Ongoing Activities7/30/18 - 8/3/18
Upcoming Activities7/30/18 - 8/3/18
Photographs
Safe
tySe
cto
r
• Demolition of ceilings – Phase 2• MEP safe off – Phase 2• Demolition of restrooms – Phase 2• Electrical overhead rough in – Phase 2• Layout of priority walls – Phase 2• Plumbing rough in – Area C Restrooms
Demolition Red Zones• CMU wall infill – Phase 2• Demolition of Media Center – Phase 2• HVAC overhead rough in – Phase 2
From the start of the project, workers on the APS Harper Archer project understand the importance of demolition red zones.
• “Danger Do Not Enter” Signage Installed• Only the demolition crew are allowed in the area. • All proper PPE required.• Silica procedures posted.
Harper Archer Elementary SchoolProject Purpose Statement: Through a highly-phased conversion, we will create a safe and quality learning
space for future generations.
Final Front Entrance of Phase 1
Priority Wall Layout
Harper Archer Elementary SchoolProject Purpose Statement: Through a highly-phased conversion, we will create a safe and quality learning
space for future generations.
Removal of Locker Curbs
Demolition of Floors in Area D Temporary Window Protection in Area E
Demolition of Restrooms in Area D