Hindalco Q2FY11 Presentation

Embed Size (px)

Citation preview

  • 8/3/2019 Hindalco Q2FY11 Presentation

    1/38

    Hindalco Industries Ltd

    Q2 FY11November 2010

  • 8/3/2019 Hindalco Q2FY11 Presentation

    2/38

    Industry Backdrop

    Results Highlights

    Aluminium: Business Conditions & performance

    Review

    Co er: Business Conditions & erformance Review

    ro ec s n p a e

  • 8/3/2019 Hindalco Q2FY11 Presentation

    3/38

    3

  • 8/3/2019 Hindalco Q2FY11 Presentation

    4/38

    Robust growth in global metals consumption

    though supported by re-stocking / base effect / stimuli

    Aluminium Consumption Copper ConsumptionWorld,

    18%,

    37.4 37.8

    41.9 41.6

    RoW

    17.5

    17.917.0

    17.9

    19.318.5

    8%

    16%.

    9%10.0

    11.1 6.0 7.2

    20%

    China11%

    12.6 17.5

    5.1

    7.3

    18%

    North America + Europe

    5%

    12.914.8 6.9

    4.1

    4

    2008 2009 2010 Q1 2010 Q2 2010 Q3

    Growth (2010 est)Source: Industry

    2008 2009 2010 Q1 2010 Q2 2010 Q3

  • 8/3/2019 Hindalco Q2FY11 Presentation

    5/38

    Indian Growth Momentum to Continue

    966

    Aluminium consumption (kt)Electrical & Electronics

    Large scope formetal

    consumption to

    rise from current

    910Building & Construction

    levels

    End user

    segments have a

    strong/positive

    H1 FY10 H1 FY11

    6%

    Consumer Durable

    . .

    Power, Transport,

    Construction,

    Industrial etc

    Rising per capita

    opper consump on

    296

    307

    utomo e ransport

    Industrial Machinery

    consumption ofin India

    4%

    H1FY10 H1FY11

    Packaging

    5H1 growth affected by temporary slowdown in electricaldemand, which is primarily dependent on Govt. allocation

  • 8/3/2019 Hindalco Q2FY11 Presentation

    6/38

    6

  • 8/3/2019 Hindalco Q2FY11 Presentation

    7/38

    Q2 FY 11: Highlights

    7 Robust Performance amidst challenging conditions

  • 8/3/2019 Hindalco Q2FY11 Presentation

    8/38

    Proactive Steps

    HigherAluminium VAPSalesImprovedMix

    HighestEverproductionofCCR

    LowerCuPremium Efficiencies

    Coal PriceSurge

    Muri

    improvement

    inAluminium

    EfficienciesimprovedCo er

    ReducedInventory levelsto.

    8

    Higher EBIT despite adverse impact

  • 8/3/2019 Hindalco Q2FY11 Presentation

    9/38

    Financial Performance

    ` Cr Q2 FY10 Q2 FY11 Change (%)Net Sales 4,915 5,860 19

    PBT 434 556 28

    PAT 344 434 26

    ` Cr H1 FY10 H1 FY11 Change (%)EPS (`) 2.02 2.27 12

    Net Sales 8,812 11,038 25

    PBITDA 1,500 1682 12

    , ,

    PAT 825 968 17

    EPS (`) 4.85 5.06 4

    9Q2 profit would have been significantly higher, but for Hirakudproduction loss and Kalwa VRS settlement

  • 8/3/2019 Hindalco Q2FY11 Presentation

    10/38

    Aluminium: Business Conditions &

    10

  • 8/3/2019 Hindalco Q2FY11 Presentation

    11/38

    Al: External Drivers

    Driver Current Assessment Impact

    LME Support from global liquidity and cost pressures,but downside risks related to rewind of financing

    deals

    INR USD USD weakness and continued FII flows to Indiamay lead to rupee appreciation

    Input

    prices

    Upward pressure related to coal and carbon costs

    Demand in Outlook positive for most aluminium-consuming

    India sectors

    11

  • 8/3/2019 Hindalco Q2FY11 Presentation

    12/38

    Aluminium Industry : Cost push to continue

    10%

    World average hot metal cost Composition

    Alumina-

    Others

    38%13%

    insisting on short-termcontracts- De coupling of

    - Correlated withcommodity price cycle

    7%

    Labour cost- Hardening of

    emerging marketcurrencies includin

    32%

    RMB

    - Electricity price hikes in China- Power cuts in certain Chinese provinces leadingto cutbacks in production (~1.5 mt capacity)

    12

    Cost Push to continue Support for prices?

