Groung Investigation and Ground Improvement Techniques for Developing Mining Pond Lands Economically

Embed Size (px)

Citation preview

  • 8/4/2019 Groung Investigation and Ground Improvement Techniques for Developing Mining Pond Lands Economically

    1/12

    GROUND INVESTIGATION AND GROUND IMPROVEMENT TECHNIQUES FOR

    DEVELOPING MINING POND LANDS ECONOMICALLY

    Nathan Narendranathan1 and Bandula Samarasinghe2

    1.Managing Director, Infra Tech Pty Ltd, 2 Jones Street, OConnor, WA 6163, Australia. ([email protected])

    2.

    Group General Manager (Corporate Sustainability and R&D), Infra Tech Pty Ltd, 2 Jones Street, OConnor, WA6163, Australia. ([email protected])

    ABSTRACT

    Brown field sites such as mining tailings ponds, old quarries and old landfills are common in most countries. The lack

    of cost effective and technically sound approaches have meant that the developers had only one choice of ground

    improvements, which is piling for all structures to be erected on such sites with deep loose or soft deposits. This paper

    provides an overview of how mining pond land can be assessed rapidly and strengthened economically to enable

    building of low rise, medium rise or even high rise structures that will not experience large settlement and differential

    settlements. Case histories from Malaysia and Australia will be presented on site investigations using shear wave

    techniques and Controlled Dynamic Compaction and other ground improvement techniques for effective ground

    strengthening.

    1. INTRODUCTION

    Mining for earths resources such as metals, precious stones, construction materials and salt has been in progress for

    thousands of years. Processes relating to mining involve excavation, separations, chemical or physical processing and

    finally the storage of waste products. These waste products could be solids or soft slimes. The soft wet slimes or pastes

    are termed as tailings and the storage locations of those are called tailings ponds or tailings dams. Tailings ponds

    normally contain very soft slimes and sediments and remain in this condition for decades after the mine closure. This

    not only poses a hazard but also creates impediments in developing these locations after mining has ceased. Several

    countries have requirements for mining pond or tailing pond closures before a mining company can be released from

    their obligations. However, in the past such regulations did not exist and hence in most countries there is a legacy of old

    disused mining ponds. This paper provides an overview of the various geotechnical issues associated with developing

    such sites and some of the ongoing research being undertaken in the authors organisation.

    2. SITE INVESTIGATIONS AND POINTS TO NOTE

    The first step in the process of tailings pond rehabilitation is the characterisation of the spatial distribution of the

    material depths, variability in depths, depth to hard layer, and assessing the physical and chemical properties of the

    sediments or slimes. Properties of interest to geotechnical engineers are the strength, solids content or moisture content,

    permeability and compressibility, to name a few.

    Also, resolving the practical issues such as access into the slime pond is vital and need to be addressed early in the

    developments. Floating access platforms made of bamboo poles and geosynthetics are possible options. Floating

    Marsh Buggies and air cushion vehicles such as hovercraft can be used for very soft areas. Figure 1 shows an air

    cushion supported work platform operating in a slimy environment as associated with tailings ponds.

  • 8/4/2019 Groung Investigation and Ground Improvement Techniques for Developing Mining Pond Lands Economically

    2/12

    Figure 1: Air cushion supported work platform

    The authors recommend the use of non invasive geophysical investigations as an economical means of obtaining a

    preliminary assessment of the sub soil strata. Echo sounding, seismic wave measurements, electromagnetics are some

    techniques that have been used with success as they can provide inidcation of sediments and hard layer profiles. Figures2, 3 and 4 provides information relating to different geophysical techniques that may be used in investigations.

    Ground Penetrating

    radar

    Figure 2: Typical Ground Penetrating Radar (GPR) profile

  • 8/4/2019 Groung Investigation and Ground Improvement Techniques for Developing Mining Pond Lands Economically

    3/12

    Figure 3: Typical seismic shear wave velocity profile

    Figure 4: Clay mine pond filled with slurry investigated by Electro Magnetics

    The geophysical investigative techniques will provide a rapid and cost effective means of looking at depth variations,

    layering, and changes in strengths. Seismic shear wave technique has been very promising in the above approach.

    Geophysical techniques can be complemented by relatively inexpensive Mackintosh Probing. These methods can

    precede traditional drilling and sampling or probing by Dutch Cone Penetrometers.

