    Innovative Business Solutions

    Risk Management

  • 8/3/2019 Innovative Business Solutions RM

    2/20

    Environmental Enterprise Factors

    IBS Stake holders (SANI) is very flexible and supportive in dealing

    with Risk at any level or phase of project.

    SANI always show participative behavior with maximum

    involvement in the issues or problems.

    Each and every possible help is carried out by defined IBS SOPs

    The tolerance of the execution depend upon the nature of theproblem and its proposed solution

  • 8/3/2019 Innovative Business Solutions RM

    3/20

    IBS Process Assets

    IBS defined strategic planning tools

    Creative, innovative thinking Group people of defined project team

    Collaboration and integration take place between differentdepartments

    Previous similar projects outcomes, obstacles are reviewed and

    taken in special consideration

    IBS defined standard and Policies in dealing with risks and issues

    are covered under IBS SOP documents and IBS standard code of

    implementation

  • 8/3/2019 Innovative Business Solutions RM

    4/20

    Methods & Approach in Managing Risk

    IBS Risk Management standards are based on ISO31000.

    IBS focused on coordinated and economical application ofresources to minimize, monitor, and control the probability and/orimpact of unfortunate events

    IBS has defined method of managing risk i.e. contingency planning,making use of existing assets, PM metrics (STCQ),PM risk analysissoftware etc

    IBS work on approaches like incorporating stake holder perceptionsof risk into corporate risk management strategies

