    Intelligent Scheduling Systems for Shipbuilding

    Jae Kyu Lee, Kyoung Jun Lee, June Seok Hong, Wooju Kim, Eun Young Kim, Soo Yeoul Choi, Ho Dong Kim,Ok Ryul Yang, and Hyung Rim Choi

    AI Magazine Volume 16 Number 4 (1995) ( AAAI)

  • 8/14/2019 Intelligent Scheduling Systems for Shipbuildins

    2/17

    s Daewoo Shipbuilding Company, one of thelargest shipbuilders in the world, has experienceda great deal of trouble with the planning andscheduling of its production process. To solve theproblems, from 1991 to 1993, Korea AdvancedInstitute of Science and Technology (KAIST) andDaewoo jointly conducted the Daewoo Ship-building Scheduling (das) Project. To integratethe scheduling expert systems for shipbuilding,

    we used a hierarchical scheduling architecture. Toautomate the dynamic spatial layout of objects invarious areas of the shipyard, we developed spa-tial scheduling expert systems. For reliable esti-mation of person-hour requirements, we imple-mented the neural networkbased person-hourestimator. In addition, we developed the paneled-block assembly shop scheduler and the long-range production planner. For this large-scaleproject, we devised a phased development strate-gy consisting of three phases: (1) vision revela-tion, (2) data-dependent realization, and (3)prospective enhancement. The DAS systems weresuccessfully launched in January 1994 and areactively being used as indispensable systems inthe shipyard, resulting in significant improve-ment in productivity and visible and positiveeffects in many areas.

    D aewoo Shipbuilding Company is oneof the largest shipbuilders in the world.Its main products are the very largecrude oil carrier (VLCC) and the containership. Other products include heavy machin-ery, plants, and automobiles; these productsare minor contributors to the companys sales.Its shipbuilding yard has three docks: One isthe largest dock in the world, capable of man-ufacturing a 1-million-ton VLCC, that has aGoliath crane that can hold as much as 900tons. There are 12,000 employees, and thesales in 1993 were $2 billion.

    Shipbuilding is make-to-order manufactur-ing, and it takes a long time to complete theproducts. There are many complicated pro-cesses between an order and the final deliv-ery, and a large amount of working capital isrequired. It is difficult to manage the materi-al, human, facility, and informationresources. Therefore, the scheduling and con-trol of a shipbuilding plant is a very complextaska nightmare.

    The Companys Strugglewith Scheduling

    The company has struggled since its concep-tion for an effective scheduling process toachieve total optimization. Poor schedulingkeeps workers waiting for the prerequisitesubassemblies; causes fluctuations in workloads, resulting in expensive overtime work;

    and causes delays in delivery. The companytried various project management programs,such as PROJACS, VISION , and X-PERT, as well asin-house development using conventionalprograms, but these efforts were unsuccessfulbecause the flexibility of the schedulersknowledge, as well as complicated interrelat-ed factors, could not be represented. In addi-

    tion, no software could support the dynamicspatial layout even though the spatialresources associated with material-handlingequipment such as cranes are bottlenecked.To develop the integrated scheduling expertsystems that could overcome these problems,the Korea Advanced Institute of Science andTechnology (KAIST) and Daewoo jointly ledthe Daewoo Shipbuilding Scheduling ( DAS)Expert System Project from 1991 to 1993. TheDAS systems were successfully launched in Jan-uary 1994 and have been become indispens-able systems in the shipyard, resulting in asignificant improvement in productivity and

    positive effects in many areas.

    Application DescriptionThe DAS Project adopted various expert systemtechnologies to cope with the schedulingtask. Key subsystems in DAS are (1) DAS-ERECT,the erection scheduler at docks; (2) DAS-CURVE,the curved-block assembly shop scheduler; (3)DAS-PANEL, the paneled-block assembly shopscheduler; (4) DAS-MH , t he neura l ne t-workbased man-hour estimator; and (5) DAS-LPP, the long-term production planner.

    DAS-ERECT: Erection Scheduler at DocksThe initial shipbuilding process begins withblock division. Typically, a large tanker isdivided into hundreds of various-sized blocks,as shown in figure 1. These blocks can be cat-egorized into two types: (1) flat bottom,which are assembled in the paneled-blockassembly shop (PBS), and (2) curved bottom,which are assembled in the curved-blockassembly shop (CBS). Multiple blocks mightbe assembled into larger ones (calledsuperblocks ) in the preerection shop (PES) toreduce the assembly time needed at the mainerection dock. At the main docks, a numberof blocks and superblocks are constructed(erected) using a large Goliath crane. In ashipbuilding plant, typically one or two drydocks are for erection, with correspondingpreerection shops, as shown in figure 2.

