Upload
others
View
5
Download
0
Embed Size (px)
Citation preview
Commercial in Confidence
PJH/JAH/O:Reports/FAR/S7412/1190 TESLA Exploration International Limited
INEOS Enterprises Limited November 2013
2D SEISMIC SURVEY
Undertaken within
Holford, Cheshire Basin
By
TESLA EXPLORATION INTERNATIONAL LIMITED
on behalf of
INEOS ENTERPRISES LIMITED
November 2013
Prepared by: Phillip Hounsell Approved by: Mark Rees
TESLA Exploration International Limited
Unit 2, Nix’s Hill
Nix’s Hill Industrial Estate
Alfreton
Derbyshire
DE55 7GN
United Kingdom
Telephone: 01773 838950
Facsimile: 01773 836492
Email: [email protected]
Web: www.teslaexploration.com
Commercial in Confidence
PJH/JAH/O:Reports/FAR/S7412/1190 TESLA Exploration International Limited
INEOS Enterprises Limited November 2013
CONTENTS
1. SYNOPSIS
2. OVERVIEW
3. SURVEYING
4. RECORDING
5. HEALTH, SAFETY and ENVIRONMENT
6. PERMIT
7. DATA PROCESSING & QC
8. CONCLUSIONS AND RECOMMENDATIONS
9. CREW VISITORS
APPENDICES
1 SURVEY STATISTICS
2 PARAMETER SHEET
3 CONTACT LIST
4 FINAL HSE REPORT
5 PERSONNEL LISTING
6 EQUIPMENT SCHEDULE
7. SOURCE AND RECEIVER LAYOUTS
Commercial in Confidence
PJH/JAH/O:Reports/FAR/S7412/1190 TESLA Exploration International Limited
INEOS Enterprises Limited November 2013
1. SYNOPSIS
This report covers the acquisition of a Vibroseis sourced 2D seismic survey
undertaken by Tesla Exploration International Ltd on behalf of INEOS Enterprises Ltd
The survey lies within Middlewich in the Southwest, Northwich to the Northwest and
the M6 running South to North the area is known as the Cheshire Basin. The total
number of km acquired was 17.7Km.
The majority of the permit functions were carried out by the client’s land agent. The
land agents main involvement was to notifying all the tenant farmers of the Seismic
survey. TESLA provided a permit liaison officer to assist in locating the best access
points to the lines. Survey operations commenced on the 15th
November 2013, with
initial emphasis being placed on the setting out and programming of Lines.
Recording operation started on 18th
November 2013 and finished on 23rd
November
2013. All field based survey activity, including restoration and de-mobilisation of the
local field office, was concluded by 26th
November 2013.
The survey area was characterised by an area of gently rolling topography. Most of
the survey line were situated on cross country open farm land which keep the lines
straight.
The survey area was characterised by its central east west tarmacadam road A530
King Street and its network of smaller linking roads Drakelow lane, Yalehouse road,
Moss lane, Lilly lane and B5081.
Typical Prospect Situation Photographs
Typical Prospect Situation Photographs
Commercial in Confidence
PJH/JAH/O:Reports/FAR/S7412/1190 TESLA Exploration International Limited
INEOS Enterprises Limited November 2013
2. OVERVIEW
The Permit Liaison Officer commenced permit activity in 11 November 2013. The main role
was to liaise with INEOS land agent, walk all line and review all accesses for Vibs and line
crew.
A local field office/base was established at Drakelow Hall Farm, Byley where the equipment
was also stored. The facility was situated central to the prospect area, ensuring the
travelling times to the furthest most points of the survey were within the acceptable time
frame. Electricity was provided through a generator supply and telephone communication
was provided by mobile telephones. Internet facilities were provided through dongles. A
clean, potable water supply was readily available on site.
Any roads affected by the majority of the traverse routes were of sound construction with
no apparent breaks or weaknesses in the tarmac surface. The roads themselves were either
quiet or extremely busy especially in the mornings and afternoons.
TESLA Base Camp
Client liaison was maintained throughout all aspects of the survey with Mr Jacques Bal (Geo
Stock) and Mr John Boundy who represented the interests of INEOS Enterprises Limited.
Commercial in Confidence
PJH/JAH/O:Reports/FAR/S7412/1190 TESLA Exploration International Limited
INEOS Enterprises Limited November 2013
3. SURVEYING
Locations
Proposed Survey Routes
Commercial in Confidence
PJH/JAH/O:Reports/FAR/S7412/1190 TESLA Exploration International Limited
INEOS Enterprises Limited November 2013
Actual Survey Routes
General
The survey party mobilised to the Holford 2D survey area on the 15th
November 2013. A
base office was set up at the Tesla yard at Drakelow Hall Farm, Byley. A GPS control station
was established at the base for use as a RTK base station using a Smartnet enabled GPS
receiver. The position was subsequently checked by INEOS to ensure compatibility with the
Holford survey network.
Surveying continued until the 20th
November 2013. The survey consisted of 17.7 km of
cross country Vibroseis 2D. Wooden pegs were used to mark receiver positions. Source
points were centred midway between two receiver points. Receiver stations were pegged at
a 20m horizontal interval, source was nominally programmed at alternate receiver points.
Source programs for the vib teams were produced for each line as the survey progressed.
Equipment
A Leica System 1200 ‘SmartRover’ RTK GPS receivers was available for GPS observations.
GPS observations are based on broadcast correction service via a GSM connection to Leica
‘SmartNet’.
‘SmartNet’ is enabled by the current network of Ordnance Survey base stations to create a
high density, high redundancy network. Data from over 100 of these base stations around
Commercial in Confidence
PJH/JAH/O:Reports/FAR/S7412/1190 TESLA Exploration International Limited
INEOS Enterprises Limited November 2013
the country is received over the internet at a highly secure location in London Docklands
where it is processed using ‘Leica SpiderNet’, Leica Geosystems advanced network
calculation software, and made available directly in the field by a GSM connection. By
having the OSGB36 CSCS model and OSGM02 geoid model installed on the field receivers
direct output in OS grid and Newlyn Datum orthometric height is available.