    IBS is currently working on Catastrophe Approach of managing risk

  • 8/3/2019 Innovative Business Solutions RM

    5/20

    IBS Risk Identification in Budgeting

    Risk Significance Level

    Exceeding allocated Capital High 5

    Real Estate value rise High 5

    Negotiation to Owner Fail Moderate 3

    Rise in Contractor fees High 5

    Rise in Construction Material pricing High 5

    Machine failure High 4

    Transportation expense Moderate 3.5

    Rise in Labor Hour rate High 5

    Shortage of Material High 5

    Air conditioning failure Moderate 3

  • 8/3/2019 Innovative Business Solutions RM

    6/20

    Risk Significance Level

    Rain will affect badly the Walls Moderate 3

    Improper drainage system Moderate-High 4.5

    Rise in installation expense High 5

    Less Experienced labor recruited Moderate 5

    Rise in demand of labor High 5

    Delay of working Moderate 4

    Un favorable situation Moderate 4

    Labor Strike High 5

    Safety Measures High 4.5

    Making parallel Application High 4.7

    Undefined methods of procedures High 5

  • 8/3/2019 Innovative Business Solutions RM

    7/20

    Risk Significance Level

    Extra involvement of Government Low 1

    Misunderstanding b/w team Moderate-High 4.5

    Different style of working Moderate 5

    Risk in selection criteria High 5

    Diverse knowledge level Moderate to High 5

    Autocratic decision Making High 4.7

    Highly Complex approach High 5

    Improper defined Scope High 5

    Un revised HR policies Moderate 3.8

    Untimely resource allocation Moderate to High 4.6

    System N/W failure High 4.5

  • 8/3/2019 Innovative Business Solutions RM

    8/20

    Risk Significance Level

    Power Failure High 5

    Cable Cutting faults Moderate-High 4.6

    DB installation Moderate 3.8

    Random Error Arrival Moderate 4.5

    Complex design & Development Methods Moderate to High 5

    Sudden Telecom N/W down Low-Moderate 3.5

    S/W Compatibility issue Moderate 4.6

    Increase demand of customer High 5

    Competitor Position Moderate to High 4.5

    Crashing project activities Moderate to High 4.6

    Scheduling and Budgeting Inefficiency High 5

  • 8/3/2019 Innovative Business Solutions RM

    9/20

    Risk ConsiderationRisk Area/Activity Effect on SCTQ

    Exceeding allocated Capital Finance Cost , Scope

    Real Estate value rise Construction Cost

    Negotiation to Owner Fail Purchasing Flats Cost

    Rise in Contractor fees Purchasing Flats Cost

    Rise in Construction Material pricing Construction Cost

    Machine failure Construction Cost, Time

    Transportation expense Construction

    renovation

    Cost

    Rise in Labor Hour rate Construction Cost , Time

    Shortage of Material Services,

    Construction

    Cost Time

    Air conditioning failure Renovation Cost

  • 8/3/2019 Innovative Business Solutions RM

    10/20

    Risk Area/Activity Effect on SCTQ

    Rain will affect badly the Walls Renovation Cost Quality

    Improper drainage system Renovation Cost Quality

    Rise in installation expense Safety Measures Cost

    Less Experienced labor recruited Construction Time Quality

    Scope Cost

    Rise in demand of labor Construction Cost

    Delay of working Renovation,

    Construction,

    Services

    Time Scope

    Un favorable situation All Time Scope

    Labor Strike Construction Time Cost

    Safety Measures Production,

    Construction

    Cost

    Making parallel Application Deliverables SCTQ

    Undefined methods of procedures IBS Plan SCTQ

  • 8/3/2019 Innovative Business Solutions RM

    11/20

    Risk Area/ Activity Effect on SCTQ

    Extra involvement of Government IBS Charter ---

    Misunderstanding b/w team Project LifeCycle

    SCTQ

    Different style of working Project Life SCTQ

    Risk in selection criteria HR Time Quality

    Cost

    Diverse knowledge level Project Execution Time QualityScope

    Autocratic decision Making Project Life

    Cycle

    Time Scope

    Quality

    Highly Complex approach Production SCTQ

    Improper defined Scope Project Life SCTQ

    Un revised HR policies HR Quality

    Untimely resource allocation Execution Time Cost

    System N/W failure Deployment Time Quality

  • 8/3/2019 Innovative Business Solutions RM

    12/20

    Risk Area/ Activity Effect on SCTQ

    Power Failure Development,

    maintenance

    Time quality

    Cable Cutting faults Maintenance Time Cost

    DB installation Deployment Time quality

    Random Error Arrival Development

    Testing

    Time Quality

    Complex design & Development Methods Project Life SCTQ

    Sudden Telecom N/W down Deployment Time Quality

    S/W Compatibility issue Deployment Quality Time

    Increase demand of customer Acceptance SCTQ

    Competitor Position General SCTQ

    Crashing project activities Execution,

    Planning

    Time quality

    Cost

    Scheduling and Budgeting Inefficiency IBS MP SCTQ

  • 8/3/2019 Innovative Business Solutions RM

    13/20

    IBS Risk ResponsibilitiesRisk Area/Activity Prioritization Responsibility

    Exceeding allocated

    Capital

    Finance 1 Sr. Finance Manager

    Real Estate value rise Construction 1 Sr. Secretary of IBS

    Negotiation to Owner

    Fail

    Purchasing

    Flats

    2 Sr. Secretary of IBS

    Rise in Contractor

    fees

    Purchasing

    Flats

    2 Sr. Finance Manager

    Rise in Construction

    Material pricing

    Construction 1 Sr. HR and Finance

    Manager

    Machine failure Construction 1 HR Manager

    Transportation

    expense

    Construction

    renovation

    3 HR and Finance

    Manager

    Rise in Labor Hour

    rate

    Construction 1 HR Manager

    Shortage of Material Services,

    Construction

    1 HR and Finance

    Manager

    Air conditioning

    failure

    Renovation 4 HR Manager

  • 8/3/2019 Innovative Business Solutions RM

    14/20

    Risk Area/Activity Responsibility Priority