    The important characteristics of erectionscheduling are as follows:

    Sequential Erection at Each Dock: Blocksand superblocks in a dock have to be erected

    Articles

    WINTER 1995 79Copyright 1995, American Association for Artificial Intelligence. All rights reserved. 0738-4602-1995 / $2.00

  • 8/14/2019 Intelligent Scheduling Systems for Shipbuildins

    3/17

    one at a time because there is only oneGoliath crane at each dock. However, someplants might have multiple docks.

    Large Search Space: Because the sched-ulers have to consider multiple ships, eachcomposed of 400 to 500 blocks, a manualsearch for the best schedule is beyond themental-processing capacity of any humanscheduler. Thus, there is a need to develop aproper search method.

    Technical Knowledge for ErectionSequencing: The technical knowledge thatrestricts the erection sequences is available.

    Use of Resources: Key resources in ship-building include human work forces, cranes,and space. To use these resources effectively, aschedule should be established to balance theloads among the PBS, the CBS, and thepreerection shops and docks.

    Hierarchical System Architecture forShipbuilding Scheduling

    For erection scheduling at the dock, we useda hierarchical scheduling architecture (Lee,Suh, and Fox 1993) and developed the con-straint-directed graph search technique (Leeet al. 1994). In the hierarchical architecture,detailed schedules for the lower-level assem-bly plants are delegated to the individualplants schedulers ( DAS-CURVE and DAS-PANEL) tosatisfy the requirements of the higher-levelscheduler ( DAS-ERECT) (figure 3). However, if lower-level scheduling is impossible, thehigher-level scheduler attempts to adjust theoriginal requirements. In the constraint-directed graph search, we amalgamated thenotions of graph expansion and constraint-directed pruning into an algorithm.

    To reduce complexity during the generativescheduling phase and improve the robustnessduring the reactive scheduling phase, a hier-archical architecture, as shown in figure 3,was adopted. In this architecture, part of theoverall scheduling is delegated to the lower-level schedulersPBS and CBS schedulersthat schedule and control their respectivework areas. In our model, each lower-levelscheduler can handle its own work area inde-pendently as long as it satisfies the require-ments imposed by the higher-level dockscheduler.

    The characteristics of the hierarchicalscheduling architecture can be summarized asfollows:

    Block Assembly Due-Date Generation byDocks Generative Scheduler: The docks

    generative scheduler determines the due date of each blocks assembly. In this stage, the totalcapacities of lower-level assembly shops such

    Articles

    80 AI MAGAZINE

    Figure 1. A Ship and Its Partition into Blocks.

    Figure 2. Typical Shipbuilding Procedure.

    D O C K

    Curved Block

    Curved-bottomed BlockFlat-bottomed Block

    Panelled Block

    Pre-Erection Shop

    Super Block

    Assembly Shop Assembly Shop

    PBS CBS

  • 8/14/2019 Intelligent Scheduling Systems for Shipbuildins

    4/17

    as the PBS and the CBS are considered. Then,the scheduler requests the relevant lower-lev-el schedulers to deliver the blocks by thesedue dates.

    Distributed Scheduling and Controlling by PBS and CBS Schedulers: Each schedulerat PBS and CBS schedules its own work areaaccording to the requested due dates as wellas the spatial and person-power constraints.When a certain block cannot be assembled intime, the scheduler reports the trouble to thehigher-level dock scheduler to obtain assis-tance in resolving the inconsistency. Then,the due date of a block might be adjusted, orovertime might be required.

    Constraint-Directed Graph SearchTo find the best erection sequence at thedock, a new search procedure was developed.The first approach we considered was tograph search to expand nodes and select aproper node, possibly using an evaluation

    function (Nilsson 1980). However, the appli-cation of a pure graph search was inappropri-ate in this case because the measurement of multiple realistic evaluation functions isalmost impossible. We also observed thatthere are precedence constraints betweennodes. To accommodate both the graph-expansion framework and the constraint con-siderations, we proposed an algorithm calledthe constraint-directed graph search (CDGS).

