http://nodal.ercot.com 1 Market Trials DAM/RUC/SASM Weekly Update July 02, 2010

Http://nodal.ercot.com 1 Market Trials DAM/RUC/SASM Weekly Update July 02, 2010

Embed Size (px)

Citation preview

Page 1: Http://nodal.ercot.com 1 Market Trials DAM/RUC/SASM Weekly Update July 02, 2010

http://nodal.ercot.com 1

Market TrialsDAM/RUC/SASM

Weekly Update

July 02, 2010

Page 2: Http://nodal.ercot.com 1 Market Trials DAM/RUC/SASM Weekly Update July 02, 2010

http://nodal.ercot.com 2

Antitrust Admonition

ANTITRUST ADMONITION

ERCOT strictly prohibits Market Participants and their employees who are participating in ERCOT activities from using their participation in ERCOT activities as a forum for engaging in practices or communications that violate the antitrust laws. The ERCOT Board has approved guidelines for members of ERCOT Committees, Subcommittees and Working Groups to be reviewed and followed by each Market Participant attending ERCOT meetings. If you have not received a copy of these Guidelines, copies are available at the Client Relations desk. Please remember your ongoing obligation to comply with all applicable laws, including the antitrust laws.

DISCLAIMER

All presentations and materials submitted by Market Participants or any other Entity to ERCOT staff for this meeting are received and posted with the acknowledgement that the information will be considered public in accordance with the ERCOT Websites Content Management Operating Procedure.

Page 3: Http://nodal.ercot.com 1 Market Trials DAM/RUC/SASM Weekly Update July 02, 2010

http://nodal.ercot.com 3

Agenda

• DAM/ RUC/SASM summary

• QSE Activities for Next Week

• General Reminders/Updates

• Environment Report

– Outages– Known Issues

• Special Topic

• Question and Answers / General Discussion

• Appendix

ERCOT asks that Market Participants log into the WebEx session using their company name

and then their name. This will allow ERCOT to take roll-call offline.

Page 4: Http://nodal.ercot.com 1 Market Trials DAM/RUC/SASM Weekly Update July 02, 2010

Market Trials 2010 Roadmap

http://nodal.ercot.com 4

Page 5: Http://nodal.ercot.com 1 Market Trials DAM/RUC/SASM Weekly Update July 02, 2010

http://nodal.ercot.com 5

Submission Overview for Friday June 25

DAM submission overview

• 173 QSEs participated for Op Day 6/26

• Energy Bids in the range of 25,623 to 42,607 MW per hour

• Cleared 19,852 to 28,222 MW energy per hr

• Cleared 11,657 to 16,818 PTP bids per hr

• Four major Load Zone prices ranged from $25.89 to $45.72

Page 6: Http://nodal.ercot.com 1 Market Trials DAM/RUC/SASM Weekly Update July 02, 2010

http://nodal.ercot.com 6

Submission Overview for Monday June 28

DAM submission overview• 193 QSEs participated for Op Day 6/29

• Energy Bids in the range of 27,734 to 44,948 MW per hour

• Cleared 19,852 to 28,222 MW energy per hr

• Cleared 11,618 to 13,719 PTP bids per hr

• Four major Load Zone prices ranged from $27.00 to $42.53

Page 7: Http://nodal.ercot.com 1 Market Trials DAM/RUC/SASM Weekly Update July 02, 2010

http://nodal.ercot.com 7

Submission Overview for Tuesday June 29

Submission overview• 219 QSEs participated for Op Day 6/30

• Energy Bids in the range of 27,492 to 42,492 MW per hour

• Cleared 21,193 to 29,026 MW energy per hr

• Cleared 15,832 to 18,775 PTP bids per hr

• Four major Load Zone prices ranged from $24.13 to $41.75.

