If you can't read please download the document
Upload
barbulescubogdan9570
View
225
Download
0
Embed Size (px)
Citation preview
7/27/2019 Innovative Pre-Cast Cantilever Constructed Bridge Concept
1/197
INNOVATIVE PRE-CAST CANTILEVER CONSTRUCTED BRIDGE CONCEPT
by
Brent Tyler Visscher
A thesis submitted in conformity with the requirements
for the degree of Master of Applied Science
Graduate Department of Civil Engineering
University of Toronto
Copyright by Brent Tyler Visscher (2008)
7/27/2019 Innovative Pre-Cast Cantilever Constructed Bridge Concept
2/197ii
Innovative Pre-cast Cantilever Constructed Bridge Concept
Brent Tyler Visscher
Master of Applied Science
Department of Civil Engineering
University of Toronto, Canada
2008
ABSTRACT
Minimum impact construction for bridge building is a growing demand in modern urban
environments. Pre-cast segmental construction is one solution that offers low-impact, economical,
and aesthetically pleasing bridges. The standardization of pre-cast concrete sections and segments
has facilitated an improved level of economy in pre-cast construction. Through the development
of high performance materials such as high strength fibre-reinforced concrete (FRC), further
economy in pre-cast segmental construction may be realized. The design of pre-cast bridges using
high-strength FRC and external unbonded tendons for cantilever construction may provide an
economical, low-impact alternative to overpass bridge design.
This thesis investigates the feasibility and possible savings that can be realized for a single cell
box girder bridge with thin concrete sections post-tensioned exclusively with external unbonded
tendons in the longitudinal direction. A cantilever-constructed single cell box girder with a
curtailed arrangement of external unbonded tendons is examined.
7/27/2019 Innovative Pre-Cast Cantilever Constructed Bridge Concept
3/197iii
ACKNOWLEGEMENTS
This work has been partially supported by the National Science and Engineering Research
Council of Canada.
I would like to thank my supervisor Dr. Paul Gauvreau for his guidance, support, andfellowship throughout the course of this design project.
Many thanks are owed to my friends and colleagues, especially those within our bridge
engineering research group, for their helpful discussions and insightful contributions to the
development of this project: Billy Cheung, Jamie McIntyre, Kris Mermigas, Talayah Noshiravani,
Graham Potter, Carlene Ramsay, Jason Salonga, and Jimmy Susetyo. Additional thanks go out to
other graduate students who I have had the pleasure of spending time with throughout my graduate
study: Jeff Erochko, Hyungjoon Kim, Nabil Mansour, Michael Montgomery, and Lydell Wiebe.
Special thanks to Jimmy Susetyo for his generous contributions in concrete material design and for
his laboratory assistance in test specimen preparation. I would like to thank John MacDonald for
his contribution during cylinder testing.
Finally, I thank my family for their constant encouragement and support throughout this task.
7/27/2019 Innovative Pre-Cast Cantilever Constructed Bridge Concept
4/197iv
TABLE OF CONTENTS
ABSTRACT. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . ii
ACKNOWLEGEMENTS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . iii
TABLE OF CONTENTS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . iv
LIST OF FIGURES . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . viii
LIST OF TABLES . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . xii
LIST OF SYMBOLS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . xiii
1.0 INTRODUCTION . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .1
1.1 Statement of Problem . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2
1.2 Scope and Objective . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3
1.3 Thesis Structure . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4
2.0 BACKGROUND . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .7
2.1 Constitutive Laws for High Performance FRC. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7
2.1.1 Compressive Stress-Strain Behaviour. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7
2.1.2 Tensile Stress-Strain Behaviour . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 10
2.2 Typical Modern Highway Overpass Bridge Design Currently in Ontario . . . . . . . . . . . . . . . . . . . . . . . . . . 13
2.2.1 Standardization of Precast Components . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 14
2.3 Description of the Proposed Segmental Box Girder Concept . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 15
2.4 Visual Comparison of Proposed Box Girder with Typical Slab-on-Girder Overpass . . . . . . . . . . . . . . . . . 22
2.5 Benefits and Drawbacks of the Proposed Design . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 25
2.5.1 Benefits . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 25
2.5.2 Drawbacks. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 27
3.0 LONGITUDINAL FLEXURE. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .28
3.1 Introduction. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 28
3.2 Moment-Curvature Response . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 29
3.3 Behaviour of Unbonded Tendons . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 30
3.3.1 Reference State of Strain. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 31
3.3.2 Long-Term Effective Prestress . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 32
3.4 Tendon Stress Calculation Methods . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 333.5 Preliminary Design Assumptions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 37
3.6 Preliminary Design Methodology for Cantilever Tendons. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 39
3.6.1 Loading . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 39
3.6.2 Ultimate Moment Resistance . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 42
3.6.3 Sizing of Cantilever Tendons . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 44
3.7 Change in Structural System. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 47
3.8 Preliminary Design Methodology for Continuity Tendons . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 50
7/27/2019 Innovative Pre-Cast Cantilever Constructed Bridge Concept
5/197v
3.8.1 Ultimate Moment Resistance . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 50
3.8.2 Spreading of Forces. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 51
3.8.3 Sizing of Continuity Tendons . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 53
3.8.4 Secondary Prestress Moment due to Continuity Tendons . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 55
3.9 Bottom Flange Sizing . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 58
3.10 Prestress Distribution . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 60
3.11 Ultimate Limit State . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 63
3.12 Serviceability Limit States . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 64
3.12.1 Construction . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 65
3.12.2 Cracking . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 65
3.12.3 Global Deflection . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 67
3.13 Refinement in Tendon Stress . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 67
3.13.1 Ductility of Fibre-Reinforced Concrete . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 67
3.13.2 Deformation Capacity. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 69
3.13.3 Example of Tendon Stress Increase for Negative Bending . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 70
3.13.4 Discussion . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 72
3.14 Global System Considerations . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 73
3.14.1 Span-to-Depth Ratio for Constant Depth Box Girder. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 73
3.14.2 Range of Spans . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 74
3.14.3 Alternative Girder Designs . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 76
4.0 TRANSVERSE FLEXURE . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .78
4.1 Introduction. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 78
4.2 Typical Transverse Prestressing for Segmental Bridges. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 79
4.3 Prestressing Concept for Light Weight Slab Design . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 79
4.3.1 Post-Tensioning . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 804.3.2 Pretensioning. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 81
4.4 Bond Strength of 15mm Pretensioning Strands in FRC . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 82
4.4.1 Mechanisms of Bond . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 82
4.4.2 Development of Stress in a 15mm Pretensioning Strand . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 83
4.4.3 Improvement of Bond Strength due to High Strength FRC . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 84
4.5 Methods of Analysis . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 85
4.5.1 Grillage Analysis. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 86
4.5.2 Frame Analysis . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 88
4.6 Comparative Study for Transverse Stiffness . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 88
4.6.1 Cross Sections. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 89
4.6.2 Material Definitions used in Analysis. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 91
4.6.3 Loading . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 92
4.6.4 Deflections . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 92
4.7 Prestress Moments . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 94
4.8 Service Loads . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 95
4.9 Cross Section Design and Layout . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 97
