Upload
susi3i
View
595
Download
10
Embed Size (px)
Citation preview
Chiller Plant Design Chiller Plant Design ConsiderationsConsiderations
Jon R. Haviland, P.E., CEMAssistant Vice PresidentMarx/Okubo Associates
Better Buildings by Design 2005 Chiller Plant Design 2
Plant design optionsEquipment optionsNew plant design considerationsRetrofit design considerationsRetrofit project case study
Better Buildings by Design 2005 Chiller Plant Design 3
Plant Design OptionsPlant Design Options
Better Buildings by Design 2005 Chiller Plant Design 4
Single Chiller SystemSingle Chiller System
Loads
Tower
Chiller
TWP
CWP
Better Buildings by Design 2005 Chiller Plant Design 5
Single Chiller SystemSingle Chiller SystemAdvantages– Lower first cost– Simple system for installation and control
Disadvantages– Inefficient at low load conditions– Lack of back-up and redundancy
Better Buildings by Design 2005 Chiller Plant Design 6
Parallel Chiller SystemParallel Chiller SystemTower
Chiller 1
Chiller 2
Loads
TWP1
CWP1
TWP2
CWP2
Better Buildings by Design 2005 Chiller Plant Design 7
Parallel Chiller SystemParallel Chiller SystemAdvantages– More efficient at low load conditions– Provides back-up and/or redundancy
Disadvantages– Increased first cost– More difficult to control effectively, especially with
different size chillers (should have computerized system)
– More equipment to maintain
Better Buildings by Design 2005 Chiller Plant Design 8
Series Chiller SystemSeries Chiller System
CWP
TWP
Tower
Loads
Chiller 2 Chiller 1
Better Buildings by Design 2005 Chiller Plant Design 9
Series Chiller SystemSeries Chiller SystemAdvantages– Easier to control with simple control systems– Effective with different size chillers– Utilize one stand-by pump– Good for large temperature differential systems
Disadvantages– Increased pumping requirements for chilled water– Chillers may not be interchangeable
Better Buildings by Design 2005 Chiller Plant Design 10
PrimaryPrimary--Secondary Chilled Secondary Chilled Water SystemsWater Systems
Better Buildings by Design 2005 Chiller Plant Design 11
PrimaryPrimary--Secondary Chilled Secondary Chilled Water SystemsWater Systems
Advantages– Uncouples chillers and loads to allow variable flow in
loads– Can be used with large temperature differential systems– Can be used with thermal storage systems– Can be used with water-side economizer systems– Improved control– Reduced operating costs
Better Buildings by Design 2005 Chiller Plant Design 12
PrimaryPrimary--Secondary Chilled Secondary Chilled Water SystemsWater Systems
Disadvantages– Higher first costs– Requires more, sophisticated equipment– Requires sophisticated control system
Better Buildings by Design 2005 Chiller Plant Design 13
Variable Flow PrimaryVariable Flow Primary
New chillers can operate with variable flowSimplifies system designBypass with modulating control valve required to maintain minimum flowSystem can be parallel or series design
Better Buildings by Design 2005 Chiller Plant Design 14
Equipment OptionsEquipment Options
Better Buildings by Design 2005 Chiller Plant Design 15
Electric ChillersElectric Chillers
Reciprocating chillersRotary screw chillersCentrifugal chillersAir-cooled chillers
Better Buildings by Design 2005 Chiller Plant Design 16
NonNon--electric Chillerselectric Chillers
Absorption chillers– Single-effect absorption chiller
Low pressure steamHot waterUse in CHP applications
– Double-effect absorption chillersMedium pressure steamDirect-firedHeat recovery
Better Buildings by Design 2005 Chiller Plant Design 17
NonNon--electric Chillerselectric Chillers
Centrifugal or screw chiller without electric motor– Natural gas engine– Steam turbine– Dual drive – engine and electric motor
Better Buildings by Design 2005 Chiller Plant Design 18
Other Cooling SourcesOther Cooling Sources
Air-side economizerWater-side economizerThermal energy storage
Better Buildings by Design 2005 Chiller Plant Design 19
New Plant Design New Plant Design ConsiderationsConsiderations
Determine requirementsDesign processAfter construction considerations
Better Buildings by Design 2005 Chiller Plant Design 20
Determine RequirementsDetermine Requirements
Capacity required– Current load– Potential future loads– Redundancy requirement– Provisions for special loads
Better Buildings by Design 2005 Chiller Plant Design 21
Determine RequirementsDetermine Requirements
Operating profile– Hours per day– Days per week– Continuous loads– Load diversity
