Innovative Pre-Cast Cantilever Constructed Bridge Concept

Embed Size (px)

Citation preview

  • 7/27/2019 Innovative Pre-Cast Cantilever Constructed Bridge Concept

    1/197

    INNOVATIVE PRE-CAST CANTILEVER CONSTRUCTED BRIDGE CONCEPT

    by

    Brent Tyler Visscher

    A thesis submitted in conformity with the requirements

    for the degree of Master of Applied Science

    Graduate Department of Civil Engineering

    University of Toronto

    Copyright by Brent Tyler Visscher (2008)

  • 7/27/2019 Innovative Pre-Cast Cantilever Constructed Bridge Concept

    2/197ii

    Innovative Pre-cast Cantilever Constructed Bridge Concept

    Brent Tyler Visscher

    Master of Applied Science

    Department of Civil Engineering

    University of Toronto, Canada

    2008

    ABSTRACT

    Minimum impact construction for bridge building is a growing demand in modern urban

    environments. Pre-cast segmental construction is one solution that offers low-impact, economical,

    and aesthetically pleasing bridges. The standardization of pre-cast concrete sections and segments

    has facilitated an improved level of economy in pre-cast construction. Through the development

    of high performance materials such as high strength fibre-reinforced concrete (FRC), further

    economy in pre-cast segmental construction may be realized. The design of pre-cast bridges using

    high-strength FRC and external unbonded tendons for cantilever construction may provide an

    economical, low-impact alternative to overpass bridge design.

    This thesis investigates the feasibility and possible savings that can be realized for a single cell

    box girder bridge with thin concrete sections post-tensioned exclusively with external unbonded

    tendons in the longitudinal direction. A cantilever-constructed single cell box girder with a

    curtailed arrangement of external unbonded tendons is examined.

  • 7/27/2019 Innovative Pre-Cast Cantilever Constructed Bridge Concept

    3/197iii

    ACKNOWLEGEMENTS

    This work has been partially supported by the National Science and Engineering Research

    Council of Canada.

    I would like to thank my supervisor Dr. Paul Gauvreau for his guidance, support, andfellowship throughout the course of this design project.

    Many thanks are owed to my friends and colleagues, especially those within our bridge

    engineering research group, for their helpful discussions and insightful contributions to the

    development of this project: Billy Cheung, Jamie McIntyre, Kris Mermigas, Talayah Noshiravani,

    Graham Potter, Carlene Ramsay, Jason Salonga, and Jimmy Susetyo. Additional thanks go out to

    other graduate students who I have had the pleasure of spending time with throughout my graduate

    study: Jeff Erochko, Hyungjoon Kim, Nabil Mansour, Michael Montgomery, and Lydell Wiebe.

    Special thanks to Jimmy Susetyo for his generous contributions in concrete material design and for

    his laboratory assistance in test specimen preparation. I would like to thank John MacDonald for

    his contribution during cylinder testing.

    Finally, I thank my family for their constant encouragement and support throughout this task.

  • 7/27/2019 Innovative Pre-Cast Cantilever Constructed Bridge Concept

    4/197iv

    TABLE OF CONTENTS

    ABSTRACT. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . ii

    ACKNOWLEGEMENTS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . iii

    TABLE OF CONTENTS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . iv

    LIST OF FIGURES . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . viii

    LIST OF TABLES . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . xii

    LIST OF SYMBOLS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . xiii

    1.0 INTRODUCTION . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .1

    1.1 Statement of Problem . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2

    1.2 Scope and Objective . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3

    1.3 Thesis Structure . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4

    2.0 BACKGROUND . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .7

    2.1 Constitutive Laws for High Performance FRC. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7

    2.1.1 Compressive Stress-Strain Behaviour. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7

    2.1.2 Tensile Stress-Strain Behaviour . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 10

    2.2 Typical Modern Highway Overpass Bridge Design Currently in Ontario . . . . . . . . . . . . . . . . . . . . . . . . . . 13

    2.2.1 Standardization of Precast Components . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 14

    2.3 Description of the Proposed Segmental Box Girder Concept . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 15

    2.4 Visual Comparison of Proposed Box Girder with Typical Slab-on-Girder Overpass . . . . . . . . . . . . . . . . . 22

    2.5 Benefits and Drawbacks of the Proposed Design . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 25

    2.5.1 Benefits . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 25

    2.5.2 Drawbacks. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 27

    3.0 LONGITUDINAL FLEXURE. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .28

    3.1 Introduction. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 28

    3.2 Moment-Curvature Response . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 29

    3.3 Behaviour of Unbonded Tendons . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 30

    3.3.1 Reference State of Strain. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 31

    3.3.2 Long-Term Effective Prestress . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 32

    3.4 Tendon Stress Calculation Methods . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 333.5 Preliminary Design Assumptions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 37

    3.6 Preliminary Design Methodology for Cantilever Tendons. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 39

    3.6.1 Loading . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 39

    3.6.2 Ultimate Moment Resistance . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 42

    3.6.3 Sizing of Cantilever Tendons . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 44

    3.7 Change in Structural System. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 47

    3.8 Preliminary Design Methodology for Continuity Tendons . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 50

  • 7/27/2019 Innovative Pre-Cast Cantilever Constructed Bridge Concept

    5/197v

    3.8.1 Ultimate Moment Resistance . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 50

    3.8.2 Spreading of Forces. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 51

    3.8.3 Sizing of Continuity Tendons . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 53

    3.8.4 Secondary Prestress Moment due to Continuity Tendons . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 55

    3.9 Bottom Flange Sizing . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 58

    3.10 Prestress Distribution . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 60

    3.11 Ultimate Limit State . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 63

    3.12 Serviceability Limit States . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 64

    3.12.1 Construction . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 65

    3.12.2 Cracking . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 65

    3.12.3 Global Deflection . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 67

    3.13 Refinement in Tendon Stress . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 67

    3.13.1 Ductility of Fibre-Reinforced Concrete . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 67

    3.13.2 Deformation Capacity. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 69

    3.13.3 Example of Tendon Stress Increase for Negative Bending . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 70

    3.13.4 Discussion . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 72

    3.14 Global System Considerations . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 73

    3.14.1 Span-to-Depth Ratio for Constant Depth Box Girder. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 73

    3.14.2 Range of Spans . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 74

    3.14.3 Alternative Girder Designs . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 76

    4.0 TRANSVERSE FLEXURE . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .78

    4.1 Introduction. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 78

    4.2 Typical Transverse Prestressing for Segmental Bridges. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 79

    4.3 Prestressing Concept for Light Weight Slab Design . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 79

    4.3.1 Post-Tensioning . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 804.3.2 Pretensioning. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 81

    4.4 Bond Strength of 15mm Pretensioning Strands in FRC . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 82

    4.4.1 Mechanisms of Bond . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 82

    4.4.2 Development of Stress in a 15mm Pretensioning Strand . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 83

    4.4.3 Improvement of Bond Strength due to High Strength FRC . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 84

    4.5 Methods of Analysis . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 85

    4.5.1 Grillage Analysis. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 86

    4.5.2 Frame Analysis . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 88

    4.6 Comparative Study for Transverse Stiffness . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 88

    4.6.1 Cross Sections. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 89

    4.6.2 Material Definitions used in Analysis. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 91

    4.6.3 Loading . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 92

    4.6.4 Deflections . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 92

    4.7 Prestress Moments . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 94

    4.8 Service Loads . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 95

    4.9 Cross Section Design and Layout . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 97

    4.9.1 Transverse Rib Proportions. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 97

  • 7/27/2019 Innovative Pre-Cast Cantilever Constructed Bridge Concept

    6/197vi

    4.9.2 Web Spacing . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 98

    4.10 Design for Barrier Impact Loads . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 99

    5.0 SHEAR. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .101

    5.1 Introduction to Strut-and-Tie Models . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 101

    5.2 Funicular Load Path for Girders Prestressed with Curtailed Tendons . . . . . . . . . . . . . . . . . . . . . . . . . . . . 103