4.9.1 Transverse Rib Proportions. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 97
7/27/2019 Innovative Pre-Cast Cantilever Constructed Bridge Concept
6/197vi
4.9.2 Web Spacing . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 98
4.10 Design for Barrier Impact Loads . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 99
5.0 SHEAR. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .101
5.1 Introduction to Strut-and-Tie Models . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 101
5.2 Funicular Load Path for Girders Prestressed with Curtailed Tendons . . . . . . . . . . . . . . . . . . . . . . . . . . . . 103
5.3 Parallel Chord Truss Models . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1075.4 Arching Models . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 110
5.4.1 Tied Arch Model (Noshiravani, 2007) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 111
5.5 Preliminary Design Model . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 116
5.6 Opening of Joints in Segmental Bridges. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 118
5.7 Design of Web Reinforcement . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 119
5.7.1 Comparison to CAN/CSA-S6-06 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 120
6.0 ANCHORAGE ZONE. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .125
6.1 Introduction. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 125
6.2 Flow of Forces . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 126
6.3 Strut-and-Tie Model for Local Spreading of Forces. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 127
6.3.1 Anchorage of External Unbonded Tendons in Slab Blisters (Wollman, 1993) . . . . . . . . . . . . . . . . . . 127
6.3.2 Design Model for External Tendon Blisters . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 129
6.4 Detailing . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 133
6.5 Reinforcement. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 135
7.0 FIXED END ABUTMENT . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .138
7.1 Introduction. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 138
7.2 Bras de la Plaine Bridge, France (Tanis, 2003) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 138
7.3 Flexible Supports . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 140
7.4 Design Approach . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 140
7.4.1 Preliminary Design Alternatives. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 141
7.4.2 Recommended Design . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 142
7.5 Sizing of Flexible Piles . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 143
7.6 Future Work . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 144
8.0 MATERIAL UTILIZATION . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .145
8.1 Reference Bridges . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 145
8.1.1 Windward Viaduct, Interstate Route H-3, Hawaii, USA (Hawaii DOT, 1991) . . . . . . . . . . . . . . . . . . 1458.1.2 Hwy 407 - Islington Avenue Underpass, Toronto, Canada (MTO, 1990) . . . . . . . . . . . . . . . . . . . . . . 147
8.2 Concrete Consumption . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 148
8.3 Mild Reinforcing Steel Utilization . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 150
8.4 Longitudinal Post-Tensioning Utilization. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 152
8.5 Transverse Post-Tensioning Utilization . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 153
8.6 Summary . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 154
9.0 CONCLUSIONS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .155
7/27/2019 Innovative Pre-Cast Cantilever Constructed Bridge Concept
7/197vii
9.1 Longitudinal Design . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 155
9.2 Transverse Design. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 156
9.3 Shear Design . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 156
9.4 Anchorage Zone Design . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 156
9.5 Economy . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 157
9.6 Future Work . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 157
10.0 REFERENCES. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .159
APPENDIX A - DESIGN DRAWINGS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .164
APPENDIX B - MATERIAL TESTING . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .175
APPENDIX C - CAN/CSA-S6-06 SHEAR PROVISIONS . . . . . . . . . . . . . . . . . . . . . . . .178
CURRICULUM VITAE. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .180
7/27/2019 Innovative Pre-Cast Cantilever Constructed Bridge Concept
8/197viii
LIST OF FIGURES
2.0 BACKGROUND ..................................................................................................................7
Figure 2-1. Variation in modulus of elasticity with the ultimate compressive strength of concrete............... 8
Figure 2-2. Compressive stress-strain relationship for nominal 80MPa FRC test specimens and simplified
model ...................................................................................................................................... 9
Figure 2-3. Photo of intensively cracked compression cylinder after failure and significant post-peakstraining ................................................................................................................................ 10
Figure 2-4. a) Dogbone-shaped specimen: dimensions and sensors, b) test set-up of the uniaxial tensile test,
showing the front side of the specimen (adapted from Habel et al., 2006) .............. ............ 11
Figure 2-5. Tensile stress-strain relationship for nominal 80MPa FRC test specimens and simplified model:12
Figure 2-6. Typical slab-on-girder highway underpass built in Markham, Ontario on Highway 407.
Photograph courtesy of Scott Steves, 2006............... ................ ............. ................ .............. . 13
Figure 2-7. Recommended girder spacing with respect to span length for standard CPCI precast I-girders
(adapted from CPCI, 1996)....... .............. ............... ............... ............... ............... ............... ... 14
Figure 2-8. Plan and elevation view of a possible cantilever-constructed overpass bridge.......................... 16
Figure 2-9. Cross section and details of the constant depth box girder shown in Figure 2-8 ....................... 17
Figure 2-10. Typical standard segment components of proposed box girder concept.................................. 18
Figure 2-11. Top flange supported by steel struts, a) example shown of Shibakawa Viaduct, Japan (photo
courtesy of Takashi Kosaka, 2006), b) rendering of proposed 90m overpass structure ....... 19
Figure 2-12. Second Severn Bridge, a) total external unbonded prestressing tendons, b) cantilever
construction showing bulkhead face of segment with no continuous bonded steel across the
joint and no internal bonded tendons (adapted from Mizon, 1997).............. ............... ......... 20
Figure 2-13. Possible tendon arrangement shown for half the span (symmetrical about span centreline)... 21
Figure 2-14. Numbering scheme for segment labels..................................................................................... 22
Figure 2-15. Rendered perspective views on typical highway overpass construction using precast CPCI
girders (left) and proposed cantilever-constructed single cell box girder (right) as seen on an
overcast day....... ................ ............... .............. ................ .............. ............... ............... ........... 23
Figure 2-16. Deck cross sections for a) two-span precast CPCI girder overpass and b) proposed cantilever-
constructed single cell box girder. ........................................................................................ 23
Figure 2-17. Visual slenderness attained through shadow casting for a superstructure with a a) small deck
overhang and b) large deck overhang. ............... .................. .............. ............... .............. ...... 25
Figure 2-18. Collapse slab-on-girder bridge after being struck by tractor-trailer (adapted from El-Tawil,
2005) ..................................................................................................................................... 26
Figure 2-19. Elevation (1:2500 scale) showing the result of elevating the overpass road grade.................. 27
3.0 LONGITUDINAL FLEXURE..........................................................................................28
Figure 3-1. Idealization of box cross section for analysis of longitudinal flexure........................................ 29
Figure 3-2. Internal lever arm from tendon elevation to the compression flange, a) for a continuously guidedtendon, b) for a tendon attached only at discrete locations........... ................ ............... ......... 30
Figure 3-3. Strain Distribution at ultimate limit state (adapted from Naaman, 2006) .................................. 31
Figure 3-4. Material strains due to equilibrium in the reference state and in the ultimate state ................... 31
Figure 3-5. Family of moment-curvature responses for a specific cross section and varying prestress force
assuming a concentric prestress .............. ............... ............... ............... ............... ............... ... 35
Figure 3-6. Iterative method behaviour for tendon stress calculation for a) girder impending plastic hinging,
b) girder experiencing plastic hinging ................. ................ .............. ............... .............. ...... 36
Figure 3-7. Iterative method solution for obtaining tendon stress by incrementing applied load................. 37
7/27/2019 Innovative Pre-Cast Cantilever Constructed Bridge Concept
9/197ix
Figure 3-8. Typical segment cross section .................................................................................................... 40