Better Buildings by Design 2005 Chiller Plant Design 22
Design ProcessDesign Process
Schematic design of possible options– Chiller sizing– Chiller Performance– Cooling sources– Operating temperatures– Cooling tower selection– Basic plant layout
Better Buildings by Design 2005 Chiller Plant Design 23
Chiller SizingChiller Sizing
Benefits of different size chillers– Fewer total operating hours– More operation above 50% load
Depends on load profile
Better Buildings by Design 2005 Chiller Plant Design 24
Even Chillers - 8,463 operating hours
Better Buildings by Design 2005 Chiller Plant Design 25
Uneven Chillers - 7,624 operating hours
Better Buildings by Design 2005 Chiller Plant Design 26
Chiller SizingChiller Sizing
Use of different size chillers may eliminate need for pony chillerVariable speed chillers provide improved part load performance and minimum capacity
Better Buildings by Design 2005 Chiller Plant Design 27
Chiller Performance RatingsChiller Performance RatingsAmerican Refrigeration Institute Standard 550/590-98Standard conditions– Full load– Chilled water temperatures - 54 F to 44 F– Condenser water temperatures - 85 F to 95 F
Efficiency rating - kW/Ton
Better Buildings by Design 2005 Chiller Plant Design 28
Chiller Performance RatingsChiller Performance RatingsPart load efficiency– Integrated Part Load Value (IPLV)
Standard temperature conditionsWeighted average of kW/ton at various loads
– Non-standard Part Load Value (NPLV)Specific application temperaturesSame weighting as IPLV
Better Buildings by Design 2005 Chiller Plant Design 29
Chiller Performance RatingsChiller Performance RatingsIPLV/NPLV rating scale– A = kW/ton at 100% load– B = kW/ton at 75% load– C = kW/ton at 50% load– D = kW/ton at 25% load
ARI Standard 550-98– IPLV = 1/(0.01/A + 0.42/B + 0.45/C + 0.12/D)
Better Buildings by Design 2005 Chiller Plant Design 30
Cooling SourcesCooling Sources
Use of different fuel sources provides flexibility and reliabilityTypes to be considered depend on several factors– Utility rates and structure– Load profile– Air quality considerations– Maintenance considerations
Better Buildings by Design 2005 Chiller Plant Design 31
Cooling SourcesCooling Sources
Economizer cycle– Air-side generally most effective– Water-side use
Building configuration does not allow air-sideCooling for special load requirementsClimatic considerations
Better Buildings by Design 2005 Chiller Plant Design 32
Operating TemperaturesOperating Temperatures
Chilled water supply temperature– Lower supply temperature
Reduced air flow requirementsImproved dehumidificationIncreased chiller operating cost versus reduced fan operating costs, especially with a VAV system
Better Buildings by Design 2005 Chiller Plant Design 33
Operating TemperaturesOperating Temperatures
Chilled water ∆T– Higher ∆T means reduced pipe size and
pumping requirement, increased coil size, and reduced fan energy
– Optimum temperature depends on amount of piping in system
Better Buildings by Design 2005 Chiller Plant Design 34
Chilled Water Chilled Water ∆∆T T ComparisonComparison
Better Buildings by Design 2005 Chiller Plant Design 35
Operating TemperaturesOperating Temperatures
Condenser water supply temperature– Lower supply temperature improves chiller
efficiency– Approach temperature can be 6 – 10 ºF above
design wet bulb– Use 0.4% design temperature data
Better Buildings by Design 2005 Chiller Plant Design 36
Operating TemperaturesOperating Temperatures
Condenser water ∆T– Normal 10ºF works well in most cases– Larger ∆T common with absorption chillers
due to higher load and should be considered for large systems or when the cooling tower is remote from the chiller plant
– Reduced chiller efficiency versus smaller pipes and reduced pumping horsepower
Better Buildings by Design 2005 Chiller Plant Design 37
Cooling Tower SelectionCooling Tower Selection
Selection should be based on required water flow, optimum approach temperature and ∆TAllowance for potential tenant equipment loadSelection should based on water-side economizer conditions if that is part of system
Better Buildings by Design 2005 Chiller Plant Design 38
Cooling Tower SelectionCooling Tower Selection
Increasing size of the cooling tower is generally the least expensive way to improve the efficiency and provide some safety margin in the systemUse of variable speed drive on the fan motor minimizes any operating cost penalty
Better Buildings by Design 2005 Chiller Plant Design 39
