Upload
manish-randhawa
View
225
Download
0
Embed Size (px)
Citation preview
8/3/2019 Hindalco Q2FY11 Presentation
1/38
Hindalco Industries Ltd
Q2 FY11November 2010
8/3/2019 Hindalco Q2FY11 Presentation
2/38
Industry Backdrop
Results Highlights
Aluminium: Business Conditions & performance
Review
Co er: Business Conditions & erformance Review
ro ec s n p a e
8/3/2019 Hindalco Q2FY11 Presentation
3/38
3
8/3/2019 Hindalco Q2FY11 Presentation
4/38
Robust growth in global metals consumption
though supported by re-stocking / base effect / stimuli
Aluminium Consumption Copper ConsumptionWorld,
18%,
37.4 37.8
41.9 41.6
RoW
17.5
17.917.0
17.9
19.318.5
8%
16%.
9%10.0
11.1 6.0 7.2
20%
China11%
12.6 17.5
5.1
7.3
18%
North America + Europe
5%
12.914.8 6.9
4.1
4
2008 2009 2010 Q1 2010 Q2 2010 Q3
Growth (2010 est)Source: Industry
2008 2009 2010 Q1 2010 Q2 2010 Q3
8/3/2019 Hindalco Q2FY11 Presentation
5/38
Indian Growth Momentum to Continue
966
Aluminium consumption (kt)Electrical & Electronics
Large scope formetal
consumption to
rise from current
910Building & Construction
levels
End user
segments have a
strong/positive
H1 FY10 H1 FY11
6%
Consumer Durable
. .
Power, Transport,
Construction,
Industrial etc
Rising per capita
opper consump on
296
307
utomo e ransport
Industrial Machinery
consumption ofin India
4%
H1FY10 H1FY11
Packaging
5H1 growth affected by temporary slowdown in electricaldemand, which is primarily dependent on Govt. allocation
8/3/2019 Hindalco Q2FY11 Presentation
6/38
6
8/3/2019 Hindalco Q2FY11 Presentation
7/38
Q2 FY 11: Highlights
7 Robust Performance amidst challenging conditions
8/3/2019 Hindalco Q2FY11 Presentation
8/38
Proactive Steps
HigherAluminium VAPSalesImprovedMix
HighestEverproductionofCCR
LowerCuPremium Efficiencies
Coal PriceSurge
Muri
improvement
inAluminium
EfficienciesimprovedCo er
ReducedInventory levelsto.
8
Higher EBIT despite adverse impact
8/3/2019 Hindalco Q2FY11 Presentation
9/38
Financial Performance
` Cr Q2 FY10 Q2 FY11 Change (%)Net Sales 4,915 5,860 19
PBT 434 556 28
PAT 344 434 26
` Cr H1 FY10 H1 FY11 Change (%)EPS (`) 2.02 2.27 12
Net Sales 8,812 11,038 25
PBITDA 1,500 1682 12
, ,
PAT 825 968 17
EPS (`) 4.85 5.06 4
9Q2 profit would have been significantly higher, but for Hirakudproduction loss and Kalwa VRS settlement
8/3/2019 Hindalco Q2FY11 Presentation
10/38
Aluminium: Business Conditions &
10
8/3/2019 Hindalco Q2FY11 Presentation
11/38
Al: External Drivers
Driver Current Assessment Impact
LME Support from global liquidity and cost pressures,but downside risks related to rewind of financing
deals
INR USD USD weakness and continued FII flows to Indiamay lead to rupee appreciation
Input
prices
Upward pressure related to coal and carbon costs
Demand in Outlook positive for most aluminium-consuming
India sectors
11
8/3/2019 Hindalco Q2FY11 Presentation
12/38
Aluminium Industry : Cost push to continue
10%
World average hot metal cost Composition
Alumina-
Others
38%13%
insisting on short-termcontracts- De coupling of
- Correlated withcommodity price cycle
7%
Labour cost- Hardening of
emerging marketcurrencies includin
32%
RMB
- Electricity price hikes in China- Power cuts in certain Chinese provinces leadingto cutbacks in production (~1.5 mt capacity)
12
Cost Push to continue Support for prices?
