Upload
sathishe
View
218
Download
0
Embed Size (px)
Citation preview
7/31/2019 Integration of Value Engineering
1/17
Office of Acquisition and Property Management
Integration of ValueEngineering (VE)
and theFive-Year Planning Process
7/31/2019 Integration of Value Engineering
2/17
7/31/2019 Integration of Value Engineering
3/17
Background VE Requirements
Public Law 104-106 (1996) requires all agenciesestablish a VE program
OMB Circular A-131 requires VE to reduce nonessential
procurement and program costs Threshold is $1 million for projects and programs
DOI submits annual VE accomplishment report
submitted to OMB by December 31 of each year
DOIs requirements are in Department Manual 369
Department of the InteriorDecember 2007
7/31/2019 Integration of Value Engineering
4/17
Background - Value EngineeringPresentation Overview
Public Law 104-106 defines VE as:
An analysis of the functions of a program,
project, system, product, item of equipment,building, facility, service, or supply of anexecutive agency, performed by qualified
agency or contractor personnel, directed atimproving performance, reliability, quality, safety,and life cycle costs.''
Department of the InteriorDecember 2007
7/31/2019 Integration of Value Engineering
5/17
Background - Value Engineering
VE applies to all projects, programs,equipment
Studies can be performed by in-house orcontractor personnel
VE can be applied at any point in projector program life cycle
Department of the InteriorDecember 2007
7/31/2019 Integration of Value Engineering
6/17
Background - Value Engineering
Construction projects
VE usually applied at conceptual and design stages
May be applied more than once on an individual
project
Objective is to:
Ensure all viable alternatives have been examined
Avoid cost and realize cost savings
Improve quality of completed project
Facilitate the government receiving best value
Department of the InteriorDecember 2007
7/31/2019 Integration of Value Engineering
7/17
DOIs Current VE Requirements
VE program is mandatory for all bureausand offices and programs, projects, andactivities
Applies to:
Construction, repair, rehabilitation, and
renovation projects with estimated cost$500,000 or greater
Department of the InteriorDecember 2007
7/31/2019 Integration of Value Engineering
8/17
DOIs Current VE Requirements
VE is performed when concept andestimated cost is detailed enough forcomparison of alternatives
Goal is to achieve saving equal to orgreater than 4 percent of a bureaus
aggregate annual construction budget
Department of the InteriorDecember 2007
7/31/2019 Integration of Value Engineering
9/17
Objective of VE Integration
The two primary objectives of integrating VE and
the Five-Year planning process are:
1) Foster thorough planning and analysis tocomplete high quality construction and repairprojects at an appropriate cost
2) Use VE as a tool to limit project cost andschedule variance
Department of the InteriorDecember 2007
7/31/2019 Integration of Value Engineering
10/17
Potential Revisions to DOI Requirements
The below revisions will be discussed by bureau
VE coordinators. Additional items may be added.
1) Define the project stage at which VE resultsare reported.
2) Clearly define the stage in project developmentat which VE is performed.
Department of the InteriorDecember 2007
7/31/2019 Integration of Value Engineering
11/17
Potential Revisions to DOI Requirements
3) Ensure construction Capital Planning andInvestment Control (CPIC) guide identifies pointsin project life cycle to perform VE.
4) Define application of VE to design/buildprojects.
5) Consider raising the VE threshold to $1 millionfrom $500,000
- $1 million is minimum threshold per A-131
Department of the InteriorDecember 2007
7/31/2019 Integration of Value Engineering
12/17
Potential Revisions to DOI Requirements
6) Define how VE is applied to dam projects
7) Acknowledge that sustainable buildingpractices may justifiably increase someproject costs to create environmentalbenefit
8) Consider whether VE should be appliedmore rigorously to non-project work
Department of the InteriorDecember 2007
7/31/2019 Integration of Value Engineering
13/17
Revision of Appendix Q
Appendix Q is the VE section of theconstruction CPIC guide
Core of the Appendix is DepartmentManual 369 (VE)
Department of the InteriorDecember 2007
7/31/2019 Integration of Value Engineering
14/17
Integration Process
Revise Department Manual Part 369 (VE)
Goal is for final revision June 1, 2008
Revise Appendix Q of the Construction CPICGuide
Goal is for final revision June 1, 2008
Bureau VE coordinators will submit proposedrevisions to both documents by January 22,2008
Department of the InteriorDecember 2007
7/31/2019 Integration of Value Engineering
15/17
Integration Process
Include revised VE requirements in AttachmentG for the FY 2011- FY 2015 Five Year Plan
This guidance will be issued in FY 2008
Add a VE data field to the Project Data Sheetincluded in the FY 2011- FY 2015 Five Year
Plan
Department of the InteriorDecember 2007
7/31/2019 Integration of Value Engineering
16/17
Bureau VE Program Coordinators
DOI Bill Hamele
BIA Alan Roit
BLM Linda Force, Ed Giagni
BOR Norman Hyndman
FWS Marshall Wright
NPS Rich Turk
USGS Clarence (Bill) Fulk
Contact your coordinator with questions
Department of the InteriorDecember 2007
7/31/2019 Integration of Value Engineering
17/17
Questions, Comments?
Department of the InteriorDecember 2007