    5.3 Parallel Chord Truss Models . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1075.4 Arching Models . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 110

    5.4.1 Tied Arch Model (Noshiravani, 2007) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 111

    5.5 Preliminary Design Model . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 116

    5.6 Opening of Joints in Segmental Bridges. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 118

    5.7 Design of Web Reinforcement . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 119

    5.7.1 Comparison to CAN/CSA-S6-06 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 120

    6.0 ANCHORAGE ZONE. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .125

    6.1 Introduction. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 125

    6.2 Flow of Forces . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 126

    6.3 Strut-and-Tie Model for Local Spreading of Forces. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 127

    6.3.1 Anchorage of External Unbonded Tendons in Slab Blisters (Wollman, 1993) . . . . . . . . . . . . . . . . . . 127

    6.3.2 Design Model for External Tendon Blisters . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 129

    6.4 Detailing . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 133

    6.5 Reinforcement. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 135

    7.0 FIXED END ABUTMENT . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .138

    7.1 Introduction. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 138

    7.2 Bras de la Plaine Bridge, France (Tanis, 2003) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 138

    7.3 Flexible Supports . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 140

    7.4 Design Approach . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 140

    7.4.1 Preliminary Design Alternatives. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 141

    7.4.2 Recommended Design . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 142

    7.5 Sizing of Flexible Piles . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 143

    7.6 Future Work . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 144

    8.0 MATERIAL UTILIZATION . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .145

    8.1 Reference Bridges . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 145

    8.1.1 Windward Viaduct, Interstate Route H-3, Hawaii, USA (Hawaii DOT, 1991) . . . . . . . . . . . . . . . . . . 1458.1.2 Hwy 407 - Islington Avenue Underpass, Toronto, Canada (MTO, 1990) . . . . . . . . . . . . . . . . . . . . . . 147

    8.2 Concrete Consumption . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 148

    8.3 Mild Reinforcing Steel Utilization . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 150

    8.4 Longitudinal Post-Tensioning Utilization. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 152

    8.5 Transverse Post-Tensioning Utilization . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 153

    8.6 Summary . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 154

    9.0 CONCLUSIONS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .155

  • 7/27/2019 Innovative Pre-Cast Cantilever Constructed Bridge Concept

    7/197vii

    9.1 Longitudinal Design . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 155

    9.2 Transverse Design. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 156

    9.3 Shear Design . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 156

    9.4 Anchorage Zone Design . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 156

    9.5 Economy . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 157

    9.6 Future Work . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 157

    10.0 REFERENCES. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .159

    APPENDIX A - DESIGN DRAWINGS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .164

    APPENDIX B - MATERIAL TESTING . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .175

    APPENDIX C - CAN/CSA-S6-06 SHEAR PROVISIONS . . . . . . . . . . . . . . . . . . . . . . . .178

    CURRICULUM VITAE. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .180

  • 7/27/2019 Innovative Pre-Cast Cantilever Constructed Bridge Concept

    8/197viii

    LIST OF FIGURES

    2.0 BACKGROUND ..................................................................................................................7

    Figure 2-1. Variation in modulus of elasticity with the ultimate compressive strength of concrete............... 8

    Figure 2-2. Compressive stress-strain relationship for nominal 80MPa FRC test specimens and simplified

    model ...................................................................................................................................... 9

    Figure 2-3. Photo of intensively cracked compression cylinder after failure and significant post-peakstraining ................................................................................................................................ 10

    Figure 2-4. a) Dogbone-shaped specimen: dimensions and sensors, b) test set-up of the uniaxial tensile test,

    showing the front side of the specimen (adapted from Habel et al., 2006) .............. ............ 11

    Figure 2-5. Tensile stress-strain relationship for nominal 80MPa FRC test specimens and simplified model:12

    Figure 2-6. Typical slab-on-girder highway underpass built in Markham, Ontario on Highway 407.

    Photograph courtesy of Scott Steves, 2006............... ................ ............. ................ .............. . 13

    Figure 2-7. Recommended girder spacing with respect to span length for standard CPCI precast I-girders

    (adapted from CPCI, 1996)....... .............. ............... ............... ............... ............... ............... ... 14

    Figure 2-8. Plan and elevation view of a possible cantilever-constructed overpass bridge.......................... 16

    Figure 2-9. Cross section and details of the constant depth box girder shown in Figure 2-8 ....................... 17

    Figure 2-10. Typical standard segment components of proposed box girder concept.................................. 18

    Figure 2-11. Top flange supported by steel struts, a) example shown of Shibakawa Viaduct, Japan (photo

    courtesy of Takashi Kosaka, 2006), b) rendering of proposed 90m overpass structure ....... 19

    Figure 2-12. Second Severn Bridge, a) total external unbonded prestressing tendons, b) cantilever

    construction showing bulkhead face of segment with no continuous bonded steel across the

    joint and no internal bonded tendons (adapted from Mizon, 1997).............. ............... ......... 20

    Figure 2-13. Possible tendon arrangement shown for half the span (symmetrical about span centreline)... 21

    Figure 2-14. Numbering scheme for segment labels..................................................................................... 22

    Figure 2-15. Rendered perspective views on typical highway overpass construction using precast CPCI

    girders (left) and proposed cantilever-constructed single cell box girder (right) as seen on an

    overcast day....... ................ ............... .............. ................ .............. ............... ............... ........... 23

    Figure 2-16. Deck cross sections for a) two-span precast CPCI girder overpass and b) proposed cantilever-

    constructed single cell box girder. ........................................................................................ 23

    Figure 2-17. Visual slenderness attained through shadow casting for a superstructure with a a) small deck

    overhang and b) large deck overhang. ............... .................. .............. ............... .............. ...... 25

    Figure 2-18. Collapse slab-on-girder bridge after being struck by tractor-trailer (adapted from El-Tawil,

    2005) ..................................................................................................................................... 26

    Figure 2-19. Elevation (1:2500 scale) showing the result of elevating the overpass road grade.................. 27

    3.0 LONGITUDINAL FLEXURE..........................................................................................28

    Figure 3-1. Idealization of box cross section for analysis of longitudinal flexure........................................ 29

    Figure 3-2. Internal lever arm from tendon elevation to the compression flange, a) for a continuously guidedtendon, b) for a tendon attached only at discrete locations........... ................ ............... ......... 30

    Figure 3-3. Strain Distribution at ultimate limit state (adapted from Naaman, 2006) .................................. 31

    Figure 3-4. Material strains due to equilibrium in the reference state and in the ultimate state ................... 31

    Figure 3-5. Family of moment-curvature responses for a specific cross section and varying prestress force

    assuming a concentric prestress .............. ............... ............... ............... ............... ............... ... 35

    Figure 3-6. Iterative method behaviour for tendon stress calculation for a) girder impending plastic hinging,

    b) girder experiencing plastic hinging ................. ................ .............. ............... .............. ...... 36

    Figure 3-7. Iterative method solution for obtaining tendon stress by incrementing applied load................. 37

  • 7/27/2019 Innovative Pre-Cast Cantilever Constructed Bridge Concept

    9/197ix

    Figure 3-8. Typical segment cross section .................................................................................................... 40

    Figure 3-9. Comparison of live load models defined in CAN/CSA-S6-06 .................................................. 41

    Figure 3-10. ULS bending moments on continuous girder........................................................................... 42

    Figure 3-11. Cantilever prestress concepts for haunched and constant depth girders .................................. 44

    Figure 3-12. Preliminary ULS demand and capacity for cantilever PT........................................................ 45

    Figure 3-13. Layout of cantilever tendons .................................................................................................... 46

    Figure 3-14. Redistribution of forces through concrete creep due to change in structural system (adapted fromPodolny et al., 1982)............................................................................................................. 48