    Since the engineering properties will be governed by the geochemistry of the tailings, it is very important to carry out

    chemical and geochemical analysis of the tailings to assess the components in the tailings. This can be done by X ray

    diffraction, scanning electron microscopy along with more conventional mass spectrometry techniques. The authors

    recommend the use of assessing the specific surface area and mineral types by Methylene Blue Test (MBT), which is a

    rapid and inexpensive filed test. Correlations can be developed between engineering properties and MBT values basedon the exchangeable ions determination.

    An adequate investigation is a pre requisite for an in-depth understanding of the tailings properties and hence will

    influence the selection and design of economical ground improvement processes.

    While using investigative techniques such as Dutch Cone Penetrometer for probing to measure the cone resistance and

    sleeve friction is very useful it should also be borne in mind that the empirical equations correlating the cone resistance

    and sleeve friction to various engineering properties such as bearing capacity, elastic modulus etc. were established for

    soils and not mining pond slimes. These tests could be used to get a relative assessment of the ground conditions which

  • 8/4/2019 Groung Investigation and Ground Improvement Techniques for Developing Mining Pond Lands Economically

    4/12

    should be followed by some form of sampling and testing, especially if local experience or knowledge base is not

    available.

    3. RHEOLOGY AND ENGINEERING PROPERTIES OF MINING SLIMES

    Though mine tailings and slimes are derivatives of soils and rocks, it should be borne in mind that the mining and mineprocessing operations and any chemicals used in the processing might have rendered the tailings with different

    properties to soft clays or silts. The geochemistry and electro chemistry of the slimes could be changed thereby

    affecting the application of traditional engineering analytical equations or even ground improvement techniques. In

    general many of the tailings will tend to have a large negative charge on them. Furthermore the amount of

    exchangeable ions (cat ions) will determine how stable the tailings will be after strengthening and will in fact have a

    major influence on the strengthening process. Chemical or other additives used in the processing of the mineral may

    also be present in the slimes and this need to be factored into. The grading of the fines and the types of minerals present

    in the slimes will have an effect on the engineering properties.

    Depending on the age of the tailings the solid content could vary from 15% to 50%. The sedimentation process is often

    very slow due to the fact that the fine particles possess large negative charge which prevents rapid agglomeration and

    setting. Sampling of these slimes and carrying out tests such as one dimensional consolidation test is quite common in

    the geotechnical industry. The consolidation test data are used to assess compressibility, prediction of settlements etc

    using conventional one dimensional small strain consolidation theory.

    It should be noted that conventional consolidation theory will not give representative predictions of settlements,

    consolidation times etc. since this approach does not account for the change in permeability of the tailings as

    consolidations proceed. In addition the coupling of the soil particle settlement and fluid movement is also not

    accounted for. It is necessary to use large strain consolidation theory which accounts for the change in permeability of

    the setting sediments or tailings. In the 1960s and 1970s, treatment of the mathematics associated with large strain

    consolidation theory was difficult and hence simplified finite difference modelling was used. However with the

    development of powerful computers it is now possible to use 2D and 3D consolidation analysis using large strain

    consolidation theory.

    In a technical and contractual sense application of inappropriate predictive tools can not only lead to uncertainties in

    settlement prediction but also contractual disputes between clients and ground improvement specialists.

    4. TRADITIONAL APPROACHES FOR BUILDING ON BROWN FIELD SITES

    4.1 LEAVE AS IS WITH SURCHARGE FOR SEDIMENTATION

    In the past the view has been to leave the site to sediment for decades with some amount of surcharge fill placed in

    stages. This will seldom work since the low permeability of most tailings will require several decades before

    appreciable improvements can be seen to the strength and compressibility. Relying on evaporation also is not reliable

    since a dry crust forms during intense evaporation and this crust reduces further long term evaporation of the underling

    slimes. Figure 5 shows a coal mine tailing pond after 20 years of closure.