    Algorithm of CDGSTo develop an algorithm for the CDGS proce-dure, we considered the case of a single ves-sel; however, this algorithm can be extendedto multiple-vessel and multiple-dock cases.Notations N i: a node i (which implies ablock in this case), i = 1, ... , m.

    Whole = {N i | i = 1, ... , m}. KL = potential list of keel-laying blocks,which are the first to be laid for eachvessel.

    Path = list of scheduled nodes. Potential = union of adjacent nodes tothe ones in current Path, excluding thosein the Path itself.

    Erectable = list of nodes that satisfy thetechnical constraints among the nodesin the current Potential.i-th ( List ) = i-th node in the List list.

    AlgorithmPhase 1. Initialize.Step 0. Acquire the required data andconstraints.

    Step 1. Put all the nodes to be erected inthe Whole list , and initialize the emptylists.

    Whole {N 1 , ... , N m}.

    Path .

    Potential .

    Erectable .

    Phase 2. Select keel-laying block.

    Step 2. Generate the candidate keel-lay-ing blocks, and store them in KL. In thisstep, the potential keel-laying block-selection constraints are used.

    KL Keel_Laying_Constraints ( Whole ).

    Step 3. Select a keel-laying block basedon the selection strategy. Put the selectedkeel-laying block in the Path list.

    Articles

    WINTER 1995 81

    Figure 3. Hierarchical Architecture of Shipbuilding Scheduling.

    Reactive

    CheckPBS/CBScapacityroughlyGenerative

    Scheduler

    Checkdockcapacityin detail

    Scheduler

    Panelled BlockDue Date

    Curved BlockDue Date

    Check CBScapacity in detail

    Check PBScapacity in detail

    DAS-

    PBS SchedulerDAS - PANEL DAS - CURVE

    CBS Scheduler

    Dock

    ERECT

    Scheduler

  • 8/14/2019 Intelligent Scheduling Systems for Shipbuildins

    5/17

    STRUCTURAL-PART-OF: BOTTOM

    Relative PositionREAR: 5060-232 5060-222LEFT: 5060-6A0RIGHT: 5060-6B0FRONT: 5060-204UP: 5060-442 5060-6C0 5060-4B0DOWN:

    Estimated Durations (days) and Man-hours

    BLOCK-ASSEMBLY-DURATION: 9BLOCK-ASSEMBLY-MANHOUR: 346DOCK-SETTING-DURATION: 1DOCK-SETTING-MANHOUR: 57DOCK-FITTING-DURATION: 4DOCK-FITTING-MANHOUR: 73DOCK-WELDING-DURATION: 3DOCK-WELDING-MANHOUR: 73

    Generated SchedulesASSEMBLY-SST: 92/01/03

    ASSEMBLY-SFT: 92/01/11DOCK-SETTING-SST: 92/02/09DOCK-SETTING-SFT: 92/02/09DOCK-FITTING-SST: 92/02/10DOCK-FITTING-SFT: 92/02/13DOCK-WELDING-SST: 92/02/11DOCK-WELDING-SFT: 92/02/13 }}

    Note: SST = scheduled start time; SFT =scheduled finish time.Ten types of technical constraint are

    acquired and can be grouped into three class-es: (1) general technical constraints, (2) con-straints on partial sequence, and (3) con-straints on precedence relationship.Descriptive examples from each class are asfollows:

    General technical constraints: A keel-laying block should be selected among thenonside and bottom blocks of engine roomor midbody part.

    Constraints on partial sequence: All theblocks should satisfy the structural stabilitycondition. Therefore, the transverse sequenceof the mid-body must satisfy the sequenceBottom Bulk Head Side-Shell Deck.

    Constraints on precedence relationship:The block that needs supporting facilitiesmust be erected after having erected the baseblocks on which the facilities should stand.

    To illustrate, use three erected blocks asshown in figure 4. Suppose Path = { PA , PB,

    PC}. Then, there are 10 potentially erectableblocks. Therefore, Potential = { P 1, P 2, , P 10}.The potentially erectable blocks and theirpositions are shown in figure 5.

    We can derive Erectable list from the Potential list by considering technical con-

    N k Select_a_Keel_Laying_Block ( KL). KL KL {N k}. Path Path + {N k}.Whole Whole Path.

    Phase 3. Expand graph.Step 4. Expand Potential of current Pathby adding adjacent nodes of N k whilenot in the Path .

    Potential Potential {Adjacent_Node ( N k) Path }.

    Step 5. If the Potential = and Whole = ,all nodes are erected appropriately. Stop.