    Figure 3-15. Time-dependent creep coefficient assuming t0= 28 days, a) for 75 year period, b) for 5 year

    period ............. .............. ................ .............. ............... .............. ............... .............. ................ . 49

    Figure 3-16. Sectional forces due to prestressing with top and bottom tendons........................................... 51

    Figure 3-17. Moment development length, la, due to anchorage of continuity tendon (adapted from Menn,

    1990) ..................................................................................................................................... 52

    Figure 3-18. Required moment development length for a girder post-tensioned with unbonded tendons... 53

    Figure 3-19. Layout of continuity tendons.................................................................................................... 54

    Figure 3-20. Preliminary ULS demand and capacity for continuity tendons................................................ 55

    Figure 3-21. Secondary prestress moment due to prestressed continuity tendon ......................................... 57Figure 3-22. Ultimate state of stress for section with undersized bottom flange.......................................... 59

    Figure 3-23. Appropriately sized bottom flange thickness for negative bending at ULS............................. 59

    Figure 3-24. Primary prestress force distribution.......................................................................................... 61

    Figure 3-25. Girder response for varying prestress force.............................................................................. 63

    Figure 3-26. Girder response at ULS (half span shown)............................................................................... 64

    Figure 3-27. Girder response at SLS (half span shown) ............................................................................... 66

    Figure 3-28. Stress-strain response of FRC and typical normal-weight concrete......................................... 68

    Figure 3-29. FRC comparison for total moment-curvature response in negative bending........................... 69

    Figure 3-30. Plastic hinging in negative moment regions............................................................................. 70

    Figure 3-31. 90m span with midspan hinge when load is close to failure.................................................... 71

    Figure 3-32. Stresses in unbonded tendons for curtailed prestressing. a) change in tendon stresses during

    construction due to the addition of segments and post-tensioning, b) change in tendon stresses

    due to the application of increasing uniform load until failure.......... ............... ............... ..... 72

    Figure 3-33. Ultimate behaviour for a continuous girder using unbonded draped tendons (adapted from

    Muller et al., 1990) ............................................................................................................... 73

    Figure 3-34. Material consumption for varying span/depth ratios................................................................ 74

    Figure 3-35. Concept comparison of haunched girder and constant depth girder elevation......................... 76

    4.0 TRANSVERSE FLEXURE ..............................................................................................78

    Figure 4-1. Possible pretensioning arrangement........................................................................................... 82

    Figure 4-2. Bond mechanisms between FRC and 15mm pretensioning strand (adapted from Chao, 2006) 83

    Figure 4-3. Idealized strand stress profile in a pretensioned strand under applied load (adapted from Kahn,

    2002) ..................................................................................................................................... 83

    Figure 4-4. Generalized frame element properties for grillage analysis (adapted from Menn, 1990).......... 87

    Figure 4-5. 3-dimensional grillage model..................................................................................................... 88

    Figure 4-6. Comparison of top flange thicknesses of AASHTO-PCI-ASBI standard box girder examples

    (adapted from Prestress/Precast Concrete Institute, 1997) ............. .............. ............... ......... 90

    Figure 4-7. Cross section dimensions for typical segment............................................................................ 91

  • 7/27/2019 Innovative Pre-Cast Cantilever Constructed Bridge Concept

    10/197x

    Figure 4-8. Assumed stress-strain material properties for investigation of transverse stiffness................... 91

    Figure 4-9. Live load models for transverse load analysis............................................................................ 92

    Figure 4-10. Vertical slab deflection envelope due to live load, AASHTO-PCI-ASBI box girder .............. 93

    Figure 4-11. Edge beam stiffening ................................................................................................................ 93

    Figure 4-12. Vertical slab deflection envelope due to live load of proposed box girder: a) thin slab stiffened

    with transverse ribs only, b) thin slab stiffened with transverse ribs and longitudinal edge

    beam............... ............... ............... .............. ............... .............. .............. ............... ................ . 94

    Figure 4-13. Moment distribution due to non-concentric prestress applied at the transfer length ............... 95

    Figure 4-14. Total transverse bending moments for transverse flexure........................................................ 96

    Figure 4-15. SLS top slab stress ranges at the extreme fibre due to service loading.................................... 97

    Figure 4-16. Longitudinal section for a typical segment .............................................................................. 98

    Figure 4-17. Web spacing requirements........................................................................................................ 99

    Figure 4-18. Truss model for basis of barrier reinforcement ........................................................................ 99

    Figure 4-19. PL-2 barrier detail for impact loading.................................................................................... 100

    5.0 SHEAR..............................................................................................................................101

    Figure 5-1. 45 degree truss model (adapted from Ritter, 1899) .................................................................. 102Figure 5-2. Possible truss models for girders with unbonded and bonded prestressing steel (adapted from

    Gauvreau, 1993).......... ............... ............... .............. ................ .............. ............... ............... 102

    Figure 5-3. Alternative girder designs to resist applied load Q .................................................................. 104

    Figure 5-4. Effect of prestress arrangement on funicular compression chord ............................................ 105

    Figure 5-5. Funicular shape of compression spine for continuous cantilever girder with curtailed tendons106

    Figure 5-6. Strut-and-tie model for a fully prestressed flanged section. a) simplified model; b) through d)

    detailed model of web, top flange and bottom flange, respectively (adapted from Schlaich et

    al., 1989) ............................................................................................................................. 108

    Figure 5-7. Variable angle truss model (adapted from Collins et al., 1997) ............................................... 109

    Figure 5-8. Arch spreading of forces for a rectangular section (adapted from Schlaich et al., 1989) ........ 110

    Figure 5-9. Comparison of tied arch model for a rectangular section and a flanged section (adapted from

    Noshiravani, 2006)...... ............... .............. ............... .............. ................ .............. ................ 112

    Figure 5-10. Girder dimensions (adapted from Noshiravani, 2007) ........................................................... 113

    Figure 5-11. Girder cross section and web reinforcement (adapted from Noshiravani, 2007)................... 113

    Figure 5-12. Tied arch model for load stage corresponding to flexural cracking (adapted from Noshiravani,

    2007) ................................................................................................................................... 113

    Figure 5-13. Tied arch model for load stage corresponding to ULS (adapted from Noshiravani, 2007) ... 114

    Figure 5-14. Crack pattern and alternative parallel chord model for load stage corresponding to flexural

    cracking............................................................................................................................... 115

    Figure 5-15. Crack pattern and alternative parallel chord model for load stage corresponding to ULS .... 116

    Figure 5-16. Truss model for shear design. a) fully prestressed state for continuous beam; b) modified modelto account for flange decompression (formation of plastic hinge) .............. .............. ......... 117

    Figure 5-17. Prestress forces applied to truss model in Figure 5-16 for each applied anchorage force ..... 117

    Figure 5-18. Incorrect hanger reinforcement model for shear stresses crossing an open joint (adapted from

    Virlogeux, 1993) ................................................................................................................. 118

    Figure 5-19. ULS Combination 1 maximum shear demands...................................................................... 119

    Figure 5-20. ULS transverse steel demand and chosen capacity ................................................................ 120

    Figure 5-21. Web reinforcement ................................................................................................................. 120

  • 7/27/2019 Innovative Pre-Cast Cantilever Constructed Bridge Concept

    11/197xi

    Figure 5-22. Shear panel tests for normal reinforced concrete and FRC concrete (adapted from Susetyo,

    2007) ................................................................................................................................... 122

    Figure 5-23. Shear parameter predictions according to CAN/CSA-S6-06................................................. 123

    6.0 ANCHORAGE ZONE.....................................................................................................125

    Figure 6-1. Top and bottom corner anchorage blisters................................................................................ 126

    Figure 6-2. Flow of forces at an intermediate anchorage............................................................................ 127