  • 8/4/2019 Groung Investigation and Ground Improvement Techniques for Developing Mining Pond Lands Economically

    5/12

    Figure 5: Coal mine tailing pond after 20 years

    4.2 PILING

    There is a view that piling of any structures built on tailings ponds will prevent settlement. This is partially correct and

    may not always be the most functional solution. See Figure 6, showing differential settlement. Most tailings ponds are

    filled up to create a platform that is above the flood levels or to match surrounding developments and roads. The newly

    placed fill will trigger settlements in the underlying soft slimes. This settlement (unless accelerated) will occur over 10

    to 25 years depending on the permeability of the slimes. Piles supporting any structures will then be subjected to down

    drag forces (called negative friction) and hence will be overloaded. If the piles are designed to withstand these negative

    friction forces then the cost of piling tends to be expensive. Furthermore settlement of the fill platform will cause

    breakage and differential settlement between piled structures and other un piled pipelines, roads, aprons etc that are

    supported directly on the fill.

    Figure 6: Photo of differential settlement behind piled bridge

    Thus it is apparent that ground improvement of mine tailings ponds will be required if sustainable and economical infra

    structure developments are to be undertaken in such areas. The significance of this for a country like Malaysia can be

    appreciated when it is realised that many of the mining areas have been located very close to large cities and towns as

    shown in the mine location plan in Figure 7.

  • 8/4/2019 Groung Investigation and Ground Improvement Techniques for Developing Mining Pond Lands Economically

    6/12

    Figure 7: Mining areas in Peninsula Malaysia (From Mineral Distribution Map of peninsula Malaysia 6th

    edition 1973)

    5. GROUND IMPROVEMENT SOLUTIONS

    The approaches and technologies available for ground strengthening are constantly evolving. These techniques must

    consider the following factors.

    Type of soils Type and magnitude of loads Time available for ground improvement Constraints placed by surrounding developments Availability of skilled geotechnical personnel Cost

    Some of these technologies applied in Malaysia and Australia are discussed in this paper. Figure 8 shows a slime pond

    with fresh slime being pumped in for storage.

  • 8/4/2019 Groung Investigation and Ground Improvement Techniques for Developing Mining Pond Lands Economically

    7/12

    Figure 8: A slime pond with fresh slime being pumped in for storage

    5.1 HIGH IMPACT ENERGY DYNAMIC COMPACTION (HIEDYC)

    There are many techniques that use high impact dynamic energy for the compaction of ground. The methods of

    delivering dynamic compaction energy to the ground include dropping heavy weights on the ground from a height

    traditionally called Dynamic Compaction (DC), imparting dynamic energy on a compaction plate placed on the ground

    by varied means and imparting energy on the ground by rolling a non circular drum on the ground to be compacted,

    referred to as HIEDYC in this paper. The method of compaction adopted depends on many factors, such as the type of

    soil, depth to water table, strength requirement and the depth of improvement required.

    A heavy drum with a square cross section has been pulled using a prime mover so that the roller continues to thump the

    ground imparting the energy as it advances. Compactors with various cross sections have been adapted such as

    triangular and pentagonal. Over the years, these shapes have been refined to maximise the ground compaction depth and

    minimise vibration when being towed at appropriate speeds.

    The depth of improvement and strengths achieved in different compaction techniques depend on the type and condition

    of the soil, size and shape of the compactor and the travel speed. Based on these factors, the cost and time required for

    compaction vary as well.

    HIEDYC compaction has been applied to sands, silts, silty sands, sandy clays and clays at moisture contents not

    exceeding OMC +4%. In general, it was assumed that HIEDYC process is applicable to sands only. However, HIEDYC

    has been applied successfully for the compaction of clay fills according to authors past project experience.

    Figure 9 shows the application of HIEDYC in clay fills at Senai Desaru Expressway in Malaysia, a 77km long highway

    in the Malaysian road network (Infra Tech Pty Ltd 2008).

  • 8/4/2019 Groung Investigation and Ground Improvement Techniques for Developing Mining Pond Lands Economically

    8/12

    Figure 9: Application of HIEDYC on clay fills at Senai Desaru Expressway in Malaysia and Cowal Gold Mine, New

    South Wales

    A summary of typical soil properties from some projects where the successful compaction achieved using HIEDYC

    deep compaction is presented in Table 1.

    Table 1: Summary of typical soil properties from some ITPL projects where the compaction was successfully achieved

    using HIEDYC deep compaction.