Page 8: Http://nodal.ercot.com 1 Market Trials DAM/RUC/SASM Weekly Update July 02, 2010

http://nodal.ercot.com 8

Scenario Overview for Tuesday June 29

– Ran SASM• Simulated AS undeliverability

– Procured NSPIN from hours 1800-2400

• Simulated AS failure to provide

– Procured NSPIN, REGDN and REGUP from hours 2000-

2400

– Increased load forecast for the DRUC run.• Increase load forecast by 1600 MW for hour 1600-2000

Page 9: Http://nodal.ercot.com 1 Market Trials DAM/RUC/SASM Weekly Update July 02, 2010

http://nodal.ercot.com 9

Submission Overview for Wednesday June 30

Submission overview

• 215 QSEs participated for Op Day 7/01

• Energy Bids in the range of 26,158 to 39,957 MW per hour

• Cleared 19,624 to 26,354 MW energy per hr

• Cleared 13,325 to 15,839 PTP bids per hr

• Four major Load Zone prices ranged from $29.00 to $42.48.

Page 10: Http://nodal.ercot.com 1 Market Trials DAM/RUC/SASM Weekly Update July 02, 2010

http://nodal.ercot.com 10

Scenario Overview for Wednesday June 30

– Increased load forecast for the DRUC run.• Increase load forecast by approximately 1600 MW for hours

1200-2400

Page 11: Http://nodal.ercot.com 1 Market Trials DAM/RUC/SASM Weekly Update July 02, 2010

http://nodal.ercot.com 11

Submission Overview for Thursday July 1

Submission overview

• 215 QSEs participated for Op Day 7/2

• Energy Bids in the range of 25,564 to 38,703 MW per hour

• Cleared 19,713 to 25,604 MW energy per hr

• Cleared 16,169 to 18,886 PTP bids per hr

• Four major Load Zone prices ranged from $26.85 to $41.80.

Page 12: Http://nodal.ercot.com 1 Market Trials DAM/RUC/SASM Weekly Update July 02, 2010

http://nodal.ercot.com 12

Scenario Overview for Thursday July 1

– Delayed posting of DAM results and DRUC run• Sent notification via notice builder of a half hour delay in DAM

posting.

• Sent notification via notice builder of a half hour delay in the

DRUC run.

Page 13: Http://nodal.ercot.com 1 Market Trials DAM/RUC/SASM Weekly Update July 02, 2010

http://nodal.ercot.com 13

RUC Execution Overview for this week

RUC overview for the week:

- ERCOT overwrite of COP’s 7/1

Page 14: Http://nodal.ercot.com 1 Market Trials DAM/RUC/SASM Weekly Update July 02, 2010

http://nodal.ercot.com 14

Next Week’s Activities

Next week – Op Days are 7/7-7/10

DAM executing on 7/6-7/9

• No guardrails - Bids/offers should be reasonable

• COPs should reflect zonal throughout the week. We are requesting no

COP updates as a result of nodal market processes.

• Operational Scenarios:

– No operational Scenarios scheduled

Week 10Note: Dates are DAM execution days

7/6/2010 - 7/9/2010

ObjectiveNetwork Constraints Included

DAM 4 x week

DAM submissions No guardrails

COP Updates Reflect zonal

DRUC W/ each DAMHRUC LimitedWRUC 1 x weekSASM As neededOp Scenarios No Scenarios

Page 15: Http://nodal.ercot.com 1 Market Trials DAM/RUC/SASM Weekly Update July 02, 2010

http://nodal.ercot.com 15

Next Week’s Activities

DRUC executing on 7/6-7/9 after DAM

WRUC, HRUC and SASM executing on 7/7-7/9

• HRUC and SASM

– WRUC executing on Wednesday

– HRUC will be executed on Wednesday, Thursday and Friday at 1 pm

(target Operating Hours will be the balance of the Op Day)

• May be run for additional, non-supported hours

– SASM will be opened if needed based on system conditions

Next week• Outages will be ignored July 1-9 for internal Outage Schedule testing

• Again, next week ERCOT may do workarounds outside the normal

business process to sidestep any issues that arise. Furthermore, we may

approve the results of the RUC software even if the result is operationally

unreasonable. The purpose of this is to exercise settlement and billing

determinants related to RUC.

