Case Assignment and Scheduling Record Page 1 of 1
Section 1 - Office of Commission Clerk
Docket No. 130201-EI Date Docketed: 07/26/2013 Title: Commission review of numeric conservation goals (Tampa Electric Company).
Company: Tampa Electric Company
Official Filing Date: -----Last Day to Suspend:
Referred to:
Expiration:
AFD AIT APA CAO ("()" indicates OPR) I X
Section 2 - OPR Completes and returns to CLK in 10 workdays.
CLK DET ECO (ENG) GCL X X X
Time Schedule Program Module (5 WARNING: THIS SCHEDULE IS AN INTERNAL PLANNING DOCUMENT
IT IS TENTATIVE AND SUBJECT TO REVISION.
Staff Assignments FOR UPDATES CONTACT THE RECORDS SECTION: (850) 413-6170
IDM TEL X
Due Dates
OPR Staff p Ellis, P Buys [I] Current CASR revision level R Graves c Lewis T Matthews 1. Testimonv & Exhibits - Staff
2. Discovery Actions Complete 3. Revised CASR Due/Close Docket 4. 5. 6. 7.
Staff Counsel L Tan, K Corbari 8. C Murphy 9.
10. OCRs (IDM) W Clemence, D Dowds 11.
D Marr 12. (AFD) M ci , 13. (ECO) S Brown_ L c.; 1 hPr~ 14.
J Harlow 1 1;nnn 15. B McNultv A Orteaa 16 . J Wu 17.
18. 19. 20. 21. 22. 23. 24. 25. 26. 27. 28. 29.
Recommended assiqnments for hearinq 30. and/or decidinq this case: 31.
32. Full Commission ...X.. Commission Panel - 33 . Hearing Examiner Staff 34. - - 35. Date filed with CLK: 07125/2014 36.
37. Initials OPR 38.
Staff Counsel 39. 40.
Sect1on 3 - Cha1rman Completes Ass1gnments are as follows:
- Heannq Off. ( ) 1cer s Prehearina Officer Commissioners Hrg Staff
Exam ALL j GH I ED I BI I BW I PT
X I J I I I Where panels are ass1gned the sen1or Comm1ss1oner is Panel Chairman : the identical panel decides the case. Where one Commissioner, a Hearing Examiner or a Staff Member is assigned the full Commission decides the case.
PSC/CLK015-C (Rev. 07/12) * COMPLETED EVENTS
Commissioners
GH 1 ED 1 BI 1 BW -, PT l I X I I
Approved: Date:
Previous Current
SAME 05/19/2014 SAME 07/07/2014
12/01/2014 01/16/2015
ADM
FPSC Commission ClerkCORRESPONDENCEFEB 06, 2015DOCUMENT NO. 00807-15
Case Assignment and Scheduling Record Page 1 of 1
Section 1 - Office of Commission Clerk
Docket No. 130201-EI Date Docketed: 07/26/2013 Title: Commission review of numeric conservation goals (Tampa Electric Company).
Company: Tampa Electric Company
Official Filing Date: -----Last Day to Suspend:
Referred to: ("()" indicates OPR)
Expiration:
AFD AIT APA X
CAO CLK DET ECO (ENG) GCL X X X
Section 2 - OPR Completes and returns to CLK in 10 workdays. Time Schedule Program Module C5 WARNING: THIS SCHEDULE IS AN INTERNAL PLANNING DOCUMENT
IT IS TENTATIVE AND SUBJECT TO REVISION. Staff Assignments FOR UPDATES CONTACT THE RECORDS SECTION:(850) 413-6770
IDM TEL X
Due Dates
OPR Staff p Ell is, R Graves ~ Current CASR revision level c Lewic;
1. Testimony & Exhibits - Staff 2. Discovery Actions Comolete 3. Hearina (7/21 - 23/14) (7 /30 - 31/14) 4. Transcript of Hearinq Due 5. Briefs Due 6. Staff Recommendation 7. Agenda
Staff Counsel L Tan 8. Standard Order 9. Revised CASR Due/Close Docket
OCRs (!OM) W Clemence D Dowds 10. D Marr 11.
(AFD) M Cicchetti 12. (ECO) S Brown 1 H;:~rlnw 13.