Figure 3-9. Comparison of live load models defined in CAN/CSA-S6-06 .................................................. 41
Figure 3-10. ULS bending moments on continuous girder........................................................................... 42
Figure 3-11. Cantilever prestress concepts for haunched and constant depth girders .................................. 44
Figure 3-12. Preliminary ULS demand and capacity for cantilever PT........................................................ 45
Figure 3-13. Layout of cantilever tendons .................................................................................................... 46
Figure 3-14. Redistribution of forces through concrete creep due to change in structural system (adapted fromPodolny et al., 1982)............................................................................................................. 48
Figure 3-15. Time-dependent creep coefficient assuming t0= 28 days, a) for 75 year period, b) for 5 year
period ............. .............. ................ .............. ............... .............. ............... .............. ................ . 49
Figure 3-16. Sectional forces due to prestressing with top and bottom tendons........................................... 51
Figure 3-17. Moment development length, la, due to anchorage of continuity tendon (adapted from Menn,
1990) ..................................................................................................................................... 52
Figure 3-18. Required moment development length for a girder post-tensioned with unbonded tendons... 53
Figure 3-19. Layout of continuity tendons.................................................................................................... 54
Figure 3-20. Preliminary ULS demand and capacity for continuity tendons................................................ 55
Figure 3-21. Secondary prestress moment due to prestressed continuity tendon ......................................... 57Figure 3-22. Ultimate state of stress for section with undersized bottom flange.......................................... 59
Figure 3-23. Appropriately sized bottom flange thickness for negative bending at ULS............................. 59
Figure 3-24. Primary prestress force distribution.......................................................................................... 61
Figure 3-25. Girder response for varying prestress force.............................................................................. 63
Figure 3-26. Girder response at ULS (half span shown)............................................................................... 64
Figure 3-27. Girder response at SLS (half span shown) ............................................................................... 66
Figure 3-28. Stress-strain response of FRC and typical normal-weight concrete......................................... 68
Figure 3-29. FRC comparison for total moment-curvature response in negative bending........................... 69
Figure 3-30. Plastic hinging in negative moment regions............................................................................. 70
Figure 3-31. 90m span with midspan hinge when load is close to failure.................................................... 71
Figure 3-32. Stresses in unbonded tendons for curtailed prestressing. a) change in tendon stresses during
construction due to the addition of segments and post-tensioning, b) change in tendon stresses
due to the application of increasing uniform load until failure.......... ............... ............... ..... 72
Figure 3-33. Ultimate behaviour for a continuous girder using unbonded draped tendons (adapted from
Muller et al., 1990) ............................................................................................................... 73
Figure 3-34. Material consumption for varying span/depth ratios................................................................ 74
Figure 3-35. Concept comparison of haunched girder and constant depth girder elevation......................... 76
4.0 TRANSVERSE FLEXURE ..............................................................................................78
Figure 4-1. Possible pretensioning arrangement........................................................................................... 82
Figure 4-2. Bond mechanisms between FRC and 15mm pretensioning strand (adapted from Chao, 2006) 83
Figure 4-3. Idealized strand stress profile in a pretensioned strand under applied load (adapted from Kahn,
2002) ..................................................................................................................................... 83
Figure 4-4. Generalized frame element properties for grillage analysis (adapted from Menn, 1990).......... 87
Figure 4-5. 3-dimensional grillage model..................................................................................................... 88
Figure 4-6. Comparison of top flange thicknesses of AASHTO-PCI-ASBI standard box girder examples
(adapted from Prestress/Precast Concrete Institute, 1997) ............. .............. ............... ......... 90
Figure 4-7. Cross section dimensions for typical segment............................................................................ 91
7/27/2019 Innovative Pre-Cast Cantilever Constructed Bridge Concept
10/197x
Figure 4-8. Assumed stress-strain material properties for investigation of transverse stiffness................... 91
Figure 4-9. Live load models for transverse load analysis............................................................................ 92
Figure 4-10. Vertical slab deflection envelope due to live load, AASHTO-PCI-ASBI box girder .............. 93
Figure 4-11. Edge beam stiffening ................................................................................................................ 93
Figure 4-12. Vertical slab deflection envelope due to live load of proposed box girder: a) thin slab stiffened
with transverse ribs only, b) thin slab stiffened with transverse ribs and longitudinal edge
beam............... ............... ............... .............. ............... .............. .............. ............... ................ . 94
Figure 4-13. Moment distribution due to non-concentric prestress applied at the transfer length ............... 95
Figure 4-14. Total transverse bending moments for transverse flexure........................................................ 96
Figure 4-15. SLS top slab stress ranges at the extreme fibre due to service loading.................................... 97
Figure 4-16. Longitudinal section for a typical segment .............................................................................. 98
Figure 4-17. Web spacing requirements........................................................................................................ 99
Figure 4-18. Truss model for basis of barrier reinforcement ........................................................................ 99
Figure 4-19. PL-2 barrier detail for impact loading.................................................................................... 100
5.0 SHEAR..............................................................................................................................101
Figure 5-1. 45 degree truss model (adapted from Ritter, 1899) .................................................................. 102Figure 5-2. Possible truss models for girders with unbonded and bonded prestressing steel (adapted from
Gauvreau, 1993).......... ............... ............... .............. ................ .............. ............... ............... 102
Figure 5-3. Alternative girder designs to resist applied load Q .................................................................. 104
Figure 5-4. Effect of prestress arrangement on funicular compression chord ............................................ 105
Figure 5-5. Funicular shape of compression spine for continuous cantilever girder with curtailed tendons106
Figure 5-6. Strut-and-tie model for a fully prestressed flanged section. a) simplified model; b) through d)
detailed model of web, top flange and bottom flange, respectively (adapted from Schlaich et
al., 1989) ............................................................................................................................. 108
Figure 5-7. Variable angle truss model (adapted from Collins et al., 1997) ............................................... 109
Figure 5-8. Arch spreading of forces for a rectangular section (adapted from Schlaich et al., 1989) ........ 110
Figure 5-9. Comparison of tied arch model for a rectangular section and a flanged section (adapted from
Noshiravani, 2006)...... ............... .............. ............... .............. ................ .............. ................ 112
Figure 5-10. Girder dimensions (adapted from Noshiravani, 2007) ........................................................... 113
Figure 5-11. Girder cross section and web reinforcement (adapted from Noshiravani, 2007)................... 113
Figure 5-12. Tied arch model for load stage corresponding to flexural cracking (adapted from Noshiravani,
2007) ................................................................................................................................... 113
Figure 5-13. Tied arch model for load stage corresponding to ULS (adapted from Noshiravani, 2007) ... 114
Figure 5-14. Crack pattern and alternative parallel chord model for load stage corresponding to flexural
cracking............................................................................................................................... 115
Figure 5-15. Crack pattern and alternative parallel chord model for load stage corresponding to ULS .... 116
Figure 5-16. Truss model for shear design. a) fully prestressed state for continuous beam; b) modified modelto account for flange decompression (formation of plastic hinge) .............. .............. ......... 117
