Upload
vuongkien
View
217
Download
0
Embed Size (px)
Citation preview
Heat Integration Potential in Batch Processes Using PinCH 2.0
D. Olsen, R. Kislig and B. WelligLucerne School of Engineering and Architecture, Horw, Switzerland
P. KrummenacherPlanair SA, La Sagne, Switzerland
1. Characteristics of Repeated Single Product Batch Processes
4. Batch Supertargeting Results
Fig. 1: Batch example [1] showing the weekly production cycles diagram and the associated equipmentwise repeat operation period (EROP) time slice model formed due to the overlap of the individual batches as calculated in PinCH 2.0.
• Batch process production cycles are often operated in a repeated and over-lapped manner to maximize production capacity.
• Pieces of equipment can contain mul-tiple streams, e.g. reactor with two non-flowing streams as illustrated by E2.1.
• Within the weekly production cycle, an equipmentwise repeated operation period (EROP) can be identified that consists of time slices (TS) to be used for direct heat integration, not only in the single product batch itself, but also across overlapped batches.
Fig. 4: Optimal ∆Tmin values per Time Slice and associated number of units, minimum total HEN area and minimum cost for the shown Batch Example [1].
• The method combines energy and cost optimiza-tion with the required flexibility for HEN design.
• The target results aid the practicing engineer in making critical decisions when designing the HEN (in addition to the optimized area matrices and key pinch match matrices).
6. References[1] R. Kislig: Batch Supertargeting Analysis - Conventional
Design and Resequence Design, Hochschule Luzern, Master Thesis, 2012.
[2]
P. Jones: Targeting and design of heat exchanger networks under multiple base case operation, PhD Thesis, University of Manchester Institute of Science and Technology (UMIST), U.K., 1991.
[3]
P. Krummenacher: Contribution To The Heat Integration Of Batch Processes (With or Without Heat Storage), Thèse No. 2480, École Polytechnique Fédérale de Lausanne, Switzerland, 2001.
PinCH is funded by the Swiss Federal Office of Energy (SFOE) and the Swiss Private Sector Energy Agency (EnAW).
2. Direct Heat Integration Potential• An increase in the energy efficiency of batch processes can be achieved
through direct heat exchange. • However, heat exchanger network (HEN) design for minimal investment cost is
a challenge due to the time dependency of the streams.
Fig. 2: HEN designs for time slices 1 - 3 assuming separate networks in each time slice (i.e. no reuse of heat exchangers has been accounted for).
3. Batch Supertargeting Optimization
Fig. 3: Simple two time slices example illustrating HEN design for conventional and resequence design type contraints.
• In order to achieve minimum investment cost for batch processes, it is important to reuse heat ex-changers and maximize the common area over all the time slices [2].
• Supertargeting optimization to minimize total cost can be done based on conventional and resequence design constraints [3].
• Supertargeting optimization is applicable to multiple base case operation [3].
• PinCH 3.0 to include support for indirect heat transfer, i.e. heat storage.
2
Resequence DesignConventional Design
1200 m2
1
21100 m2
3
550 m2
4
100 m2
5
120 m2
Total Area: 3070 m2
1200 m22
11100 m2
3450 m2
4550 m2
5100 m2
6
120 m2
Total Area: 3520 m2
600 m2
1
4
1100 m2
3550 m2
120 m2
E1 E2 E3
Total Area: 2370 m2
Time Slice 1
H1
C1C2
1200 m2
2
4
450 m2
1
3400 m2
100 m2
Time Slice 2
Total Area: 2150 m2
H2
C3C4
E1 E2 E3
E1 E2 E3E1 E2 E3
TS 1 TS 2
Separate Design Mode
TS 3
Overview:
Goals: • Batch processes and their time depen-
dent nature provide a unique challenge in achieving optimum heat integration.
• Our goals in developing PinCH 2.0 are to provide practical features and graphical tools that an engineer in the practice can use in such batch process optimization.
Design Method Separate Design Conventional Design Resequence DesignOpt. ∆Tmin TS1 25 25 20.5
TS2 18 18 18TS3 14 14 8TS4 25 25 20.5TS5 18 18 18TS6 14 14 8
Number of Units 40 19 11Total Area [m²] 440 244.8 231.7
Total Cost [kCHF] 475.7 390.7 345.9
Time [h]
B1
E1.1
E1.2
E2.1
E2.2
E3
E4
B2
B3
TS1 TS2 TS3
EROP
ShutdownStartup
E1.1
E2.1
E3
E4
Fixed Single Batch – B1
B1
TS4 TS5 TS6
5. Significance and Future Work