-12

10-10

10-8

Frequency (Hz)

Am

pli

tud

e (V

rms

/ H

z1/2 )

nfft/fs = 1.00 : navs = 1 : enbw = 1.50 : nsecs = 1

G1:DER_DATA_Hfs = 16384 : 2006-04-25 14:04:56

Page 23: GEO600 during S5

Seismic improvements(here: backing pumps)

AC outdoor unit

Page 24: GEO600 during S5

The Owl

Page 25: GEO600 during S5

Chasing the owl; different alignments

Page 26: GEO600 during S5

Chasing the owl; different alignments

Page 27: GEO600 during S5

Chasing the owl; different alignments yet

Page 28: GEO600 during S5

Chasing the owl… away

• Spotted and repaired bad contact in SR-2f module

• Since then the owl is gone !???... So far

• Strange, as the owl was there before the module....

Page 29: GEO600 during S5

0.782 Hz spaced line forests

h(t). 0.7e-13/f^2 * TCIb_Mag_X fits pretty well for a 80Hz < f < 620 Hz

Factor 2 off @ 600Hz

Page 30: GEO600 during S5

Mag. Lines @ 600 Hz

Page 31: GEO600 during S5

Magnetic features in Central

Page 32: GEO600 during S5

Magnetic features in Central cntd.

Page 33: GEO600 during S5

Magnetic features in East house

Page 34: GEO600 during S5

Magnetic lines sometimes gone !?

Page 35: GEO600 during S5

(magnetic) 0.782 Hz lines self made with UPSs?

Page 36: GEO600 during S5

Hourly glitches on mains: ‚Rundsteuersignal‘

Magnetic coupling from mains to h(t) might have to do with too many N – PE connections

Page 37: GEO600 during S5

Some detective work

Page 38: GEO600 during S5

S5: a piece of detective work

Page 39: GEO600 during S5

S5: a piece of detective workSeismic correlations between the 3 corner stationsfor one of the events

Time [s]

Cor

rela

tion

[%

]

C/EN/C

N/E

Page 40: GEO600 during S5

S5: a piece of detective work

Page 41: GEO600 during S5

S5: a piece of detective work

Preparing gravel mining

KBU Kies & Baustoffunion

Page 42: GEO600 during S5

Ripples in h(t)

Page 43: GEO600 during S5

Ripples in h(t)

come from seismic in the north

Page 44: GEO600 during S5

Problems (solved & remaining)

• Glitches (Josh)– Dust– Saturations– Magnetic– Sine Gaussians– Power up– Others

• Other problems– Mains: hourly glitches, lines forests, ground currents– PPD– Periodic disturbances probably from end buildings –> coated lenses in

next maintenace period– Seismic: isolated many machines(pumps, ACs, fans etc, even some

computers in CB)– Vetoes: worked a lot on vetoing glitch events. Can veto about 30%(?)

of glitches

Page 45: GEO600 during S5

Future:

• Continue S5

• Decide on maintenance period in autumn

• find power losses

• increase to full injected power

Page 46: GEO600 during S5

Subtracting MID AA Feedback noise from H in the time domain (Josh)

Conclusions:- Works well ! - Time-domain subtraction of MID AA FBs using _very_ simple filters already improves H factor 2-3 from 10-70Hz.- H with MID AA FBs subtracted is not too far from SR FB 10-80Hz.- Improving this in hardware would be better because software subtraction won't reduce upconversion.

Page 47: GEO600 during S5

Phase noise couplingNot confirmed by coherence