Conventional RTK techniques based on the control station established by SmartNet was
used.
The GPS teams used a Land Rover 110 station wagon and a Ford Transit van to transport
personnel and equipment.
Field Ops
Lines were staked out using RTK GPS to position and survey the receiver stations. Vibrator
points were programmed for 1 vib, if any vibrator point was offset to the receiver line the
position was pegged and the position recorded.
Q.A.
The GPS log files for each day’s work were examined for errors in point numbering, receiver
height, co-ordinate quality etc. prior to insertion into the main database. The original data
was kept on backup files as a comparison. At the start and during a day’s work the teams
would log a measurement to either a point observed on a previous day or to a control
station. These points would be compared in the field and in the office for any errors in
either equipment or data input. All QA shots agreed within 0.5m X-Y /0.25m Z of previously
acquired positions, therefore no re-observations were required on this survey.
As the survey progressed the lines were overlaid using AutoCAD onto Ordnance Survey
raster maps then visually checked for positioning errors.
Computation
Raw data from the controllers were down loaded directly to the P.C. at the end of each
day’s work. .
The data were then converted to an ASCII file and exported to Leica ‘LISCAD’ for data
manipulation and terrain modelling.
885 receiver points on 4 lines were positioned and surveyed during the period, with a total
line length of 17.7 km.
Commercial in Confidence
PJH/JAH/O:Reports/FAR/S7412/1190 TESLA Exploration International Limited
INEOS Enterprises Limited November 2013
Geodetic Parameters
Ellipsoid : GRS 1980
.a 6378137.0 1/f 298.25722210088
Projection : OSGB(36)
Latitude of origin : 49º 00’ 00” N
Central Meridian : 02º 00’ 00” W
False Easting : 400000m
False Northing : -100000m
Scale Factor At Origin : 0.99960127170
Commercial in Confidence
PJH/JAH/O:Reports/FAR/S7412/1190 TESLA Exploration International Limited
INEOS Enterprises Limited November 2013
4. RECORDING
Prior to the start of layout, all recording equipment cables and geophones were tested with
industry standard testers to manufacturer’s specification. This comprised using the Seismic
Source Bird Dog II geophone tester for geophone integrity. Megga insulation tester with the
geophone immersed in water and a GEOX cable tester for both the traverse line and
networking cables.
The recording instrument an Aram Aries system serial number SPM_440 supporting Aries
software version 3.108.01.02 also underwent a complete set of daily instrument tests to
ensure the system was working correctly, and a system diagnostic report (figure: 1) saved to
the system hard drive.
ACID Daily Testing Report Dump
1 Pass 1 @ 08:19:47, November 19, 2013
2 Register testing completed successfully.
3 Sample Rate 50Hz -- Dual-Port memory download succeeded.
4 All cards passed OCXO test.
5 Sample Rate 75Hz -- Dual-Port memory download succeeded.
6 All cards passed OCXO test.
7 Sample Rate 100Hz -- Dual-Port memory download succeeded.
8 All cards passed OCXO test.
9 Sample Rate 150Hz -- Dual-Port memory download succeeded.
10 All cards passed OCXO test.
11 Sample Rate 200Hz -- Dual-Port memory download succeeded.
12 All cards passed OCXO test.
13 Sample Rate 250Hz -- Dual-Port memory download succeeded.
14 All cards passed OCXO test.
15 Sample Rate 300Hz -- Dual-Port memory download succeeded.
16 All cards passed OCXO test.
17 Sample Rate 400Hz -- Dual-Port memory download succeeded.
18 All cards passed OCXO test.
19 Sample Rate 500Hz -- Dual-Port memory download succeeded.
20 All cards passed OCXO test.
21 Sample Rate 600Hz -- Dual-Port memory download succeeded.
22 All cards passed OCXO test.
23 Sample Rate 800Hz -- Dual-Port memory download succeeded.
24 All cards passed OCXO test.
25 Sample Rate 1000Hz -- Dual-Port memory download succeeded.
26 All cards passed OCXO test.
27 Sample Rate 1200Hz -- Dual-Port memory download succeeded.
28 All cards passed OCXO test.
29 Sample Rate 1600Hz -- Dual-Port memory download succeeded.
30 All cards passed OCXO test.
31 Sample Rate 2000Hz -- Dual-Port memory download succeeded.
32 All cards passed OCXO test.
Commercial in Confidence
PJH/JAH/O:Reports/FAR/S7412/1190 TESLA Exploration International Limited
INEOS Enterprises Limited November 2013
33 Sample Rate 2400Hz -- Dual-Port memory download succeeded.
34 All cards passed OCXO test.
35 Sample Rate 3200Hz -- Dual-Port memory download succeeded.
36 All cards passed OCXO test.
37 Sample Rate 3600Hz -- Dual-Port memory download succeeded.
38 All cards passed OCXO test.
39 Sample Rate 4000Hz -- Dual-Port memory download succeeded.
40 All cards passed OCXO test.
41
42 All tests completed successfully.
Figure 1: System diagnostic report
While the recording equipment was being laid out we moved onto the testing of the Aries
recording system timing against the Seismic Source Universal Encoder UE_ II electronics. The
Aries system AX program was then used to verify the timing of the source control system,
the Seismic Source Encoder against the recording instrument to ensure the correct time
delay was entered in order to achieve zero time delay between the recording system and
the encoder. The AX program was run several times in order to check the consistency of the
timing between systems. An average was taken and then entered into the Internal Start
window.
An Internal Start of + 1000046 µs was selected. The system time break check was also
selected with a +/- 20 µs entered. This represents a tolerance of acceptable time Break in
µs. When a Time Break occurs outside tolerance, a warning is displayed during the
acquisition process and the acquisition halted.
