Hilton Central School District
Capital Project Planning Team Kickoff Meeting
December 14, 2011
Meeting Outline
• Introductions • The Capital Project Planning Process• Determining Maximum Capital
Project Size• Formation of Subcommittees• Resources for Subcommittees• Future Meeting Schedule
Capital Project Planning Process
Project Planning Phase• Building Condition Survey• Review and Prioritization by Community Project Planning Team
Project Approval Phase• Approval by BOE of Project Planning Team Recommendations
• Voter Approval• Submission of Final Plans and Specifications to SED for Approval
Construction Phase• Opening of Bids• Scheduling and Execution of Construction
December 2011 –
September 2012
September 2012 – January
2013
January 2013 – December
2014
Determining Maximum Project Size
• Objective– A capital project that is substantially property
tax neutral
• Sources of Property Tax Offsets– Building Aid
• approximately 90% of project cost
– Capital Reserve Fund • $1.5 million
– Reductions in annual operation costs • i.e. electricity produced by a wind turbine reduces
annual utility costs
Sample Project Financing
• $15 million project, financed with $1.5m paid by Capital Reserve, and $13.5m serial bonds (15-year bonds)
Annual Budgeted Debt Service on $13.5 million 15-year bond, ignoring interest
$900,000
Annual Building Aid on $15 Million Project with 90% Building Aid
$900,000
Net Annual Local Property Tax Impact
$0
Formation of Subcommittees
Subcommittee Facilitator
High School Brian Bartalo
Merton Williams Middle School Tim Dobbertin
Northwood Elementary School Kirk Ashton
Quest Elementary School Karen Spillman
Village Elementary School Tracie Czebatol
Athletics (Districtwide ) Mike Giruzzi
Food Service (Districtwide) Scott Ziobrowski
Technology (Districtwide ) Laurie Hazard
Transportation Fred Paye
Alternative Energy Adam Geist
Subcommittee Resources
• Building Condition Survey (BCS)– State required detailed architectural/engineering study
of all facility infrastructure components, with estimated remaining useful life and cost of replacement
• Programmatic Needs– Recommendations by Subcommittee Facilitator of
building/department needs not covered by BCS
• Go Green Committee Report– Preliminary study of alternative energy infrastructure
needs to meet District goal of 50% reduction in use of commercially produced energy by 2015-16 school year
Capital Project Planning Committee WIKI
• www.hiltoncppc.pbworks.com • Contains BCS for each building• Will be used for posting
subcommittee minutes• Other materials will be posted as
they become available
Future Meetings
Date Agenda
January 11, 2012
Subcommittee progress reports and recommendations, if available
February 15, 2012
Subcommittee progress reports and recommendations, if available
March 14, 2012 Subcommittee progress reports and recommendations, if available
April 18, 2012 Subcommittee progress reports and recommendations, if available
May 9, 2012 Subcommittee progress reports and recommendations, if available
June 13, 2012 Initial discussion of prioritization of recommendations
June 27, 2012 Final discussion of prioritization of recommendations
October 9. 2012 Board of Education approval and scheduling of vote
December 11, 2012
Public vote on proposed capital project