J Linao B McNultv J Wu 14. 15. 16. 17. 18. 19. 20. 21. 22. 23. 24. 25. 26. 27. 28. 29.
Recommended assiqnments for hearinq 30. and/or decidinq this case: 31.
32. Full Commission _x_ Commission Panel 33. -Hearing Examiner Staff 34. - - 35. Date filed with CLK: 07/25/2014 36.
37. Initials OPR 38.
Staff Counsel 39. 40.
Sect1on 3 - Cha1rman Completes Ass1gnments are as follows:
- Hear1nq Off" ( ) 1cer s Prehearinq Officer Commissioners Hrg Staff
Exam ALL I GH I ED I BI I BL I BW
X I I I I I Where panels are ass1gned the sen1or Comm1ss1oner is Panel Chairman: the identical panel decides the case. Where one Commissioner, a Hearing Examiner or a Staff Member is assigned the full Commission decides the case.
PSC/CLK015-C (Rev. 07/12) ~ COMPLETED EVENTS
Commissioners
GH I ED I BI I BL I BW 1 1 X 1 1
Approved: Date:
Previous Current
SAME 05/19/2014 SAME 07/07/2014 SAME 07/21/2014 SAME 08/08/2014
09/08/2014 09/30/2014 09/22/2014 11/13/2014 10/02/2014 11/25/2014 10/22/2014 12/15/2014 12/01/2014 12/31/2014
ADM
Case Assignment and Scheduli ng Record Page 1 of 1
Section 1 - Office of Commission Clerk
Docket No.130201-EI Date Docketed: 07/26/2013 Title: Commission review of numeric conservation goals (Tampa Electric Company).
Company: Tampa Electric Company
Official Filing Date: ----Last Day to Suspend:
Referred to: ("()" indicates OPR)
Expiration:
AFD AIT APA CAO X I
~e~~jon 2 - OPR Completes and returns to CLK in 10 workdays.
CLK DET ECO (ENG) CCL X X X
Time Schedule Program Module C5 WARNING: THIS SCHEDULE IS AN INTERNAL PLANNING DOCUMENT
IT IS TENTATIVE AND SUBJECT TO REVISION.
St aff A~~ignmeQ~s FOR UPDATES CONTACT THE RECORDS SECTION:(8SO) 413- 6770
ID'1 TEL X
Due Dates
OPR Staff P Ell i s , R Graves [iJ Current CASR revision level C Lewis
1. Testimony & Exhibits - Staff 2. Discovery Actions Complete 3. Hearing (7 /21 - 23/14) (7 /30 - 31/14) 4. Transcript of Hearing Due 5. Transcript of Heari ng Due (7 /30 - 31/14) 6. Briefs Due 7. Staff Recommendation
Staff !:;oun~el L Tan 8. Agenda 9. Standard Order
OCRs (!OM) W Clemence. 0 Dowds 10 . Revised CASR Due/Close Docket D Marr 11.
(AFD) M Cicchetti 12. (ECO) S Brown J Harlow 13.
J Linao . B McNultv J Wu 14. 15. 16. 17. 18. 19. 20 . 21. 22. 23. 24. 25. 26. 27 . 28. 29.
Recommended assignments for hearing 30. and/or deciding this case: 31.
32. Full Commission ..X... Commission Panel - 33. Hearing Exami ner Staff 34 . - - 35. Date filed with CLK: 07/11/2014 36.
37 . Initials OPR 38.
Staff Counsel 39 . 40.
Sect1on 3 - Cha1rman Compl etes Ass1gnments are as follows:
- Hear1ng 0 1cer s ff" ( ) Prehearin Officer Commissioners Hrg Staff Commissioners
Exam ALL I GH I ED I BI I BL I BW GH
X I I I I I Where panel s are ass1gned t he sen1or Comm1 ss1oner is Panel Chairman: t he identical panel decides the case. Approved: Where one Commissioner , a Hearing Examiner or a Staff Member is assigned t he full Commission decides the case.
PSC/CLK015-C (Rev. 07/12) ~ COMPLETED EVENTS
Date:
Previous Current
SAME 05/19/2014 SAME 07/07/2014 SAME 07/21/2014 SAME 08/08/2014 SAME 08/15/2014 SAME 09/08/2014
09/25/2014 09/22/2014 10/09/2014 10/02/2014 10/29/2014 10/22/2014
SAME 12/01/2014
ADM
Case Assignment and Schedul i ng Record Page 1 of 1
Section 1 - Office of Commission Clerk
Docket No. 130201-EI Date Docketed: 07/26/2013 Title: Commission review of numeric conservation goals (Tampa Electric Company).