    If Potential = and Whole , thesearch procedure has problems. Stopwith an error message.Step 6. Among the nodes in Potential,select the nodes that also satisfy thetechnical constraints.

    Erectable Technical_Constraints

    ( Potential ).Step 7. If Erectable = , backtrack.

    N z last_th(Path). Path Path {N z}.Whole Cons (Whole, N z).

    Potential Potential {N z} {Added_Potential_by ( N z)}.

    Erectable Technical_Constraints( Potential ).

    N k Evaluate_and_Find_the_Best( Erectable ).

    Then, go to step 4. Otherwise, contin-ue to the next step.Step 8. Select the best node to be erectedfrom Erectable . Update each list.

    N k Evaluate_and_Find_the_Best( Erectable ).

    Path Cons( Path, N k). Potential Potential {N k}.Whole Whole {N k}.Go to step 4.

    Knowledge Representation for CDGSThe knowledge base used in the CDGS com-prises object-oriented data and constraints.Objects represent the hierarchical structure of blocks and superblocks and the resourcesused in each shop (PBS, CBS, PE shop, dockshop, and so on), as follows:

    {{ 5060-203IS-A: BLOCKSHOP: PBSPART-OF: MID-BODY

    Articles

    82 AI MAGAZINE

  • 8/14/2019 Intelligent Scheduling Systems for Shipbuildins

    6/17

    straints such as structural stability. Supposethe Erectable list has become { P 1, P 2}. Toselect one block, we evaluate blocks P 1 and

    P 2. Use two criteria: (1) the resource-use levelof lower-level assembly shops and (2) the ear-liest erection start time at the dock. Supposethat blocks P 1 and P 2 in the current Erectablelist are flat bottomed, and they are evaluatedby the use level of the PBS. If the block is tobe erected on the seventh day at the dock,the block P 2 should be preferred as the nextblock to be erected. If P 2 is selected, the Pathlist becomes { PA, PB, PC , P 2}. This procedureis repeated until all blocks are erected. Figure6 shows an erection network scheduled byDAS-ERECT.

    Spatial Scheduling in ShipbuildingIn the shipbuilding plants that handle theheavy and bulky blocks, it is necessary to useexpensive material-handling equipment suchas cranes and work plates. Because the space

    equipped with such facilities is typically lim-ited and bottlenecked, the scheduling needsto consider the spatial resources as well as tra-ditional resources such as personnel andmachines. We call this kind of schedulingspatial scheduling . As the term implies, spatialscheduling deals with the optimal dynamicspatial layout schedules. In a shipyard, spatialscheduling problems occur frequently in vari-ous working areas such as erection docks,preerection shops, and the block-assemblyshop.

    To date, human schedulers have carried outthe spatial scheduling manually, using noautomated aids. Even though human expertshave extensive experience in spatial schedul-ing, it takes a long time and much effort toproduce a satisfactory schedule because of thehuge search space required to consider theblocks geometric shapes. For example, spatialscheduling for six months is beyond thescope of a humans mental capacity; so, it wasimpossible to build such a large-scale spatialschedule in advance. Nevertheless, the spatialresource tends to be a critical resource inshipbuilding. Therefore, automation of thespatial scheduling process was critical toimprove productivity in the shipbuildingplants and achieve the total integration of scheduling expert systems.

    At Daewoo, some attempts have beenmade to solve the spatial scheduling problem.One approach was a simple spatial schedulingsystem that assumed that the shape of blockscan be approximated to a rectangle. However,the field schedulers rejected it because theapproximation sacrificed spatial use too

    much. DAS-CURVE assumes the approximationof the blocks shape to a polygon, on whichthe schedulers agree.

    Another approach that failed was the inter-active spatial scheduling support system thatprovided the graphic user interface for thehuman scheduler. The interactive system wasnot effective because it couldnt automate thetedious spatial scheduling process and reducethe information burden and scheduling time.It could only replace the paper and pencilwith a computerized interface.

    The objectives of spatial scheduling canvary somewhat depending on the nature of agiven plant. In general, however, spatialscheduling systems pursue the objectives of due-date satisfaction, maximal use of spatialand nonspatial resources, and minimizationof waiting times for work-in-process andfinal-product inventories.

    Articles

    WINTER 1995 83

    Figure 4. Partially Erected Blocks.

    Figure 5. Spatial Position of Potentially Erectable Blocks.