Figure 5-17. Prestress forces applied to truss model in Figure 5-16 for each applied anchorage force ..... 117
Figure 5-18. Incorrect hanger reinforcement model for shear stresses crossing an open joint (adapted from
Virlogeux, 1993) ................................................................................................................. 118
Figure 5-19. ULS Combination 1 maximum shear demands...................................................................... 119
Figure 5-20. ULS transverse steel demand and chosen capacity ................................................................ 120
Figure 5-21. Web reinforcement ................................................................................................................. 120
7/27/2019 Innovative Pre-Cast Cantilever Constructed Bridge Concept
11/197xi
Figure 5-22. Shear panel tests for normal reinforced concrete and FRC concrete (adapted from Susetyo,
2007) ................................................................................................................................... 122
Figure 5-23. Shear parameter predictions according to CAN/CSA-S6-06................................................. 123
6.0 ANCHORAGE ZONE.....................................................................................................125
Figure 6-1. Top and bottom corner anchorage blisters................................................................................ 126
Figure 6-2. Flow of forces at an intermediate anchorage............................................................................ 127
Figure 6-3. Strut-and-tie model for corner blister (Adapted from Wollman, 1993) ................................... 129
Figure 6-4. Strut-and-tie model for corner blister satisfying static equilibrium; a) 3d isometric view, b) front
view, c) side elevation............... ............... .............. ............... .............. ................ .............. .. 130
Figure 6-5. Jack clearances necessary for installation (adapted from VSL, 2007)..................................... 132
Figure 6-6. Minimum anchorage eccentricities to box girder corner.......................................................... 132
Figure 6-7. Anchorage blister lengths ......................................................................................................... 133
Figure 6-8. Strut-and-tie anchorage model for a bottom tendon................................................................. 133
Figure 6-9. Tension ties linking deviation force to box reinforcement (adapted from Beaupre et al., 1990)134
Figure 6-10. Flow of forces for different reinforcement details ................................................................. 135
Figure 6-11. Anchorage zone reinforcement for critical 19 strand bottom tendon..................................... 136
7.0 FIXED END ABUTMENT .............................................................................................138
Figure 7-1. Bras de la Plaine Bridge, Reunion Island, France (adapted from Tanis, 2003) ....................... 139
Figure 7-2. Ballasted abutment of Bras de la Plaine Bridge (adapted from Tanis, 2003)........................... 139
Figure 7-3. Counterweight abutment concept (superseded)........................................................................ 141
Figure 7-4. Tie-down abutment concept (superseded)................................................................................ 142
Figure 7-5. Proposed conceptual abutment design...................................................................................... 143
8.0 MATERIAL UTILIZATION .........................................................................................145
Figure 8-1. Partial elevation view of Windward Viaduct (adapted from Hawaii DOT, 1991) ................... 146Figure 8-2. Typical cross section of Windward Viaduct (adapted from Hawaii DOT, 1991)..................... 146
Figure 8-3. Post-tensioning arrangement for typical span of Windward Viaduct (adapted from Hawaii DOT,
1991) ................................................................................................................................... 147
Figure 8-4. General arrangement of Islington Avenue Underpass (adapted from MTO, 1990) ................. 148
Figure 8-5. Typical cross section of Islington Avenue Underpass (adapted from MTO, 1990) ................. 148
7/27/2019 Innovative Pre-Cast Cantilever Constructed Bridge Concept
12/197xii
LIST OF TABLES
2.0 BACKGROUND ..................................................................................................................7
Table 2-1. Reference concrete mix quantities (Susetyo, 2007)....................................................................... 9
Table 2-2. Simplified constitutive law for the nominal 80Mpa stress-strain behaviour used in analysis..... 12
3.0 LONGITUDINAL FLEXURE..........................................................................................28Table 3-1. Procedure for calculating the stress in an unbonded tendon due to girder deflections................ 34
Table 3-2. Procedure for calculating uniform applied load corresponding to a desired tendon stress.......... 37
Table 3-3. Estimation of dead load for typical segment................................................................................ 40
Table 3-4. Estimation of superimposed dead load for typical segment ........................................................ 40
Table 3-5. Preliminary prestressing scheme for cantilever tendons based on ultimate capacity .................. 46
Table 3-6. Calculation of long-term bending moment redistribution............................................................ 50
Table 3-7. Preliminary prestressing scheme for continuity tendons based on ultimate capacity.................. 54
Table 3-8. Secondary prestress moment calculation ..................................................................................... 56
Table 3-9. Tendon unit sizes (15mm strands) used for cantilever post-tensioning ....................................... 70
6.0 ANCHORAGE ZONE.....................................................................................................125
Table 6-1. Area of steel required for local spreading reinforcement for top tendons (in mm2).................. 137
Table 6-2. Area of steel required for local spreading reinforcement for bottom tendons (in mm2) ........... 137
8.0 MATERIAL UTILIZATION .........................................................................................145
Table 8-1. Concrete consumption for one span of the Windward Viaduct (Hawaii DOT, 1991) ............... 149
Table 8-2. Concrete consumption for Islington Avenue Underpass (MTO, 1990) ..................................... 149
Table 8-3. Concrete consumption for proposed cantilever box girder........................................................ 149
Table 8-4. Mild reinforcing steel utilization for one span of the Windward Viaduct (Hawaii DOT, 1991)150
Table 8-5. Mild reinforcing steel utilization for Islington Ave Underpass (MTO, 1990)........................... 151
Table 8-6. Mild reinforcing steel utilization for proposed box girder.........................................................151
Table 8-7. Post-tensioning utilization for one span of the Windward Viaduct (Hawaii DOT, 1991) .........152
Table 8-8. Post-tensioning utilization for Islington Ave. Underpass (MTO, 1990).................................... 152
Table 8-9. Post-tensioning utilization for proposed cantilever box girder.................................................. 152
Table 8-10. Transverse prestressing steel utilization for one span of the Windward Viaduct (Hawaii DOT,
1991) ................................................................................................................................... 153
Table 8-11. Transverse prestressing steel utilization for Islington Avenue Underpass (MTO, 1990) ........ 153
Table 8-13. Relative material consumption of proposed box girder...........................................................154
Table 8-12. Transverse prestressing steel utilization for proposed box girder............................................ 154
7/27/2019 Innovative Pre-Cast Cantilever Constructed Bridge Concept
13/197xiii
LIST OF SYMBOLS
Ap area of unbonded prestressing steel
Aps area of prestressing strand
As area of bonded steel
b width of compression flange
bbf width of bottom flange
bc concrete width function for idealized cross section
btf width of top flange
c distance from neutral axis to extreme compression fibre
d depth of cross section; centre-to-centre distance between tension and compression
piles
db diameter of bonded steel
dp distance from centroid of prestressing steel to extreme compression fibre
dv effective shear depth taken as the greater of 0.9d or 0.72h (CSA 23.3-04)
e eccentricity of prestressing steel
eb continuity tendon eccentricity from girder axis
Ec compressive modulus of elasticity of concrete
Ep elastic modulus of prestressing steel
Et
tensile modulus of elasticity of concrete
et cantilever tendon eccentricity from girder axis
fc stress in concrete
Fc force in concrete
fc cylinder compressive strength of concrete
fci initial concrete strength at transfer
long-term effective prestress
fps stress in bonded prestressing strand
fpu ultimate stress of prestressing steel
fpy yield stress of prestressing steel
fse effective stress in bonded pretensioning steel after losses
fsi stress in bonded prestressing strand just prior to transfer
fsy yield stress of bonded reinforcing steel
ft dogbone tensile strength of concrete
fp
7/27/2019 Innovative Pre-Cast Cantilever Constructed Bridge Concept
14/197
7/27/2019 Innovative Pre-Cast Cantilever Constructed Bridge Concept
15/197xv
Ptot total prestress force of unbonded tendons for top and bottom prestressing steel
q uniform load