Company: Tampa Electric Company
Official Fili ng Date: ___ _ Expiration: Last Day to Suspend:
Referred to: AFD AIT APA CAO CLK DET ECO (ENG) CCL IDM TEL (" ()" indicates OPR) X I X X I X X
Section 2 - OPR Completes and returns to CLK in 10 workdays. Time Schedule Program Module C5 WARNING: THIS SCHEDULE IS AN INTERNAL PLANNING DOCUMENT
IT IS TENTATIVE AND SUBJECT TO REVISION.
Staff A~~ignments FOR UPDATES CONTACT THE RECORDS SECTION:(850) 413-6110
Due Dates
OPR Staff P Ellis, R Graves [[] Current CASR revision level C Lewis
1. Testimony & Exhibits - Staff 2. Prehearinq 3. Transcript of Prehearing Due 4. Prehearing Order 5. Discovery Actions Complete 6. Hearing (7/21 - 23/14) (7/30 - 31/14) 7. Transcript of Hearing Due
SYtLCounsel L Tan 8. Transcript of Hearing Due (7 /30 - 31/14) 9. Briefs Due
OCRs (IOM) W Clemence. D Dowds 10. Staff •'ltion D Marr 11. Agenda
(AFD) M Cicchetti 12. Standard Order CECO) S Brown J Harlow 13. Revised CASR Due/Close Docket
J Linao B McNultv J Wu 14. 15. 16. 17. 18. 19. 20. 21. 22. 23. 24. 25. 26. 27. 28. 29.
Recommended assignments for hearing 30. and/or deciding this case: 31.
32. Full Commission 1._Commission Panel - 33. Hearing Exami ner Staff 34. - - 35. Date filed with CLK: 06/16/2014 36.
37. Initial s OPR 38.
Staff Counsel 39. 40.
Sect1on 3 - Cha1rman Completes Ass1gnments are as follows:
- Heanng 0 1cer s ff. ( ) Prehearin Officer
Commissioners Hrg Staff Commissioners Exam
ALL I GH I ED I BI I BL I BW GH X I I I I I
Where panels are ass1gned the sen1or Comm1sS10ner is Panel Chairman: the identical panel decides the case. Approved: Where one Commissioner, a Hearing Examiner or a Staff Member is assigned the full Commission decides the case.
PSC/CLK015-C (Rev . 07/12) ~ COMPLETED EVENTS
Date:
Previous Current
SAME 05/ 19/ 2014 SAME 06/ 26/ 2014 SAME 07/ 03/ 2014 SAME 07/ 07/ 2014 SAME 07/ 07/ 2014 SAME 07/ 21/2014 SAME 08/ 08/ 2014 SAME 08/ 15/ 2014 SAME 09/08/2014 SAME 09/25/2014
10/07/2014 10/09/2014 10/27/2014 10/ 29/2014
SAME 12/01/ 2014
ADM
Case Assignment and Scheduling Record Page 1 of 1
Section 1 - Office of Commission Clerk
Docket No. 130201-EI Date Docketed: 07/ 26/2013 Title: Commission review of numeric conservation goals (Tampa Elect r ic Company).
Company: Tampa Electric Company
Official Filing Date: - ---Last Day to Suspend:
Referred to: ("()" indi cates OPR)
Expi r ation:
AFD AIT APA X
CAO CLK OET ECO (ENG) CCL X X I X
Section 2 - OPR Completes and returns to CLK in 10 workdays. Time Schedule Program Module C5 WARNING: THIS SCHEDULE IS AN INTERNAL PLANNING DOCUMENT
IT IS TENTATIVE AND SUBJECT TO REVISION.