    PA PB

    PC

    PA PB

    PC

    P2 P1

    P3

    P4

    P5

    P6

    P7

    P8P9

    P10

  • 8/14/2019 Intelligent Scheduling Systems for Shipbuildins

    7/17

    ration space is the space through which thereference point of an object (a robot, forexample) with fixed orientation can possiblypass without colliding with obstacles that arepresent. In our research, there are two kindsof configuration space: (1) the obstacle-avoid-ing space and (2) the inner locatable space. Inthe obstacle-avoiding space S (a i|B), the refer-ence point of an object a

    ican be located

    without colliding with the already locatedobjects that are regarded as obstacles. In theinner locatable space S (a i|W ), the referencepoint of an object a i can be located withinthe boundary of a work area W . Thus, thefeasib le locatable space S (a i |B,W ) can bederived by intersecting the previous twospaces: S(a i|B,W ) = S(a i|B) S(a i|W ).

    Figure 7 illustrates the spaces where theobject a1 is to be located within W , on whichtwo objects b1 and b2 are already located.Because the feasible locatable space is a con-tinuous space, it is impossible to find all the

    points in it. To extract a set of meaningfuldiscrete points out of the continuous space,we define the distinctive locatable point set

    D (a i|B,W ), which consists of the vertexes of the feasible locatable space.

    Theoretically speaking, the distinctivelocatable point set does not guarantee findingan optimal location (Lee and Lee 1995). How-ever, the points have empirically providedsatisfactory locations with the advantage of computational efficiency.

    The distinctive locatable points can be clas-sified into four categories: (1) DO(a i|B,W ), theunion of the feasible vertexes of each obsta-cle-avoiding space; (2) D I (a i|B,W ), the feasiblevertexes of the inner locatable space; (3)

    DOI (a i|B,W ), the union of the feasible intersec-tion points between the boundaries of eachobstacle-avoiding space and the inner locat-able space; and (4) DOO (a i|B,W ), the union of the feasible intersection points between theboundaries of each obstacle-avoiding space.

    The following points are illustrated in fig-ure 7: three DO(a i|B,W ), marked as triangles;three D I (a i |B,W ), marked as squares; six

    D OI (a i|B,W ), marked as circles; and two DOO(a i|B,W ), marked as diamonds. The cate-gorized points can be used to reduce thesearch space by identifying a special categoryof the distinctive locatable point set contin-gent to the situation.

    Search in the Distinctive LocatablePoint SetBecause most layout problems are NP com-plete, we propose four positioning strategiesthat can effectively be applied contingent to

    Typical constraints include crane capacity,person-hour availability, assembly due date,precedence between associated assemblies,physical adjacency of coupled objects foroperational efficiency, minimum requireddistance between blocks, and maximumacceptable waiting times for completed andwork-in-process blocks.

    Typical necessary input data include jobswith due dates and their constituent activi-ties, two-dimensional geometric spatialobjects of the activities, required processingtimes for each activity, and spatial shapes of work plates.

    In the shipbuilding domain, the shapes of most objects tend to be convex polygonssuch as triangles, rectangles, or trapezoids.Some blocks might have some local concavi-ty. However, in most cases, the local concavespace is not usable by other objects. There-fore, these objects can be approximated asconvex polygons.

    In shipbuilding, the orientation of anobject is prefixed to four alternative orienta-tions (0 o, 90 o, 180 o, and 270 o) to ensure sta-ble crane operations.

    Search Space in Spatial SchedulingTo find the feasible locatable positions of anobject ai within a workplate W that do notoverlap a scheduled object b j, we can adoptthe notion of configuration space (Zhu andLatombe 1991; Lozano-Perez 1983). Configu-

    Articles

    84 AI MAGAZINE

    Figure 6. An Erection Network Scheduled by DAS- ERECT .

  • 8/14/2019 Intelligent Scheduling Systems for Shipbuildins

    8/17

    the situation: (1) the maximal remnant spaceuse strategy, (2) the maximal free rectangularspace strategy, (3) the initial positioning strat-egy, and (4) the edging strategy.

    Because each strategy has its own meritsdepending on the situation, we synthesized acomposite positioning algorithm that canapply an adequate positioning strategy con-tingently. Key issues in composite positioningare identification of a situation, reduction of search space, and selection of effective strate-gy. In this study, we identified four types of situation that depend on the existence of already located objects, the attempted loca-tion (near corner, edge, or other object), andthe shapes of the objects. The strategies areby no means complete. However, we empiri-cally verified that these four situation typescan still effectively capture the possible situa-tions.

