76
Chiller Plant Design Chiller Plant Design Considerations Considerations Jon R. Haviland, P.E., CEM Assistant Vice President Marx/Okubo Associates [email protected]

Haviland- Chiller Plant Design Considerations

  • Upload
    susi3i

  • View
    595

  • Download
    10

Embed Size (px)

Citation preview

Page 1: Haviland- Chiller Plant Design Considerations

Chiller Plant Design Chiller Plant Design ConsiderationsConsiderations

Jon R. Haviland, P.E., CEMAssistant Vice PresidentMarx/Okubo Associates

[email protected]

Page 2: Haviland- Chiller Plant Design Considerations

Better Buildings by Design 2005 Chiller Plant Design 2

Plant design optionsEquipment optionsNew plant design considerationsRetrofit design considerationsRetrofit project case study

Page 3: Haviland- Chiller Plant Design Considerations

Better Buildings by Design 2005 Chiller Plant Design 3

Plant Design OptionsPlant Design Options

Page 4: Haviland- Chiller Plant Design Considerations

Better Buildings by Design 2005 Chiller Plant Design 4

Single Chiller SystemSingle Chiller System

Loads

Tower

Chiller

TWP

CWP

Page 5: Haviland- Chiller Plant Design Considerations

Better Buildings by Design 2005 Chiller Plant Design 5

Single Chiller SystemSingle Chiller SystemAdvantages– Lower first cost– Simple system for installation and control

Disadvantages– Inefficient at low load conditions– Lack of back-up and redundancy

Page 6: Haviland- Chiller Plant Design Considerations

Better Buildings by Design 2005 Chiller Plant Design 6

Parallel Chiller SystemParallel Chiller SystemTower

Chiller 1

Chiller 2

Loads

TWP1

CWP1

TWP2

CWP2

Page 7: Haviland- Chiller Plant Design Considerations

Better Buildings by Design 2005 Chiller Plant Design 7

Parallel Chiller SystemParallel Chiller SystemAdvantages– More efficient at low load conditions– Provides back-up and/or redundancy

Disadvantages– Increased first cost– More difficult to control effectively, especially with

different size chillers (should have computerized system)

– More equipment to maintain

Page 8: Haviland- Chiller Plant Design Considerations

Better Buildings by Design 2005 Chiller Plant Design 8

Series Chiller SystemSeries Chiller System

CWP

TWP

Tower

Loads

Chiller 2 Chiller 1

Page 9: Haviland- Chiller Plant Design Considerations

Better Buildings by Design 2005 Chiller Plant Design 9

Series Chiller SystemSeries Chiller SystemAdvantages– Easier to control with simple control systems– Effective with different size chillers– Utilize one stand-by pump– Good for large temperature differential systems

Disadvantages– Increased pumping requirements for chilled water– Chillers may not be interchangeable

Page 10: Haviland- Chiller Plant Design Considerations

Better Buildings by Design 2005 Chiller Plant Design 10

PrimaryPrimary--Secondary Chilled Secondary Chilled Water SystemsWater Systems

Page 11: Haviland- Chiller Plant Design Considerations

Better Buildings by Design 2005 Chiller Plant Design 11

PrimaryPrimary--Secondary Chilled Secondary Chilled Water SystemsWater Systems

Advantages– Uncouples chillers and loads to allow variable flow in

loads– Can be used with large temperature differential systems– Can be used with thermal storage systems– Can be used with water-side economizer systems– Improved control– Reduced operating costs

Page 12: Haviland- Chiller Plant Design Considerations

Better Buildings by Design 2005 Chiller Plant Design 12

PrimaryPrimary--Secondary Chilled Secondary Chilled Water SystemsWater Systems

Disadvantages– Higher first costs– Requires more, sophisticated equipment– Requires sophisticated control system

Page 13: Haviland- Chiller Plant Design Considerations

Better Buildings by Design 2005 Chiller Plant Design 13

Variable Flow PrimaryVariable Flow Primary

New chillers can operate with variable flowSimplifies system designBypass with modulating control valve required to maintain minimum flowSystem can be parallel or series design

Page 14: Haviland- Chiller Plant Design Considerations

Better Buildings by Design 2005 Chiller Plant Design 14

Equipment OptionsEquipment Options

Page 15: Haviland- Chiller Plant Design Considerations

Better Buildings by Design 2005 Chiller Plant Design 15

Electric ChillersElectric Chillers

Reciprocating chillersRotary screw chillersCentrifugal chillersAir-cooled chillers