    Figure 6-3. Strut-and-tie model for corner blister (Adapted from Wollman, 1993) ................................... 129

    Figure 6-4. Strut-and-tie model for corner blister satisfying static equilibrium; a) 3d isometric view, b) front

    view, c) side elevation............... ............... .............. ............... .............. ................ .............. .. 130

    Figure 6-5. Jack clearances necessary for installation (adapted from VSL, 2007)..................................... 132

    Figure 6-6. Minimum anchorage eccentricities to box girder corner.......................................................... 132

    Figure 6-7. Anchorage blister lengths ......................................................................................................... 133

    Figure 6-8. Strut-and-tie anchorage model for a bottom tendon................................................................. 133

    Figure 6-9. Tension ties linking deviation force to box reinforcement (adapted from Beaupre et al., 1990)134

    Figure 6-10. Flow of forces for different reinforcement details ................................................................. 135

    Figure 6-11. Anchorage zone reinforcement for critical 19 strand bottom tendon..................................... 136

    7.0 FIXED END ABUTMENT .............................................................................................138

    Figure 7-1. Bras de la Plaine Bridge, Reunion Island, France (adapted from Tanis, 2003) ....................... 139

    Figure 7-2. Ballasted abutment of Bras de la Plaine Bridge (adapted from Tanis, 2003)........................... 139

    Figure 7-3. Counterweight abutment concept (superseded)........................................................................ 141

    Figure 7-4. Tie-down abutment concept (superseded)................................................................................ 142

    Figure 7-5. Proposed conceptual abutment design...................................................................................... 143

    8.0 MATERIAL UTILIZATION .........................................................................................145

    Figure 8-1. Partial elevation view of Windward Viaduct (adapted from Hawaii DOT, 1991) ................... 146Figure 8-2. Typical cross section of Windward Viaduct (adapted from Hawaii DOT, 1991)..................... 146

    Figure 8-3. Post-tensioning arrangement for typical span of Windward Viaduct (adapted from Hawaii DOT,

    1991) ................................................................................................................................... 147

    Figure 8-4. General arrangement of Islington Avenue Underpass (adapted from MTO, 1990) ................. 148

    Figure 8-5. Typical cross section of Islington Avenue Underpass (adapted from MTO, 1990) ................. 148

  • 7/27/2019 Innovative Pre-Cast Cantilever Constructed Bridge Concept

    12/197xii

    LIST OF TABLES

    2.0 BACKGROUND ..................................................................................................................7

    Table 2-1. Reference concrete mix quantities (Susetyo, 2007)....................................................................... 9

    Table 2-2. Simplified constitutive law for the nominal 80Mpa stress-strain behaviour used in analysis..... 12

    3.0 LONGITUDINAL FLEXURE..........................................................................................28Table 3-1. Procedure for calculating the stress in an unbonded tendon due to girder deflections................ 34

    Table 3-2. Procedure for calculating uniform applied load corresponding to a desired tendon stress.......... 37

    Table 3-3. Estimation of dead load for typical segment................................................................................ 40

    Table 3-4. Estimation of superimposed dead load for typical segment ........................................................ 40

    Table 3-5. Preliminary prestressing scheme for cantilever tendons based on ultimate capacity .................. 46

    Table 3-6. Calculation of long-term bending moment redistribution............................................................ 50

    Table 3-7. Preliminary prestressing scheme for continuity tendons based on ultimate capacity.................. 54

    Table 3-8. Secondary prestress moment calculation ..................................................................................... 56

    Table 3-9. Tendon unit sizes (15mm strands) used for cantilever post-tensioning ....................................... 70

    6.0 ANCHORAGE ZONE.....................................................................................................125

    Table 6-1. Area of steel required for local spreading reinforcement for top tendons (in mm2).................. 137

    Table 6-2. Area of steel required for local spreading reinforcement for bottom tendons (in mm2) ........... 137

    8.0 MATERIAL UTILIZATION .........................................................................................145

    Table 8-1. Concrete consumption for one span of the Windward Viaduct (Hawaii DOT, 1991) ............... 149

    Table 8-2. Concrete consumption for Islington Avenue Underpass (MTO, 1990) ..................................... 149

    Table 8-3. Concrete consumption for proposed cantilever box girder........................................................ 149

    Table 8-4. Mild reinforcing steel utilization for one span of the Windward Viaduct (Hawaii DOT, 1991)150

    Table 8-5. Mild reinforcing steel utilization for Islington Ave Underpass (MTO, 1990)........................... 151

    Table 8-6. Mild reinforcing steel utilization for proposed box girder.........................................................151

    Table 8-7. Post-tensioning utilization for one span of the Windward Viaduct (Hawaii DOT, 1991) .........152

    Table 8-8. Post-tensioning utilization for Islington Ave. Underpass (MTO, 1990).................................... 152

    Table 8-9. Post-tensioning utilization for proposed cantilever box girder.................................................. 152

    Table 8-10. Transverse prestressing steel utilization for one span of the Windward Viaduct (Hawaii DOT,

    1991) ................................................................................................................................... 153

    Table 8-11. Transverse prestressing steel utilization for Islington Avenue Underpass (MTO, 1990) ........ 153

    Table 8-13. Relative material consumption of proposed box girder...........................................................154

    Table 8-12. Transverse prestressing steel utilization for proposed box girder............................................ 154

  • 7/27/2019 Innovative Pre-Cast Cantilever Constructed Bridge Concept

    13/197xiii

    LIST OF SYMBOLS

    Ap area of unbonded prestressing steel

    Aps area of prestressing strand

    As area of bonded steel

    b width of compression flange

    bbf width of bottom flange

    bc concrete width function for idealized cross section

    btf width of top flange

    c distance from neutral axis to extreme compression fibre

    d depth of cross section; centre-to-centre distance between tension and compression

    piles

    db diameter of bonded steel

    dp distance from centroid of prestressing steel to extreme compression fibre

    dv effective shear depth taken as the greater of 0.9d or 0.72h (CSA 23.3-04)

    e eccentricity of prestressing steel

    eb continuity tendon eccentricity from girder axis

    Ec compressive modulus of elasticity of concrete

    Ep elastic modulus of prestressing steel

    Et

    tensile modulus of elasticity of concrete

    et cantilever tendon eccentricity from girder axis

    fc stress in concrete

    Fc force in concrete

    fc cylinder compressive strength of concrete

    fci initial concrete strength at transfer

    long-term effective prestress

    fps stress in bonded prestressing strand

    fpu ultimate stress of prestressing steel

    fpy yield stress of prestressing steel

    fse effective stress in bonded pretensioning steel after losses

    fsi stress in bonded prestressing strand just prior to transfer

    fsy yield stress of bonded reinforcing steel

    ft dogbone tensile strength of concrete

    fp

  • 7/27/2019 Innovative Pre-Cast Cantilever Constructed Bridge Concept

    14/197

  • 7/27/2019 Innovative Pre-Cast Cantilever Constructed Bridge Concept

    15/197xv

    Ptot total prestress force of unbonded tendons for top and bottom prestressing steel

    q uniform load

    Q applied load

    Qu applied load corresponding to the ultimate state

    tbf thickness of bottom flange

    ttf thickness of top flange

    uf average flexural bond stress of pretensioning strand

    V shear

    Vc shear resistance attributed to concrete

    Vf factored shear demand

    Vs shear resistance attributed to transverse reinforcement

    w width of web; uniform dead load

    x coordinate along longitudinal axis of girder

    y elevation in cross section (where bottom fibre elevation is y = 0)

    yclo cantilever tip deflection at closure

    midspan deflection of continuous system due to long-term creep

    ratio of the average stress in compression block to the specified concrete strength