    Composite Positioning AlgorithmCompute D(a i|B,W ) = [d 1,d 2, , d k, . , d z].CS: = D (a i| B,W ) /* CS = a set of candidatesolutions */If CS = Null

    Then /* a i cannot be allocated in W without changing the currentschedule */Start backtracking.

    ElseIf there are no located objects yet

    Then reset CS:= D I (a i|W ).If a i is not rectangular

    Then apply the initialpositioning strategy.

    Else /* a i is rectangular */Then select a point arbitrarily.

    Else /* there are no located objectsyet*/

    If most b js are rectangular or nearrectangularThen apply the maximal freerectangular space strategy.

    Else /* most b js are not rectangular*/

    If CS = DOI(a i| B,W )Then apply the edgingstrategy.

    ElseThen apply the maximalremnant space-use strategy.

    Backtracking and Adjustment inSpatial SchedulingIf we cannot find a feasible schedule for a cer-tain day, we have to backtrack to adjust thecurrent spatial layout, the starting times of already scheduled activities, and the resourcecommitment level. Some of the backtracking

    adjustment could have been avoided if wecould have looked ahead to needs over thenext several days. However, obtaining infor-mation on the precise impact of these futureneeds is almost as expensive as the schedul-ing itself. Therefore, we adopted the back-tracking and adjustment strategy.

    For the shipbuilding domain, we used thefollowing six types of adjustment: (1) work-plate reselection, (2) intraplate spatial adjust-ment, (3) interplate spatial adjustment, (4)intraplate temporal adjustment, (5) intraplatespatiotemporal adjustment, and (6) interplatespatiotemporal adjustment.

    Principles for the spatial scheduler to fol-low in sequencing the application of theseadjustment types can be summarized as fol-lows:

    First, monitor the status of the free rectan-gular space of each work plate as a measure of spaciousness. For a new object, assign a workplate according to this criterion as long as thespecial constraints for the new object are sat-

    isfied. However, if the shape of the free spaceturns out to be unsuitable for accommodat-ing the particular shape of a new object, thenreselect the work plate if other sufficientlyspacious options exist.

    Second, apply the spatial adjustment(including the work-plate reselection) beforeapplying the temporal adjustment becausethe temporal adjustment invokes a trade-off between the tardiness of new activity and the

    Articles

    WINTER 1995 85

    b1

    b2

    aj

    Figure 7. Feasible Locatable Space and Distinctive Locatable Points.

  • 8/14/2019 Intelligent Scheduling Systems for Shipbuildins

    9/17

    DAS-CURVE: Curved-Block AssemblyShop SchedulerDAS-CURVE is a representative spatial schedul-ing expert system (Lee, Lee, and Choi 1995;Lee and Lee 1992) for the curved-bottomblock assembly shop, first applying UNIK (uni-fied knowledge)- SPACE. The system generatesthe spatial schedule of assembling blocks to

    meet the due dates imposed by DAS-ERECT. Theblock assembly shop has about 15 workplates, with cranes to lift blocks and sub-assemblies. The resources are limited by theavailability of the spatial work plates as wellas the nonspatial resources of personnel andcranes. Figure 8 illustrates an output screen of DAS-CURVE that shows a snapshot of the spatiallayout status of the eight work plates in theshop for one day. Figure 9 illustrates thedynamic spatial layouts of a work plate dur-ing an indicated time interval.

    As the term spatial scheduling implies, visu-al interactive scheduling is an essential fea-ture for the schedulers initiative. Therefore,DAS-CURVE is equipped with a mouse-basedgraphic user interface. To maintain consisten-cy between the users visual interactive inputand the invisible constraints, the reactivescheduling capability should work behind thescreen, typically adopting the adjustmentmethods described earlier.

    Spatial Scheduling in Other SystemsIn erection scheduling, the spatial schedulingproblem occurs in the preerection shop nearthe docks. The preerection shop shares manysimilarities with the curved-bottom blockassembly shop, but it also has some specialspatial layout constraints. These special con-straints result from the differences in thetechnical constraints between the two shops.The spatial scheduling module reflectingthese features is imbedded in DAS-ERECT.