Auxiliary Channel Allocation;
For vibroseis operations 3 channels are available, due to previous seismic surveys recorded
in this area the optimum sweep parameters had already been selected and was then
processed on the Testif-I Check Reference sweep program, this program compares the
synthetic sweep with a recorded one and produces a number of plots (figure: 2 ) to show
how similar the sweeps are. After seeing both signals looked similar a stored Auto
Correlation (ACCOR) sweep was generated, this will then become the reference sweep. The
auxiliary channel assignments will be as follows:
Channel Auxiliary assignment
1 PTB (System Predicted Time Break)
2 True Reference (Pilot) 500 ms display delay
3 Wire line Reference
4 ACCOR Autocorrelation of stored reference 1000ms display delay
Commercial in Confidence
PJH/JAH/O:Reports/FAR/S7412/1190 TESLA Exploration International Limited
INEOS Enterprises Limited November 2013
Figure 2: Plot showing the generated synthetic sweep frequency range 20Hz to 180Hz
compared to the recorded reference sweep.
Before the start of production a 100 Hz frequency test was also acquired by use of a Verif-i
precision clock. The precision clock is connected to a geophone takeout and then the 100 Hz
signal is recorded through the Aries recording system. This then allows the SEG Y file to be
processed on Testif-I software allowing the exact frequency recorded being displayed and
the PPM (Parts Per Million) error time shown ensuring the recording system master clock is
Commercial in Confidence
PJH/JAH/O:Reports/FAR/S7412/1190 TESLA Exploration International Limited
INEOS Enterprises Limited November 2013
being checked (figure: 3). All 100 Hz frequency tests acquired by use of a precision clock
were then processed on Testif-i software shown below.
Figure 3: Processed 100 Hz precision clock record, showing a system error of -1.264 PPM. A
geophone tap test was also recorded to ensure we were recording SEG polarity. In order to
comply with the SEG polarity convention a tap on the top of a normally connected spread
geophone should result in a positive number on tape and an up-break to camera (figure: 4).
This was also used as a QC aid to ensure station positioning was correct.
Commercial in Confidence
PJH/JAH/O:Reports/FAR/S7412/1190 TESLA Exploration International Limited
INEOS Enterprises Limited November 2013
Figure 4: The processed camera record showed an up-break in response to a tap on the top
of the geophone.
The nominal geophones spacing was a linear array with two strings of 6 geophones evenly
spaced over 20 meters with an element spacing of 1.66 meters. If for any reason the
geophones could not be laid in a full linear array due to obstructions there was several
alternative geophone patterns agreed with the client representative, these alternative
geophone arrays would be noted on the SPS files in order for the processor to spot any
irregularities. These patterns would be two strings of 6 geophones evenly spaced over 20
meters with an element spacing of 1.66 meters perpendicular on the peg cross-line because
Commercial in Confidence
PJH/JAH/O:Reports/FAR/S7412/1190 TESLA Exploration International Limited
INEOS Enterprises Limited November 2013
of obstacles or if the incline over the array exceeded 1 meter in elevation, Two strings of 6
geophones bunched over 1 meter on the peg inline because of obstacles with an element
spacing of 0.09 meters, Two strings of 6 geophones bunched over 5 meter on the peg inline
because of obstacles with an element spacing of 0.45 meters, Two strings of 6 geophones
bunched over 10 meter on the peg inline because of obstacles with an element spacing of
0.90 meter, Two strings of 6 geophones bunched over 15 meter on the peg inline because of
obstacles with an element spacing of 1.36 meter. If we were unable to plant geophones due
to solid ground or obstacles, this station would be left open and recorded as a dead station.
The geophone station interval was 20 meters, the source points were nominally spaced at
40 meters additional VPs where recorded at the beginning and end of each line to give
extract fold of cover when stacking on and rolling off. Any programmed additional shots
could be recorded if necessary to compensate for shots omitted due to PPV readings or wet
ground.
Once there was enough line equipment laid out on receiver line IN-13-03 to give a sufficient
offset range we ran a set of daily tests. The Aries SPM recording filters were set at 3 hz to
205 hz @ 1 ms sample rate with a 30 dB preamp gain with a record length of 3 seconds, a
comprehensive set of daily tests was recorded on the entire line, this comprised of, Full
band, EIN, Impulse, Gain, THD, CMR, XFD for the Aries boxes. The geophones were also
tested for any channels responding irregularly, these tests consisted of Noise, Pulse,
Sensitivity, Resistance, Leakage, THD, Impedance and XFD. A daily system diagnostic test
was recorded to ensure the Aries system was working correctly. All the daily test results
were recorded as SEG files and made available to the client. Also prior to start of production
a noise strip was also recorded to tape as a daily monitor of the noise on active spread.
The vibrators were also tested, before the start of production a set of radio similarities
(figure: 5) were recorded on each vibrator to ensure its correct performance prior to
starting.
Figure 5: Radio similarity test vibrator 3 @ 50% drive level displaying phase within +/- 5
degrees of 180°
Commercial in Confidence
PJH/JAH/O:Reports/FAR/S7412/1190 TESLA Exploration International Limited
INEOS Enterprises Limited November 2013
The VP points would be taken into a selected area known as the active patch; this area
would give sufficient coverage for the inline offset, depending on the VP point would deter
the amount of active channels nominally 75 – 75 symmetrical split with a 0 station gap on
the VP point allowing 75 active stations either side of the source point giving a maximum
offset of 1500 meters high and low. Each shot would be recorded into a separate patch; a
reduced patch was also used for stacking on and off.
The prospect area consisted of 4 source and receiver lines. The total survey area recorded
covered approximately 17.7 kilometers made up predominantly of cross country sections
with some vibroseis on roads and tracks. Receiver lines IN-13-01 and IN-13-03 crossed the
main A530 road and we had been instructed not to cross this section of carriageway with
conventional road mats. This was overcome by the use of a net-link (figure: 6), the net-links
would be setup either side of the carriage way and then allow data to be transferred back to
the Aries box below then through the cables to the recording truck The lines also crossed
the railway line and was network beneath the track by using an existing culvert.