Staff Assignments FOR UPDATES CONTACT THE RECORDS SECTION:(BSO) 413- 6770
IDM TEL X
Due Dat es
OPR Staff C Lewis, P El l is ~ Current CASR revision level R Craw~s
1. Testimony & Exhi bits - Staff 2. Testimony & Exhibits - Intervenor 3. Testimony & Exhibits - Rebuttal 4. Preheari ng Stat ements 5. Preheari ng 6 . Transcri pt of Preheari ng Due 7. Prehearing Order
S_taff Counsel L Tan 8. Discovery Actions Cor11>lete 9. Hearing (7/21 - 23/14) (7/30 - 31/14)
OCRs (!OM) W ClPmPnr P D Dowds 10. Transcrint of Hearina OuP D Marr 11. Transcript of Hearing Due (7/30 - 31/14)
(AFD) M Cicchetti 12. Briefs Due CECO) S Brown 1 Har l ow 13 . Staff R, •n=1tion
J Linao B McNultv J Wu 14 . Aaenda 15. Standard Or der 16. Revised CASR Due/Close Docket 17. 18. 19. 20. 21. 22. 23. 24. 25. 26. 27. 28. 29.
Recommended assignments for hearing 30. and/or deci di ng this case: 31.
32. Full Commissi on _x_commissi on Panel - 33. Heari ng Exami ner Staff 34. - - 35. Date filed with CLK: 05/06/2014 36.
37. Initials OPR 38.
Staff Counsel 39. 40 .
Sect1on 3 - Cha1rman Completes Ass1gnments are as follows:
- H eanng 1cer s Off" ( ) p h re ear1 ng Off" 1cer Commissioners Hrg Staff
Exam ALL I GH I ED I BI I Bl I BW
X I I I I I Where panel s are ass1 gned t he sen1or Comm1ss1oner i s Panel Chai rman: t he i dentical panel decides the case. where one Commissioner , a Heari ng Exami ner or a Staff Member is assi gned t he full Commission decides t he case .
PSC/CLK015-C (Rev. 07/12) * COMPLETED EVENTS
Commissioners
GH I ED I BI I Bl I BW I I X I I
Approved: Date:
Previous Current
SAME OS/19/2014 OS/ OS/2014 OS/19/2014 06/02/2014 06/ 10/2014
SAME 06/10/2014 SAME 06/26/2014 SAME 07/03/2014 SAME 07/07/2014 SAME 07/07/2014 SAME 07/21/2014 SAME 08/08/2014 SAME 08/ 15/2014 SAME 09/08/2014 SAME 09/25/2014 SAME 10/07/2014 SAME 10/27/2014 SAME 12/01/2014
ADM
Case Assignment and Scheduling Record Page 1 of 1
Section 1 - Office of Commission Clerk
Docket No. 130201-EI Date Docketed: 07/ 26/ 2013 Title: Commission review of numeric conservation goals (Tampa Electric Company).
Company: Tampa Electric Company
Official Filing Date: ___ _ Expiration: Last Day to Suspend: Referred to: AFD AIT APA CAO CLK DET ECO (ENG) GCL IDM TEL ("()" indicates OPR) X X X X X
Section 2 - OPR Completes and returns to CLK in 10 workdays. Time Schedule Program Module C5 WARNING: THIS SCHEDULE IS AN INTERNAL PLANNING DOCUMENT
IT IS TENTATIVE AND SUBJECT TO REVISION.
Staff Assignments FOR UPDATES CONTACT THE RECORDS SECTION:(BSO) 413-6770
Due Dates
OPR Staff c Lewis , p Ell is [}] Current CASR revision level R Graves
1. Testimony & Exhibits - Intervenor 2. Testimony & Exhibits - Staff 3. Testimony & Exhibits - Rebuttal 4. Prehearinq Statements 5. Prehearing 6. Transcript of Prehearing Due 7. Prehearing Order
Staff Counsel L Tan 8. Discovery Actions Complete 9. Hearinq (7/21 - 23/14) (7/30 - 31/14)
OCRs (IDM) W Clt>mPnl'P D Onwd.;; 10. iot of Hearina Due D Marr 11. Transcript of Hearing Due (7/30 - 31/14)
(AFD) M Cicchetti 12. Briefs Due (ECO) S Brown J Harlow 13. Staff la1'ion
1 l inen B MrNultv 1 Wu 14 . Act>nda 15. Order 16. Revised CASR Due/Close Docket 17. 18. 19. 20. 21. 22 . 23. 24. 25. 26. 27. 28. 29.
Recommended assiqnments for hearinq 30. and/or decidinq this case: 31.