Week 10Note: Dates are DAM execution days

7/6/2010 - 7/9/2010

ObjectiveNetwork Constraints Included

DAM 4 x week

DAM submissions No guardrails

COP Updates Reflect zonal

DRUC W/ each DAMHRUC LimitedWRUC 1 x weekSASM As neededOp Scenarios No Scenarios

Page 16: Http://nodal.ercot.com 1 Market Trials DAM/RUC/SASM Weekly Update July 02, 2010

http://nodal.ercot.com 16

General Reminders/Updates

• Network Model Update

– An updated settlement points and MP short name list was posted for the 6/15 load at http://nodal.ercot.com/readiness/markettrials/index.html

– Next scheduled load is 7/14

• Reminder regarding External Interfaces Specification v1.19M

– Posted at http://nodal.ercot.com/readiness/sandbox/index.html

– Targeted for delivery on 7/9

• July 1-9 outages will be disregarded in the various processes.

– ERCOT will be performing Outage Scheduling testing during this period.

• ERCOT will be continuing to run WRUC

– Please be aware that WRUC requires valid COP data seven days out in order to have a good solution during the study period

• ERCOT will continue to announce on the Market Call the operating days for the next week

– Less operating days during LFC test weeks

– August is open to run operating days as necessary to complete verifications

• No Market call on Monday due to the holiday

Page 17: Http://nodal.ercot.com 1 Market Trials DAM/RUC/SASM Weekly Update July 02, 2010

http://nodal.ercot.com 17

Support Metrics

* This week, 24 out of 147 questions were responded to outside of the 24 hour time frame.

Market Participant Inbound Questions

Last Week This Week

Page 18: Http://nodal.ercot.com 1 Market Trials DAM/RUC/SASM Weekly Update July 02, 2010

http://nodal.ercot.com 18

Day-to-day operations summary: Planned / Unplanned Outages

• Planned Outages

• 07/02/2010 6:00 P.M. – 11:00 P.M. – Database maintenance activities are planned during this period and will affect availability of

following application services:» EWS ( Web Services)» MM UI

• Unplanned Outages

• 06/29/2010 12:10 P.M. – 12:45 P.M. – Users were unable to launch MM UI & CRR applications via the MIS portal due a script

failure.

Page 19: Http://nodal.ercot.com 1 Market Trials DAM/RUC/SASM Weekly Update July 02, 2010

Environment Report-Known Issues

Full DAM/RUC/SASM known issues list will post every Friday night at http://nodal.ercot.com/readiness/markettrials/dam/index.html

New DAM/RUC/SASM known issues

• Queries for updated Resource parameters returning rounded values

– After updating Resource Parameters with new values that include a decimal place, users are seeing rounded values returned when they query for the updated parameters (via either Web Services or Market Manager UI)

– The values are being captured correctly in the MMS database, but are returning incorrectly due to a rounding issue in EIP.

– This issue discovered for Ramp Up Rate, Ramp Down Rate, and Break Point for both Normal and Emergency Ramp Rates

http://nodal.ercot.com 19

Page 20: Http://nodal.ercot.com 1 Market Trials DAM/RUC/SASM Weekly Update July 02, 2010

http://nodal.ercot.com 20

Known issues closed out

Closed 14393 Limited DAM Energy Only Offer and Bid Award retrieval issue

DAM Energy Only Offer and Bid Award retrieval does not function if an Offer/Bid ID had been submitted for that day with leading or trailing spaces and only one non-space character. This can be avoided by ensuring that each Offer/Bid ID contains at least two non-space characters.

This can be avoided by ensuring that each Offer/Bid ID contains at least two non-space characters.

MMS Under review

Closed 15607 Awards xml file downloaded on Market Manager contains special characters at the beginning of the file.

Awards xml file downloaded on Market Manager contains special characters at the beginning of the file.

Open the xml file in Notepad, delete the special characters, save.