Figure 6: Net-link setup crossing a busy trunk road.
Half way through recording on line IN-13-03 the client had planned to carry out a series of
sweep parameter tests to ensure the correct sweep parameter had been selected, these are
the series of tests listed below requested by the client in order to test alternative sweep
parameters. All test data was returned to base to be processed in order to confirm the best
sweep parameter.
Commercial in Confidence
PJH/JAH/O:Reports/FAR/S7412/1190 TESLA Exploration International Limited
INEOS Enterprises Limited November 2013
Sweep range test:
1 Vibrators, 2 composites @ 75% drive level 12-160Hz sweep, 10 second sweep length, start
tapers 250ms and end tapers 250ms linear.
1 Vibrators, 2 composites @ 75% drive level 12-160Hz sweep, 10 second sweep length, start
tapers 250ms and end tapers 250ms linear, diversity stack On, 300ms window.
1 Vibrators, 2 composites @ 75% drive level 15-170Hz sweep, 10 second sweep length, start
tapers 250ms and end tapers 250ms linear.
1 Vibrators, 2 composites @ 75% drive level 20-180Hz sweep, 10 second sweep length, start
tapers 250ms and end tapers 250ms linear.
1 Vibrators, 2 composites @ 75% drive level 25-190Hz sweep, 10 second sweep length, start
tapers 250ms and end tapers 250ms linear.
1 Vibrators, 2 composites @ 75% drive level 25-190Hz sweep, 10 second sweep length, start
tapers 250ms and end tapers 250ms +3 dB/Octave.
1 Vibrators, 2 composites @ 75% drive level 15-170Hz sweep, 10 second sweep length, start
tapers 250ms and end tapers 250ms +3 dB/Octave.
1 Vibrators, 2 composites @ 75% drive level 20-180Hz sweep, 10 second sweep length, start
tapers 250ms and end tapers 250ms +3 dB/Octave.
1 Vibrators, 2 composites @ 75% drive level 25-190Hz sweep, 10 second sweep length, start
tapers 250ms and end tapers 250ms +3 dB/Octave.
1 Vibrators, 2 composites @ 75% drive level 20-180Hz sweep, 10 second sweep length, start
tapers 250ms and end tapers 250ms linear, 2 sweeps, 1 mtr move up between sweep 1 and
2.
1 Vibrators, 4 composites @ 75% drive level 20-180Hz sweep, 10 second sweep length, start
tapers 250ms and end tapers 250ms linear, 4 sweeps, 1 mtr move up between sweep 2 and
3.
1 Vibrators, 6 composites @ 75% drive level 20-180Hz sweep, 10 second sweep length, start
tapers 250ms and end tapers 250ms linear, 6 sweeps, 1 mtr move up between sweep 3 and
4.
1 Vibrators, 3 composites @ 40% drive level 20-180Hz sweep, 10 second sweep length, start
tapers 250ms and end tapers 250ms linear, 3 sweeps, standing.
Once the parameter tests were complete it was confirmed that we had started production
with the optimum sweep but needed to increase the number of composites from 2 sweeps
Commercial in Confidence
PJH/JAH/O:Reports/FAR/S7412/1190 TESLA Exploration International Limited
INEOS Enterprises Limited November 2013
to 4 sweeps per vibrator point to increase the data quality. We then did a complete set of
wire-line similarities on all 3 Vibrators model: I/O AHV IV-PLS362 at the preferred sweep
parameter; start frequency 20 hertz to end frequency 180 hertz with a sweep length of 10
seconds, sweep type linear with start/end tapers of 250 milliseconds to determine the
performance of the vibrators. The vibrators would connect their wireline similarity boxes
(DSU) to a geophone takeout and the Ground Force and True Reference signals recorded
through the Aram Aries recording system. This then gives the start time error between the
Vibrators electronics and the Seismic Source UE_II Encoder and the SEG Y file then
processed on Testif-I software, this would then plot the phase and distortion of each
vibrator (figure: 7) for individual machines and a multi-vibrator similarity (figure: 8) giving a
comparison of all vibrators.
Commercial in Confidence
PJH/JAH/O:Reports/FAR/S7412/1190 TESLA Exploration International Limited
INEOS Enterprises Limited November 2013
Figure 7: Processed Testif-I Advance vibrator wireline similarity of vibrator 3 at 30% drive
level showing a start time error of 2 µs and total distortion, also the fundamental amplitude
in (Ib) expected at 30% drive level.
Commercial in Confidence
PJH/JAH/O:Reports/FAR/S7412/1190 TESLA Exploration International Limited
INEOS Enterprises Limited November 2013
Figure 8: Processed Testif-I Multi-vibrator wireline similarities show a comparison of
performance between vibrators 2,3 & 4 at 30% drive level. The multi sweep analysis shows
the units comparison in phase, correlation and distortion.
Commercial in Confidence
PJH/JAH/O:Reports/FAR/S7412/1190 TESLA Exploration International Limited
INEOS Enterprises Limited November 2013
The wet ground and the shortness of the 10 second sweep, sweeping through the frequency
range 20Hz to 180Hz contributed to the high levels of distortion. The vibrators were
constantly monitored in production and the Post Sweep Service (PSS) displayed and
recorded. At time the drive levels needed decreasing to reduce the distortion levels being
reported. A road sweeper was also used to ensure any mud from the vibrators was cleaned
from roads and private tracks.
The data quality throughout the prospect had been variable with a combination of good to
fair records, 99% of VP point were cross country with the higher drive levels achieved where
possible without exceeding distortion tolerances, and variable drive levels close to areas
with services and PPV monitoring of buildings, houses, HP gas pipelines, so the drive levels
would be reduced in order to comply with Tesla Exploration International Limited
recommended safety distance limits. All buildings required PPV monitoring to ensure that
the vibrations from the vibrators did not cause any damage to property within close
proximity of the source line. If PPV levels reached the Tesla recommended safety limits,
drive levels or number of vibrators was reduced to ensure no damage.