Page 16: Haviland- Chiller Plant Design Considerations

Better Buildings by Design 2005 Chiller Plant Design 16

NonNon--electric Chillerselectric Chillers

Absorption chillers– Single-effect absorption chiller

Low pressure steamHot waterUse in CHP applications

– Double-effect absorption chillersMedium pressure steamDirect-firedHeat recovery

Page 17: Haviland- Chiller Plant Design Considerations

Better Buildings by Design 2005 Chiller Plant Design 17

NonNon--electric Chillerselectric Chillers

Centrifugal or screw chiller without electric motor– Natural gas engine– Steam turbine– Dual drive – engine and electric motor

Page 18: Haviland- Chiller Plant Design Considerations

Better Buildings by Design 2005 Chiller Plant Design 18

Other Cooling SourcesOther Cooling Sources

Air-side economizerWater-side economizerThermal energy storage

Page 19: Haviland- Chiller Plant Design Considerations

Better Buildings by Design 2005 Chiller Plant Design 19

New Plant Design New Plant Design ConsiderationsConsiderations

Determine requirementsDesign processAfter construction considerations

Page 20: Haviland- Chiller Plant Design Considerations

Better Buildings by Design 2005 Chiller Plant Design 20

Determine RequirementsDetermine Requirements

Capacity required– Current load– Potential future loads– Redundancy requirement– Provisions for special loads

Page 21: Haviland- Chiller Plant Design Considerations

Better Buildings by Design 2005 Chiller Plant Design 21

Determine RequirementsDetermine Requirements

Operating profile– Hours per day– Days per week– Continuous loads– Load diversity

Page 22: Haviland- Chiller Plant Design Considerations

Better Buildings by Design 2005 Chiller Plant Design 22

Design ProcessDesign Process

Schematic design of possible options– Chiller sizing– Chiller Performance– Cooling sources– Operating temperatures– Cooling tower selection– Basic plant layout

Page 23: Haviland- Chiller Plant Design Considerations

Better Buildings by Design 2005 Chiller Plant Design 23

Chiller SizingChiller Sizing

Benefits of different size chillers– Fewer total operating hours– More operation above 50% load

Depends on load profile

Page 24: Haviland- Chiller Plant Design Considerations

Better Buildings by Design 2005 Chiller Plant Design 24

Even Chillers - 8,463 operating hours

Page 25: Haviland- Chiller Plant Design Considerations

Better Buildings by Design 2005 Chiller Plant Design 25

Uneven Chillers - 7,624 operating hours

Page 26: Haviland- Chiller Plant Design Considerations

Better Buildings by Design 2005 Chiller Plant Design 26

Chiller SizingChiller Sizing

Use of different size chillers may eliminate need for pony chillerVariable speed chillers provide improved part load performance and minimum capacity

Page 27: Haviland- Chiller Plant Design Considerations

Better Buildings by Design 2005 Chiller Plant Design 27

Chiller Performance RatingsChiller Performance RatingsAmerican Refrigeration Institute Standard 550/590-98Standard conditions– Full load– Chilled water temperatures - 54 F to 44 F– Condenser water temperatures - 85 F to 95 F

Efficiency rating - kW/Ton

Page 28: Haviland- Chiller Plant Design Considerations

Better Buildings by Design 2005 Chiller Plant Design 28

Chiller Performance RatingsChiller Performance RatingsPart load efficiency– Integrated Part Load Value (IPLV)

Standard temperature conditionsWeighted average of kW/ton at various loads

– Non-standard Part Load Value (NPLV)Specific application temperaturesSame weighting as IPLV

Page 29: Haviland- Chiller Plant Design Considerations

Better Buildings by Design 2005 Chiller Plant Design 29

Chiller Performance RatingsChiller Performance RatingsIPLV/NPLV rating scale– A = kW/ton at 100% load– B = kW/ton at 75% load– C = kW/ton at 50% load– D = kW/ton at 25% load

ARI Standard 550-98– IPLV = 1/(0.01/A + 0.42/B + 0.45/C + 0.12/D)

Page 30: Haviland- Chiller Plant Design Considerations

Better Buildings by Design 2005 Chiller Plant Design 30

Cooling SourcesCooling Sources

Use of different fuel sources provides flexibility and reliabilityTypes to be considered depend on several factors– Utility rates and structure– Load profile– Air quality considerations– Maintenance considerations

Page 31: Haviland- Chiller Plant Design Considerations

Better Buildings by Design 2005 Chiller Plant Design 31

Cooling SourcesCooling Sources

Economizer cycle– Air-side generally most effective– Water-side use

Building configuration does not allow air-sideCooling for special load requirementsClimatic considerations