MMSUI Under review

Closed 15465 Total cleared Bids and total cleared Offers should be equal. However, when DAM is AS insufficient, the clearing engine can over-procure offers by a small amount (1-3 MW).

Total cleared Bids and total cleared Offers should be equal. However, when DAM is AS insufficient, the clearing engine can over-procure offers by a small amount (1-3 MW).

  MMS Under review

Closed 13792 EMS defects regarding the table that counts offline and online hours to send to the market system for purposes of respecting minimum online time and offline time.

EMS - issue during the database loads or software migrations where in some cases it is not properly counting the data in the table that keeps track of how long the unit has been online or offline past the last data load.

Second issue where EMS was overwriting the telemetered resource status for purposes of writing to this table when small MW generation values were seen in the telemetry. EMS will change this to look at net MW rather than gross, and will also add a threshold value to ignore small values likely to be telemetry errors/deviations.

ERCOT workaround in place for the first issue

EMS Fix in next EMS release

Closed 13792 EMS defect regarding offline resources generating small MW quantities

EMS overwrites the offline resource status if the unit is telemetered some some gross MW value. Fix will eliminate this overwrite.

  EMS Fix in next EMS release

Closed   Reports delivered late to Phase 4.0 The following report will be delivered late for Phase 4.0:NP5-751-CD, Daily RUC Committed or Decommitted Resources NP5-752-CD, Hourly RUC Committed or Decommitted Resources

  MIS Targeted for early May release

Closed 15053 The ability for DAM Operators to send free-form messages is not yet available

In its current state, if DAM or DRUC is delayed and a message needs to be sent, it is not being received by the QSE.

The workaround is that the DAM Operators will use the CM-VDI-NOTF for freeform messages until a solution is implemented.

MMS/MIS Under review

Page 21: Http://nodal.ercot.com 1 Market Trials DAM/RUC/SASM Weekly Update July 02, 2010

Summary of DAM/RUC/SASM market trials

Next week:

- Focus on quality will continue to supersede timelines (i.e., may re-run DAM/RUC late to get better solution)

- ERCOT continuing to address data issues

- In short-term continue to need COPs to reflect actual plans (to compare with zonal)

- More communication between ERCOT and MPs to address submission/data issues

- We will continue to contact QSE periodically to address zonal/nodal COP inconsistencies to assist QSEs in identifying mismatches.

http://nodal.ercot.com 21

Page 22: Http://nodal.ercot.com 1 Market Trials DAM/RUC/SASM Weekly Update July 02, 2010

LZ_South high price analysis OD 6/19

http://nodal.ercot.com 22

– There was a large bid (over 5000 MW) with a price at 500 $/MWh which became the marginal bid and set the price from hour 15-20.

– From Hour 15 to 18, only Energy only offers/bids at LZ_SOUTH can solve constraint LA_PAL_VCAVAZ1_1 under contingency SLA_LOM8.  This limited the energy clearing at LZ_SOUTH.

– From Hour 19 to 20, only Energy only offers/bids at LZ_SOUTH can solve constraint N_VICT_VICTOR1_1 under contingency SVICMAG9.  This limited the energy clearing at LZ_SOUTH  

Page 23: Http://nodal.ercot.com 1 Market Trials DAM/RUC/SASM Weekly Update July 02, 2010

http://nodal.ercot.com 23

FAQ

Data Center Location Internet IP WAN IP

Taylor66.128.17.12566.128.17.128

192.168.172.126192.168.172.128

Austin 66.128.16.125 192.168.175.115

• EWS Notification Delivery & Network Firewall Configuration

– EWS Notification deliveries are currently originating from the following ERCOT servers listed below. To meet system demand and scalability requirements, we will be adding additional servers to this mix. To prevent any service disruptions, as a result of addition of new servers, we recommend your network firewall rules be configured to allow traffic based on address range as opposed limiting them to specific IPs.