The observer would monitor each shot record for noise or channels responding irregularly.
All monitors were delivered along with a comprehensive daily log to the office for
generating the daily report and daily SPS files produced for data QC.
Small isolated sections of noise were experienced on all traverses, predominately adjacent
to farm buildings and dwellings and close proximity of the railway line. On all lines there
were a number of road junctions and intersections which also contributed to higher levels of
random noise, due to the high volume of traffic on the busy A530 main road.
All recorded data was stored on LTO Ultrium 2 cartridges, all data was backed up and CD’s
produced containing all SPS files and copies off all daily tests and observers reports. All was
shipped on completion of recording to processing
The final day of production was 23rd
November 2013. Once we had finished recording this
then released all the line equipment and the line crews started the picking up of cables and
geophones. All equipment was then returned to base to be counted and packed.
Commercial in Confidence
PJH/JAH/O:Reports/FAR/S7412/1190 TESLA Exploration International Limited
INEOS Enterprises Limited November 2013
5. HEALTH, SAFETY and ENVIRONMENT
Overview
The full implementation of TESLA EXPLORATION’s Occupational, Health and Safety
management system (OHS-MS) was applied by ensuring adequate meetings, auditing, risk
identification and analysis, reporting, control and follow up was maintained on a regular
basis. This resulted in the completion of the project with the target of Zero LTI achieved.
Before the commencement of the project, the TESLA EXPLORATION crew management
produced a PROJECT SPECIFIC HSE PLAN, specific to the location, terrain and legal HSE
requirements of the United Kingdom, Europe and industry guidelines (OGP/IAGC). TESLA
EXPLORATION management on the crew made every effort to ensure that the Health, Safety
and Welfare of the crew personnel were maintained at the highest possible level. This also
included the prevention any foreseeable environmental damage that could occur during the
course of the seismic survey.
From the first day to the end of the project, TESLA EXPLORATION Crew 1190 provided all the
necessary HSE requirements to the crew personnel and sub contractors.
The HSE Advisor on the crew used the TESLA EXPLORATION HSE Management System
manual in accordance with the local conditions and associated HSE legal requirements.
Throughout the operation, successful identification of hazards and risk control enabled all
operations to be completed in a completely safe and timely manner.
The Party Chief promoted the benefits of safe work practices and visibly demonstrated his
commitment with regular participation in HSE activities. By doing so, he presented a positive
message to both the senior and junior staff.
There were visits from both INEOS ENTERPRISES LTD and TESLA EXPLORATION LTD senior
management during the course of the survey. All parties demonstrated their support and
commitment to the crew regarding HSE matters.
Overall, TESLA EXPLORATION crew 1190 produced a high quality product whilst maintaining
a safe and environmentally friendly working atmosphere.
HSE activities:
Total Man-hours exposure for the contract: 3,000
Total LTI free hours for the contract: 3,000
Total Miles driven: 7,934
Total recordable incident cases: 0
Medical Treatment Cases: 0
Commercial in Confidence
PJH/JAH/O:Reports/FAR/S7412/1190 TESLA Exploration International Limited
INEOS Enterprises Limited November 2013
First Aid Cases: 0
Restricted Work cases: 0
Inductions: 41
Toolbox Talks: 10
Safety Meetings: 4
Stop cards: 4
Safety Observations: 3
Internal Audit: 1
Management Safety Inspection: 1
All visitors received an orientation HSE induction and were supervised around the prospect
area.
First aid kits for all vehicles were inspected and refilled prior to the commencement of the
works.
Both the base and office locations were supplied with adequate first aid and welfare
facilities.
TESLA EXPLORATION carried out total of 2 audits/inspections with regular observation
reports.
All crewmembers received a full HSE induction on arrival at the crew base.
All crewmembers received the relevant PPE and training on the use and care of the items
before starting work.
All representatives of the client, subcontractors and TESLA EXPLORATION management and
crewmembers were encouraged to attend the daily toolbox talks.
All vehicles were issued with a copy of the crew ERP (Emergency Response Procedures).
Comprehensive vehicle checks were carried out on a daily basis by all of the designated
drivers.
All vehicles were also supplied with a copy of the expected HSE standards as set out by
INOES ENTERPRISES Ltd.
A fire prevention check was carried out on all of the fire extinguishers prior to the start of
operations.
HSE toolbox meetings:
An essential part of the HSE management system requires the transfer of information and
feedback from crew level. This was achieved through regular crew toolbox meetings.
Commercial in Confidence
PJH/JAH/O:Reports/FAR/S7412/1190 TESLA Exploration International Limited
INEOS Enterprises Limited November 2013
with employees
and sub-
contractors.
Sub contractor Safety Rep /
Behavioural Safety Meetings
Tool Box Talks.
Environmental Considerations
The crew worked within the guidelines as set out in the TESLA EXPLORATION environmental
policies.
The following general instructions were explained to the crew:
To minimize all travel, particularly along the off road traverse routes by making use of good
daily planning.
All rubbish and waste material to be returned back to the base facility at the end of each
working day.
Oils and fluids are not to be changed or replaced in the field.
A spill containment system should always be in place wherever there is storage of oils and
other lubricants and chemicals.
All operations are to be carefully planned to minimize disturbance and effects to flora and
fauna.
Chance finds of habitats are to be marked on a map and avoided.
Acts of interference and vandalism by the workforce would not be tolerated.
Waste segregation rules and line clearance regulations were complied with. All surveying
pegs, markers and bunting was completely removed from site.
Emergency response procedures
A range of contingency plans were developed on crew, to apply in the unlikely event of
emergency situations such as fire, illness or injury and oil spill etc. These emergency plans
were processed and posted in the mess, offices and a copy provided for each vehicle.
Instruction was also given for all personnel/visitors relating to the plan at the initial
induction phase.
Emergency Drills
The objective of the drills is to determine the efficiency of the response of the crew to
control an emergency situation, to check the readiness of the team responsible for
controlling an emergency and to test available equipment.