32. Full Commission ~Commission Panel - 33. Hearing Examiner Staff 34. - - 35. Date filed with CLK: 03/05/2014 36.
37. Initials OPR 38.
Staff Counsel 39. 40.
Sect1on 3 - Cha1rman Completes Ass1gnments are as follows:
- Heannq 1cer s Off' ( ) Peh r ear1nq Off' 1cer
Commissioners Hrg Staff Exam
ALL I GH I ED I BI I BL I BW X I I I I I
Where panel s are ass1gned the sen1or Comm1ss1oner is Panel Chairman: the identical panel decides the case. Where one Commissioner, a Hearing Exami ner or a Staff Member is assigned the full Commission decides the case.
PSC/CLK015-C (Rev. 07/12) * COMPLETED EVENTS
Commissioners
GH I ED I BI I BL I BW I I X I I
Approved: Date:
Previous Current
SAME 05/ 05/ 2014 SAME 05/ 19/ 2014 SAME 06/ 02/ 2014 SAME 06/10/2014 SAME 06/26/2014 SAME 07/03/2014 SAME 07/07/2014 SAME 07/07/2014 SAME 07/ 21/2014 SAME 08/ 08/ 2014 SAME 08/ 15/ 2014 SAME 09/08/2014 SAME 09/25/2014 SAME 10/07/2014 SAME 10/27/2014 SAME 12/01/2014
ADM
Case Assignment and Scheduling Record Page 1 of 1
Section 1 - Office of Commission Clerk
Docket No.130201-EI Date Docketed: 07/26/2013 Title: Commission review of numeric conservation goals (Tampa Electric Company).
Company: Tampa Electric Company
Official Filing Date: Expiration: Last Day to Suspend:
Referred to: AFD AIT APA CAO CLK DET ECO (ENG) GCL !OM TEL (" ()" indicates OPR) X I X X X X
Section 2 - OPR Completes and returns to CLK in 10 workdays. Time Schedule Program Module C5 WARNING: THIS SCHEDULE IS AN INTERNAL PLANNING DOCUMENT
IT IS TENTATIVE AND SUBJECT TO REVISION.
Staff Assignments FOR UPDATES CONTACT THE RECORDS SECTION: (850) 413-6770
Due Dates OPR Staff C Lewis, P Ellis [!] Current CASR revision level
T Matthews 1. Testimony & Exhibits - Company 2. Testimony & Exhibits - Intervenor 3. Testimony & Exhibits - Staff 4. Testimony & Exhibits - Rebuttal 5. Prehearing Statements 6. Prehearing 7. Transcript of Prehearing Due
Staff Counsel L Tan 8. Prehearing Order 9. Discovery Actions Complete
OCRs (!OM) W Clemence, D Dowds 10. Hearina (7/21 - 23/14) (7/30 - 31/14) D Marr 11. Transcript of Hearing Due
(AFD) M Cicchetti 12. Transcript of Hearing Due (7/30 - 31/14) (ECO) S Brown J Harlow 13. Bd~fs Du~
J Linao 14. Staff at ion 15. Aaenda 16. Ord~r 17. R~vis~d CASR Du~/Clos~ Dock~t 18. 19. 20. 21. 22. 23. 24. 25. 26. 27. 28. 29.
Recommended assiqnments for hearinq 30. and/or decidinq this case: 31.
32. Full Commission _K_Commission Panel - 33. Hearing Examiner Staff 34. - - 35. Date filed with CLK: 03/05/2014 36.
37. Initials OPR 38.
Staff Counsel 39. 40.
Sect1on 3 - Cha1rman Completes Ass1gnments are as follows:
- Hear1ng 0 1cer s ff" ( ) Prehearin Officer Commissioners Hrg Staff Commissioners
Exam ALL I GH I ED I BI I BL I BW GH
X I I I I I Where panels are ass1gned the sen1or Comm1Ss1oner is Panel Chairman: the identical panel decides the case. Approved: Where one Commissioner, a Hearing Examiner or a Staff M.ember is assigned the full Commission decides the case.