Q applied load
Qu applied load corresponding to the ultimate state
tbf thickness of bottom flange
ttf thickness of top flange
uf average flexural bond stress of pretensioning strand
V shear
Vc shear resistance attributed to concrete
Vf factored shear demand
Vs shear resistance attributed to transverse reinforcement
w width of web; uniform dead load
x coordinate along longitudinal axis of girder
y elevation in cross section (where bottom fibre elevation is y = 0)
yclo cantilever tip deflection at closure
midspan deflection of continuous system due to long-term creep
ratio of the average stress in compression block to the specified concrete strength
live load factor
prestress load factor
ratio of the depth of compression block to the neutral axis depth
girder deflection
centre-to-centre spacing of transverse ribs
change in beam length due to prestress, dead load, and applied load
elongation of unbonded prestressing steel relative to initial prestress
initial change in beam length due to prestress and dead load
increase in tendon force due to girder deformations
loss in prestress due to superimposed dead load
increase in prestress due to superimposed dead load
change in strain in prestressing steel relative to strain due to initial prestress
strain
bottom fibre strain
ultimate strain of concrete
initial longitudinal strain in concrete at level of prestressing steel
y
1
L
P
1
b
lcp
lcp lp0
lp0
P
P
Pdl
p
b
'c
c0
7/27/2019 Innovative Pre-Cast Cantilever Constructed Bridge Concept
16/197xvi
average initial strain in concrete due to prestress and dead load
strain caused by concrete stress fc
strain in concrete at level of prestressing steel
ultimate compressive strain
strain in prestressing steel
initial strain in prestressing steel
top fibre strain
cracking strain of fibre-reinforced concrete
strain of concrete at mid depth of member
girder slope; angle of principle compressive stress in the web; angle of force
resultant trajectory for arching shear
angle of compression force in slabs due to anchorage bursting forces
angle of compression force in anchorage blister projected onto flange
angle of compression force in anchorage blister projected onto web
coefficient of friction
fully redistributed concrete stress
bottom fibre stress
concrete actual stress at time of closure
concrete stress obtained assuming entire structure is built simultaneously on
falsework
stress in prestressing steel
long-term effective prestress
top fibre stress
curvature
resistance factor for concrete
resistance factor for prestressing steel
resistance factor for steel
cantilever tip rotation at closure
c0 avg,
cf
cp
cu
P
P0
t
't
x
b
fw
b
clo
fa l
p
p
t
c
p
s
clo
7/27/2019 Innovative Pre-Cast Cantilever Constructed Bridge Concept
17/197
1
1.0 INTRODUCTION
In modern urban environments, providing increased capacity on existing roadways and bridges
is a significant challenge. Engineers are faced with several demanding factors including tightconstruction scheduling, the maintenance of traffic in highly travelled corridors, and the creation
of structures that enhance the urban landscape. Precast segmental construction is one solution that
can provide aesthetically pleasing structures that can be erected on difficult construction sites. By
the method of match-cast precasting, segments can be fabricated and prepared off-site and erected
rapidly with minimal effect on traffic.
Traditional methods of bridge construction over high-volume highways generally require lane
closures, traffic delays, and in some cases total road closures and traffic detours. Faced with agrowing economy and increased need for traffic flow reliability, minimum impact construction and
rapid erection for bridge building is becoming more crucial especially in the dense urban
environment. This necessity is realized not only for commuter traffic but also industries that rely
on just-in-time delivery. In Europe, new technologies have been implemented exclusively for the
purpose of fast erection in order to minimize impact of construction. Recent implementations of
fast construction in Ontario has been the use of full-width precast panels for overpass bridge
construction over Highway 401 in the Municipality of Chatham-Kent (Rapoport, 2006), and the
recent use of a self-propelled modular transporter for replacement of an overpass bridge on
Highway 417 in Ottawa (Tinkess, 2007). The implementation of new rapid bridge building
technology in Ontario is a testament to the increasing need of new construction methods for fast,
low-impact construction.
New opportunities for efficient and aesthetically pleasing designs exist through the
development of high performance materials such as high strength concrete. Due to the low water-
to-cement ratio made possible by the inclusion of water reducing admixtures, high strength
concrete exhibits favourable design properties such as higher ultimate stress and stiffer modulus of
elasticity. The impact on design due to these improved material properties is the ability to create
more elegant structural designs that make better use materials through the use of thinner sections
that result in light weight solutions. The increased stiffness of new materials allows engineers to
design more slender shapes that add to the aesthetic transparency of the structure.
7/27/2019 Innovative Pre-Cast Cantilever Constructed Bridge Concept
18/1972
Light weight girders with thin sections for prestressed concrete structures can be made possible
through the use of external unbonded tendons. Flange and web sections with large amounts of
internal bonded steel generally require a significant amount of concrete clear cover solely for the
purpose of durability and corrosion protection. This sacrificial layer of concrete is necessary to
protect the bonded tendons from environmental exposure, but it is not designed as an efficient use
of materials from a strength perspective. By removing the tendons from the concrete section, the
concrete thickness may be reduced to make more efficient use of concrete material, while reducing
the overall weight of the superstructure.
1.1 Statement of Problem
A new minimum-impact solution for rapid highway overpass construction is desired which
makes efficient use of high-performance concrete and external unbonded tendons. The use of
external unbonded tendons in prestressed concrete structures allows for the minimization of
concrete consumption, reduction in dead load due to thinner cross sections, and simplified
construction.
The cantilever method is one type of segmental construction that is self-supporting as it allows
erection of the bridge from the fixed end with no interference with the ground below and no
requirement for falsework. This method is attractive for minimum impact highway overpass
construction since it allows the bridge to be built overhead of the traffic with no requirement for
equipment and machinery below the bridge. For prestressed concrete cantilever-constructed
bridges, cantilever tendons are traditionally designed as internally bonded within the top flange.
Flange thickness is governed by the space required for tendons inside the concrete section, and the
minimum reinforcing steel required for adequate crack control and durability.
Through the development of high-performance materials such as high strength fibre-reinforced
concrete (FRC), improved mechanical properties have been observed to allow engineers greater
possibilities for the design of prestressed concrete structures. Of interest are the benefits to be
gained by the adaptation of high strength FRC and unbonded tendons for use with precast
segmental structures. Quality control of concrete is maximized for precasting in comparison to
cast-in-place concrete, as it is fabricated, cast and cured in a controlled environment. The use of
high strength FRC in combination with external unbonded tendons in concrete structures appears
to be a complimentary pairing of materials as external tendons allow for the minimization of
7/27/2019 Innovative Pre-Cast Cantilever Constructed Bridge Concept
19/1973
concrete consumption and high strength concrete allows for large precompression stresses from
external prestressing.
Precast segmental cantilevered-construction using exclusively external unbonded tendons with
no continuous reinforcing steel is traditionally not done in standard practice. One rare example of
the use of total external unbonded tendons for precast segmental cantilever construction is theSecond Severn Bridge across the River Severn between England and Wales. Although the use of
total external unbonded prestressing for this bridge was primarily due to a Government durability
requirement, this design also simplified deck unit production and enabled thinner webs and flanges
(Mizon, 1997). Extending the use of external unbonded tendons to cantilever construction
potentially provides an opportunity for designers to erect medium span overpass bridges faster, off
the right-of-way, with little or no interference with traffic demands.
1.2 Scope and Objective
The purpose of this study is to develop and validate a design concept using a new application
of external unbonded tendons intended for rapid overpass bridge construction requiring a low-
impact construction technique.
The objectives of this study are as follows:
develop valid design assumptions for consideration of the proposed bridge type
determine the global member response of the superstructure under serviceability and ultimatelimit states
incorporate the use of high performance (80MPa characteristic compressive strength) fibre-
reinforced concrete (FRC) for the design of thin sections to reduce dead load and minimize
reinforcing steel
validate the use of external unbonded tendons as a new application in segmental cantilevered
construction
The member response investigated for this study examines explicitly the effects of longitudinal
flexure, longitudinal shear and transverse flexure due to the force effects of dead load, live load,
and prestress.