Flow diagrams outlining the emergency response structure and advising contact numbers
were posted on the office notice board, the recording unit and mess facility.
Safety advice notices were also posted on the mess notice board.
Commercial in Confidence
PJH/JAH/O:Reports/FAR/S7412/1190 TESLA Exploration International Limited
INEOS Enterprises Limited November 2013
Instructions in case of Fire were placed by room exits.
Emergency MEDEVAC procedures including the INEOS instructions were posted in all of the
vehicles and in the Party Chief’s office.
All relevant TESLA EXPLORATION policies were posted on the main notice board. Prospect
site-specific hazards were also posted on the main notice board.
Vehicle Management
Vehicle movement/transportation is always identified as the most hazardous operation on
land seismic crews. Because of the high potential for vehicle accidents it was recognised the
whole crew had to be actively engaged in its prevention.
Due to the nature of the ground on some of the survey lines, Polaris Rangers were used to
minimize damage to the environment. Before commencement of operations all Rangers
were fitted with measures to ensure that they were road worthy and legal. All Ranger
drivers had received the relevant training before the contract started and a copy of their
qualifications kept on the crew training records.
During normal operations drivers kept the senior observer informed of their location.
Throughout of the project, radio communication and mobile telephone signals were good
including reasonable access to the Internet.
Security
The operations base was in a rural location within the confines of a local farming operation
near to the village of Byley. A security patrol was maintained during the hours of darkness
and no vandalism or theft was reported throughout the whole of the operation.
Safe passage for pedestrians was maintained at all times. Noise was also kept to a minimum
during working hours to ensure good relations with neighbours.
Ramp signs were placed on roads where cables crossed. The cables where protected in
rubber cable mats.
All hazards were clearly marked and visible to all personnel on site. Other work activities
from the owners of the farms did not interfere or cause any hazards to the crew.
Commercial in Confidence
PJH/JAH/O:Reports/FAR/S7412/1190 TESLA Exploration International Limited
INEOS Enterprises Limited November 2013
Internal Inspections
2 audits and inspections were completed during the course of the survey. The crew HSE
Advisor carried one of the audits out and the TESLA EXPLORATION management team, who
visited the crew, conducted the other inspection.
The HSE advisor made daily visits to the field operations to observe and monitor the
activities of the crew. When examples of bad practice and unsafe actions were observed,
the work was stopped and the correct procedures were explained, demonstrated and
implemented.
The client representative also conducted frequent observations of the field operations and
gave valuable feedback to the crew management.
Findings for recommended corrective actions were mainly provided by the completion of
STOP cards. The results were discussed at the following toolbox meeting on the next day.
Vehicle related incidents and LTI’s
For the period of the contract (November 15th- November 24th 2013), there were no
accidents/incidents resulting in lost time due to injury.
Key Performance Indicators
Daily safety statistics were recorded by the HSE Advisor and forwarded to the Crew
Manager who compiled a crew daily/weekly/monthly report.
Vibration monitoring
During recording operations regular vibration monitoring checks were carried out (PPV).
Monitoring results were recorded and logged when operations took place near to any
buildings and services in the prospect area. TESLA EXPLORATION will keep all findings on file
in the unlikely event of any civil litigation that may arise at a later date. The client
representative has also retained copies of the files.
Crew Medical Care
The nearest Accident & Emergency hospital facility and a local doctor’s surgery to the
prospect area were identified the same day on arrival, or as soon as possible. All crew
personnel were made aware of this by means of the crew’s toolbox meetings, Emergency
Response Procedure (ERP) and initially on their induction. The crew had 13 1st
Aid trained
Commercial in Confidence
PJH/JAH/O:Reports/FAR/S7412/1190 TESLA Exploration International Limited
INEOS Enterprises Limited November 2013
personnel on call at any one time. A list was produced and placed on the HSE notice board
in order for the crew to fully understand who their nearest first aid trained operative was.
Observation and analyses
Statistics showed a total of 7 stop cards given to the HSE department. The stops cards that
were given to the HSE department were of a high quality and did assist the crew in the
development of risk reduction measures. Intensive efforts were made by the crew
Management team to improve hazard reporting by ensuring this was a regular subject at
safety meetings.
Encourage should be given to the lower ranked members of the workforce. His or her
superiors should impress the ‘blame free’ attitude on each individual.
TESLA EXPLORATION is committed to the provision of adequate and suitable PPE (Personal
Protective Equipment) for its employees.
6. PERMIT
The Permit Liaison Officer commenced permit activity on 11 November 2013. The main role
was to liaise with INEOS land agent, walk all line and review all accesses for Vibs and line
crew.
Line IN-13-03 was walked first to identify any potential issues with line positioning and
vibrator access. During a subsequent meeting with Robert Hodson, INEOS permit man, and
John Boundy, INEOS project manager, all were made aware of the issues identified and the
adjustments that were required to access the lines. Once the changes were confirmed all
fields were walked again and marked with bunting to showing the access. This was repeated
for each line.
After some very heavy rainfall re-examination of field access was required for all lines and
some adjustments were identified. The first line to be shot was walked with John Boundy
and Jacques Bal to demonstrate how access would be gained in flooded fields and
agreement was reached on routes to be used to access the lines to lessen environmental
impact.
Commercial in Confidence
PJH/JAH/O:Reports/FAR/S7412/1190 TESLA Exploration International Limited
INEOS Enterprises Limited November 2013
A meeting at INEOS offices was arranged to clarify progress, Tesla also received further
maps and service plans during this visit.
Meetings were arrange with the HP gas pipeline representative and helped to mark the
pipelines on site in preparation for our programming, The Fuel pipeline representative who
helped to mark the pipelines on site in preparation for our programming.
Commercial in Confidence
PJH/JAH/O:Reports/FAR/S7412/1190 TESLA Exploration International Limited
INEOS Enterprises Limited November 2013
7. DATA PROCESSING AND QC
Data Processing was carried out off site by TESLA Exploration International Limited, Unit 2
Nix’s Hill, Nix’s Hill Industrial Estate, Alfreton, Derbyshire DE55 7GN.