• Current IPs in Play:

Data Center Location Internet IP Range WAN IP Range

Taylor 66.128.17.0 - 255 192.168.172.0 - 255

Austin 66.128.16.0 - 255 192.168.175.0 - 255

• Recommended IP Ranges:

Page 24: Http://nodal.ercot.com 1 Market Trials DAM/RUC/SASM Weekly Update July 02, 2010

http://nodal.ercot.com 24

Q&A

Q&A / Open Forum

Page 25: Http://nodal.ercot.com 1 Market Trials DAM/RUC/SASM Weekly Update July 02, 2010

Appendix

Appendix– AS Info for the week– Pre- and post-DAM reports– Special Topics

http://nodal.ercot.com 25

Page 26: Http://nodal.ercot.com 1 Market Trials DAM/RUC/SASM Weekly Update July 02, 2010

http://nodal.ercot.com 26

Submission Overview for June 25

Page 27: Http://nodal.ercot.com 1 Market Trials DAM/RUC/SASM Weekly Update July 02, 2010

http://nodal.ercot.com 27

Submission Overview for June 28

Page 28: Http://nodal.ercot.com 1 Market Trials DAM/RUC/SASM Weekly Update July 02, 2010

http://nodal.ercot.com 28

Submission Overview for June 29

Page 29: Http://nodal.ercot.com 1 Market Trials DAM/RUC/SASM Weekly Update July 02, 2010

http://nodal.ercot.com 29

Submission Overview for June 30

Page 30: Http://nodal.ercot.com 1 Market Trials DAM/RUC/SASM Weekly Update July 02, 2010

http://nodal.ercot.com 30

Submission Overview for July 1

Page 31: Http://nodal.ercot.com 1 Market Trials DAM/RUC/SASM Weekly Update July 02, 2010

Other

Note:• All transactions will be supported.

• Trade submission and confirmation (Energy, Capacity and AS Trades) may be exercised at this time.

• DAM notifications will be active.

• Phase 2 Validation process will be active and supported.

• QSE transactions that do not follow the guidelines are subject to cancellation at ERCOT’s discretion.

• ERCOT may run DAM on non-supported days. No QSE participation is requested, and ERCOT staff will not be available to answer questions regarding the outputs of these non-supported processes.

• CRR information from the market trials auction will be integrated into the market system. CRR Offers (by NOIEs) must contain CRR IDs from this auction in order to be valid.

http://nodal.ercot.com 31

Page 32: Http://nodal.ercot.com 1 Market Trials DAM/RUC/SASM Weekly Update July 02, 2010

Supplemental Materials

Slide 32

Reference and Description Location Version

External Interfaces Specification

http://nodal.ercot.com/readiness/sandbox/index.html 1.19

Explanation of Market Submission Items

http://nodal.ercot.com/readiness/markettrials/connectivity/index.html

0.26

Market Manager User Guide http://nodal.ercot.com/readiness/markettrials/connectivity/index.html

0.06

MMS Requirements http://nodal.ercot.com/docs/pd/mms/index.html#req Various

Market Connectivity Handbook http://nodal.ercot.com/readiness/markettrials/connectivity/index.html

0.97

DAM/RUC Known Issues List http://nodal.ercot.com/readiness/markettrials/dam/index.html

N/A

Web Services XSDs http://nodal.ercot.com/readiness/sandbox/index.html 1.3.19

Sample Reports, Extracts, and DDLs

http://nodal.ercot.com/readiness/reports/index.html Various

DAM ERCOT Operating Procedures

http://nodal.ercot.com/readiness/markettrials/dam/index.html

2.0

DRUC/WRUC ERCOT Operating Procedures

http://nodal.ercot.com/readiness/markettrials/dam/index.html

0.2

http://nodal.ercot.com 32

Page 33: Http://nodal.ercot.com 1 Market Trials DAM/RUC/SASM Weekly Update July 02, 2010

http://nodal.ercot.com 33

Report Postings

Posted by 6 am:

• Ancillary Services (AS) Plan

• Load Ratio Shares (these will be static based on Zonal production data as of October 16, 2009) *