Determine Basic Plant Determine Basic Plant LayoutLayout
Select system that will best fit needs of projectFor simpler systems, parallel system with different size chillers is probably best choice
Better Buildings by Design 2005 Chiller Plant Design 40
Determine Basic Plant Determine Basic Plant LayoutLayout
Systems with different occupancy schedules or load requirements need more complex system– Primary-secondary plant offers most flexibility– Variable primary flow works with new electric
chillers with less complexity than a primary-secondary system
Better Buildings by Design 2005 Chiller Plant Design 41
Determine Basic Plant Determine Basic Plant LayoutLayout
Large chilled water ∆T– Series plant– Primary-secondary with primary flow greater
than secondary flow
Better Buildings by Design 2005 Chiller Plant Design 42
Design ProcessDesign Process
Analyze options– Opinion of probable costs– Operating cost estimates
Screening measuresEnergy simulation
– Life cycle costs
Better Buildings by Design 2005 Chiller Plant Design 43
Design ProcessDesign Process
Complete design of chosen option– Peer review– Operator review– Determine sequence of operations
Better Buildings by Design 2005 Chiller Plant Design 44
New Plant Design New Plant Design ConsiderationsConsiderations
After construction activities– Commissioning– Training
Better Buildings by Design 2005 Chiller Plant Design 45
Chiller Plant Retrofit Chiller Plant Retrofit ConsiderationsConsiderations
Don’t Simply Replace; Don’t Simply Replace; ReRe--engineerengineer
Better Buildings by Design 2005 Chiller Plant Design 47
Chiller Plant Retrofit Chiller Plant Retrofit ConsiderationsConsiderations
Basic process should follow same steps as outlined aboveAdditional considerations– Engineer and contractor should have experience
with this type of project
Better Buildings by Design 2005 Chiller Plant Design 48
Chiller Plant Retrofit Chiller Plant Retrofit ConsiderationsConsiderations
Additional considerations– Engineer needs to familiarize himself with
existing plantRecord drawingsOperator interviewObservation of plant
Better Buildings by Design 2005 Chiller Plant Design 49
Chiller Plant Retrofit Chiller Plant Retrofit ConsiderationsConsiderations
– Constructability should be considered during design phase
Operator reviewContractor review
– Coordination critical during construction phase
Retrofit Project Case StudyRetrofit Project Case Study
Better Buildings by Design 2005 Chiller Plant Design 51
BackgroundBackground
Vacated single tenant building26 years oldAdjacent buildings under same ownership with sale of one or all unlikelyBuilding to be taken to shell condition and renovated for multi-tenant useDue diligence based on these assumptions
Better Buildings by Design 2005 Chiller Plant Design 52
Site PlanSite Plan
Better Buildings by Design 2005 Chiller Plant Design 53
ParticipantsParticipants
OwnerProject managerProperty managers (2 firms)– Contract maintenance staff
Construction managerConsultants– Architect– Engineer
Better Buildings by Design 2005 Chiller Plant Design 54
Existing Central PlantExisting Central Plant
Located in penthouseTwo 360-ton single effect absorption chillers Two low pressure steam boilers– Modified to meet AQMD requirements– Also provides heating and domestic hot water
Two cell cooling tower– Replaced three years earlier– Capacity for single effect absorption chillers
Better Buildings by Design 2005 Chiller Plant Design 55
Possible OptionsPossible Options
Electric chillersAbsorption chillersEngine-driven chillersThermal storageIndependent or with adjacent building
Better Buildings by Design 2005 Chiller Plant Design 56
Alternatives ConsideredAlternatives Considered
Stand-alone alternatives– Two 350-ton electric chillers– Two 350-ton absorption chillers– Two 350-ton engine-driven chillers– Electric chillers with 4500 ton-hour thermal
storage
Better Buildings by Design 2005 Chiller Plant Design 57
Alternatives ConsideredAlternatives Considered
Integrated alternatives– Provide piping between two buildings – Utilize one of the four options above for the
stand-alone plant
Better Buildings by Design 2005 Chiller Plant Design 58
Alternatives ConsideredAlternatives Considered
Single plant alternatives– Abandon plant in Building 2 and expand plant
in Building 3 with piping between the buildings– Existing Plant in Building 3
Three 250-ton electric chillers in plant on parking level P-2Cooling tower on roof
Better Buildings by Design 2005 Chiller Plant Design 59