Line IN-13-03 Line IN-13-02
Line IN-13-04 Line IN-13-01
8. CONCLUSIONS AND RECOMMENDATIONS
The survey was completed to the instructions of the Client, with data quality ranging from
fair to good.
Fold of cover was maintained.
The impact on the local community was minimal with many farmers and land owners
complimenting the crew on its methods of operation, diligence and efficiency.
All HSE tools were used to good effect, with stop card being discussed at toolbox meeting
insuring that everybody being made aware of any hazards.
The survey was successfully completed without any lost time incident or accident being
reported during all operational phases.
Commercial in Confidence
PJH/JAH/O:Reports/FAR/S7412/1190 TESLA Exploration International Limited
INEOS Enterprises Limited November 2013
9. CREW VISITORS
All visitors to the field crew were given an INEOS Enterprises Limited Safety briefing. TESLA
Exploration also gave a safety brief and induction on arrival.
Visitors included:-
Mark Rees Tesla Exploration
Ian Angus Tesla Exploration
Mike Wildblood Tesla Exploration
Robert Hodson Land Agent INEOS Enterprises Limited
Richard Stevenson INEOS Enterprises Limited
Allen Capper INEOS Enterprises Limited
David Peterson INEOS Enterprises Limited
Gary Rawlinson E-On
Deborah Whitworth-Hilton E-On
Ian Walker E-On
Commercial in Confidence
PJH/JAH/O:Reports/FAR/S7412/1190 TESLA Exploration International Limited
INEOS Enterprises Limited November 2013
APPENDIX 1
Commercial in Confidence
PJH/JAH/O:Reports/FAR/S7412/1190 TESLA Exploration International Limited
INEOS Enterprises Limited November 2013
SURVEY STATISTICS:-
Permit Liaison Days Tesla 13 Days
Survey Main Survey 5.35 Days
Extra Survey 0 Hrs
Reduced Survey 2.35 Hrs
Receiver Pegs Surveyed 885 – 2D
Source Pegs Surveyed 444 – 2D
Total km 17.7 Km
Recording Linear Extent 17.7 Km
Receiver stations Laid 885
VP’s Recorded (2-4 Sweeps) 582 2D
Recording Days 4.5 Days
Recording Travel Hours 3.5 Hrs
Recording Work Hours 46.5 Hrs
Total Working Hours 50.0 Hrs
Layout/ PickUp 0.95 Hrs
Downtime Hours 4.00 Hrs
Standby Hours 0.25 Hrs
PPV Monitoring 4.0 Days
Security 5.0 Days
Road Sweeper 5.0 Days
Lines:
IN-13-03 Stn numbers 101-360 Number VPs 144
IN-13-02 Stn numbers 101-347 Number VPs 159
IN-13-04 Stn numbers 101-255 Number VPs 114
IN-13-01 Stn numbers 101-327 Number VPs 150
Total VP’s 567
Commercial in Confidence
PJH/JAH/O:Reports/FAR/S7412/1190 TESLA Exploration International Limited
INEOS Enterprises Limited November 2013
APPENDIX 2
Commercial in Confidence
PJH/JAH/O:Reports/FAR/7412/1190 TESLA Exploration International Limited
INEOS Enterprises limited November 2013
Commercial in Confidence
PJH/JAH/O:Reports/FAR/S7412/1190 TESLA Exploration International Limited
INEOS Enterprises Limited November 2013
APPENDIX 3
Commercial in Confidence
PJH/JAH/O:Reports/FAR/7412/1190 TESLA Exploration International Limited
INEOS Enterprises limited November 2013
Ineos Enterprises Ltd
HOLFORD Rev 2
Northwich Sites 05-Nov-2013
G3 Planning Project - Seismic Survey Who's Who
TITLE Organisation Forename Name Location E-Mail Address Telephone No. Fax Number MobileTelephone No
IEL PROJECT MANAGEMENT
Brine & Water Operations Manager Ineos Enterprises Jon Whieldon Holford
Project Manager Ineos Enterprises Richard Stevenson Holford
IEL Duty Manager Ineos Enterprises
Technical Manager Ineos Enterprises Robin Craig Holford
Project Engineer Ineos Enterprises David Peterson Holford
Work Liaison / Management Ineos Enterprises John Boundy Holford
SHE & Quality Manager Ineos Enterprises Allan Craig Enterprise House
Public Relations & Communications Ineos Enterprises Janet Ward Enterprise House
Senior Buyer Ineos Enterprises Sarah Roberts Enterprise House
Farmer Liaison Ineos Enterprises Robert Hodson Holford
Security / Incident Control PANAD
Holford Shift Operator Ineos Enterprises
TESLA EXPLORATION
Regional Manager Tesla Exploration Mark Rees Alfreton
Party Chief Tesla Exploration Mike Wildblood Alfreton
Senior Surveyor Tesla Exploration Paul Hardie Alfreton
BASE CAMP
Drakelow Hall Farm Alan & Joan Hollingshead Drakelow Hall Farm
GEOLOGY SUPPORT
Project Manager Geostock Arnaud Reveillere France
Senior Geophysical Engineer Geostock Sacha di Giandomenico France
Senior Geophysical Engineer Geostock Patrick Renoux France
Senior Geophysical Engineer Geostock Jacques Bal France
OTHER ORGANISATIONS
Compass Minerals Winsford Salt Mine Gary Sinclair
NTS Surveyor National Grid Malcolm Woodcock
NB: For Emergency Services use RVP 08
Commercial in Confidence
PJH/JAH/O:Reports/FAR/S7412/1190 TESLA Exploration International Limited
INEOS Enterprises Limited November 2013
APPENDIX 4
Commercial in Confidence
PJH/JAH/O:Reports/FAR/S7412/1190 TESLA Exploration International Limited
INEOS Enterprises Limited November 2013
Commercial in Confidence
PJH/JAH/O:Reports/FAR/S7412/1190 TESLA Exploration International Limited