    Source: Industry &company estimates

  • 8/3/2019 Hindalco Q2FY11 Presentation

    13/38

    Strong Production performance despite Hirakudproduction loss

    Alumina (kt)11%

    Metal (kt)

    123140

    12% Growth in Output(H1 FY11 vs H1 FY10)

    312

    347

    100 103

    Alumina 10%

    Metal -4%

    FRP 3%

    Hkud

    Q2 FY10 Q2 FY11 Q2 FY10 Q2 FY11

    Extrusions 3%Rkoot Rkoot

    54,042

    FRP (ton) Extrusions (ton)2%

    Adverse impact

    contained through

    2%

    , ,9,637 efficiency

    improvement

    Higher alumina &

    13 Q2 FY10 Q2 FY11 Q2 FY10 Q2 FY11

    wire rod production

  • 8/3/2019 Hindalco Q2FY11 Presentation

    14/38

  • 8/3/2019 Hindalco Q2FY11 Presentation

    15/38

  • 8/3/2019 Hindalco Q2FY11 Presentation

    16/38

    Aluminium Business: Financial Performance

    Q2 FY10 Q2 FY11 Change (%)(` cr)

    Net Sales & OperatingRevenue 1,649 1,911 16

    EBIT 259 424 64

    Net Sales & Operating

    (` cr)

    Revenue, ,

    EBIT 714 976 37

    16

  • 8/3/2019 Hindalco Q2FY11 Presentation

    17/38

    Copper: Business Conditions &

    17

  • 8/3/2019 Hindalco Q2FY11 Presentation

    18/38

    Copper: External Drivers

    Driver Current Assessment Impact

    TCRC Long term TCRC lower than last year

    LME/INR LME being supported by liquidity

    INR Appreciating rupee

    Acid prices Recently on an improving trend

    prices

    firm

    18

    a eng ng mes

  • 8/3/2019 Hindalco Q2FY11 Presentation

    19/38

    Custom Smelters : Low TCRC, Rising energy costs

    Structural shortages likely tocontinue

    (Mn Ton)

    Rising energy costs

    13.2 13.1

    13.7

    Mine Supply

    Smelter Demand

    12.312.2

    12.4 12.5

    12.8. .

    Input

    Vs HiFY10

    Importedcoal >10

    Furnace oil >20

    2007 2008 2009 2010(E)

    2011(P)

    TCRC to continue to remain under pressureLNG >5

    19

    enc mar were s gn can yhigher than FY11 benchmark

  • 8/3/2019 Hindalco Q2FY11 Presentation

    20/38

    Cu: Production Performance

    Q2: Record cathode production and sharp jump in Own CCR production

    94

    a o e5%

    43

    wn41%

    Q2 FY10 Q2 FY11

    31

    Q2 FY10 Q2 FY11

    20

    rong opera ona per ormance

  • 8/3/2019 Hindalco Q2FY11 Presentation

    21/38

    Copper Business: Financial Performance

    Net Sales & Operating

    (` cr)

    Revenue, ,

    EBIT 217 129 (41)

    H1 FY10 H1 FY11 Change (%)(` cr)

    Revenue 5,748 7,265 26

    EBIT 374 253 (32)

    21

  • 8/3/2019 Hindalco Q2FY11 Presentation

    22/38

    Mining : ABML Highlights

    Nifty Sulfide Production (tons) Nifty EBIDTA (A$ mn)

    11% 18%

    29491

    89.7

    26488 .

    FY10 H1 FY11 H1 FY10 H1 FY11 H1

    22

    Strong Performance

  • 8/3/2019 Hindalco Q2FY11 Presentation

    23/38

  • 8/3/2019 Hindalco Q2FY11 Presentation

    24/38

    24

  • 8/3/2019 Hindalco Q2FY11 Presentation

    25/38

    Utkal Alumina

    Engineering Basic Engg-100 % Complete, Detailed Engg- 95% Completed, not on

    StatutoryClearances

    Obtained

    Commitment Over 82%

    Site Progress More than 7,000 people working at site.Major Contractors like L & T, Simplex, GDC mobilized fully at site.94% of Piling work completed. RCC, structural, fabrication anderection has been ramped up and is on track for timely completion.

    25 Expected completion -Q2 FY12

  • 8/3/2019 Hindalco Q2FY11 Presentation

    26/38

    Activity at Site: Utkal

    Evaporation area: Erection of equipmentunder progress

    Mud Washing: erection of DCWunder progress

    BTG Packa e: ESP#1: Hooper erection under progress

    26

  • 8/3/2019 Hindalco Q2FY11 Presentation

    27/38

  • 8/3/2019 Hindalco Q2FY11 Presentation

    28/38

    Activity at Site: Mahan smelter

    Pot Room Cathode sealingshop

    GTC1 ID Fan1 ag ter &

    crust bath silosupport structureerection

    foundations & Stack

    28

  • 8/3/2019 Hindalco Q2FY11 Presentation

    29/38

    Activity at Site: Mahan CPP

    Erection work in Boiler #2 Chimney #4 - Assembly of Slip form

    Erection of Boiler#2 columns

    Reinforcement & Shuttering work for TG#2Deck slab

    29

  • 8/3/2019 Hindalco Q2FY11 Presentation

    30/38

    Aditya Smelter

    -

    Statutoryapprovals

    Major approvals received. Forest land stage I clearancereceived. Permission to start project site consolidation activities

    . .

