Bhide & Hall Architects, P.A. GREEN COVE SPRINGS est . 1874

GREEN COVE SPRINGSConstruction Bid Documents - Completed Oct. 31, 2015 Council Approval Bidding - 30 days Bid Award Construction Contract Construction Dec. 15 - May 15, 2016 Prepare

  • Upload
    others

  • View
    2

  • Download
    0

Embed Size (px)

Citation preview

Page 1: GREEN COVE SPRINGSConstruction Bid Documents - Completed Oct. 31, 2015 Council Approval Bidding - 30 days Bid Award Construction Contract Construction Dec. 15 - May 15, 2016 Prepare

Bhide & Hall Architects, P.A.

GREEN COVE SPRINGS

e s t . 1 8 7 4

Page 2: GREEN COVE SPRINGSConstruction Bid Documents - Completed Oct. 31, 2015 Council Approval Bidding - 30 days Bid Award Construction Contract Construction Dec. 15 - May 15, 2016 Prepare

Introduce Design Team

Project Approach

Schedule

Design Concepts

Page 3: GREEN COVE SPRINGSConstruction Bid Documents - Completed Oct. 31, 2015 Council Approval Bidding - 30 days Bid Award Construction Contract Construction Dec. 15 - May 15, 2016 Prepare

• Local Firm • Established in 1974

• 16 Employees • 6 Registered Architects

Page 4: GREEN COVE SPRINGSConstruction Bid Documents - Completed Oct. 31, 2015 Council Approval Bidding - 30 days Bid Award Construction Contract Construction Dec. 15 - May 15, 2016 Prepare

B h i d e & H a l l A r c h i t e c t s , P. A .

A R C H I T E C T S Bob McVeigh, Principal Brian Sawyer, Principal Wendell Hall, Principal Sandy Ciciora, Architect Paul Lutton, Architect Amit Vaswani, Architect P R O J E C T M A N A G E R S Jaime Mendoza

A R C H I T E C T I N T E R N S Ahmon Williams Alex Knoll Lauren Wells Patrice Garrett Peter Ryan C A D D T E C H N I C I A N S Ivette Crespo Dylan Deguzman

L A N D S C A P E A R C H I T E C T Castle Bay Design & Studio Jonathan Daniels, RLA M E C H A N I C A L E N G I N E E R M.V. Cummings Engineers, Inc. Wayne Kelly, P.A. C I V I L E N G I N E E R Michele Agee, P.E., P.A. Michele Agee, P.E.

S T R U C T U R A L E N G I N E E R JAMSE Engineering, Inc. John Miller, P.E. E L E C T R I C A L E N G I N E E R Haddad Engineering, Inc. Namir Haddad, P.E.

Page 5: GREEN COVE SPRINGSConstruction Bid Documents - Completed Oct. 31, 2015 Council Approval Bidding - 30 days Bid Award Construction Contract Construction Dec. 15 - May 15, 2016 Prepare
Page 6: GREEN COVE SPRINGSConstruction Bid Documents - Completed Oct. 31, 2015 Council Approval Bidding - 30 days Bid Award Construction Contract Construction Dec. 15 - May 15, 2016 Prepare

Wild Waters Recreational Facility

Typhoon Lagoon Water Park Expansion

Friendship Fountain

JAWS Universal Studios

Page 7: GREEN COVE SPRINGSConstruction Bid Documents - Completed Oct. 31, 2015 Council Approval Bidding - 30 days Bid Award Construction Contract Construction Dec. 15 - May 15, 2016 Prepare

Accessible Design

Subsurface Conditions

Project Schedule

Budget

Operations and Maintenance

Park Context

Page 8: GREEN COVE SPRINGSConstruction Bid Documents - Completed Oct. 31, 2015 Council Approval Bidding - 30 days Bid Award Construction Contract Construction Dec. 15 - May 15, 2016 Prepare

Fieldwork: Existing Conditions / Existing Drawings

Design Conference with Staff / Final Scope

Confirmed Layout Concept

Plans and Specifications

Bidding

Construction Administration

Page 9: GREEN COVE SPRINGSConstruction Bid Documents - Completed Oct. 31, 2015 Council Approval Bidding - 30 days Bid Award Construction Contract Construction Dec. 15 - May 15, 2016 Prepare