Several actions have not been considered explicitly within the scope of this thesis. These
effects include: a) thermal action, b) torsional loads, and c) combined effects of moment, shear, and
torsion. These effects are important to the final design and for the full understanding of structural
behaviour, and could possibly have an impact on the proposed design concept. Future work is
7/27/2019 Innovative Pre-Cast Cantilever Constructed Bridge Concept
20/1974
necessary for the complete validation of the superstructure concept. In addition, the primary focus
of this thesis has been on the design and development of the superstructure system for a light
weight box girder design using high strength FRC. The design and development of the substructure
system is briefly discussed but a detailed design of the substructure is beyond the scope of this
work.
1.3 Thesis Structure
This document consists of 9 chapters. Chapter 1 introduces the topic and establishes the design
motivation for using high performance concrete and external unbonded tendons for the application
of rapid highway bridge construction. Chapter 2 presents background information on material
properties and the proposed structural system for discussion. Chapter 3 describes the behaviour of
unbonded tendons in a system with curtailed prestressing and the design for longitudinal flexure of
the proposed bridge. Chapter 4 discusses the motivation for minimizing the thickness of the top
flange and provides a feasible solution for transverse bending using a thin top flange and transverse
pretensioning. Chapter 5 presents a variation of design models for the analysis of shear behaviour
in concrete structures prestressed with unbonded tendons, and provides the design for shear for the
proposed bridge. Chapter 6 describes the importance of anchorages for girders prestressed with
external tendons, and provides the design developed for anchorage reinforcement. Chapter 7
briefly discusses a design concept for a substructure design. Chapter 8 reviews the material
consumption for the proposed bridge and compares the material consumption of other
conventionally constructed bridge designs. Conclusions for this work are summarized in Chapter
9.
Chapter 2 begins by describing the benefits of FRC and the improved constitutive laws that are
distinctive of the material. The results of a mini experimental study are presented and used for the
basis of a simplified design model for the behaviour of high strength FRC in compression. Typical
highway overpass bridges are discussed and the proposed alternative solution is described and
compared.
Chapter 3 first describes the flexural response of concrete girders prestressed with unbonded
tendons and convenient analysis techniques for the preliminary design of girders. For concrete
girders that are prestressed under the action of self-weight, a reference state of strain is described
that corresponds to the deformations of the girder after jacking. To begin the design process,
conservative preliminary design assumptions are described for the state of stress of the unbonded
7/27/2019 Innovative Pre-Cast Cantilever Constructed Bridge Concept
21/1975
tendons. Following this, the design methodology for cantilever tendons is discussed for a
preliminary estimate of tendon arrangement. The change in structural system due to closure of the
span is discussed and an estimation for long-term redistribution of forces is presented. The design
methodology for continuity tendons is then presented and the effect of the tendon layout on
secondary prestress moments is described. Based on the designed prestress loads, the bottom
flange of the girder is designed for negative bending at the support. The girder behaviour is then
analyzed under factored loads at the ultimate limit state, and unfactored loads for seviceability
performance. Following this, a refinement in tendon stress at the ultimate limit state is investigated
to improve the economy of prestress strand consumption. Finally, the effect of span-to-depth ratio
of the proposed box girder is presented, and a practical range of spans for the proposed box girder
is identified.
Chapter 4 describes the design challenges of satisfying prestress requirements for the thin top
slab in transverse bending due applied vertical loads and prestress forces. The design assumption
of small concrete covers is addressed. The chosen pre-tensioning prestress system is justified based
on the available studies that demonstrate the improved bond strength characteristics between high
strength FRC and 15mm pretensioning strands. The method of analysis to determine the live load
distribution of forces is described. A comparative study between the proposed box girder and an
AASHTO-PCI-ASBI standard box girder (Precast/Prestressed Concrete Institute, 1997) is then
carried out for the validation of the thin top flange design in transverse bending on the basis of
maximum allowable deflections. The deflections and computed stress ranges of the top flange at
service loads is shown for the final design. Finally, a design detail for a proposed PL-2 barrier
defined in the CAN/CSA S6-06 (Canadian Standards Association, 2006) is presented for the
resistance of impact loads.
Chapter 5 begins with a discussion on strut-and-tie models and the description of the funicular
load path in a prestressed girder with curtailed unbonded prestressing tendons. Various approaches
to shear design are discussed based on alternative decompositions of the funicular load path in
concrete structures. A parallel chord model is discussed and the variable angle parallel chord model
used in the CAN/CSA-S6-06 shear provisions is described. Based on the results of a previous
study, an arching model by Noshiravani (2007) is described and compared to the parallel chord
model. For the proposed box girder, a parallel chord model is decided to be most appropriate to
describe the flow of forces in the box girder to transfer vertical loads. The proposed girder is then
7/27/2019 Innovative Pre-Cast Cantilever Constructed Bridge Concept
22/1976
analyzed for the shear demands based on CAN/CSA-S6-06 load configurations. Finally, the design
for web reinforcement is presented based on the parallel chord model.
Chapter 6 begins with a discussion of anchorages for prestressed concrete girders with external
unbonded tendons. The fundamentally different flow of forces within the anchorage zone for an
unbonded tendon is then described in comparison to the anchorage zone of an internal tendon. Athree-dimensional strut-and-tie model is developed for the design of reinforcement required to
anchor an external unbonded tendon at a corner blister. Possible reinforcement detailing based on
the developed truss model is proposed to enable the required flow of forces.
Chapter 7 briefly describes a conceptual abutment design for the proposed bridge. The
abutment must: a) adequately provide anchorage of all cantilever prestressing, b) resist large fixed
end moments due to negative flexure of the superstructure, and c) provide longitudinal flexibility
to allow for thermal movements since the proposed bridge is designed to be monolithic at the
midspan with no expansion joints. A detailed analysis of substructure behaviour is beyond the
scope of this work, however.
Chapter 8 first describes two reference bridges which are used to determine the material
utilization of conventional construction in comparison to the proposed box girder bridge. One
reference bridge is representative of traditional cantilever construction, and the other reference is
representative of a typical highway overpass structure in Ontario. Concrete usage, mild steel
reinforcement utilization, longitudinal prestressing and transverse prestressing steel consumption
quantities are compared.
Chapter 9 concludes with a summary of findings for the design components investigated within
this study. Recommendations for the design of cantilever-constructed bridges prestressed with
unbonded tendons are provided. Advantages of using thin concrete sections with unbonded
tendons are described, and the disadvantages are identified. Necessary future work is discussed for
the full validation of the proposed design concept.
7/27/2019 Innovative Pre-Cast Cantilever Constructed Bridge Concept
23/197
7
2.0 BACKGROUND
This chapter begins by discussing the behaviour of fibre-reinforced concrete (FRC) under axial
compression and axial tension. The results of a small experimental program are presented andbriefly discussed for test specimens fabricated with nominal 80MPa strength concrete, similar to
the concrete intended for design. A simple stress-strain model is developed for the FRC specimens
tested which will be used for the behaviour of concrete throughout the work of this study.
Following this, conventional highway overpass bridge construction using precast components is
described and a description of the proposed bridge concept using precast segments is presented. A
visual comparison of the proposed bridge to a conventional overpass is made to evaluate the
aesthetic qualities of the proposed bridge. Finally, benefits and drawbacks of the proposed bridge
concept are identified.
2.1 Constitutive Laws for High Performance FRC
2.1.1 Compressive Stress-Strain Behaviour
The innovation of material technology has introduced a widespread variety of high
performance concrete materials that have improved mechanical properties over traditional 35MPa
concrete mix designs. High performance concretes (HPC) range to approximately 100MPa and
ultra-high-performance fibre-reinforced concrete (UHPFRC) can be as high as 200MPa. Research
programs have been carried out in many countries to study the behaviour high performance
concrete, leading to significant changes to design codes in several countries. (Paultre et al., 2003).