INEOS Enterprises Limited November 2013
APPENDIX 5
Commercial in Confidence
PJH/JAH/O:Reports/FAR/S7412/1190 TESLA Exploration International Limited
INEOS Enterprises Limited November 2013
PERSONNEL LIST
Regional Manager Mark Rees
Party Chief Phillip Hounsell
HSE Officer Ken Harris
Administrator Nicolas LeBaud
Permit Liaison Paul Hardie
Senior Surveyor Paul Hardie
Surveyors Michael Young
Survey Assistants Steven Kesson
Bob Clayton
Senior Observers Wayne Eaton Line Foremen Scott Nicholls
Observers Carl Fletcher
Senior Mechanic Jamie Fawcett Line Crew Wayne Adams
Mechanics Thomas Seik Andy Best
Adam Detlaf
Vibrator co-ordinator/ Alf Johnson Mark Forward
PPV monitor. Terry Hornby Mark Hindmarch
Jason Kelly
Vib Drivers Kevin Shaw Wayne Nicholls
Colin Major James Price
Mick Golightly John Patterson
Trouble shooters Mark Boulton
Denis Cronin
Commercial in Confidence
PJH/JAH/O:Reports/FAR/S7412/1190 TESLA Exploration International Limited
INEOS Enterprises Limited November 2013
APPENDIX 6
Commercial in Confidence
PJH/JAH/O:Reports/FAR/S7412/1190 TESLA Exploration International Limited
INEOS Enterprises Limited November 2013
FIELD CREW EQUIPMENT LIST
Office/Administration/Permit
Office equipment, including fax and photocopier
2 cars
3 mobile telephones
2 IBM compatible PCs
1 Office / yard set up with internet access, photocopier, scanner etc
Survey
1 3 unit Kinematics GPS system (Leica Viva GS10) (2012)
1 Leica Viva TS15 Robotic Total Station (2012)
1 Set of line-laying equipment
1 Traverse set
3 Vehicles (2010-2013)
1 Survey software package, to output co-ordinates in UK00A format
1 IBM compatible PC
Recording
1 4x2 Recording truck complete with power generation (2008)
1 ARAM Aries Recording system (version 3.108.01) configured for Vibroseis and/or
explosives source recording complete with plotter, cartridge drive, and sufficient ground
equipment for a total of 450 (depends on option) receiver stations with a station
interval of up to 35m and adequate LTUs and traverse line (2007-12)
450 Strings of SM24 10Hz geophones with 75 mm spikes, 12 per string,
(6x2) per station (2009)
10 Support vehicles (2009-2013)
Complete sets of road safety crossing signs and cable protectors
Complete set of road traffic management signs
1 Bird Dog II geophone tester
1 Set electronic test equipment
Verif-i Sandwich Box-vibrator analysis (2010)
Verif-i Precision 100Hz Clock (2009)
Verif-i Testif-i Equipment testing software (2009)
1 Vibrock V901 PPV Meter (2012)
1 Seismic Source Universal Encoder 2 (2013)
3 Seismic Source Force II Vibrator Electronics (2009)
1 Novatel Vibrator DGPS System (2009)
3 I/O 362 4 x 4 Vibrators, 61,800lb peak force (1998)
1 Mercedes Benz 4x4 Mobile Workshop/Store (2012)
12 Motorola Mobile radios (2010)
12 Motorola Handheld radios (2010)
1 Trakranger Radio/vehicle tracking software (2012)
1 Bunded fuel bowser (2013)
Commercial in Confidence
PJH/JAH/O:Reports/FAR/S7412/1190 TESLA Exploration International Limited
INEOS Enterprises Limited November 2013
Processing
SEISMIC PROCESSING CENTRE
a) Hardware
Dual Xeon System, Red Hat Enterprise v 3.0 (Linux) [February 2006]
2 x Intel Xeon (dual core) 3.0 GHz processors
6 GB RAM
3 x 73 GB internal SCSI 320 disks, hardware RAID 0 array, with a hotspare
InforTrend SCSI to SATA RAID Array Subsystem, with 9 x 500 GB SATA300disks, arranged as RAID
0+1 with hotspare
OverLand Tape Autoloader Subsystem with LT0-3 (400/800 GB) drive and 11-slots
OverLand Tape Autoloader Subsystem with LT0-4 (800/1600 GB) drive and 24-slots
IBM DLT8000 (40/80 GB) Tape Drive and Exabyte 5/10 GB Tape Drive in IBM enclosure
DVD +/- RW drive
Riello online UPS
HPC Intel Xeon System, Red Hat Enterprise v 5.0 (Linux) [August 2012]
Printing/Plotting
HP 2800 A3 + colour Inkjet printer
HP K8600 A3 + colour Inkjet printer
HP T1100 44" roll colour Inkjet plotter
Dell 3130cn A4 colour Laser printer
Other
Fast PC’s (various) each with either dual 20” or single 24” LCD displays with usual Microsoft Office
software; NetSarang X software to enable PC’s to act as X-Terminals to our Linux server (running
SeisSpace/ProMAX).
Scanning capabilities, with Contex XD2490 24” colour scanner
b) Software
Linux
SeisSpace/ProMAX R5000 2D/3D Seismic Processing Software
In Seam Seismic Processing software (British Coal developed)
Microsoft PC
ArcView v10 GIS Mapping Software
Google Earth Pro (x2)
Surfer and Surpac Contouring Packages
Commercial in Confidence
PJH/JAH/O:Reports/FAR/S7412/1190 TESLA Exploration International Limited
INEOS Enterprises Limited November 2013
AutoCAD Map 3D 2011 drawing/design Software
Green Mountain Millennium Suite Refraction statics
IHS Kingdom Suite 2D/3D Interpretation Software with SynPAK and VuPAK extensions
Commercial in Confidence
PJH/JAH/O:Reports/FAR/S7412/1190 TESLA Exploration International Limited
INEOS Enterprises Limited November 2013
APPENDIX 7