    live load factor

    prestress load factor

    ratio of the depth of compression block to the neutral axis depth

    girder deflection

    centre-to-centre spacing of transverse ribs

    change in beam length due to prestress, dead load, and applied load

    elongation of unbonded prestressing steel relative to initial prestress

    initial change in beam length due to prestress and dead load

    increase in tendon force due to girder deformations

    loss in prestress due to superimposed dead load

    increase in prestress due to superimposed dead load

    change in strain in prestressing steel relative to strain due to initial prestress

    strain

    bottom fibre strain

    ultimate strain of concrete

    initial longitudinal strain in concrete at level of prestressing steel

    y

    1

    L

    P

    1

    b

    lcp

    lcp lp0

    lp0

    P

    P

    Pdl

    p

    b

    'c

    c0

  • 7/27/2019 Innovative Pre-Cast Cantilever Constructed Bridge Concept

    16/197xvi

    average initial strain in concrete due to prestress and dead load

    strain caused by concrete stress fc

    strain in concrete at level of prestressing steel

    ultimate compressive strain

    strain in prestressing steel

    initial strain in prestressing steel

    top fibre strain

    cracking strain of fibre-reinforced concrete

    strain of concrete at mid depth of member

    girder slope; angle of principle compressive stress in the web; angle of force

    resultant trajectory for arching shear

    angle of compression force in slabs due to anchorage bursting forces

    angle of compression force in anchorage blister projected onto flange

    angle of compression force in anchorage blister projected onto web

    coefficient of friction

    fully redistributed concrete stress

    bottom fibre stress

    concrete actual stress at time of closure

    concrete stress obtained assuming entire structure is built simultaneously on

    falsework

    stress in prestressing steel

    long-term effective prestress

    top fibre stress

    curvature

    resistance factor for concrete

    resistance factor for prestressing steel

    resistance factor for steel

    cantilever tip rotation at closure

    c0 avg,

    cf

    cp

    cu

    P

    P0

    t

    't

    x

    b

    fw

    b

    clo

    fa l

    p

    p

    t

    c

    p

    s

    clo

  • 7/27/2019 Innovative Pre-Cast Cantilever Constructed Bridge Concept

    17/197

    1

    1.0 INTRODUCTION

    In modern urban environments, providing increased capacity on existing roadways and bridges

    is a significant challenge. Engineers are faced with several demanding factors including tightconstruction scheduling, the maintenance of traffic in highly travelled corridors, and the creation

    of structures that enhance the urban landscape. Precast segmental construction is one solution that

    can provide aesthetically pleasing structures that can be erected on difficult construction sites. By

    the method of match-cast precasting, segments can be fabricated and prepared off-site and erected

    rapidly with minimal effect on traffic.

    Traditional methods of bridge construction over high-volume highways generally require lane

    closures, traffic delays, and in some cases total road closures and traffic detours. Faced with agrowing economy and increased need for traffic flow reliability, minimum impact construction and

    rapid erection for bridge building is becoming more crucial especially in the dense urban

    environment. This necessity is realized not only for commuter traffic but also industries that rely

    on just-in-time delivery. In Europe, new technologies have been implemented exclusively for the

    purpose of fast erection in order to minimize impact of construction. Recent implementations of

    fast construction in Ontario has been the use of full-width precast panels for overpass bridge

    construction over Highway 401 in the Municipality of Chatham-Kent (Rapoport, 2006), and the

    recent use of a self-propelled modular transporter for replacement of an overpass bridge on

    Highway 417 in Ottawa (Tinkess, 2007). The implementation of new rapid bridge building

    technology in Ontario is a testament to the increasing need of new construction methods for fast,

    low-impact construction.

    New opportunities for efficient and aesthetically pleasing designs exist through the

    development of high performance materials such as high strength concrete. Due to the low water-

    to-cement ratio made possible by the inclusion of water reducing admixtures, high strength

    concrete exhibits favourable design properties such as higher ultimate stress and stiffer modulus of

    elasticity. The impact on design due to these improved material properties is the ability to create

    more elegant structural designs that make better use materials through the use of thinner sections

    that result in light weight solutions. The increased stiffness of new materials allows engineers to

    design more slender shapes that add to the aesthetic transparency of the structure.

  • 7/27/2019 Innovative Pre-Cast Cantilever Constructed Bridge Concept

    18/1972

    Light weight girders with thin sections for prestressed concrete structures can be made possible

    through the use of external unbonded tendons. Flange and web sections with large amounts of

    internal bonded steel generally require a significant amount of concrete clear cover solely for the

    purpose of durability and corrosion protection. This sacrificial layer of concrete is necessary to

    protect the bonded tendons from environmental exposure, but it is not designed as an efficient use

    of materials from a strength perspective. By removing the tendons from the concrete section, the

    concrete thickness may be reduced to make more efficient use of concrete material, while reducing

    the overall weight of the superstructure.

    1.1 Statement of Problem

    A new minimum-impact solution for rapid highway overpass construction is desired which

    makes efficient use of high-performance concrete and external unbonded tendons. The use of

    external unbonded tendons in prestressed concrete structures allows for the minimization of

    concrete consumption, reduction in dead load due to thinner cross sections, and simplified

    construction.

    The cantilever method is one type of segmental construction that is self-supporting as it allows

    erection of the bridge from the fixed end with no interference with the ground below and no

    requirement for falsework. This method is attractive for minimum impact highway overpass

    construction since it allows the bridge to be built overhead of the traffic with no requirement for

    equipment and machinery below the bridge. For prestressed concrete cantilever-constructed

    bridges, cantilever tendons are traditionally designed as internally bonded within the top flange.

    Flange thickness is governed by the space required for tendons inside the concrete section, and the

    minimum reinforcing steel required for adequate crack control and durability.

    Through the development of high-performance materials such as high strength fibre-reinforced

    concrete (FRC), improved mechanical properties have been observed to allow engineers greater

    possibilities for the design of prestressed concrete structures. Of interest are the benefits to be

    gained by the adaptation of high strength FRC and unbonded tendons for use with precast

    segmental structures. Quality control of concrete is maximized for precasting in comparison to

    cast-in-place concrete, as it is fabricated, cast and cured in a controlled environment. The use of

    high strength FRC in combination with external unbonded tendons in concrete structures appears

    to be a complimentary pairing of materials as external tendons allow for the minimization of

  • 7/27/2019 Innovative Pre-Cast Cantilever Constructed Bridge Concept

    19/1973

    concrete consumption and high strength concrete allows for large precompression stresses from

    external prestressing.

    Precast segmental cantilevered-construction using exclusively external unbonded tendons with

    no continuous reinforcing steel is traditionally not done in standard practice. One rare example of

    the use of total external unbonded tendons for precast segmental cantilever construction is theSecond Severn Bridge across the River Severn between England and Wales. Although the use of

    total external unbonded prestressing for this bridge was primarily due to a Government durability

    requirement, this design also simplified deck unit production and enabled thinner webs and flanges

    (Mizon, 1997). Extending the use of external unbonded tendons to cantilever construction

    potentially provides an opportunity for designers to erect medium span overpass bridges faster, off

    the right-of-way, with little or no interference with traffic demands.

    1.2 Scope and Objective

    The purpose of this study is to develop and validate a design concept using a new application

    of external unbonded tendons intended for rapid overpass bridge construction requiring a low-

    impact construction technique.

    The objectives of this study are as follows:

    develop valid design assumptions for consideration of the proposed bridge type

    determine the global member response of the superstructure under serviceability and ultimatelimit states

    incorporate the use of high performance (80MPa characteristic compressive strength) fibre-

    reinforced concrete (FRC) for the design of thin sections to reduce dead load and minimize

    reinforcing steel

    validate the use of external unbonded tendons as a new application in segmental cantilevered

    construction

    The member response investigated for this study examines explicitly the effects of longitudinal

    flexure, longitudinal shear and transverse flexure due to the force effects of dead load, live load,

    and prestress.