Source: Industry &company estimates
8/3/2019 Hindalco Q2FY11 Presentation
13/38
Strong Production performance despite Hirakudproduction loss
Alumina (kt)11%
Metal (kt)
123140
12% Growth in Output(H1 FY11 vs H1 FY10)
312
347
100 103
Alumina 10%
Metal -4%
FRP 3%
Hkud
Q2 FY10 Q2 FY11 Q2 FY10 Q2 FY11
Extrusions 3%Rkoot Rkoot
54,042
FRP (ton) Extrusions (ton)2%
Adverse impact
contained through
2%
, ,9,637 efficiency
improvement
Higher alumina &
13 Q2 FY10 Q2 FY11 Q2 FY10 Q2 FY11
wire rod production
8/3/2019 Hindalco Q2FY11 Presentation
14/38
8/3/2019 Hindalco Q2FY11 Presentation
15/38
8/3/2019 Hindalco Q2FY11 Presentation
16/38
Aluminium Business: Financial Performance
Q2 FY10 Q2 FY11 Change (%)(` cr)
Net Sales & OperatingRevenue 1,649 1,911 16
EBIT 259 424 64
Net Sales & Operating
(` cr)
Revenue, ,
EBIT 714 976 37
16
8/3/2019 Hindalco Q2FY11 Presentation
17/38
Copper: Business Conditions &
17
8/3/2019 Hindalco Q2FY11 Presentation
18/38
Copper: External Drivers
Driver Current Assessment Impact
TCRC Long term TCRC lower than last year
LME/INR LME being supported by liquidity
INR Appreciating rupee
Acid prices Recently on an improving trend
prices
firm
18
a eng ng mes
8/3/2019 Hindalco Q2FY11 Presentation
19/38
Custom Smelters : Low TCRC, Rising energy costs
Structural shortages likely tocontinue
(Mn Ton)
Rising energy costs
13.2 13.1
13.7
Mine Supply
Smelter Demand
12.312.2
12.4 12.5
12.8. .
Input
Vs HiFY10
Importedcoal >10
Furnace oil >20
2007 2008 2009 2010(E)
2011(P)
TCRC to continue to remain under pressureLNG >5
19
enc mar were s gn can yhigher than FY11 benchmark
8/3/2019 Hindalco Q2FY11 Presentation
20/38
Cu: Production Performance
Q2: Record cathode production and sharp jump in Own CCR production
94
a o e5%
43
wn41%
Q2 FY10 Q2 FY11
31
Q2 FY10 Q2 FY11
20
rong opera ona per ormance
8/3/2019 Hindalco Q2FY11 Presentation
21/38
Copper Business: Financial Performance
Net Sales & Operating
(` cr)
Revenue, ,
EBIT 217 129 (41)
H1 FY10 H1 FY11 Change (%)(` cr)
Revenue 5,748 7,265 26
EBIT 374 253 (32)
21
8/3/2019 Hindalco Q2FY11 Presentation
22/38
Mining : ABML Highlights
Nifty Sulfide Production (tons) Nifty EBIDTA (A$ mn)
11% 18%
29491
89.7
26488 .
FY10 H1 FY11 H1 FY10 H1 FY11 H1
22
Strong Performance
8/3/2019 Hindalco Q2FY11 Presentation
23/38
8/3/2019 Hindalco Q2FY11 Presentation
24/38
24
8/3/2019 Hindalco Q2FY11 Presentation
25/38
Utkal Alumina
Engineering Basic Engg-100 % Complete, Detailed Engg- 95% Completed, not on
StatutoryClearances
Obtained
Commitment Over 82%
Site Progress More than 7,000 people working at site.Major Contractors like L & T, Simplex, GDC mobilized fully at site.94% of Piling work completed. RCC, structural, fabrication anderection has been ramped up and is on track for timely completion.
25 Expected completion -Q2 FY12
8/3/2019 Hindalco Q2FY11 Presentation
26/38
Activity at Site: Utkal
Evaporation area: Erection of equipmentunder progress
Mud Washing: erection of DCWunder progress
BTG Packa e: ESP#1: Hooper erection under progress
26
8/3/2019 Hindalco Q2FY11 Presentation
27/38
8/3/2019 Hindalco Q2FY11 Presentation
28/38
Activity at Site: Mahan smelter
Pot Room Cathode sealingshop
GTC1 ID Fan1 ag ter &
crust bath silosupport structureerection
foundations & Stack
28
8/3/2019 Hindalco Q2FY11 Presentation
29/38
Activity at Site: Mahan CPP
Erection work in Boiler #2 Chimney #4 - Assembly of Slip form
Erection of Boiler#2 columns
Reinforcement & Shuttering work for TG#2Deck slab
29
8/3/2019 Hindalco Q2FY11 Presentation
30/38
Aditya Smelter
-
Statutoryapprovals
Major approvals received. Forest land stage I clearancereceived. Permission to start project site consolidation activities
. .