    Project type of soilPlastic

    limit

    Liquid

    limitPI

    %

    finesOMC MDD

    Compacted

    moisture

    content

    Remarks

    Senai Desaru

    Expressway,

    Malaysia

    Light

    yellowish

    red motled

    white sandy

    silty clay

    35.97 51.10 15.13 49.8 15.0 1.81 17% to 21% HIEDYC Penta

    mostly compacted

    in wetter than

    OMC

    AMC

    Henderson,

    WA,

    Australia

    GW

    CL

    ML

    NP NP NP 7 10.5 2.03 4% to 6% HIEDYC Penta

    mostly compacted

    very dry22 35 13 95 NT NT

    25 32 7 9 NT NT

    Cowal Gold

    Mine, NSW,

    Australia

    Orange

    brown silty

    clay, tracegravel

    14 35 21 Natural

    moisture

    HIEDYC Penta

    mostly compacted

    in wet state

    Mermaid

    Marine

    Supply Base,

    Dampier,

    WA,

    Australia

    Sandy clay

    Gravelly

    sand

    Silty clay

    18 31 13 62 NT NT Natural

    moisture

    HIEDYC Tria

    mostly compacted

    in dry stateNP NP NP 5 10.1 1.922

    18 52 34 99 NT NT

    NP Non plastic

    NT Not tested

    Source: Project geotechnical reports of Infra Tech Group

    The data in Table 1 demonstrates the applicability of HIEDYC compaction for sands, clays and silts provided the

    appropriate HIEDYC module is used. It was also noted that the soils were compacted at moisture contents ranging

    between 5% wetter to very dry natural moisture state. In addition to soils, HIEDYC has also been used to compact old

    landfills filled with building rubble (Infra Tech Pty Ltd 2009-2).as well as ponds with slimes (Infra Tech Pty Ltd 2004

    and Infra Tech Pty Ltd 2009-3).

    To decide on the most optimum high impact energy ground improvement solutions, it is necessary to have not only anunderstanding of the operational aspect of HIEDYC rollers, but also a sound understanding of geotechnical engineering.

    Due to the requirement of matching the equipment to the ground to be compacted to achieve performance criteria, there

    are several configurations of HIEDYC modules that have been deployed in the projects that are used as case studies in

  • 8/4/2019 Groung Investigation and Ground Improvement Techniques for Developing Mining Pond Lands Economically

    9/12

    this paper. Authors organisation operates these equipment under the trade mark HIEDYC and has three basic

    modules, namely Tria, Qadra and Penta. Table 2 provides basic information of these modules with an overview of their

    capabilities and applications. Photographs of these three modules; Penta, Qadra and Tria are shown in Figure 10.

    Table 2: HIEDYC modules, capabilities and applications

    ModuleNumber of

    sides

    Mass

    (tonnes)

    Mining engineering applications Civil engineering applications

    Tria 3 17 Pit floors/rock crushing, haul roads, soil

    dumps, rock dumps, tailings

    consolidation and strengthening.

    Subgrade compaction, earthwork

    compaction, coarse sand and silt

    compaction and clay soils or slime

    ponds in conjunction with Prefabricated

    Vertical Drains

    Qadra 4 14 Haul roads, soil dumps, tailings

    consolidation and strengthening.

    Subgrade compaction for road

    pavements, earthwork compaction and

    sand and silt compaction not greater

    than 1.5m

    Penta 5 16 Pit floors/rock crushing, haul roads, soil

    dumps, rock dumps, tailings

    consolidation and strengthening.

    Subgrade compaction, earthwork

    compaction, coarse sand and silt

    compaction and clay soils or slime

    ponds in conjunction with Prefabricated

    Vertical Drains

    Figure 10: Photographs of HIEDYC modules, (L to R) Tria, Qadra and Penta

    Application of high impact energy compaction when used in combination with other techniques can be effective andalso the application of this technique can be made much broader, facilitating the compaction of varied types of soils.

    One such application is the use of prefabricated vertical drains in conjunction with HIEDYC for deep compaction of

    clay soils as shown in Figure 11.

    Figure 11: Installation of PVD in old tine mine pond in Kepong and HIEDYC deep compaction over PVD

  • 8/4/2019 Groung Investigation and Ground Improvement Techniques for Developing Mining Pond Lands Economically

    10/12

    5.2 CONTROLLED DYNAMIC COMPACTION (CDYC)

    Another form of deep dynamic compaction suitable for mining pond improvements is Controlled Dynamic Compaction,

    (CDYC).