Alternatives ConsideredAlternatives Considered
Single plant alternatives– New Equipment possibilities
600-ton electric chillerTwo 350-ton engine-driven chillersTwo low temperature chillers plus 4500 ton-hour thermal storage
Better Buildings by Design 2005 Chiller Plant Design 60
ConstructibilityConstructibility IssuesIssues
Building 2 options– Electric capacity– Cooling tower and structure– Existing chilled water riser size– Noise considerations
Better Buildings by Design 2005 Chiller Plant Design 61
ConstructibilityConstructibility IssuesIssues
Building 3 options– Cooling tower capacity– Condenser water riser size– Thermal storage space requirements– Engine exhaust routing– Electrical capacity
Better Buildings by Design 2005 Chiller Plant Design 62
AnalysisAnalysis
Opinion of probable costsScheduleOperating costs– DOE-2 simulations– Nine options considered
Better Buildings by Design 2005 Chiller Plant Design 63
AnalysisAnalysis
Other considerations– Electricity riser problem in Building 2– Impact of utility deregulation
Better Buildings by Design 2005 Chiller Plant Design 64
Economic AnalysisEconomic Analysis
Based on estimated impact of deregulationFinal options– Integrated system with new chillers in Building
2 connected to Building 3 plant700-tons electric700-tons absorption
Better Buildings by Design 2005 Chiller Plant Design 65
Economic AnalysisEconomic Analysis
First Cost– 700 ton electric
$929,223$1,109,273 with potential bus duct repair
– 700 ton absorption$1,395,247
Better Buildings by Design 2005 Chiller Plant Design 66
Economic AnalysisEconomic Analysis
Annual energy cost– 700 ton electric - $778,160– 700 ton absorption - $680,769
Simple Payback– Without bus riser repair – 4.5 years– With bus riser repair – 1.9 years
Better Buildings by Design 2005 Chiller Plant Design 67
Final ChoiceFinal Choice
Absorption chillers in Building 2 with connection to Building 3– Proactive ownership with long term outlook– Support from local natural gas utility– Optimum conditions for new plant in Building
2– Significant problems with expanding plant in
Building 3
Better Buildings by Design 2005 Chiller Plant Design 68
Chiller PurchaseChiller Purchase
Chiller pre-purchased by owner– Maintain control over final selection and
options– Delivery critical
Potential full building tenant wanted early availabilityCity rigging restrictions – Saturday night only
Better Buildings by Design 2005 Chiller Plant Design 69
Chiller PurchaseChiller Purchase
Bid to major manufacturersBid specified conditions of capacity, giving cost, efficiency, delivery and willingness to accept penalty clauseAllow manufacturers to suggest alternatives of capacity and/or efficiency and additional cost for this
Better Buildings by Design 2005 Chiller Plant Design 70
New Central PlantNew Central Plant
Two 360-ton direct fired absorption chillers with lower supply temperatureOne 120-ton rotary screw chiller for off hours use (minimum effective absorption chiller capacity)Primary-secondary piping systemPiping between the two buildings with transfer pumps and metering
Better Buildings by Design 2005 Chiller Plant Design 71
Single Line DiagramSingle Line Diagram
Better Buildings by Design 2005 Chiller Plant Design 72
Sequence of OperationsSequence of Operations
Seven modes of operation identified with written sequenceIndependent versus integrated operationElectric or gas chiller base loadOccupied versus unoccupied
Better Buildings by Design 2005 Chiller Plant Design 73
Phase IIPhase II
Building 1 central plant– Originally absorption chillers and boilers– Reciprocating chillers installed in 1987
Noise complaintsReliability issues
– Small chiller in Building 3 plant for Fitness Center after hours use with piping to lower level air handling unit
Better Buildings by Design 2005 Chiller Plant Design 74
New Building 1 PlantNew Building 1 Plant
Two centrifugal chillers and new cooling tower– Tower selected for maximum capacity for space
available– Chillers selected to match cooling tower
capacity– Use existing connection (increase size to
maximize transfer capacity) with new riser
Better Buildings by Design 2005 Chiller Plant Design 75
New Single Line DiagramNew Single Line Diagram
Better Buildings by Design 2005 Chiller Plant Design 76
SummarySummary
Project illustrates choices available and retrofit process discussedOwnership with long term outlookCooperation by all participantsLife is easier with a vacant building