Page 32: Haviland- Chiller Plant Design Considerations

Better Buildings by Design 2005 Chiller Plant Design 32

Operating TemperaturesOperating Temperatures

Chilled water supply temperature– Lower supply temperature

Reduced air flow requirementsImproved dehumidificationIncreased chiller operating cost versus reduced fan operating costs, especially with a VAV system

Page 33: Haviland- Chiller Plant Design Considerations

Better Buildings by Design 2005 Chiller Plant Design 33

Operating TemperaturesOperating Temperatures

Chilled water ∆T– Higher ∆T means reduced pipe size and

pumping requirement, increased coil size, and reduced fan energy

– Optimum temperature depends on amount of piping in system

Page 34: Haviland- Chiller Plant Design Considerations

Better Buildings by Design 2005 Chiller Plant Design 34

Chilled Water Chilled Water ∆∆T T ComparisonComparison

Page 35: Haviland- Chiller Plant Design Considerations

Better Buildings by Design 2005 Chiller Plant Design 35

Operating TemperaturesOperating Temperatures

Condenser water supply temperature– Lower supply temperature improves chiller

efficiency– Approach temperature can be 6 – 10 ºF above

design wet bulb– Use 0.4% design temperature data

Page 36: Haviland- Chiller Plant Design Considerations

Better Buildings by Design 2005 Chiller Plant Design 36

Operating TemperaturesOperating Temperatures

Condenser water ∆T– Normal 10ºF works well in most cases– Larger ∆T common with absorption chillers

due to higher load and should be considered for large systems or when the cooling tower is remote from the chiller plant

– Reduced chiller efficiency versus smaller pipes and reduced pumping horsepower

Page 37: Haviland- Chiller Plant Design Considerations

Better Buildings by Design 2005 Chiller Plant Design 37

Cooling Tower SelectionCooling Tower Selection

Selection should be based on required water flow, optimum approach temperature and ∆TAllowance for potential tenant equipment loadSelection should based on water-side economizer conditions if that is part of system

Page 38: Haviland- Chiller Plant Design Considerations

Better Buildings by Design 2005 Chiller Plant Design 38

Cooling Tower SelectionCooling Tower Selection

Increasing size of the cooling tower is generally the least expensive way to improve the efficiency and provide some safety margin in the systemUse of variable speed drive on the fan motor minimizes any operating cost penalty

Page 39: Haviland- Chiller Plant Design Considerations

Better Buildings by Design 2005 Chiller Plant Design 39

Determine Basic Plant Determine Basic Plant LayoutLayout

Select system that will best fit needs of projectFor simpler systems, parallel system with different size chillers is probably best choice

Page 40: Haviland- Chiller Plant Design Considerations

Better Buildings by Design 2005 Chiller Plant Design 40

Determine Basic Plant Determine Basic Plant LayoutLayout

Systems with different occupancy schedules or load requirements need more complex system– Primary-secondary plant offers most flexibility– Variable primary flow works with new electric

chillers with less complexity than a primary-secondary system

Page 41: Haviland- Chiller Plant Design Considerations

Better Buildings by Design 2005 Chiller Plant Design 41

Determine Basic Plant Determine Basic Plant LayoutLayout

Large chilled water ∆T– Series plant– Primary-secondary with primary flow greater

than secondary flow

Page 42: Haviland- Chiller Plant Design Considerations

Better Buildings by Design 2005 Chiller Plant Design 42

Design ProcessDesign Process

Analyze options– Opinion of probable costs– Operating cost estimates

Screening measuresEnergy simulation

– Life cycle costs

Page 43: Haviland- Chiller Plant Design Considerations

Better Buildings by Design 2005 Chiller Plant Design 43

Design ProcessDesign Process

Complete design of chosen option– Peer review– Operator review– Determine sequence of operations

