WWW.EYALSYSTEMS.CO.IL 6401136 -04 Eyal Systems Ltd R.
Instruction Manual
Shahak6+ - Collective Protection System
R. Eyal Systems ltd – Collective Protection Systems
- 1 -
Electric Blower
Outlet hose (Grey)
Inlet hose (Transparent)
Filter
System Components
Power Switch
Electric Blower
Power Supply
Power Socket
Manual Blower connector (2 parts)
Manual Backup Blower
)פתח יציאת -האוויר מהממ"דנמצא על הקיר.
הרחק מהמערכת(
מאוורר חיווי
)פתח יציאת -האוויר מהממ"דנמצא על הקיר.
הרחק מהמערכת(
מאוורר חיווי
)פתח יציאת -האוויר מהממ"דנמצא על הקיר.
הרחק מהמערכת(
מאוורר חיווי
Over Pressure Valve
Inlet Valve
Inlet Valve cap
Air Outlet
Indication fan
R. Eyal Systems ltd – Collective Protection Systems
- 2 -
Dear Customer
Eyal Systems thanks you for choosing to install the Shahak6+ collective
protection system in your home. This System, installed in the Mamad
(Protective room) will enable you and your close ones a safe and comfortable
stay without the need of protective gas masks, in case of a chemical attack.
We recommend reading this instruction manual carefully in order to be ready
to use it in case of an emergency.
Table of contents
Chapter Page
1. Safety Instructions 3
2. Operational Principle 3
3. Operating Instructions 5
4. Preparing the system
(Transition from routine time to emergency) 10
5. Transition back to routine 10
6. System Maintenance 11
7. Testing the system 11
8. Contact information 12
9. warranty certificate 13
R. Eyal Systems ltd – Collective Protection Systems
- 3 -
Safety Instructions
This system should be operated as instructed in this manual only.
Before connecting to power, check the integrity of the system, power
cable and power plug. Make sure there is no water damage, rodent
damage or anything else that looks unusual.
If the power cable or power adaptor is damaged, it must not be used, and
should be replaced only by a qualified technician.
Children must be denied access to the system and its components.
If any damages or malfunctions occur, do not attempt to repair and please
contact Eyal Systems office for professional assistance.
R. Eyal Systems ltd – Collective Protection Systems
- 4 -
Operational Principle
Shahak6+ Collective protection systems allow you and your loved ones to
remain safe and comfortable for a long duration of time:
1. Inserts filtered air into the protected room.
2. Builds an overpressure that prevents dangerous chemicals and gases from
penetrating the room.
3. Removes high levels of CO2 from the room, caused by breathing, and
supplies fresh Oxygen constantly.
4. Two Valves (Inlet Valve & Outlet Valve) protect both the occupants of the
room and the system from shockwaves caused by nearby blasts.
5. The outlet valve regulates the pressure in the room keeping a steady and
comfortable room pressure.
6. If the fan on the Outlet valve is spinning, the room is in the correct
pressure, and the system is functioning properly. The room is safe, and no
gas masks are required.
When the fan on the outlet valve is spinning – the room is safe !
Toxic air
Shahak6+ system supplies clean filtered air into the room
The room is kept in a steady overpressure – air can only
flow outwards, keeping toxic air out.
The outlet valve releases surplus
air, keeping a constant safe
room pressure.
Safe room illustration
R. Eyal Systems ltd – Collective Protection Systems
- 5 -
Operating instructions
1. Release the fastening straps. Pull the filter so that both sides are
within reach (as shown in drawing below).
Remove the Incoming air hose (Transparent, folded over the Manual
blower)
2. Remove the top & bottom caps from the filter. The open by turning
them counterclockwise.
R. Eyal Systems ltd – Collective Protection Systems
- 6 -
3. Remove the cap from the incoming valve
(On the wall, next to the system)
4. Connect the inlet hose (transparent) to the top of the filter. Firmly
tighten clockwise until you feel a locking click.
5. Connect the free end of the inlet hose (transparent) to the incoming
air valve and pull on the tightening arms firmly.
2
1 3
R. Eyal Systems ltd – Collective Protection Systems
- 7 -
6. Connect the free end of the outlet hose (grey) to the bottom of the
filter. Firmly tighten clockwise.
R. Eyal Systems ltd – Collective Protection Systems
- 8 -
Option A – Electrical Blower (Normal)
Follow these steps unless there is a power outage
7.A. Assure the grey outlet hose is connected to both the filter and the electric blower (located in the back of the cabinet)
8.A. Connect the electric blower to the power outlet using the power
cord. Turn the blower on with the red switch located on the front panel of the blower. The switch will light up.
9.A. A spinning fan on the over pressure valve (located on the wall,
opposite of the cabinet) indicates that the system is operating properly. If the fan is still, check if the door and window are closed tightly, and review stages 1 thru 10 again.
R. Eyal Systems ltd – Collective Protection Systems
- 9 -
Emergency manual operation –Option B In case of a power outage, the manual blower should be connected and
operated manually. Connect the systems as instructed in stages 1-6
7.B. Remove the Manual Blower and the manual blower holder (shown in
picture below) from the system. Connect the holder to the fixer (located on the wall below the system) by sliding it downwards.
8.B. Disconnect the hose from the electric blower an insert the end into the back of the manual blower.
9.B. Connect the blower to the holder using the connection buttons.
R. Eyal Systems ltd – Collective Protection Systems
- 11 -
10.B. The blower should be operated constantly with a back and forth motion in a rate of approx. 22 cycles per minute (full cycle every 3 seconds). If done correctly, the indication fan on the outlet valve should spin continuously.
If the power comes back on, return to normal electric operation as described in phase 7A-9A
R. Eyal Systems ltd – Collective Protection Systems
- 11 -
6. Maintenance
Shahak6+ system does not require any maintenance.
It is recommended that once every two years, a qualified technician from the
manufacturer would check the system and test it to assure it is working
properly, and that there is no damage to the system or the room.
7. Contact Information:
R. Eyal Systems Ltd.
Remez 11, Afula 1855511
Tel: 04-6401136
Fax: 04-6401137
Email: [email protected]
Website: WWW.EyalSystems.co.il
WWW.EYALSYSTEMS.CO.IL 6401136 -04 Eyal Systems Ltd R.
8. Warranty
1. The warranty applies only to a system that has been installed
and checked by a qualified technician.
2. The warranty applied for all parts of the system for a duration of
10 years from the date of installation.
3. The filter must stay closed and sealed.
Removal of the seal voids the warrany
4. The company is not liable in the following cases:
Damage caused by vandalism.
Damage caused by ill treatment or not according to the
instructions in this pamphlet.
Damage cause by fire, water damage, lightning or electrical
surge.
5. Any attempt to remove elements from the system or detach the
cabinet from the wall will void the warranty.
6. Only a sign warranty is valid from the date of the signature.
7. This pamphlet should be kept inside the cabinet at all times.
_________________ __________________ ____________
Date of Installation Technician name Signature