Design codes are continually evolving documents using a consistent philosophy and the latest
research results, often reflecting the prior state of the art and tradition of the country of origin
(Paultre et al., 2003). However, because concrete is a heterogeneous material without standardized
mixture designs, the compressive stress-strain responses of different concrete mixtures exhibit
significant scatter (Graybeal, 2007). As a result, the empirical definitions of compressive stiffness
of HPC is not entirely consistent among design codes. A comparison of elastic modulus code
definitions and recent results of some researchers are displayed in Figure 2-1below.
7/27/2019 Innovative Pre-Cast Cantilever Constructed Bridge Concept
24/1978
Figure 2-1. Variation in modulus of elasticity with the ultimate compressive strength of concrete
While these design values for elastic stiffness are useful for the calculation of structural
behaviour at the serviceability limit state, very little information is available in the literature that
discusses the post-peak descending branch of FRC. The post peak behaviour is important since it
has a considerable effect on the flexural ductility of a member at the ultimate limit state. Due to the
large amount of scatter in the elastic stiffness constitutive laws, and the lack of information
published on the compressive post-peak response of FRC, compression cylinder tests were
performed to develop a full range stress-strain material model for use in the analysis of the
proposed design.
A concrete mix design was adapted from Susetyo (2007) for a nominal 80MPa FRC containing
1.5% hooked steel fibre volume ratio. The reference concrete mix design is outlined in Table 2-1.
Two compression cylinder specimens were tested for the basis of the simplified stress-strain model
shown in Figure 2-2. The average peak stress was observed to be 74.5MPa, and the average
uncracked elastic modulus was observed to be 43680MPa. A more thorough description of the
experimental program is given in Appendix B. The compression cylinder test results were
compared with a previous study by Chao et al. (2006), who performed cylinder tests for a 75MPaFRC mortar matrix containing no coarse aggregate and 1% steel fibres, and found there was good
agreement in the results. The curves are comprised of a stiff initial ascending branch, followed by
a ductile post-peak descending branch.
0
00001
00002
00003
0000400005
00006
00007
00008
00009
00108060402
80Mpa concrete strengthintended for design
Ec[MPa]
fc[MPa]
Graybeal 2007 (fc 200MPa)
CHBDC 2006 (fc 85MPa)
ACI 1992 (fc 83MPa)
ACI 2005 (fc 40MPa)
Ma et al. 2004 (fc 200MPa)
CEB-FIP 1990 (fc 88MPa)
CSA 2004 (fc 80MPa)
CSA 2004 (fc 40MPa)
7/27/2019 Innovative Pre-Cast Cantilever Constructed Bridge Concept
25/1979
Figure 2-2. Compressive stress-strain relationship for nominal 80MPa FRC test specimens and simplified model
The presence of fibres in the concrete matrix provides excellent confinement which facilitates
the sustained compressive stresses after concrete crushing and allows for significant ductility in the
post-peak response. Figure 2-3displays a failed FRC compression cylinder after the test. Even
after significant post-peak straining, the concrete remains intact and very little spalling from the
surface is observed. The resistance to spalling not only contributes to the strength of FRC at the
ultimate limit state, but it also provides an important benefit for durability of structures as it
improves the performance for frost resistance during freeze-thaw cycles (Xu et al., 1998).
Table 2-1. Reference concrete mix quantities (Susetyo, 2007)
Material Measured Unit Quantity Equivalent Volume
HSF Cement kg 600 0.191
Sand (SSD) kg 1133 0.419
10mm limestones (SSD) kg 802 0.292
Water L 162 0.162
Water Reducer mL 4200 -
Superplasticizer mL 9600 -
Entrapped Air 0.02
Total Volume m3 1.083
0
01
02
03
04
05
06
07
08
09
001
800.0700.0600.0500.0400.0300.0200.0100.00
Chao (2006)
UofT testscompression modeldeveloped for design
# specimens tested = 2E
avg= 43680 MPa
c avg
= 0.00209 mm/mmf
c avg= 74.6 MPa
fc[MPa]
c[mm/mm]
7/27/2019 Innovative Pre-Cast Cantilever Constructed Bridge Concept
26/19710
Figure 2-3. Photo of intensively cracked compression cylinder after failure and significant post-peak straining
2.1.2 Tensile Stress-Strain Behaviour
Since fibre-reinforced concrete exhibits a more ductile tension stress-strain response in
comparison to the brittle nature of normal concrete, the standard ASTM C496 cylinder splitting
test is insufficient to measure the tensile response of FRC. In lieu of the ASTM C496 test,
deformation-controlled dogbone-shaped test specimens loaded in uniaxial tension have been
performed by previous researchers to provide a tensile stress-strain relationship of FRC. Susetyo
(2007) performed a dogbone tension test on the nominal 80MPa FRC similar to the test set-up by
Habel et al. (2006), shown in Figure 2-4below.
7/27/2019 Innovative Pre-Cast Cantilever Constructed Bridge Concept
27/19711
Figure 2-4. a) Dogbone-shaped specimen: dimensions and sensors, b) test set-up of the uniaxial tensile test, showingthe front side of the specimen (adapted from Habel et al., 2006)
The result of the dogbone tension test performed by Susetyo (2007) is presented in Figure 2-5.
The FRC mix design predominantly exhibits tension softening following the occurrence of the first
crack. In general, the formation and opening of one primary crack dominates the post-cracking
response due to the relatively low fibre ratio of 1.5%. Although tension stiffening behaviour is
possible for some FRC mix designs (which generally requires a larger amount of fibres), an
increased consumption of steel fibres to achieve this behaviour is not necessary or economical for
the application of FRC in precast segmental construction. For either dry joints or epoxy joints
between precast units, there is no embedment length of fibres across the joint; therefore, the
smeared tension behaviour of FRC can not be relied upon at the joint interface undergoing flexural
tension forces. For epoxied joints, a brittle tensile behaviour would be expected that is related to
the cracking strength of the concrete, with no contribution of the fibres since internal equilibrium
of tension stresses in the fibres can not be established at the joint. Thus, the inclusion of steel fibres
in the concrete mix is included predominantly for the benefit of controlling plastic shrinkagecracking which replaces typical temperature and shrinkage reinforcement.
Sivakumar (2007) has provided a study which indicates that for a high strength 60MPa silica
fume cement, the inclusion of only 0.5% steel fibres reduces the plastic shrinkage cracking by 49%
compared to the same mix with no fibres. Some hybrid mix designs including steel fibres and
polyester fibres provided a better reduction in shrinkage cracking by 95% while maintaining
a) b)
100
5050
100
5050
100
100
200
LVDT
U4
Front Back
specimen
depth = 50mm
U4 - deformation transducers
LVDT - linear variable differential transformer
7/27/2019 Innovative Pre-Cast Cantilever Constructed Bridge Concept
28/197
7/27/2019 Innovative Pre-Cast Cantilever Constructed Bridge Concept
29/19713
2.2 Typical Modern Highway Overpass Bridge Design Currently in Ontario
Since the 1950s, prestressed concrete bridges have become increasingly popular, and
comprise about two-thirds of all bridges with spans between 18 and 36m (Lounis et al., 1997). The
precast concrete I-girder system represents about 50% of all prestressed concrete bridges built up
until the early 1990s (Dunker et al., 1992). Precast I-girder systems have expanded their use evenfurther in the last thirty years through the concept of spliced girders to extend the span capability
(Rabbat et al., 1999; CPCI, on-line). Although transportation equipment and available cranes
limited the length of precast pretensioned girders to around 34m in the 1960s, precast I-girders
now can be fabricated and transported in lengths of 40m to 50m and weights up to 75 to 90 tonnes
(CPCI, on-line). The standardization of girder sections has led to simplified designs, speed of
construction, and resulted in economy (Rabbat et al., 1999).