Page 44: Haviland- Chiller Plant Design Considerations

Better Buildings by Design 2005 Chiller Plant Design 44

New Plant Design New Plant Design ConsiderationsConsiderations

After construction activities– Commissioning– Training

Page 45: Haviland- Chiller Plant Design Considerations

Better Buildings by Design 2005 Chiller Plant Design 45

Chiller Plant Retrofit Chiller Plant Retrofit ConsiderationsConsiderations

Page 46: Haviland- Chiller Plant Design Considerations

Don’t Simply Replace; Don’t Simply Replace; ReRe--engineerengineer

Page 47: Haviland- Chiller Plant Design Considerations

Better Buildings by Design 2005 Chiller Plant Design 47

Chiller Plant Retrofit Chiller Plant Retrofit ConsiderationsConsiderations

Basic process should follow same steps as outlined aboveAdditional considerations– Engineer and contractor should have experience

with this type of project

Page 48: Haviland- Chiller Plant Design Considerations

Better Buildings by Design 2005 Chiller Plant Design 48

Chiller Plant Retrofit Chiller Plant Retrofit ConsiderationsConsiderations

Additional considerations– Engineer needs to familiarize himself with

existing plantRecord drawingsOperator interviewObservation of plant

Page 49: Haviland- Chiller Plant Design Considerations

Better Buildings by Design 2005 Chiller Plant Design 49

Chiller Plant Retrofit Chiller Plant Retrofit ConsiderationsConsiderations

– Constructability should be considered during design phase

Operator reviewContractor review

– Coordination critical during construction phase

Page 50: Haviland- Chiller Plant Design Considerations

Retrofit Project Case StudyRetrofit Project Case Study

Page 51: Haviland- Chiller Plant Design Considerations

Better Buildings by Design 2005 Chiller Plant Design 51

BackgroundBackground

Vacated single tenant building26 years oldAdjacent buildings under same ownership with sale of one or all unlikelyBuilding to be taken to shell condition and renovated for multi-tenant useDue diligence based on these assumptions

Page 52: Haviland- Chiller Plant Design Considerations

Better Buildings by Design 2005 Chiller Plant Design 52

Site PlanSite Plan

Page 53: Haviland- Chiller Plant Design Considerations

Better Buildings by Design 2005 Chiller Plant Design 53

ParticipantsParticipants

OwnerProject managerProperty managers (2 firms)– Contract maintenance staff

Construction managerConsultants– Architect– Engineer

Page 54: Haviland- Chiller Plant Design Considerations

Better Buildings by Design 2005 Chiller Plant Design 54

Existing Central PlantExisting Central Plant

Located in penthouseTwo 360-ton single effect absorption chillers Two low pressure steam boilers– Modified to meet AQMD requirements– Also provides heating and domestic hot water

Two cell cooling tower– Replaced three years earlier– Capacity for single effect absorption chillers

Page 55: Haviland- Chiller Plant Design Considerations

Better Buildings by Design 2005 Chiller Plant Design 55

Possible OptionsPossible Options

Electric chillersAbsorption chillersEngine-driven chillersThermal storageIndependent or with adjacent building

Page 56: Haviland- Chiller Plant Design Considerations

Better Buildings by Design 2005 Chiller Plant Design 56

Alternatives ConsideredAlternatives Considered

Stand-alone alternatives– Two 350-ton electric chillers– Two 350-ton absorption chillers– Two 350-ton engine-driven chillers– Electric chillers with 4500 ton-hour thermal

storage

Page 57: Haviland- Chiller Plant Design Considerations

Better Buildings by Design 2005 Chiller Plant Design 57

Alternatives ConsideredAlternatives Considered

Integrated alternatives– Provide piping between two buildings – Utilize one of the four options above for the

stand-alone plant

Page 58: Haviland- Chiller Plant Design Considerations

Better Buildings by Design 2005 Chiller Plant Design 58

Alternatives ConsideredAlternatives Considered

Single plant alternatives– Abandon plant in Building 2 and expand plant

in Building 3 with piping between the buildings– Existing Plant in Building 3

Three 250-ton electric chillers in plant on parking level P-2Cooling tower on roof

Page 59: Haviland- Chiller Plant Design Considerations

Better Buildings by Design 2005 Chiller Plant Design 59

Alternatives ConsideredAlternatives Considered

Single plant alternatives– New Equipment possibilities

600-ton electric chillerTwo 350-ton engine-driven chillersTwo low temperature chillers plus 4500 ton-hour thermal storage

Page 60: Haviland- Chiller Plant Design Considerations

Better Buildings by Design 2005 Chiller Plant Design 60

ConstructibilityConstructibility IssuesIssues

Building 2 options– Electric capacity– Cooling tower and structure– Existing chilled water riser size– Noise considerations

Page 61: Haviland- Chiller Plant Design Considerations

Better Buildings by Design 2005 Chiller Plant Design 61

ConstructibilityConstructibility IssuesIssues

Building 3 options– Cooling tower capacity– Condenser water riser size– Thermal storage space requirements– Engine exhaust routing– Electrical capacity

