Upload
soniaramadhani
View
32
Download
3
Embed Size (px)
Citation preview
IMPORTANCE OF RISK ALLOCATION
FOR PPP INFRASTRUCTURE PROJECTS IN INDONESIA
Risk Evaluation for IIGF Guarantee
Armand Hermawan, Director of Finance IIGF
AGENDA
2. PPP Risk Category and Risk Matrices
3. Evaluation of Risks for IIGF Guarantee
1. Risks Assessment and Allocation in PPP Project
AGENDA
2. PPP Risk Category and Risk Matrices
3. Evaluation of Risks for IIGF Guarantee
1. Risks Assessment and Allocation in PPP Project
Risk Assessment and Allocation
4
Risk Identification
Quantitative Analysis
Risk ImpactQualitative Analysis
Risk Allocation
Enlist of all
Project Risks
Identify
consequence of
Risk
• Analyze potential
impact of Risk
• How risks will be
managed
• Analyze monetary
impact of Risk
• Risk adjusted
possible costs
• Share of risk
between parties
(RISK
ALLOCATION)
• Optimal risk
transfer
Risk Assessment and Allocation: Example
5
Risk Identification
Quantitative Analysis
Risk ImpactQualitative Analysis
Risk Allocation
Commissioning
– Delay in
service
provisioning
Failure to complete
or construct
adequately
• Cost and time
overruns
• Cost of maintaining
exiting
infrastructure while
wait for new
facilities
• Dependent on
extent of time
overruns
• Dependent on
probability of risk
occurring
• Allocate risk to
bidder; cap time
and price; use
experienced builder
• Ensure
construction
company provides
performance bonds
Risk Allocation: Principles
6
• Risk should be allocated to party that is relatively able in managing the risk (or having the least cost of absorbing such risk).
• An optimal risk allocation is to lower the risk premium and the project cost and hence it has positive impact to the project stakeholders
• Highly speculative and uncertain risks, should be shared between parties unless it is agreed (after negotiation)
Some straightforward examples: • Construction risk lies with private contractor• Regulation risk lies with government
What about other risks: Demand risk? Currency risk? Cost pass‐through in pricing and moral hazard?
Risk allocation depends on bargaining power But less risk less project distress
Consequences of “imbalance” Risk Allocation
7
• The Commercial Banks could not participate in the project financing, unless the risk allocation was changed
• Problems to project completion
Solutions to the risk allocation problems were developed base on extensive negotiations between all parties involved
AGENDA
2. PPP Risk Category and Risk Matrices
3. Evaluation of Risks for IIGF Guarantee
1. Risks Assessment and Allocation in PPP Project
PPP Risk Category – Generic Risk Group to Identify Risk Events
9
1. Site risk4. Financial
risk
2. Design, construction &commissioning
risk
3. Sponsor risk
5. Operating risk
8. Interface risk
6. Revenuerisk
7. Network connectivity
risk
9. Political Risk
10. Force majeure risk
11. Asset ownership risk
• Risk Category is used for generating identified risk events in each specific PPP project
• There are 11 groups of risks
PPP Risk Category (1)
10
1. Site risk 4. Financial risk2. Design, construction and commissioning risk
3. Sponsor risk
1)Land
Acquisition
risk,
2)Landsite
Unsuitability
risk
3)Environmental
Risk
1)Financial uncertainty risk: risk
that the financiers do
continue to provide funding
to the project;
2)Financial parameter risk like
macro economic assumption
3)Financial structure risk: risk
that the financial structure is
not sufficiently robust to
provide fair returns to debt
and equity over the life of the
project; and
4)Insurance risk: (i) that any
risks of which insurances
later become uninsurable or
(ii) of substantial increases in
the rates
1)Planning Risk, i.e., facilities on the
project site fails to comply with any
applicable laws relating planning
2)Design risk: the risk that the design
may not achieve the required output
specifications;
3)Completion risk (a) delayed so that
the delivery of the services cannot
commence at the scheduled
Commercial Operation Date (COD),
or (b) delayed, unless greater cost is
incurred to keep to Scheduled COD,
or (c) delayed due to variations;
4)Cost overrun risk
5)Commissioning risk: risk that the
commissioning date is (a) delayed
or (b) the result do not meet
specification
1)PC’s event of default
risk, risk that the PC has
defaulted its financial
obligation under the
project agreement; and
2)Subcontractor risk, risk
that the sub-contractors
do not perform as
expected or found un-
qualified
PPP Risk Category (2)
11
5. Operating risk 6. Revenue risk7. Network
connectivity risk
1)Service availability risk;
2)Maintenance risk:
• the cost of maintaining assets in the required
condition may vary from the projected costs, or
• maintenance is not carried out properly;