• AS Obligations *

• Wind Generation Resource Power Potential (WGRPP) forecast * and Aggregated WGRPP forecast

• List of all Settlement Points and the mapping to Electrical Buses

• Load forecasts for ERCOT system, Weather Zones and Load Zones

• Load forecast distribution factors

• Distribution Loss Factors and forecasted Transmission Loss Factors

• Weather assumptions

 

* Denotes MIS Certified reports

Page 34: Http://nodal.ercot.com 1 Market Trials DAM/RUC/SASM Weekly Update July 02, 2010

http://nodal.ercot.com 34

Report Postings

Posted after each DAM:

• Awards (AS Offers, Energy Offers, DAM Energy-Only Offers, DAM Energy Bids, CRR Offers, and PTP Obligation Bids) *

• DAM Clearing Price for Ancillary Services (MCPC)

• Day-Ahead hourly Settlement Point Prices (SPPs)

• Day-Ahead hourly Locational Marginal Prices (LMPs)

• Shadow Prices

• Quantity of AS Offers

• Aggregated AS Offer Curve

• Total quantity of energy (in MWh) bought and sold in DAM

See DAM Handbook for a list of all DAM/RUC/SASM reports available starting in Phase 4.0 - http://nodal.ercot.com/readiness/markettrials/dam/index.html. See MIS Handbook for a comprehensive list of reports available - http://nodal.ercot.com/readiness/markettrials/mis/index.html.

* Denotes MIS Certified reports

Page 35: Http://nodal.ercot.com 1 Market Trials DAM/RUC/SASM Weekly Update July 02, 2010

Special Topics

Phase 2 Validation reports and process• Phase 2 validation re-evaluates all submitted transactions at 7 am in

the day-ahead with updated information, such as AS Obligation, CRR ownership, credit limits, etc.

• If there is a validation error, ERCOT will cancel the transaction• We send a notification that a Phase 2 report is available for a particular

transactions type, and notification containing the cancellation for the transaction.

• You can query for the Phase 2 report via web service or on the Reports page of the Market Manager in order to view the reason for the cancellation.

• Correct and resubmit prior to 10 am.• Note that submissions are locked out during the Phase 2 process,

which is currently taking about 10 minutes to complete.

http://nodal.ercot.com 35

Page 36: Http://nodal.ercot.com 1 Market Trials DAM/RUC/SASM Weekly Update July 02, 2010

Special Topics

Day-Ahead Self Commitment

DAM clearing engine treats your TPO differently if you submit Startup and Minimum Energy (SU/ME) costs as $0 vs. NULL

• If you submit with SU/ME as $0, DAM engine treats this as a normal offer where the QSE is not requesting SU/ME to be covered. HSL/LSL constraints will be respected. Also, if you are selected for an online Ancillary Service, you will also be awarded at least LSL on your offer curve.

• If you submit with SU/ME as NULL, DAM engine is signaled to ignore the HSL/LSL constraints for the resource. In this scenario, the offer curve submitted will start at 0 MW and go to the max MW quantity desired – again, DAM will ignore LSL/HSL constraints. If the offer curve submitted doesn’t start at 0 MW, it will be extended to 0 MW by DAM. If the resource is selected for Ancillary Services, no requirement to also award TPO at LSL (since no LSL constraint honored in this case).

http://nodal.ercot.com 36

Page 37: Http://nodal.ercot.com 1 Market Trials DAM/RUC/SASM Weekly Update July 02, 2010

Special Topics

Day-Ahead Self Commitment

The purpose of the NULL: It allows a QSE to use part of a Resource to serve its own load, and then offer in the rest to the DAM and enable the offer to be co-optimized with its AS Offer.

Example:

A Resource has 100 MW LSL and 400 MW HSL, and the QSE has already committed 300 MW of the Resource through some other mechanism. The QSE wishes to offer the remaining 100 MW, which would otherwise be ignored due to the 100 MW LSL.