Page 62: Haviland- Chiller Plant Design Considerations

Better Buildings by Design 2005 Chiller Plant Design 62

AnalysisAnalysis

Opinion of probable costsScheduleOperating costs– DOE-2 simulations– Nine options considered

Page 63: Haviland- Chiller Plant Design Considerations

Better Buildings by Design 2005 Chiller Plant Design 63

AnalysisAnalysis

Other considerations– Electricity riser problem in Building 2– Impact of utility deregulation

Page 64: Haviland- Chiller Plant Design Considerations

Better Buildings by Design 2005 Chiller Plant Design 64

Economic AnalysisEconomic Analysis

Based on estimated impact of deregulationFinal options– Integrated system with new chillers in Building

2 connected to Building 3 plant700-tons electric700-tons absorption

Page 65: Haviland- Chiller Plant Design Considerations

Better Buildings by Design 2005 Chiller Plant Design 65

Economic AnalysisEconomic Analysis

First Cost– 700 ton electric

$929,223$1,109,273 with potential bus duct repair

– 700 ton absorption$1,395,247

Page 66: Haviland- Chiller Plant Design Considerations

Better Buildings by Design 2005 Chiller Plant Design 66

Economic AnalysisEconomic Analysis

Annual energy cost– 700 ton electric - $778,160– 700 ton absorption - $680,769

Simple Payback– Without bus riser repair – 4.5 years– With bus riser repair – 1.9 years

Page 67: Haviland- Chiller Plant Design Considerations

Better Buildings by Design 2005 Chiller Plant Design 67

Final ChoiceFinal Choice

Absorption chillers in Building 2 with connection to Building 3– Proactive ownership with long term outlook– Support from local natural gas utility– Optimum conditions for new plant in Building

2– Significant problems with expanding plant in

Building 3

Page 68: Haviland- Chiller Plant Design Considerations

Better Buildings by Design 2005 Chiller Plant Design 68

Chiller PurchaseChiller Purchase

Chiller pre-purchased by owner– Maintain control over final selection and

options– Delivery critical

Potential full building tenant wanted early availabilityCity rigging restrictions – Saturday night only

Page 69: Haviland- Chiller Plant Design Considerations

Better Buildings by Design 2005 Chiller Plant Design 69

Chiller PurchaseChiller Purchase

Bid to major manufacturersBid specified conditions of capacity, giving cost, efficiency, delivery and willingness to accept penalty clauseAllow manufacturers to suggest alternatives of capacity and/or efficiency and additional cost for this

Page 70: Haviland- Chiller Plant Design Considerations

Better Buildings by Design 2005 Chiller Plant Design 70

New Central PlantNew Central Plant

Two 360-ton direct fired absorption chillers with lower supply temperatureOne 120-ton rotary screw chiller for off hours use (minimum effective absorption chiller capacity)Primary-secondary piping systemPiping between the two buildings with transfer pumps and metering

Page 71: Haviland- Chiller Plant Design Considerations

Better Buildings by Design 2005 Chiller Plant Design 71

Single Line DiagramSingle Line Diagram

Page 72: Haviland- Chiller Plant Design Considerations

Better Buildings by Design 2005 Chiller Plant Design 72

Sequence of OperationsSequence of Operations

Seven modes of operation identified with written sequenceIndependent versus integrated operationElectric or gas chiller base loadOccupied versus unoccupied

Page 73: Haviland- Chiller Plant Design Considerations

Better Buildings by Design 2005 Chiller Plant Design 73

Phase IIPhase II

Building 1 central plant– Originally absorption chillers and boilers– Reciprocating chillers installed in 1987

Noise complaintsReliability issues

– Small chiller in Building 3 plant for Fitness Center after hours use with piping to lower level air handling unit

Page 74: Haviland- Chiller Plant Design Considerations

Better Buildings by Design 2005 Chiller Plant Design 74

New Building 1 PlantNew Building 1 Plant

Two centrifugal chillers and new cooling tower– Tower selected for maximum capacity for space

available– Chillers selected to match cooling tower

capacity– Use existing connection (increase size to

maximize transfer capacity) with new riser

Page 75: Haviland- Chiller Plant Design Considerations

Better Buildings by Design 2005 Chiller Plant Design 75

New Single Line DiagramNew Single Line Diagram

Page 76: Haviland- Chiller Plant Design Considerations

Better Buildings by Design 2005 Chiller Plant Design 76

SummarySummary

Project illustrates choices available and retrofit process discussedOwnership with long term outlookCooperation by all participantsLife is easier with a vacant building