3)Latent defect risk: risk of loss or damaged arising
from latent defects in the project assets
4)Technology risk
• the technology inputs may fail to deliver the
required output specifications, or
• obsolescence risk;
5)Utilities risk:
• the utility may not be available, or
• the project will be delayed in relation to the
removal or relocation of utilities located at the
project sites;
6)Resource or input risk: a failure or shortage in
supply of inputs or resources (e.g. coal, other fuel)
7)Industrial relations risk: any form of industrial
action – including strikes, lockouts etc
1)Demand risk: risk that the
demand for a service will
lower from that projected; or
2)Tariff risk: risk that the tariff
for a service is lower from
that projected, due to:
• the periodical tariff
adjustment is not
performed as planned, or
• miscalculation of the tariff
estimates
1)Connectivity with the
existing network risk: the
risk that the access to the
existing network is not
(possible to be) developed
as planned;
2)Network development risk:
the risk that the required
additional network is not
(possible to be) developed
as planned;
3)Competing facility risk: the
risk that other similar
facility/infrastructure is
built which eventually
competing with the delivery
of the contracted services
PPP Risk Category (3)
12
8. Interface risk11. Asset
Ownership risk9. Political risk
10. Force Majeure risk
The risk when the
quality of works
done by government
not conform/suitable
with those done by
the PC, vice versa
Risk that events such as
loss events will occur, with
the result that the
economic value of the
asset may vary, either
during or at the end of the
contract term, from the
value upon which the
financial structure of the
project is based
1)Currency Inconvertibility and Non-
Transfer risk
2)Expropriation risk
3)Change in Law (legislative and
government policy) risk
4)Sub-sovereign or Parastatal risk:
Regulatory consent risk:
5)Tax rate change risk
Risk that a specified event
entirely outside the control
of either party (e.g. act of
god, man-made
catastrophic event)
Example: Risk Allocation in Toll Road Concession (1)
1. Site risk
Land Acquisition, Resettlement risks
Ground conditions difficulties, safety, environmental risks
Private Public Shared
Fase Pra-Konstruksi
2. Design, Construction and Commissioning risk
Design brief risk Delay in completing construction risk
Design faults Construction cost increase
Cost increase due to planning issues Commissioning risk
Konstruksi Operasi
5. Operating risk
Inavailability or poor performance of services
Industrial actions, O&M cost overruns
Traffic accident or public safety concerns
6. Revenue risk
Change in traffic demand projection
Failure of tariff adjustment due to fail in achieving agreed level of service
Periodical tariff adjustment is delayed
Miscalculation of tariff estimates
13
3. Sponsor risk
Default by the Subcontractors Default by the PC as Operartor
Default of Project Sponsor or the Project Company (PC)
4. Financial risk
Failure to achieve financial close Financial structure risk Insurance risk
Foreign exchange risk, Interest risk, inflation risk
Pre-Construction
10. Force Majeure risk
Natural FM, Political FM, Extreme weather
Prolonged force majeure
Construction Operation
11. Asset Ownership risk
Asset loss events
Asset transfer after PPP contract ends
Example: Risk Allocation in Toll Road Concession (2)
14
9.Political risk
General change of law
Currency inconvertibility, Non-transfer, Expropriation, Discriminatory, project-specific change in law, Regulatory consent, Sub-sovereign/Parastatal risks
8. Interface risk
Disparity between government support works and PC’s works
Substantial reworks due different standards
7. Network connectivity risk
Authority’s breach to maintain required network
Authority’s breach to build connecting facilities
Authority’s breach not to build competing roads
Private Public Shared
AGENDA
2. PPP Risk Category and Risk Matrices
3. Evaluation of Risks for IIGF Guarantee
1. Risks Assessment and Allocation in PPP Project
IIGF Guarantee Coverage
16
• Financial obligations of the CA under PPP Agreement
• Classified as Infrastructure Risk events (PMK 2060/2010), that the occurrence is:
1. caused by the action/inaction of the CA or the government apart from the CA on issues which are, by law, the CA or the government apart from the CA have the authority or control such action/inaction;
2. caused by a policy made by the CA or the government apart from the CA;
3. caused by a unilateral decision made by the CA or the government apart from the CA;
4. caused by the inability of the CA or the government apart from the CA in fulfilling its obligation under the PPP agreement (breach of contract).