Then going into real-time, so QSEs will need to update their TPO to cover the full capacity of the resource, from LSL to HSL, rather than from 0 MW. TPOs for real-time should always cover the entire capacity of the resource to avoid the proxy curve creation. To do the TPO update if the resource is awarded in the DAM, the QSE must provide a reason code, which is DSCM.

This functionality came about due to TPTF subgroup on the issue. It has not yet been added to the protocols but will during our protocol traceability/cleanup effort.

http://nodal.ercot.com 37

Page 38: Http://nodal.ercot.com 1 Market Trials DAM/RUC/SASM Weekly Update July 02, 2010

Special Topics

Bid/Offer efficiencies

• ERCOT has identified efficiencies in Bid/Offers submission with regard to the format of submission

• This applies to all transaction that use a Bid ID or an Offer ID (Energy Only Offers, Energy Only Bids, PTP Obligation Bids, and CRR Offers)

• Preference is for QSEs to submit the same Bid/Offer ID for each hour in the submission, versus submitting a different Bid/Offer ID for every hour. The market system treats the submission the exact same way, regardless of which format is used

• Using the preferred format will optimize DAM system performance

• For xml examples detailing this issue, please view a document that will be posted along with this presentation on the calendar page at http://www.ercot.com/calendar/2010/04/20100409-MT

• This was discussed at NATF 4/6, we send an email to the nodal technical contacts that we have on file for all QSEs, and we will add it to the External Interfaces Specification

http://nodal.ercot.com 38

Page 39: Http://nodal.ercot.com 1 Market Trials DAM/RUC/SASM Weekly Update July 02, 2010

Special Topics

JOUs and COP consistencies

• In DAM, if the different owners of the jointly-owned unit have submitted conflicting COP statuses for the current day, online statuses will overwrite offline statuses when DAM is determining the initial condition of the unit (i.e., is the unit online or offline at the start of the next operating day).

• In RUC, if the different owners have conflicting COP statuses for the next operating day:

– If any owner has OUT status for any hour then the unit is considered OUT.

– If all owners have submitted a COP, and at least one of them has an online status in a particular hour then the resource status for the unit is online (unless any owner has OUT)

http://nodal.ercot.com 39

Page 40: Http://nodal.ercot.com 1 Market Trials DAM/RUC/SASM Weekly Update July 02, 2010

Special Topic – Jointly Owned Units

JOUs are modeled as a single physical unit – DAM uses the separate logical resources when evaluating energy and ancillary services, but Network

Security Monitoring (NSM), which is a sub-process of DAM, must consider the physical unit. – http://nodal.ercot.com/docs/pd/ida/wp/sgrm/

IDA041_White_Paper_for_Split_Generation_Resource_Modeling_v1.doc

JOUs offering into DAM– Owners offer their share into the DAM separately, but the physical unit must be committed together– All owners have to offer in the unit (energy or AS) to the DAM or else it cannot be committed to any

owner (one exception for a self-commitment scenario described below). DAM must make a commitment decision about the physical unit, which it cannot do without offers from all the owners.

– Self-commitment examples (assume three owners) – remember that self-committing by submitting Startup and Minimum Energy Costs as ‘NULL’ (leaving them out of the submission altogether rather than submitting zeroes) signals the DAM software that it doesn’t need to make a commitment decision and to ignore resource constraints. • If two owners self-commit (startup/minimum energy costs are NULL) and the other submits

nothing, the unit can be awarded without making a commitment decision.• If one owner self-commits, another submits a TPO with startup/minimum energy costs, and the

third submits nothing, the unit cannot be awarded• If one owner self-commits, and the other two submit TPOs with startup/minimum energy costs,

the unit can be awarded after making a commitment decision based on the resource constraints and the submitted startup/minimum energy costs.

– Note that if self-committed, do not submit an OFFNS offer. That offer negates the self-commitment and the DAM software will not consider it as a self-committed resource (since the QSE is requesting ERCOT to evaluate the unit offline)

http://nodal.ercot.com 40