PSC/CLK015-C (Rev. 07/12) * COMPLETED EVENTS
Date:
Previous Current
SAME 04/02/2014 SAME 05/05/2014 SAME 05/19/2014 SAME 06/02/2014 SAME 06/10/2014 SAME 06/26/2014 SAME 07/03/2014 SAME 07/07/2014 SAME 07/07/2014 SAME OU21/2014 SAME 08/08/2014 SAME 08/15/2014 SAME 09/08/2014 SAME 09/25/2014 SAME 10/07/2014 SAME 10/27/2014 SAME 12/01/2014
ADM
Case Assignment and Scheduli ng Record Page 1 ot 1
Section 1 - Office of Commission Clerk
Docket No. 130201-EI Date Docketed: 07/26/2013 Title: Commission review of numeric conservation goals (Tampa Electric Company).
Company: Tampa Electric Company
Official Filing Date: Expiration: Last Day to Suspend:
Referred to: AFD AIT APA CAO CLK DET ECO (ENG) GCL IDM TEL ("()" indicates OPR) X I X X X X
Section 2 - OPR Completes and returns to CLK in 10 workdays. Time Schedule Program Module C5 WARNING: THIS SCHEDULE IS AN INTERNAL PLANNING DOCUMENT
IT IS TENTATIVE AND SUBJEa TO REVISION.
Staff Assignments FOR UPDATES CONTAa THE RECORDS SECTION:(850) 413-6770
Due Dates OPR Staff C Lewis, P Ell is [QJ Current CASR revision level Previous
T Matthews 1. Testimony & Exhibits - Company NONE 2. Testimony & Exhibits - Intervenor NONE 3. Testimony & Exhibits - Staff NONE 4. Testimony & Exhibits - Rebuttal NONE 5. Prehearing Statements NONE 6 . Prehearing NONE 7. Transcript of Prehearing Due NONE
Staff Counsel L Tan 8. Prehearing Order NONE 9. Discovery Actions Complete NONE
OCRs (IOM) W Clemence D Dowds 10. Hearina (07 /21 - 2S/14) NONE D Marr 11. Transcript of Hearing Due NONE
(AFD) M Cicchetti 12. Briefs Due NONE (ECO) S Brown J Harlow 13 . Staff n. tdation NONE
J Linao 14. Aaenda NONE 15. Standard Order NONE 16. RPvi d CASR Dui> /Cl oc;!> Dorki>t NONE 17. 18. 19. 20. 21. 22. 23. 24. 25. 26. 27. 28. 29.
Recommended assignments for hearing 30. and/or deciding this case: 31.
32. Full Commission ...X... Conrni ss ion Panel - 33. Hearing Examiner Staff 34. - - 35. Date filed with CLK: 08/29L2013 36.
37. Initials OPR 38.
Staff Counsel 39. 40.
Sect10n 3 - Cha1rman Completes Ass1gnments are as follows:
- Heanng 0 1cer s ff' ( ) Prehear1ng 0 ff icer Conrnissioners Hrg Staff Commiss i oners ADM
Exam ALL I GH I ED I BI I BL I BW
X I I I I I Where panels are ass1gned the sen1or CommlSS10ner is Panel Chairman: the identical panel decides the case. Where one Conrnissioner , a Hearing Examiner or a Staff Member is assigned the full Conrnission decides the case.
PSC/CLK015-C (Rev. 07/12) * COMPLETED EVENTS
GH I ED I BI I BL I BW I I X I I
Approved: Date: 08/29/2013 ,
Current
04/ 02/2014 05/ 05/2014 05/19/2014 06/02/2014 06/10/ 2014 06/26/2014 07/ 03/ 2014 07/07/2014 07/ 07/ 2014 07/21/2014 08/08/2014 09/08/2014 09/25/2014 10/07/2014 10/27/2014 12/01/2014
Case Assignment and Scheduling Record Page 1 of 1
Section 1 - Office of Commission Clerk
Docket No. 130201-EI Date Docketed: 07/ 26/ 2013 Title: Commission review of numeric conservation goals (Tampa Electric Company).
Company: Tampa Electric Company
Official Filing Date: ---------Last Day to Suspend:
Referred to: (" 0 " indicates OPR)
Expiration:
AFD AIT APA CAO X I
Section 2 - OPR Completes and returns to CLK in 10 workdays.
CLK OET ECO (ENG) GCL X X X
Time Schedule Program MQdule C5 WARNING: THIS SCHEDULE IS AN INTERNAL PLANNING DOCUMENT
IT IS TENTATIVE AND SUBJEa TO REVISION.
