Integration of Value Engineering

Embed Size (px)

Citation preview

  • 7/31/2019 Integration of Value Engineering

    1/17

    Office of Acquisition and Property Management

    Integration of ValueEngineering (VE)

    and theFive-Year Planning Process

  • 7/31/2019 Integration of Value Engineering

    2/17

  • 7/31/2019 Integration of Value Engineering

    3/17

    Background VE Requirements

    Public Law 104-106 (1996) requires all agenciesestablish a VE program

    OMB Circular A-131 requires VE to reduce nonessential

    procurement and program costs Threshold is $1 million for projects and programs

    DOI submits annual VE accomplishment report

    submitted to OMB by December 31 of each year

    DOIs requirements are in Department Manual 369

    Department of the InteriorDecember 2007

  • 7/31/2019 Integration of Value Engineering

    4/17

    Background - Value EngineeringPresentation Overview

    Public Law 104-106 defines VE as:

    An analysis of the functions of a program,

    project, system, product, item of equipment,building, facility, service, or supply of anexecutive agency, performed by qualified

    agency or contractor personnel, directed atimproving performance, reliability, quality, safety,and life cycle costs.''

    Department of the InteriorDecember 2007

  • 7/31/2019 Integration of Value Engineering

    5/17

    Background - Value Engineering

    VE applies to all projects, programs,equipment

    Studies can be performed by in-house orcontractor personnel

    VE can be applied at any point in projector program life cycle

    Department of the InteriorDecember 2007

  • 7/31/2019 Integration of Value Engineering

    6/17

    Background - Value Engineering

    Construction projects

    VE usually applied at conceptual and design stages

    May be applied more than once on an individual

    project

    Objective is to:

    Ensure all viable alternatives have been examined

    Avoid cost and realize cost savings

    Improve quality of completed project

    Facilitate the government receiving best value

    Department of the InteriorDecember 2007

  • 7/31/2019 Integration of Value Engineering

    7/17

    DOIs Current VE Requirements

    VE program is mandatory for all bureausand offices and programs, projects, andactivities

    Applies to:

    Construction, repair, rehabilitation, and

    renovation projects with estimated cost$500,000 or greater

    Department of the InteriorDecember 2007

  • 7/31/2019 Integration of Value Engineering

    8/17

    DOIs Current VE Requirements

    VE is performed when concept andestimated cost is detailed enough forcomparison of alternatives

    Goal is to achieve saving equal to orgreater than 4 percent of a bureaus

    aggregate annual construction budget

    Department of the InteriorDecember 2007

  • 7/31/2019 Integration of Value Engineering

    9/17

    Objective of VE Integration

    The two primary objectives of integrating VE and

    the Five-Year planning process are:

    1) Foster thorough planning and analysis tocomplete high quality construction and repairprojects at an appropriate cost

    2) Use VE as a tool to limit project cost andschedule variance

    Department of the InteriorDecember 2007

  • 7/31/2019 Integration of Value Engineering

    10/17

    Potential Revisions to DOI Requirements

    The below revisions will be discussed by bureau

    VE coordinators. Additional items may be added.

    1) Define the project stage at which VE resultsare reported.

    2) Clearly define the stage in project developmentat which VE is performed.

    Department of the InteriorDecember 2007

  • 7/31/2019 Integration of Value Engineering

    11/17

    Potential Revisions to DOI Requirements

    3) Ensure construction Capital Planning andInvestment Control (CPIC) guide identifies pointsin project life cycle to perform VE.

    4) Define application of VE to design/buildprojects.

    5) Consider raising the VE threshold to $1 millionfrom $500,000

    - $1 million is minimum threshold per A-131

    Department of the InteriorDecember 2007

  • 7/31/2019 Integration of Value Engineering

    12/17

    Potential Revisions to DOI Requirements

    6) Define how VE is applied to dam projects

    7) Acknowledge that sustainable buildingpractices may justifiably increase someproject costs to create environmentalbenefit

    8) Consider whether VE should be appliedmore rigorously to non-project work

    Department of the InteriorDecember 2007

  • 7/31/2019 Integration of Value Engineering

    13/17

    Revision of Appendix Q

    Appendix Q is the VE section of theconstruction CPIC guide

    Core of the Appendix is DepartmentManual 369 (VE)

    Department of the InteriorDecember 2007

  • 7/31/2019 Integration of Value Engineering

    14/17

    Integration Process

    Revise Department Manual Part 369 (VE)

    Goal is for final revision June 1, 2008

    Revise Appendix Q of the Construction CPICGuide

    Goal is for final revision June 1, 2008

    Bureau VE coordinators will submit proposedrevisions to both documents by January 22,2008

    Department of the InteriorDecember 2007

  • 7/31/2019 Integration of Value Engineering

    15/17

    Integration Process

    Include revised VE requirements in AttachmentG for the FY 2011- FY 2015 Five Year Plan

    This guidance will be issued in FY 2008

    Add a VE data field to the Project Data Sheetincluded in the FY 2011- FY 2015 Five Year

    Plan

    Department of the InteriorDecember 2007

  • 7/31/2019 Integration of Value Engineering

    16/17

    Bureau VE Program Coordinators

    DOI Bill Hamele

    BIA Alan Roit

    BLM Linda Force, Ed Giagni

    BOR Norman Hyndman

    FWS Marshall Wright

    NPS Rich Turk

    USGS Clarence (Bill) Fulk

    Contact your coordinator with questions

    Department of the InteriorDecember 2007

  • 7/31/2019 Integration of Value Engineering

    17/17

    Questions, Comments?

    Department of the InteriorDecember 2007