    Several actions have not been considered explicitly within the scope of this thesis. These

    effects include: a) thermal action, b) torsional loads, and c) combined effects of moment, shear, and

    torsion. These effects are important to the final design and for the full understanding of structural

    behaviour, and could possibly have an impact on the proposed design concept. Future work is

  • 7/27/2019 Innovative Pre-Cast Cantilever Constructed Bridge Concept

    20/1974

    necessary for the complete validation of the superstructure concept. In addition, the primary focus

    of this thesis has been on the design and development of the superstructure system for a light

    weight box girder design using high strength FRC. The design and development of the substructure

    system is briefly discussed but a detailed design of the substructure is beyond the scope of this

    work.

    1.3 Thesis Structure

    This document consists of 9 chapters. Chapter 1 introduces the topic and establishes the design

    motivation for using high performance concrete and external unbonded tendons for the application

    of rapid highway bridge construction. Chapter 2 presents background information on material

    properties and the proposed structural system for discussion. Chapter 3 describes the behaviour of

    unbonded tendons in a system with curtailed prestressing and the design for longitudinal flexure of

    the proposed bridge. Chapter 4 discusses the motivation for minimizing the thickness of the top

    flange and provides a feasible solution for transverse bending using a thin top flange and transverse

    pretensioning. Chapter 5 presents a variation of design models for the analysis of shear behaviour

    in concrete structures prestressed with unbonded tendons, and provides the design for shear for the

    proposed bridge. Chapter 6 describes the importance of anchorages for girders prestressed with

    external tendons, and provides the design developed for anchorage reinforcement. Chapter 7

    briefly discusses a design concept for a substructure design. Chapter 8 reviews the material

    consumption for the proposed bridge and compares the material consumption of other

    conventionally constructed bridge designs. Conclusions for this work are summarized in Chapter

    9.

    Chapter 2 begins by describing the benefits of FRC and the improved constitutive laws that are

    distinctive of the material. The results of a mini experimental study are presented and used for the

    basis of a simplified design model for the behaviour of high strength FRC in compression. Typical

    highway overpass bridges are discussed and the proposed alternative solution is described and

    compared.

    Chapter 3 first describes the flexural response of concrete girders prestressed with unbonded

    tendons and convenient analysis techniques for the preliminary design of girders. For concrete

    girders that are prestressed under the action of self-weight, a reference state of strain is described

    that corresponds to the deformations of the girder after jacking. To begin the design process,

    conservative preliminary design assumptions are described for the state of stress of the unbonded

  • 7/27/2019 Innovative Pre-Cast Cantilever Constructed Bridge Concept

    21/1975

    tendons. Following this, the design methodology for cantilever tendons is discussed for a

    preliminary estimate of tendon arrangement. The change in structural system due to closure of the

    span is discussed and an estimation for long-term redistribution of forces is presented. The design

    methodology for continuity tendons is then presented and the effect of the tendon layout on

    secondary prestress moments is described. Based on the designed prestress loads, the bottom

    flange of the girder is designed for negative bending at the support. The girder behaviour is then

    analyzed under factored loads at the ultimate limit state, and unfactored loads for seviceability

    performance. Following this, a refinement in tendon stress at the ultimate limit state is investigated

    to improve the economy of prestress strand consumption. Finally, the effect of span-to-depth ratio

    of the proposed box girder is presented, and a practical range of spans for the proposed box girder

    is identified.

    Chapter 4 describes the design challenges of satisfying prestress requirements for the thin top

    slab in transverse bending due applied vertical loads and prestress forces. The design assumption

    of small concrete covers is addressed. The chosen pre-tensioning prestress system is justified based

    on the available studies that demonstrate the improved bond strength characteristics between high

    strength FRC and 15mm pretensioning strands. The method of analysis to determine the live load

    distribution of forces is described. A comparative study between the proposed box girder and an

    AASHTO-PCI-ASBI standard box girder (Precast/Prestressed Concrete Institute, 1997) is then

    carried out for the validation of the thin top flange design in transverse bending on the basis of

    maximum allowable deflections. The deflections and computed stress ranges of the top flange at

    service loads is shown for the final design. Finally, a design detail for a proposed PL-2 barrier

    defined in the CAN/CSA S6-06 (Canadian Standards Association, 2006) is presented for the

    resistance of impact loads.

    Chapter 5 begins with a discussion on strut-and-tie models and the description of the funicular

    load path in a prestressed girder with curtailed unbonded prestressing tendons. Various approaches

    to shear design are discussed based on alternative decompositions of the funicular load path in

    concrete structures. A parallel chord model is discussed and the variable angle parallel chord model

    used in the CAN/CSA-S6-06 shear provisions is described. Based on the results of a previous

    study, an arching model by Noshiravani (2007) is described and compared to the parallel chord

    model. For the proposed box girder, a parallel chord model is decided to be most appropriate to

    describe the flow of forces in the box girder to transfer vertical loads. The proposed girder is then

  • 7/27/2019 Innovative Pre-Cast Cantilever Constructed Bridge Concept

    22/1976

    analyzed for the shear demands based on CAN/CSA-S6-06 load configurations. Finally, the design

    for web reinforcement is presented based on the parallel chord model.

    Chapter 6 begins with a discussion of anchorages for prestressed concrete girders with external

    unbonded tendons. The fundamentally different flow of forces within the anchorage zone for an

    unbonded tendon is then described in comparison to the anchorage zone of an internal tendon. Athree-dimensional strut-and-tie model is developed for the design of reinforcement required to

    anchor an external unbonded tendon at a corner blister. Possible reinforcement detailing based on

    the developed truss model is proposed to enable the required flow of forces.

    Chapter 7 briefly describes a conceptual abutment design for the proposed bridge. The

    abutment must: a) adequately provide anchorage of all cantilever prestressing, b) resist large fixed

    end moments due to negative flexure of the superstructure, and c) provide longitudinal flexibility

    to allow for thermal movements since the proposed bridge is designed to be monolithic at the

    midspan with no expansion joints. A detailed analysis of substructure behaviour is beyond the

    scope of this work, however.

    Chapter 8 first describes two reference bridges which are used to determine the material

    utilization of conventional construction in comparison to the proposed box girder bridge. One

    reference bridge is representative of traditional cantilever construction, and the other reference is

    representative of a typical highway overpass structure in Ontario. Concrete usage, mild steel

    reinforcement utilization, longitudinal prestressing and transverse prestressing steel consumption

    quantities are compared.

    Chapter 9 concludes with a summary of findings for the design components investigated within

    this study. Recommendations for the design of cantilever-constructed bridges prestressed with

    unbonded tendons are provided. Advantages of using thin concrete sections with unbonded

    tendons are described, and the disadvantages are identified. Necessary future work is discussed for

    the full validation of the proposed design concept.

  • 7/27/2019 Innovative Pre-Cast Cantilever Constructed Bridge Concept

    23/197

    7

    2.0 BACKGROUND

    This chapter begins by discussing the behaviour of fibre-reinforced concrete (FRC) under axial

    compression and axial tension. The results of a small experimental program are presented andbriefly discussed for test specimens fabricated with nominal 80MPa strength concrete, similar to

    the concrete intended for design. A simple stress-strain model is developed for the FRC specimens

    tested which will be used for the behaviour of concrete throughout the work of this study.

    Following this, conventional highway overpass bridge construction using precast components is

    described and a description of the proposed bridge concept using precast segments is presented. A

    visual comparison of the proposed bridge to a conventional overpass is made to evaluate the

    aesthetic qualities of the proposed bridge. Finally, benefits and drawbacks of the proposed bridge

    concept are identified.

    2.1 Constitutive Laws for High Performance FRC

    2.1.1 Compressive Stress-Strain Behaviour

    The innovation of material technology has introduced a widespread variety of high

    performance concrete materials that have improved mechanical properties over traditional 35MPa

    concrete mix designs. High performance concretes (HPC) range to approximately 100MPa and

    ultra-high-performance fibre-reinforced concrete (UHPFRC) can be as high as 200MPa. Research

    programs have been carried out in many countries to study the behaviour high performance

    concrete, leading to significant changes to design codes in several countries. (Paultre et al., 2003).