RESEARCH on Existing Conditions

Page 10: GREEN COVE SPRINGSConstruction Bid Documents - Completed Oct. 31, 2015 Council Approval Bidding - 30 days Bid Award Construction Contract Construction Dec. 15 - May 15, 2016 Prepare

V A L I D A T I O N M E E T I N G CONCENSUS PRO GRAM SCHEMATIC CONCEPTS

Design Criteria Confirm Project Scope Prioritize Budget Project Schedule

Site Plan Floor Plans Building Elevation Cost Estimate

Architect / City Staff Maintenance / Engineers

Page 11: GREEN COVE SPRINGSConstruction Bid Documents - Completed Oct. 31, 2015 Council Approval Bidding - 30 days Bid Award Construction Contract Construction Dec. 15 - May 15, 2016 Prepare

o Finalize Site Plan & Floor Plan o Outline Specifications o Building Systems o Cost Estimate

o Construction Plans & Specifications for Building Permit and Bidding

o Submission to Building Department o Cost Estimate

FINAL PLANS

DESIGN DEVELOPMENT

Page 12: GREEN COVE SPRINGSConstruction Bid Documents - Completed Oct. 31, 2015 Council Approval Bidding - 30 days Bid Award Construction Contract Construction Dec. 15 - May 15, 2016 Prepare

BIDDING

o Responses to contractor’s questions o Issue addenda

CONSTRUCTION

o On-site Construction Meetings - OAC

o Review/certify Contractor’s pay requests

o Site visits as needed

o Timely response to Contractor Request for Information (RFI’S)

o Submittal Review

o Finish color selection prepared for Owner’s review and approval

o Project punch out

o Delivery of close-out documents

Page 13: GREEN COVE SPRINGSConstruction Bid Documents - Completed Oct. 31, 2015 Council Approval Bidding - 30 days Bid Award Construction Contract Construction Dec. 15 - May 15, 2016 Prepare

Select Des ign Team

Des ign Team Contract

Schematic Des ign

City Counci l review/approvalPresentation to Counci l

Des ign Deveopment

Counci l review/approval

Construction Bid Documents - Completed Oct. 31, 2015

Counci l Approval

Bidding - 30 days

Bid Award

Construction Contract

ConstructionDec. 15 - May 15, 2016

Prepare Separate Documents Punch Lis t / Close-outfor pool demol i tion

OPEN MAY 30, 2016POOL City Counci l Approval MEMORIAL DAYDEMOLITIONOPTIONAL BiddingSCHEDULE

Bid Award

Demol i tion Contract

Demol i tion of poolprior to new construction

JUL AUG SEPT OCT MAY JUN JUL AUG SEPT2015 2016

NOV DEC JAN FEB MAR APRMAY JUN

Page 14: GREEN COVE SPRINGSConstruction Bid Documents - Completed Oct. 31, 2015 Council Approval Bidding - 30 days Bid Award Construction Contract Construction Dec. 15 - May 15, 2016 Prepare
Page 15: GREEN COVE SPRINGSConstruction Bid Documents - Completed Oct. 31, 2015 Council Approval Bidding - 30 days Bid Award Construction Contract Construction Dec. 15 - May 15, 2016 Prepare
Page 16: GREEN COVE SPRINGSConstruction Bid Documents - Completed Oct. 31, 2015 Council Approval Bidding - 30 days Bid Award Construction Contract Construction Dec. 15 - May 15, 2016 Prepare
Page 17: GREEN COVE SPRINGSConstruction Bid Documents - Completed Oct. 31, 2015 Council Approval Bidding - 30 days Bid Award Construction Contract Construction Dec. 15 - May 15, 2016 Prepare

o Local Firm with Resources and Staff o A Team with experience in components of

this project o Positive and practical approach to o Design o Budget o Construction Administration

Page 18: GREEN COVE SPRINGSConstruction Bid Documents - Completed Oct. 31, 2015 Council Approval Bidding - 30 days Bid Award Construction Contract Construction Dec. 15 - May 15, 2016 Prepare

Thank You