    Rain will affect badly the

    Walls

    Renovation Maintenance

    staff

    4

    Improper drainage system Renovation Maintenance 2

    Rise in installation expense Safety Measures Finance and IT 2

    Less Experienced labor

    recruited

    Construction HR 1

    Rise in demand of labor Construction HR 1

    Delay of working Renovation,

    Construction, Services

    HR 1

    Un favorable situation All All 1

    Labor Strike Construction HR 2

    Safety Measures Production,

    Construction

    IT, Development 3

    Making parallel

    Application

    Deliverables PM 2

    Undefined methods of

    procedures

    IBS Plan Project Manager 1

  • 8/3/2019 Innovative Business Solutions RM

    15/20

    Risk Area/

    Activity

    Responsibility Priority

    Extra involvement of

    Government

    IBS Charter Stake Holders 5

    Misunderstanding b/w team Project LifeCycle Project manager, Team Lead 2

    Different style of working Project Life Project Manager 1

    Risk in selection criteria HR Sr. Hr Manager 2

    Diverse knowledge level Project

    Execution

    Project Manager 2

    Autocratic decision Making Project Life

    Cycle

    Project Manager 1

    Highly Complex approach Production Project Team 1

    Improper defined Scope Project Life Project Team 1

    Un revised HR policies HR Sr. HR Manager 3

    Untimely resource allocation Execution HR Manager 2

    System N/W failure Deployment Maintenance Support 3

  • 8/3/2019 Innovative Business Solutions RM

    16/20

    Risk Area/ Activity Responsibility Priority

    Power Failure Development,

    maintenance

    Support Maintenance 1

    Cable Cutting faults Maintenance Support Maintenance 2

    DB installation Deployment Deplorer 3

    Random Error Arrival Development

    Testing

    Tester 2

    Complex design &

    Development Methods

    Project Life Project Manager 1

    Sudden Telecom N/W down Deployment Support 2

    S/W Compatibility issue Deployment Deployment 1

    Increase demand of customer Acceptance S &M Manager 1

    Competitor Position General S&M Manager 1

    Crashing project activities Execution,

    Planning

    Project Manager 1

    Scheduling and Budgeting

    Inefficiency

    IBS MP Project Team 1

  • 8/3/2019 Innovative Business Solutions RM

    17/20

    IBS Risks StrategyRisk Area/Activity Strategy

    Exceeding allocated Capital Finance Decrease demand , Increase

    revenues

    Real Estate value rise Construction Stick to reasonable possible Value

    Negotiation to Owner Fail Purchasing Flats Try another Owner

    Rise in Contractor fees Purchasing Flats Negotiate on reasonable fee

    Rise in Construction Material

    pricing

    Construction Un handled

    Machine failure Construction Make backup machinery work

    Transportation expense Construction renovation Un handled

    Rise in Labor Hour rate Construction Proper channeled Negotiations

    Shortage of Material Services, Construction Keep stock of material

    Air conditioning failure Renovation Make use of Guarantee card or

    reasonable servicing

  • 8/3/2019 Innovative Business Solutions RM

    18/20

    Risk Area/Activity Strategy

    Rain will affect badly the Walls and

    blinds

    Renovation Use Plastic blinds and water

    proof Paint

    Improper drainage system Renovation Reconsider the architect design

    and immediate action

    Rise in installation expense Safety Measures Bargaining, reduce unnecessary

    services charges

    Less Experienced labor recruited Construction Carefully hired labor

    Rise in demand of labor Construction Calming down with acceptance

    of reasonable demand

    Delay of working Renovation,

    Construction, Services

    Keep strong check

    Un favorable situation All Take extra time to face

    Labor Strike Construction Negotiate and accept some points

    Safety Measures Production, Construction Acquire and ensure safety

    measures

    Making parallel Application Deliverables Make 1 obj. with multiple

    deliverables

    Undefined methods of procedures IBS Plan Work on IBS defined method

    history learned

  • 8/3/2019 Innovative Business Solutions RM

    19/20

    Risk Area/ Activity Strategy

    Extra involvement of Government IBS Charter ------

    Misunderstanding b/w team Project Life

    Cycle

    Do conflict Management

    Different style of working Project Life Align each and every styled o/p

    Risk in selection criteria HR Make tough selection criteria

    Diverse knowledge level Project Execution Organize training workshops

    Autocratic decision Making Project Life

    Cycle

    Make participative DM

    Highly Complex approach Production Apply and encourage simple

    approach

    Improper defined Scope Project Life Try to clear objective and level of

    working

    Un revised HR policies HR Revised the old HR policies

    Untimely resource allocation Execution Make use of Pert chart

    System N/W failure Deployment Make backup N/W Plan

  • 8/3/2019 Innovative Business Solutions RM

    20/20

    Risk Area/ Activity Strategy

    Power Failure Development,

    maintenance

    Use stand by generator or batteries

    Cable Cutting faults Maintenance Keep spare cable duringdeployment

    DB installation Deployment Use Licensed S/W and Suite

    Random Error Arrival Development Testing Keep on testing the code at every

    stage

    Complex design & DevelopmentMethods Project Life Use simple approach and AgileMethod

    Sudden Telecom N/W down Deployment Wait complain then shift

    S/W Compatibility issue Deployment Check compatibility of systems

    before deployment

    Increase demand of customer Acceptance Do customer surveys, analysis

    Competitor Position General Look at their steps and strategies

    Crashing project activities Execution, Planning Do proper planning and consider

    each parameter

    Scheduling and Budgeting Inefficiency IBS MP Apply Pert chart and PDM

    properly