    Design codes are continually evolving documents using a consistent philosophy and the latest

    research results, often reflecting the prior state of the art and tradition of the country of origin

    (Paultre et al., 2003). However, because concrete is a heterogeneous material without standardized

    mixture designs, the compressive stress-strain responses of different concrete mixtures exhibit

    significant scatter (Graybeal, 2007). As a result, the empirical definitions of compressive stiffness

    of HPC is not entirely consistent among design codes. A comparison of elastic modulus code

    definitions and recent results of some researchers are displayed in Figure 2-1below.

  • 7/27/2019 Innovative Pre-Cast Cantilever Constructed Bridge Concept

    24/1978

    Figure 2-1. Variation in modulus of elasticity with the ultimate compressive strength of concrete

    While these design values for elastic stiffness are useful for the calculation of structural

    behaviour at the serviceability limit state, very little information is available in the literature that

    discusses the post-peak descending branch of FRC. The post peak behaviour is important since it

    has a considerable effect on the flexural ductility of a member at the ultimate limit state. Due to the

    large amount of scatter in the elastic stiffness constitutive laws, and the lack of information

    published on the compressive post-peak response of FRC, compression cylinder tests were

    performed to develop a full range stress-strain material model for use in the analysis of the

    proposed design.

    A concrete mix design was adapted from Susetyo (2007) for a nominal 80MPa FRC containing

    1.5% hooked steel fibre volume ratio. The reference concrete mix design is outlined in Table 2-1.

    Two compression cylinder specimens were tested for the basis of the simplified stress-strain model

    shown in Figure 2-2. The average peak stress was observed to be 74.5MPa, and the average

    uncracked elastic modulus was observed to be 43680MPa. A more thorough description of the

    experimental program is given in Appendix B. The compression cylinder test results were

    compared with a previous study by Chao et al. (2006), who performed cylinder tests for a 75MPaFRC mortar matrix containing no coarse aggregate and 1% steel fibres, and found there was good

    agreement in the results. The curves are comprised of a stiff initial ascending branch, followed by

    a ductile post-peak descending branch.

    0

    00001

    00002

    00003

    0000400005

    00006

    00007

    00008

    00009

    00108060402

    80Mpa concrete strengthintended for design

    Ec[MPa]

    fc[MPa]

    Graybeal 2007 (fc 200MPa)

    CHBDC 2006 (fc 85MPa)

    ACI 1992 (fc 83MPa)

    ACI 2005 (fc 40MPa)

    Ma et al. 2004 (fc 200MPa)

    CEB-FIP 1990 (fc 88MPa)

    CSA 2004 (fc 80MPa)

    CSA 2004 (fc 40MPa)

  • 7/27/2019 Innovative Pre-Cast Cantilever Constructed Bridge Concept

    25/1979

    Figure 2-2. Compressive stress-strain relationship for nominal 80MPa FRC test specimens and simplified model

    The presence of fibres in the concrete matrix provides excellent confinement which facilitates

    the sustained compressive stresses after concrete crushing and allows for significant ductility in the

    post-peak response. Figure 2-3displays a failed FRC compression cylinder after the test. Even

    after significant post-peak straining, the concrete remains intact and very little spalling from the

    surface is observed. The resistance to spalling not only contributes to the strength of FRC at the

    ultimate limit state, but it also provides an important benefit for durability of structures as it

    improves the performance for frost resistance during freeze-thaw cycles (Xu et al., 1998).

    Table 2-1. Reference concrete mix quantities (Susetyo, 2007)

    Material Measured Unit Quantity Equivalent Volume

    HSF Cement kg 600 0.191

    Sand (SSD) kg 1133 0.419

    10mm limestones (SSD) kg 802 0.292

    Water L 162 0.162

    Water Reducer mL 4200 -

    Superplasticizer mL 9600 -

    Entrapped Air 0.02

    Total Volume m3 1.083

    0

    01

    02

    03

    04

    05

    06

    07

    08

    09

    001

    800.0700.0600.0500.0400.0300.0200.0100.00

    Chao (2006)

    UofT testscompression modeldeveloped for design

    # specimens tested = 2E

    avg= 43680 MPa

    c avg

    = 0.00209 mm/mmf

    c avg= 74.6 MPa

    fc[MPa]

    c[mm/mm]

  • 7/27/2019 Innovative Pre-Cast Cantilever Constructed Bridge Concept

    26/19710

    Figure 2-3. Photo of intensively cracked compression cylinder after failure and significant post-peak straining

    2.1.2 Tensile Stress-Strain Behaviour

    Since fibre-reinforced concrete exhibits a more ductile tension stress-strain response in

    comparison to the brittle nature of normal concrete, the standard ASTM C496 cylinder splitting

    test is insufficient to measure the tensile response of FRC. In lieu of the ASTM C496 test,

    deformation-controlled dogbone-shaped test specimens loaded in uniaxial tension have been

    performed by previous researchers to provide a tensile stress-strain relationship of FRC. Susetyo

    (2007) performed a dogbone tension test on the nominal 80MPa FRC similar to the test set-up by

    Habel et al. (2006), shown in Figure 2-4below.

  • 7/27/2019 Innovative Pre-Cast Cantilever Constructed Bridge Concept

    27/19711

    Figure 2-4. a) Dogbone-shaped specimen: dimensions and sensors, b) test set-up of the uniaxial tensile test, showingthe front side of the specimen (adapted from Habel et al., 2006)

    The result of the dogbone tension test performed by Susetyo (2007) is presented in Figure 2-5.

    The FRC mix design predominantly exhibits tension softening following the occurrence of the first

    crack. In general, the formation and opening of one primary crack dominates the post-cracking

    response due to the relatively low fibre ratio of 1.5%. Although tension stiffening behaviour is

    possible for some FRC mix designs (which generally requires a larger amount of fibres), an

    increased consumption of steel fibres to achieve this behaviour is not necessary or economical for

    the application of FRC in precast segmental construction. For either dry joints or epoxy joints

    between precast units, there is no embedment length of fibres across the joint; therefore, the

    smeared tension behaviour of FRC can not be relied upon at the joint interface undergoing flexural

    tension forces. For epoxied joints, a brittle tensile behaviour would be expected that is related to

    the cracking strength of the concrete, with no contribution of the fibres since internal equilibrium

    of tension stresses in the fibres can not be established at the joint. Thus, the inclusion of steel fibres

    in the concrete mix is included predominantly for the benefit of controlling plastic shrinkagecracking which replaces typical temperature and shrinkage reinforcement.

    Sivakumar (2007) has provided a study which indicates that for a high strength 60MPa silica

    fume cement, the inclusion of only 0.5% steel fibres reduces the plastic shrinkage cracking by 49%

    compared to the same mix with no fibres. Some hybrid mix designs including steel fibres and

    polyester fibres provided a better reduction in shrinkage cracking by 95% while maintaining

    a) b)

    100

    5050

    100

    5050

    100

    100

    200

    LVDT

    U4

    Front Back

    specimen

    depth = 50mm

    U4 - deformation transducers

    LVDT - linear variable differential transformer

  • 7/27/2019 Innovative Pre-Cast Cantilever Constructed Bridge Concept

    28/197

  • 7/27/2019 Innovative Pre-Cast Cantilever Constructed Bridge Concept

    29/19713

    2.2 Typical Modern Highway Overpass Bridge Design Currently in Ontario

    Since the 1950s, prestressed concrete bridges have become increasingly popular, and

    comprise about two-thirds of all bridges with spans between 18 and 36m (Lounis et al., 1997). The

    precast concrete I-girder system represents about 50% of all prestressed concrete bridges built up

    until the early 1990s (Dunker et al., 1992). Precast I-girder systems have expanded their use evenfurther in the last thirty years through the concept of spliced girders to extend the span capability

    (Rabbat et al., 1999; CPCI, on-line). Although transportation equipment and available cranes

    limited the length of precast pretensioned girders to around 34m in the 1960s, precast I-girders

    now can be fabricated and transported in lengths of 40m to 50m and weights up to 75 to 90 tonnes

    (CPCI, on-line). The standardization of girder sections has led to simplified designs, speed of

    construction, and resulted in economy (Rabbat et al., 1999).

