Page 1: Improvement to Interstate 40 From I-240 to the Choctaw Road Interchange Environmental Assessment March 23, 2010 Harmony Christian Church Public Hearing

Improvementto

Interstate 40 From I-240 to the Choctaw Road

Interchange

Environmental Assessment

March 23, 2010Harmony Christian Church

Public Hearing

Page 2: Improvement to Interstate 40 From I-240 to the Choctaw Road Interchange Environmental Assessment March 23, 2010 Harmony Christian Church Public Hearing

Overview

• Introduction

• Project Team

• Purpose

• Study Area

• Why This Project is Needed

• Goals/Objectives

• Preferred Alternative

• Why We Are Here

Page 3: Improvement to Interstate 40 From I-240 to the Choctaw Road Interchange Environmental Assessment March 23, 2010 Harmony Christian Church Public Hearing

Introduction

• FHWA

• ODOT

• TETRA TECH

Page 4: Improvement to Interstate 40 From I-240 to the Choctaw Road Interchange Environmental Assessment March 23, 2010 Harmony Christian Church Public Hearing

Purpose

The purpose of the project is to address physical deficiencies, congestion, and safety issues on I-40 from the

I-240 merge to Choctaw Road.

Page 5: Improvement to Interstate 40 From I-240 to the Choctaw Road Interchange Environmental Assessment March 23, 2010 Harmony Christian Church Public Hearing

Study Area

Page 6: Improvement to Interstate 40 From I-240 to the Choctaw Road Interchange Environmental Assessment March 23, 2010 Harmony Christian Church Public Hearing

Why This Project is Needed• Traffic backs up at the Choctaw Road exits

• The acceleration / deceleration lanes for

I-40/I-240 ramps and Choctaw Road are

too short

• Low exit ramp design speeds at Choctaw Road

• Inadequate vertical sight distances

• No traffic signals on Choctaw Road

• High accident rates

• Substandard vertical clearance at the bridge

• Need for safe pedestrian and bicycle access

Page 7: Improvement to Interstate 40 From I-240 to the Choctaw Road Interchange Environmental Assessment March 23, 2010 Harmony Christian Church Public Hearing

Goals / Objectives

• Improve the safety and operation of I-40 and

the Interchanges

• Minimize Impact to the Environment

• Meet the Purpose and Needs for the project

Page 8: Improvement to Interstate 40 From I-240 to the Choctaw Road Interchange Environmental Assessment March 23, 2010 Harmony Christian Church Public Hearing

Preferred Alternative

• Diamond Interchange– Three lanes per direction (I-40)– Auxiliary lanes (I-240)– Increased Traffic Storage and Decreased Driver

Confusion and Enhance Pedestrian Safety– Simplified Construction Sequencing

(Approximately 20 months)– Traffic signals with dedicated turn lanes

Page 9: Improvement to Interstate 40 From I-240 to the Choctaw Road Interchange Environmental Assessment March 23, 2010 Harmony Christian Church Public Hearing

Preferred Alternative (Cont.)

– Choctaw Road widening to five lanes with curb and gutter (include ADA compliant sidewalks)

– Accommodate Multimodal Facilities (i.e Park-n-Ride, Bicycle Access)

– Fewer Potential Relocations– Additional Right-of-Way– Retaining Walls

Page 10: Improvement to Interstate 40 From I-240 to the Choctaw Road Interchange Environmental Assessment March 23, 2010 Harmony Christian Church Public Hearing

Preferred Alternative

With Limits of No Access

Page 11: Improvement to Interstate 40 From I-240 to the Choctaw Road Interchange Environmental Assessment March 23, 2010 Harmony Christian Church Public Hearing

Environmental Analysis

• Wetlands, Streams, Ponds, Water Quality• Threatened and Endangered Species• Cultural Resources• Hazardous Materials• Farmland• Land use, Economic and Right-of-Way Impacts• Traffic Noise• Air quality• Temporary Construction Impacts• Community Concerns

Page 12: Improvement to Interstate 40 From I-240 to the Choctaw Road Interchange Environmental Assessment March 23, 2010 Harmony Christian Church Public Hearing

Right of Way

• Right-of-Way and Relocations

Page 13: Improvement to Interstate 40 From I-240 to the Choctaw Road Interchange Environmental Assessment March 23, 2010 Harmony Christian Church Public Hearing

Why We Are Here

• Input on the Preferred Alternative– Online comments (emails to [email protected])– Written - comment forms available– Verbal – record your comments with the Court Reporter– Comments due by April 23rd.

Page 14: Improvement to Interstate 40 From I-240 to the Choctaw Road Interchange Environmental Assessment March 23, 2010 Harmony Christian Church Public Hearing

Information Sources

Environmental Assessment:

1. http://www.okladot.state.ok.us/meetings/a2010/i40ea/

2. ODOT Central Office, 200 N.E. 21st Street, Room 3D 2A (2 copies)

3. Harmony Christian Church

4. Midwest City Public Library

5. Choctaw Public Library

Nancy Ashton – ODOT

Phone: 405-521-2676

200 NE 21st Street

Oklahoma City, OK 73105

E-mail: [email protected]

Jonathan Heusel – Tetra Tech

Phone: 405-606-8600

119 North Robinson Avenue

Oklahoma City, OK 73102

E-mail: [email protected]

Page 15: Improvement to Interstate 40 From I-240 to the Choctaw Road Interchange Environmental Assessment March 23, 2010 Harmony Christian Church Public Hearing

Thank You !