    CDYC is the acronym for Controlled Dynamic Compaction technique adapted by Infra Tech Pty Ltd. CDYC has been

    found to achieve deeper compaction than that achieved by HIEDYC and was developed by the authors organisation tocater for deep ground improvements.

    The CDYC technique consists of dropping a weight by hydraulics on a steel impact plate varying in diameter between

    1.0m and 1.5m. The hammer weight and the drop height can be changed. In general 10 to 30 blows a minute can be

    imparted on the steel plate by the drop hammer. The greater efficiency of energy transfer (compared to traditional free

    fall Dynamic compaction) is due to the fact that the impact plate is constantly in contact with the ground. Figure 12

    shows the assembly and the CDYC operation in progress, while the Figure 13 shows the stages of CDYC compaction

    from a slimy pond to a developable land.

    Figure 12: CDYC equipment being assembled and CDYC ground improvement work in progress

    Figure 13: CDYC work stages in a swampy site transforming a slimy pond in to a developable land

    The ground strength after CDYC can be assessed by Electric Friction Cone Penetrometer (EFCPT) .or seismic wave

    velocity profiling. Figure 14 show the ground being pegged for testing by EFCPT and the EFCPT equipment

    conducting testing.

  • 8/4/2019 Groung Investigation and Ground Improvement Techniques for Developing Mining Pond Lands Economically

    11/12

    Figure 14: Pegging of EFCPT locations and Tests in Progress after CDYC deep compaction and EFCPT in progress

    5.3 ELECTRO OSMOSIS

    Electro osmotic (EO) consolidation means the consolidation of soft clays by the application of electric current. It wasstudied and applied for the first time by Leo Casagrande (1948). It is inherent that fine grained clay particles with large

    interfacial surface will consolidate and generate significant settlement when loaded. Electro osmosis was originally

    developed as a means of dewatering fine grained soils for the consolidation and strengthening of soft saturated clayey

    soils. Electro osmotic dewatering essentially involves applying an electric potential across the sediment layer. It is the

    process where in positively charged ions move from anode to cathode. I.e. Water moves from anode to cathode where it

    can be collected and pumped out of soil. Electro osmotic flow depends on nature of soil, water content, and pH value

    and on ionic type concentration in the pore water. Due to the applied electric potential, the electrolysis of water occurs

    at the electrodes. Electro osmotic transfer of water through clay is a result of diffuse double layer cations in the clay

    pores being attracted to a negatively charged electrode or cathode.

    When electrodes are placed across saturated clay mass and direct current is applied, water in the clay porespace is transported towards cathode by electro osmosis.

    In addition frictional drag is created by the motion of ions as they move through the clay pores helping totransport additional water.

    The flow generated by the electric gradient is called electro osmotic flow.The ability to consolidate soft sediments without the need for high surcharge fill makes Electro osmosis desirable

    especially when working on very soft ground where surcharge weight cannot be supported. Figure 15 shows electro

    osmosis in progress for soft clay deposits.

  • 8/4/2019 Groung Investigation and Ground Improvement Techniques for Developing Mining Pond Lands Economically

    12/12

    Figure 15: Electro osmosis in progress for soft clay deposits

    6. SUMMARY

    To determine economical and sustainable solutions for the development of mining pond lands, it is necessary to

    understand the soil types through adequate investigations, understand that tailings rheology and consolidation

    mechanisms. Each site will require site specific solutions. HIEDYC, CDYC and EO techniques offer good options that

    can achieve the desired outcome of transforming the mining ponds into developable lands economically and

    sustainably.

    REFERENCES

    Infra Tech Pty Ltd (2004), Closure report for Westport Container Terminal CT4, Malaysia (unpublished).

    Infra Tech Pty Ltd (2008), Closure report for Senai Desaru Expressway Project, Malaysia for Randhill Engineers.

    (unpublished).

    Infra Tech Pty Ltd, (2009 -1), Closure Report for Digesters 6 & 7, Beenyup, WA for Thiess, SKM Consulting and

    W2WA Alliance. (unpublished).

    Infra Tech Pty Ltd, (2009 -2), Closure Report for Lake Coogee Stage 1 Development for VDM Consulting and DM

    Civil. (unpublished).

    Infra Tech Pty Ltd (2009-3), Closure Report for Mermaid Marine, Dampier, WA for Ertech Contractors. (unpublished).