    Since slab-on-girder bridges represents such a large proportion of bridges of short to medium

    spans, precast slab-on-girder bridges will be regarded as a typical highway overpass design for

    comparison to the proposed precast segmental box girder design. Both of these systems are precast

    and are comparable in terms of low impact of construction solutions. A visual example of a typical

    modern slab-on-girder structure is shown in Figure 2-6. This bridge depicts a typical continuous

    two-span overpass structure supported by a centre pier in the median of the highway. The

    abutments have parallel wingwalls oriented parallel to the axis of the bridge. A concrete parapet

    lines the edges of the deck slab along the length of the bridge and continues to the furthest extents

    of the wingwalls.

    Figure 2-6. Typical slab-on-girder highway underpass built in Markham, Ontario on Highway 407. Photographcourtesy of Scott Steves, 2006.

  • 7/27/2019 Innovative Pre-Cast Cantilever Constructed Bridge Concept

    30/19714

    To maximize economy, bridge girder sections have been standardized as it provides a basis for

    consistency and allows for the multiple reuse of standard forms for several bridge projects (Figg,

    1997). The Canadian Precast/Prestressed Concrete Institute (CPCI) provides a range of standard

    sections that are available in Canada. A suggested range of spans is provided for the use of each

    standard section and a recommended transverse girder spacing is provided in relation to the girder

    span length (shown in Figure 2-7). Although this recommendation is given only as a guideline, it

    provides engineers with a launching point in which to form a slab-on-girder bridge concept.

    Figure 2-7. Recommended girder spacing with respect to span length for standard CPCI precast I-girders (adaptedfrom CPCI, 1996)

    In addition to precast concrete girder sections being standardized, the design of slab-on-girder

    bridges are also somewhat standardized as they must conform to several geometric constraints for

    evaluation using the Simplified Method of Analysis detailed in the CAN/CSA-S6-06 (cl. 5.6.1, cl.

    5.7.1). As the Simplified Method outlines an empirical approach to provide safe designs for a wide

    range of span lengths and bridge widths, the design of bridges using these methods in general

    produces conservative designs.

    2.2.1 Standardization of Precast Components

    Following the standardization of precast I-girder sections, an evolution for prestressed precast

    concrete applications emerged in 1997 for standardized segmental bridge construction (Rabbat et

    al., 1999). The AASHTO-PCI-ASBI Segmental Box Girder Standards provided a new product for

    grade separations and interchange bridges for span lengths up to 61m (Freyermuth, 1997). Two

    families of standard box girder sections exist: one intended for span-by-span construction, and

    another intended for cantilever construction. The standard box girder for span-by-span

    construction, which has a maximum intended span of 45.7m, exhibits thinner flanges since all post-

  • 7/27/2019 Innovative Pre-Cast Cantilever Constructed Bridge Concept

    31/19715

    tensioning steel is comprised of external unbonded tendons. The standard box girder for cantilever

    construction has thicker top and bottom flange components to incorporate the internal bonded

    cantilever and continuity post-tensioning tendons and a thicker web since cantilevering can achieve

    longer spans.

    Segmental spans can be erected very quickly, typically in a few days, minimizing disruption oftraffic (Figg, 1997). For bridge projects intended for the standard precast box girders, it is generally

    anticipated that segments are erected by crane (Freyermuth, 1997). The large amount of work that

    can be done off site under a controlled environment is favourable as it reduces the amount of on-

    site construction time and permits the best curing conditions for the concrete to achieve a higher

    standard of durability. Quality control can be maintained as segments fabricated with high-quality

    precast concrete can be erected during non-peak traffic hours when disruption of traffic is kept to

    a minimum.

    The recommended minimum concrete strength for the standard segmental sections is 34MPa.

    In some cases, concrete with a greater compressive strength can be used; however, no changes to

    the standard AASHTO-PCI-ASBI cross sectional dimensions and cross sectional thicknesses can

    be made to exploit the full potential and economy of high-strength concrete mix designs. These

    standard sections have been developed for the application of traditionally reinforced normal

    concrete mixes. For the application of high-performance FRC and total external unbonded post-

    tensioning, a new structural section, respecting the inherent advantages of FRC, needs to be

    developed to achieve economical designs and efficient use of the material.

    2.3 Description of the Proposed Segmental Box Girder Concept

    The proposed bridge system for precast segmental cantilever construction is a constant depth

    single cell box girder with a span-to-depth ratio of 25:1. The box girder cross section is designed

    to have thin flanges and thin webs to make efficient use of high-strength concrete and to reduce

    dead load of the superstructure. The maximum bridge span considered for this study is 90m for

    practical and visual considerations. As a practical consideration, the maximum depth of the girder

    segments should be limited to accommodate ease of transportation which is constrained by

    standard vertical clearances for existing overpass structures. As a visual consideration, the depth

    of the girder should be limited to maintain a reasonable level of slenderness for the design. At a

    25:1 span-to-depth ratio, a 90m span length corresponds to a girder depth of 3.6m.

  • 7/27/2019 Innovative Pre-Cast Cantilever Constructed Bridge Concept

    32/19716

    For the transportation of tall segments, a low-boy trailer is necessary which has a lowered

    section of the trailer to reduce the top of the bed to within 610mm of the roadway surface (Precast/

    Prestressed Concrete Institute, 1997). The minimum vertical clearance provided under highway

    bridges in Ontario is 4.7m for existing structures and 4.8m for new structures (Ontario Ministry of

    Transportation, 2002). The barrier walls of the precast segments are intended to be cast-in-place

    after the cantilever structure has been closed; therefore, the 3.6m deep girder may be transported

    along any major highway in Ontario with a minimum vertical clearance of 490mm for protruding

    reinforcing steel for the cast-in-place barrier wall.

    A conceptual plan and elevation of the proposed cantilever girder concept for the longest span

    considered of 90m is shown in Figure 2-8. The girder is erected segmentally from the abutments,

    and each cantilevered segment during construction is post-tensioned to the structure with

    permanent external unbonded post-tensioning tendons. The typical precast segment length is 3m

    to accommodate standard traffic lane widths for delivery of segments. The minimum vertical

    clearance provided over traffic lanes is 5000mm, which is consistent with standard policy for new

    structures over roadways for this bridge type (Ontario Ministry of Transportation, 2002) and a

    700mm construction tolerance has been provided for safety during construction. The 90m

    mainspan is continuous across the abutment face and the short 15m sidespan is ballasted by backfill

    material to maintain rotational restraint at the abutment face and to prevent uplift of the backspan.

    Figure 2-8. Plan and elevation view of a possible cantilever-constructed overpass bridge

  • 7/27/2019 Innovative Pre-Cast Cantilever Constructed Bridge Concept

    33/19717

    Assuming the overpass bridge structure services an arterial undivided urban roadway, the

    minimum side clearance from the edge of the travelled way to the face of the barrier is 2.0m

    (Ontario Ministry of Transportation, 2002). The arrangement of traffic lanes intended for the box

    girder bridge consists of two centrally located lanes with a width of 3.6m each, two exterior

    shoulders with a width of 2.0m each, and an allowance for traffic barriers with a width of 400mm

    each. Therefore, the total cross sectional width of the top flange considered for this design is 12.0m

    (shown in Figure 2-9). As there is no thickness requirement t