US 14 Staging Business Involvement MeetingDecember 6, 2017 4 p.m. to 6 p.m.
Janesville, Wisconsin
I-39/90 Expansion Project
US 14 Project Update
• Convert roadway from rural to urban sectiono Curb & Gutter/Storm Sewero 10’ Multi-use patho 5’ sidewalko Bus Stop at Pontiaco Offset left turn lanes
US 14 Traffic Control Staging
• 2022 Construction• 3 Alternatives• Ryan Road Underpass Open• Ramp Closures (all alternatives)• Provide Inputo Comment Formso Emailo Comments Due by December 20, 2017
US 14 Traffic Control StagingAlternative #1 (US 14 Staging)
US 14 Traffic Control StagingAlternative #2 (US 14 Partial Closure)
US 14 Traffic Control StagingAlternative #3 (US 14 Staged Closure – Phase 1)
US 14 Traffic Control StagingAlternative #3 (US 14 Staged Closure – Phase 2)
US 14 Traffic Control StagingUS 14 Detour
US 14
Janesville Economic Development Department
Forward Janesville
Janesville Area Convention & Visitors Bureau
In This Together
Questions?www.i39-90.wi.gov
Facebook.com/WisconsinI3990Project
(608) 884-1234
Votes due by December 20, 2017