Staff Assignments FOR UPDATES CONTAa THE RECORDS SEaiON:(BSO) 413-6770
IDM TEL X
Due Dates
OPR Stat..f c Lewis, p Ell is [QJ Current CASR revision level T Matthews
1. Testimony & Exhibits - Company 2. Testimony & Exhibits - Intervenor 3. Testimony & Exhibits - Staff 4. Testimony & Exhibits - Rebuttal 5. Prehe.aring Statements 6. Prehearing 7. Transcript of Prehearing Due
Staff Counsel L Tan 8. Prehearing Order 9. Discovery Actions Complete
OCRs (!OM) W C1 Pnw>nn• 0 Dowdc; 10. HPari na (07/21 - 2'i/14) 0 Marr 11. Transcript of Heari ng Due
(AFO) M Cicchetti 12. Briefs Due (ECO) S Brown 13. Staff ion
14. AaPnda 15.
Case Assignment and Scheduling Record Page 1 of 1
Section 1 - Office of Commission Clerk
Docket No.130201-EI Date Docketed: 07/26/2013 Title: Commission review of numeric conservation goals (Tan.,a Electric Company).
Company: Tan.,a Electric Company
Official Filing Date: Expiration: Last Day to Suspend:
Referred to: AFD AIT APA CAO CLK DET ECO (ENG) GCL IDM TEL ("0" indicates OPR) r-~x;,_'TI....;..;:::.;.-.,r-;,;;,:.,;,_,-...;:.;;;;_,..-=:::.:.:....""T--=~--.-=:x:;::-""T~:::x~,l-=:x:;::-"'T'--=:;::x:..:.....-r-....:...::~
Section 2 - OPR Completes and returns to CLK in 10 workdays. Time Schedule Pr29ram Module C5 WARNING: THIS SOIEOOLE IS AN INTERNAL PLANNING DOCUMENT
IT IS TENTATIVE AND SUBJECT TO REVISION.
Staff Assignments FOR UPDAT£S CONTACT THE RECORDS SECTION:(BSO) 413-6770
Due Dates
OPR Staff c Lewis, P Ell is [QJ Current CASR revision level 1. Testimonv & Exhibits - Comoanv 2. Testimony & Exhibits - Intervenor 3. Testimony & Exhibits - Staff 4. Testimony & Exhibits - Rebuttal 5. Prehearing Statements 6. Prehearing 7. Transcript of Prehearing Due
Staff Coun1~l L Tan 8. Prehearing Order 9. Discovery Actions Comolete
OCRs (IDM) W 0 ...,...nr" D Dowds_ 10. Jfearina f07121 - )r;/14) D Marr 11. Transcript of Hearing Due
(AFD) M Cicchetti 12. Briefs Due (ECO) c; R....,..,. 13. Staff 1n"
14. Aa,.nda 15. o .. d .... 16. 17. 18. 19. 20. 21. 22. 23. 24. 25. 26. 27. 28. 29.
Recommended assignments for hearing 30. and/or deciding this case: 31.
32. Full Commission ..!...Commission Panel - 33. Hearing Examiner Staff 34. - - 35. Date filed with CLK: 08/29/2013 36.
37. Initials OPR 38.
Staff Counsel 39. 40.
Sect1on 3 - Cha1rman Completes Ass1gnments are as follows:
- Hearing Officer(s) P h Off' re ear1ng 1cer
Commissioners Hrg Staff Commissioners Exam
ALL I BI IEDI Qt IBLI BW BI I ED I Qt I BL I BW
X I I I I I X I I I I Where panels are ass1gned the sen1or Comm1ss1oner is Panel Chairman: the identical panel decides the case. Approved:
Previous
NONE NONE NONE NONE
NONE
NONE NONE NONE NONE NONE NONE
NONE NONE NONE NONE
ADM
BI/TW Where one Commissioner, a Hearing Examiner or a Staff Member is assigned the full Commission decides the case.
Date: 08/29/2013
PSC/CLK015-C (Rev. 07/12) * COMPLETED EVENTS
Current
04/02/2014 05/05/2014 05/19/2014 06/02/2014 06/10/2014 06/26/2014 07/03/2014 07/07/2014 07/07/2014 07/21/2014 08/08/2014 09/08/2014 09/25 2014 10/07 2014 10/27 2014