Risk Allocation: Basis for Guarantee Appraisal
17
IIGF GUARANTEE PROVISION PROCESS
Other appraisal works
1. Consultation and Guideline
2. Screening 3. Appraisal 4. Structuring
Risk Assessment
Guarantee Application Package (GAP)
Other documents
PPP & Infrastructure Guarantee Regulatory Framework
PR 67/2005 j.o. 13/2010 on PPP
PR 78/2010 on Guarantee to PPP
Projects
Not eligible for guarantee
IIGF Risk GuidelinePPP Risk Category & PPP Risk Matrix
Comply with Risk Allocation
principles
Yes
No
2
Risk Allocation Principles
Risks considered to be guaranteed by IIGF
Draft PPP Agreement1
PMK 260/2010 on PR 78/2010
implementation
The IIGF decision in providing guarantee for risks in a PPP project is made after analyzing, among others,
the conformity of the draft PPP Agreement with the risk allocation principles
Construction OperationPre-construction
Transport
Waste Water
Toll Roads
Water Supply
Electircity
Delay or failure in obtaining licenses, permits, and approvals
Ris
k E
vents
Secto
rs: A
s p
er P
resid
entia
l Regula
tion
No. 1
3/2
01
0
Selected Oil & Gas
Irrigation
Selected Telecom
Financial close delay/failure
Change in law/regulations
Breach of contract
Competing facility risk
Integration with network
Revenue risk
Demand risk
Tariff risk
Expropriation risk
Sub-sovereign or Parastatal risk
Currency inconvertibility & non-transfer risk
Interface risk
Force majeure affecting the CA risk
18
IIGF may provide coverage of various CA’s Obligationswhich have been allocated to CA under PPP Agreement
Thank youQ&A
19
Possible CA’s Obligation to be Guaranteed (1)
No. Risk Description
1 Licenses, permits, and
approvals
Coverage for delay or failure to grant licenses, permits, and approvals (delays that would
have adverse effects on construction costs, financing charges, and the commencement of
revenue)
2 Financial close delay/failure Coverage for any delay/failure of financial closure due to any other action/inaction on the
part of the CA (beyond land and licenses/permits/approvals)
3 Change in law/regulations Coverage for impact of change in law/regulation in event that it adversely affects project,
such as tax law, law on tariff structure, or law that affects project's technical specifications
and results in changes in costs. Applies only if contract is explicit (not silent) in its basis on
and ties with existing law (i.e., protects from changes in law), where it is common for CA to
bear the risk of discriminatory change of law.
4 Breach of contract Coverage for CA’s action/inaction in violation of contract, or CA’s changing clauses of
contract unilaterally
5 Integration with network Coverage for actions/inaction that affect project operations/revenue by failure (or
inadequate) integration with existing or future networks
6 Competing facility risk Coverage for the risk that other similar facility/infrastructure is built which eventually
competes with the delivery of the contracted services
7 Revenue risk Coverage to fulfil /enforce CA’s obligations on revenue. Coverage applies only to CA’s
contractually agreed payments (annuity/viability gap/minimum revenue)
20
Possible CA’s Obligation to be Guaranteed (2)
No. Risk Description
8 Demand risk Coverage for change, borne of CA’s actions, that have an influence on demand for the
project's services
9 Pricing risk Coverage to fulfil level of revenue that was not reached due to unilateral change of tariff
10 Expropriation risk Coverage for the risk that public sector authority’s expropratory actions cause the project
to end
11 Currency inconvertibility &
non-transfer risk
Coverage for risk that the revenue/profit from the project could not be converted to the
foreign currency and /or repatriated to the investor’s home country
12 Sub-sovereign or Parastatal
risk
Coverage for risk that the subsovereign or parastatal entity which act as the CA in the
project has fail to perform its contractual payment or other material obligations (i.e. due to
unilateral decision)
13 Force majeure affecting the
CA risk
Coverage for risk that a specified event entirely outside the control of either party (e.g. act
of god, man-made catastropic event) will occur and affecting the CA, which will result in a
delay or default by the SPV in the performance of its contractual obligations.
14 Interface risk Coverage for risk that the method or standard of delivery of the public sector delivered
services will prevent or in some way frustrate the delivery of the contracted services. The
risk includes when the quality of works done by government not conform/suitable with
those done by the SPV.
21