    Commitment Around 66%. Major orders placed (along with Mahan)

    Site Progress Area grading ,Piling undergoing. R & R under progress. Civilcontractor - HCC Team has mobilized well with hydraulic rigs

    and civil work in permitted fronts is in full swing.

    30 Expected Completion Q3 FY12

  • 8/3/2019 Hindalco Q2FY11 Presentation

    31/38

    Activity at Site: Aditya Smelter and CPP

    Pot Room Foundation 220 KV switch yard

    Intake well with substation o er oun a on

    31

    Hi k d S l d P Pl E i

  • 8/3/2019 Hindalco Q2FY11 Presentation

    32/38

    Hirakud Smelter and Power Plant Expansion

    SmelterExpansion

    Capacity increase from 161 to 213 ktpa thru addition of 80 Pots of 235 kA

    ower anExpansion

    apac y o ncrease o . y on o .

    Schedule 30 pots to be commissioned by Dec2011 & balance 50 pots by Mar2012

    Progress Power Plant1. DCPL has been engaged as the EPCM consultant, Engineering is

    progressing well2. Major orders for the power plant already placed.Smelter1. Basic Engineering by GAMI- completed.2. Major orders like wagons, alumina handling placed. Other major orders

    being finalized.3. SPL has been vacated to storage shed. New plant rectifier station willbe erected over here.

    4. Site grading 80% and boundary wall 90% completed.

    32

    Smelter expansion from 155 to 161 KTPA under phased commissioning

    P j t Bl F

  • 8/3/2019 Hindalco Q2FY11 Presentation

    33/38

    Project Blue Fox

    Scope Brownfield project Can Body Stock at Hirakud

    Dismantlingand receipt ofe ui ments

    Dismantling completed. All containers received at Vizag port -13000 MT.

    Cold Mill Order placed on Achenbach.

    Hot Mill.

    progressing as per schedule.

    Civil workxcava on an oun a on o u ng co umn n progress.

    Site Leveling and Boundary wall work in progress.

    33 Project Completion Q2 FY12

    Jh kh d S lt

  • 8/3/2019 Hindalco Q2FY11 Presentation

    34/38

    Jharkhand Smelter

    Land Total land requirement of ~4000 acres for the project..

    Water Water drawl clearance received for 55 MCM.

    Environmental

    clearance

    Application to be submitted after sizeable quantity of land has

    been acquired.

    FeasibilityReports

    DFR is ready.

    34 Expected Completion FY14

    Aditya Refinery

  • 8/3/2019 Hindalco Q2FY11 Presentation

    35/38

    Aditya Refinery

    Land Majority land acquired, Rest process on track

    Water Water drawl agreement in place

    M/s Simplex Infrastructure Ltd is awarded with the job forsupply & erection of water drawl arrangement. They have

    Km.

    Forest Terms of Reference (TOR) presentation date is awaited.

    Constructionpower

    Job has been completed. Line energized.

    .

    35 Expected Completion FY14

  • 8/3/2019 Hindalco Q2FY11 Presentation

    36/38

    Towards Sustainable Leadership

    Domestic operations Expansion Projects Novelis

    User industries of aluminumhave a bullish outlook

    Robust sector fundamentals

    Greenfield projects expectedto be in global best quartilefor manufacturing costs

    Improving product mix todrive margins and growth

    Driver

    Long on Alumina

    Introduction of new futuristic

    value added products (Al) New avenues for copper use

    Infrastructure available forfurther scalability in the

    future Brownfield capacity increase

    advantage

    Roger Stone

    Convergence of EBITDAand Adjusted EBITDA

    Leader in Al Recycling

    Highlights

    Leading market share in

    VAP

    Continued focus on

    operational excellence for

    Focus on timely delivery ofplanned projects

    Maintain high quality of

    execution

    Financial turnaround with

    continued operational

    improvement

    Leverage on high end

    Sustainable rowth Achieve otential Stabilize and transform

    o um num an opper

    Low cost base and robust

    de-risked business model

    Low capex cost per ton withbest in class operatingcapacities

    ec no ogy

    Brownfield expansion

    Pinda project, Brazil

    Strategy

    Price Leader Cost Leader Capability Leader

    36

    Seamless Global One Metal business

  • 8/3/2019 Hindalco Q2FY11 Presentation

    37/38

    Forward Looking & Cautionary Statement

    Certain statements in this report may be forward looking statements within

    the meaning of applicable securities laws and regulations. Actual results could

    .

    make a difference to the companys operations include global and Indiandemand supply conditions, finished goods prices, feed stock availability and

    , ,

    changes in Government regulations, tax regimes, economic developments

    within India and the countries within which the company conducts business

    and other factors such as litigation and labour negotiations. The companyassume no responsibility to publicly amend, modify or revise any forward

    looking statement, on the basis of any subsequent development, information or

    events, or otherwise.

    37

  • 8/3/2019 Hindalco Q2FY11 Presentation

    38/38

    an you

    38