Commitment Around 66%. Major orders placed (along with Mahan)
Site Progress Area grading ,Piling undergoing. R & R under progress. Civilcontractor - HCC Team has mobilized well with hydraulic rigs
and civil work in permitted fronts is in full swing.
30 Expected Completion Q3 FY12
8/3/2019 Hindalco Q2FY11 Presentation
31/38
Activity at Site: Aditya Smelter and CPP
Pot Room Foundation 220 KV switch yard
Intake well with substation o er oun a on
31
Hi k d S l d P Pl E i
8/3/2019 Hindalco Q2FY11 Presentation
32/38
Hirakud Smelter and Power Plant Expansion
SmelterExpansion
Capacity increase from 161 to 213 ktpa thru addition of 80 Pots of 235 kA
ower anExpansion
apac y o ncrease o . y on o .
Schedule 30 pots to be commissioned by Dec2011 & balance 50 pots by Mar2012
Progress Power Plant1. DCPL has been engaged as the EPCM consultant, Engineering is
progressing well2. Major orders for the power plant already placed.Smelter1. Basic Engineering by GAMI- completed.2. Major orders like wagons, alumina handling placed. Other major orders
being finalized.3. SPL has been vacated to storage shed. New plant rectifier station willbe erected over here.
4. Site grading 80% and boundary wall 90% completed.
32
Smelter expansion from 155 to 161 KTPA under phased commissioning
P j t Bl F
8/3/2019 Hindalco Q2FY11 Presentation
33/38
Project Blue Fox
Scope Brownfield project Can Body Stock at Hirakud
Dismantlingand receipt ofe ui ments
Dismantling completed. All containers received at Vizag port -13000 MT.
Cold Mill Order placed on Achenbach.
Hot Mill.
progressing as per schedule.
Civil workxcava on an oun a on o u ng co umn n progress.
Site Leveling and Boundary wall work in progress.
33 Project Completion Q2 FY12
Jh kh d S lt
8/3/2019 Hindalco Q2FY11 Presentation
34/38
Jharkhand Smelter
Land Total land requirement of ~4000 acres for the project..
Water Water drawl clearance received for 55 MCM.
Environmental
clearance
Application to be submitted after sizeable quantity of land has
been acquired.
FeasibilityReports
DFR is ready.
34 Expected Completion FY14
Aditya Refinery
8/3/2019 Hindalco Q2FY11 Presentation
35/38
Aditya Refinery
Land Majority land acquired, Rest process on track
Water Water drawl agreement in place
M/s Simplex Infrastructure Ltd is awarded with the job forsupply & erection of water drawl arrangement. They have
Km.
Forest Terms of Reference (TOR) presentation date is awaited.
Constructionpower
Job has been completed. Line energized.
.
35 Expected Completion FY14
8/3/2019 Hindalco Q2FY11 Presentation
36/38
Towards Sustainable Leadership
Domestic operations Expansion Projects Novelis
User industries of aluminumhave a bullish outlook
Robust sector fundamentals
Greenfield projects expectedto be in global best quartilefor manufacturing costs
Improving product mix todrive margins and growth
Driver
Long on Alumina
Introduction of new futuristic
value added products (Al) New avenues for copper use
Infrastructure available forfurther scalability in the
future Brownfield capacity increase
advantage
Roger Stone
Convergence of EBITDAand Adjusted EBITDA
Leader in Al Recycling
Highlights
Leading market share in
VAP
Continued focus on
operational excellence for
Focus on timely delivery ofplanned projects
Maintain high quality of
execution
Financial turnaround with
continued operational
improvement
Leverage on high end
Sustainable rowth Achieve otential Stabilize and transform
o um num an opper
Low cost base and robust
de-risked business model
Low capex cost per ton withbest in class operatingcapacities
ec no ogy
Brownfield expansion
Pinda project, Brazil
Strategy
Price Leader Cost Leader Capability Leader
36
Seamless Global One Metal business
8/3/2019 Hindalco Q2FY11 Presentation
37/38
Forward Looking & Cautionary Statement
Certain statements in this report may be forward looking statements within
the meaning of applicable securities laws and regulations. Actual results could
.
make a difference to the companys operations include global and Indiandemand supply conditions, finished goods prices, feed stock availability and
, ,
changes in Government regulations, tax regimes, economic developments
within India and the countries within which the company conducts business
and other factors such as litigation and labour negotiations. The companyassume no responsibility to publicly amend, modify or revise any forward
looking statement, on the basis of any subsequent development, information or
events, or otherwise.
37
8/3/2019 Hindalco Q2FY11 Presentation
38/38
an you
38