Since slab-on-girder bridges represents such a large proportion of bridges of short to medium
spans, precast slab-on-girder bridges will be regarded as a typical highway overpass design for
comparison to the proposed precast segmental box girder design. Both of these systems are precast
and are comparable in terms of low impact of construction solutions. A visual example of a typical
modern slab-on-girder structure is shown in Figure 2-6. This bridge depicts a typical continuous
two-span overpass structure supported by a centre pier in the median of the highway. The
abutments have parallel wingwalls oriented parallel to the axis of the bridge. A concrete parapet
lines the edges of the deck slab along the length of the bridge and continues to the furthest extents
of the wingwalls.
Figure 2-6. Typical slab-on-girder highway underpass built in Markham, Ontario on Highway 407. Photographcourtesy of Scott Steves, 2006.
7/27/2019 Innovative Pre-Cast Cantilever Constructed Bridge Concept
30/19714
To maximize economy, bridge girder sections have been standardized as it provides a basis for
consistency and allows for the multiple reuse of standard forms for several bridge projects (Figg,
1997). The Canadian Precast/Prestressed Concrete Institute (CPCI) provides a range of standard
sections that are available in Canada. A suggested range of spans is provided for the use of each
standard section and a recommended transverse girder spacing is provided in relation to the girder
span length (shown in Figure 2-7). Although this recommendation is given only as a guideline, it
provides engineers with a launching point in which to form a slab-on-girder bridge concept.
Figure 2-7. Recommended girder spacing with respect to span length for standard CPCI precast I-girders (adaptedfrom CPCI, 1996)
In addition to precast concrete girder sections being standardized, the design of slab-on-girder
bridges are also somewhat standardized as they must conform to several geometric constraints for
evaluation using the Simplified Method of Analysis detailed in the CAN/CSA-S6-06 (cl. 5.6.1, cl.
5.7.1). As the Simplified Method outlines an empirical approach to provide safe designs for a wide
range of span lengths and bridge widths, the design of bridges using these methods in general
produces conservative designs.
2.2.1 Standardization of Precast Components
Following the standardization of precast I-girder sections, an evolution for prestressed precast
concrete applications emerged in 1997 for standardized segmental bridge construction (Rabbat et
al., 1999). The AASHTO-PCI-ASBI Segmental Box Girder Standards provided a new product for
grade separations and interchange bridges for span lengths up to 61m (Freyermuth, 1997). Two
families of standard box girder sections exist: one intended for span-by-span construction, and
another intended for cantilever construction. The standard box girder for span-by-span
construction, which has a maximum intended span of 45.7m, exhibits thinner flanges since all post-
7/27/2019 Innovative Pre-Cast Cantilever Constructed Bridge Concept
31/19715
tensioning steel is comprised of external unbonded tendons. The standard box girder for cantilever
construction has thicker top and bottom flange components to incorporate the internal bonded
cantilever and continuity post-tensioning tendons and a thicker web since cantilevering can achieve
longer spans.
Segmental spans can be erected very quickly, typically in a few days, minimizing disruption oftraffic (Figg, 1997). For bridge projects intended for the standard precast box girders, it is generally
anticipated that segments are erected by crane (Freyermuth, 1997). The large amount of work that
can be done off site under a controlled environment is favourable as it reduces the amount of on-
site construction time and permits the best curing conditions for the concrete to achieve a higher
standard of durability. Quality control can be maintained as segments fabricated with high-quality
precast concrete can be erected during non-peak traffic hours when disruption of traffic is kept to
a minimum.
The recommended minimum concrete strength for the standard segmental sections is 34MPa.
In some cases, concrete with a greater compressive strength can be used; however, no changes to
the standard AASHTO-PCI-ASBI cross sectional dimensions and cross sectional thicknesses can
be made to exploit the full potential and economy of high-strength concrete mix designs. These
standard sections have been developed for the application of traditionally reinforced normal
concrete mixes. For the application of high-performance FRC and total external unbonded post-
tensioning, a new structural section, respecting the inherent advantages of FRC, needs to be
developed to achieve economical designs and efficient use of the material.
2.3 Description of the Proposed Segmental Box Girder Concept
The proposed bridge system for precast segmental cantilever construction is a constant depth
single cell box girder with a span-to-depth ratio of 25:1. The box girder cross section is designed
to have thin flanges and thin webs to make efficient use of high-strength concrete and to reduce
dead load of the superstructure. The maximum bridge span considered for this study is 90m for
practical and visual considerations. As a practical consideration, the maximum depth of the girder
segments should be limited to accommodate ease of transportation which is constrained by
standard vertical clearances for existing overpass structures. As a visual consideration, the depth
of the girder should be limited to maintain a reasonable level of slenderness for the design. At a
25:1 span-to-depth ratio, a 90m span length corresponds to a girder depth of 3.6m.
7/27/2019 Innovative Pre-Cast Cantilever Constructed Bridge Concept
32/19716
For the transportation of tall segments, a low-boy trailer is necessary which has a lowered
section of the trailer to reduce the top of the bed to within 610mm of the roadway surface (Precast/
Prestressed Concrete Institute, 1997). The minimum vertical clearance provided under highway
bridges in Ontario is 4.7m for existing structures and 4.8m for new structures (Ontario Ministry of
Transportation, 2002). The barrier walls of the precast segments are intended to be cast-in-place
after the cantilever structure has been closed; therefore, the 3.6m deep girder may be transported
along any major highway in Ontario with a minimum vertical clearance of 490mm for protruding
reinforcing steel for the cast-in-place barrier wall.
A conceptual plan and elevation of the proposed cantilever girder concept for the longest span
considered of 90m is shown in Figure 2-8. The girder is erected segmentally from the abutments,
and each cantilevered segment during construction is post-tensioned to the structure with
permanent external unbonded post-tensioning tendons. The typical precast segment length is 3m
to accommodate standard traffic lane widths for delivery of segments. The minimum vertical
clearance provided over traffic lanes is 5000mm, which is consistent with standard policy for new
structures over roadways for this bridge type (Ontario Ministry of Transportation, 2002) and a
700mm construction tolerance has been provided for safety during construction. The 90m
mainspan is continuous across the abutment face and the short 15m sidespan is ballasted by backfill
material to maintain rotational restraint at the abutment face and to prevent uplift of the backspan.
Figure 2-8. Plan and elevation view of a possible cantilever-constructed overpass bridge
7/27/2019 Innovative Pre-Cast Cantilever Constructed Bridge Concept
33/19717
Assuming the overpass bridge structure services an arterial undivided urban roadway, the
minimum side clearance from the edge of the travelled way to the face of the barrier is 2.0m
(Ontario Ministry of Transportation, 2002). The arrangement of traffic lanes intended for the box
girder bridge consists of two centrally located lanes with a width of 3.6m each, two exterior
shoulders with a width of 2.0m each, and an allowance for traffic barriers with a width of 400mm
each. Therefore, the total cross sectional width of the top flange considered for this design is 12.0m
(shown in Figure 2-9). As there is no thickness requirement t