    The long-range planning of a shipyardshould consider the spatial capacities of docksbecause the sizes and the shapes of ships arediverse. Especially when there are hundredsof product-mix candidates, automated check-ing of spatial availability is essential becauseof the various spatial constraints on the lay-

    out of ships that exist because of the techni-cal constraints during the erection process.DAS-LPP has the dynamic spatial layout mod-ule using UNIK -SPACE (Lee, Lee, and Choi1994).

    To implement the spatial schedulingmethodology, many computational geomet-ric algorithms are used, such as the point-in-

    polygon algorithm (Preparata and Shamos1985) to determine whether a point is in a

    work-in-process inventory of allocated activi-ties. However, spatial adjustment does notincur such a cost as long as the constraint of operational adjacency among certain blocksis not violated.

    Third, apply the intraplate adjustmentbefore the interplate adjustment because theintraplate search is intuitively a more effi-

    cient option.Fourth, apply the purely spatial or tempo-ral adjustment strategy first before the spa-tiotemporal adjustment because the compos-ite spatiotemporal adjustment requiresgreater computation than the single-adjust-ment strategy.

    The sequencing rules in applying theadjustment strategies do not have to besequential. However, the computationaleffort to identify the optimal-adjustmentstrategy is expensive, as it is with the looka-head strategy. Therefore, it is desirable tohave a reasonable predetermined defaultsequence. In this study, the priority of adjust-ment strategies was incorporated into theadjustment algorithm based on this rationale.

    Another default scheduling strategy adopt-ed here with respect to the starting time of activities was the latest starting time strategy :Assign the activity to be finished one daybefore the due date to avoid the wait of work-in-process inventory. However, if this timeschedule is not possible to achieve, try tominimize the waiting time.

    The contingent choice of the proper adjust-ment strategy is related to the cause of

    scheduling failure and the scheduling status.For example,If the cause of the scheduling failure is

    deficiency of manpowerThen skip the intraplate spatialadjustment because it will not endsuccessfully.

    If the space use of a work plate isrelatively lowThen the intraplate spatialadjustment is more effective than theintraplate temporal adjustment.

    If the space use of a work plate isrelatively highThen the intraplate temporaladjustment is more effective than theintraplate spatial adjustment.

    If the space use of every work plate isvery highThen skip the interplate spatialadjustment.

    Articles

    86 AI MAGAZINE

  • 8/14/2019 Intelligent Scheduling Systems for Shipbuildins

    10/17

    convex polygon, the polygon-intersection algo-rithm (ORourke et al. 1982) to compute theintersection of two convex polygons, and the

    polygon setsum algorithm (Lozano-Perez 1983)to compute the setsum of two convex poly-gons. In addition to these known algorithms,various specialized computational geometricalgorithms are devised for spatial scheduling,such as those for enlarging polygons to theextent of the safety distance and computingfeasible intersection points among polygons.

    DAS-PANEL: Paneled-Block AssemblyShop SchedulerDA S-PANEL (Hong, Kim, and Lee 1993) is ascheduling expert system for the paneled-block assembly shop in which blocks andtheir subassemblies are welded on the assem-bly lines and adjacent off lines, respectively.Because the block size and compositions of subassemblies are diverse, the schedulingshould encompass the detailed scheduling of subassemblies as well as the main assemblyline scheduling of blocks. DAS-PANEL has twocharacteristics: (1) Because the blocks madein the shop are one of a kind, the speed of

    the assembly line should not be fixed inadvance. To improve the productivity of theassembly line, it is necessary to generate a

    schedule that can dynamically change thecycle time according to the characteristics of the blocks. (2) Its objective is to minimize notonly the assembly time of blocks on the mainline but also the waiting times of subassem-blies and blocks. DAS-PANEL was built using atypical forward-chaining rule-based tool,UNIK-FWD , written in C++. Figure 10 shows thedynamically changing cycle time generatedby DAS-PANEL.

    DAS-MH: Neural NetworkBasedMan-Hour EstimatorTo establish reliable scheduling expert sys-tems, the estimation of accurate person-hour requirements for each assembly is aprerequisite. To supply the required weldingperson-hour input of each one-of-a-kindblock for DAS scheduling systems, we adopt-ed the artificial neural network as an esti-mator (Lee and Kim 1994).

    To build a reliable and efficient neural net-work model, we followed this research proce-

    Articles

    WINTER 1995 87

    Figure 8. An Output Screen Showing a Snapshot of Spatial Layout in DAS-CURVE.

  • 8/14/2019 Intelligent Scheduling Systems for Shipbuildins

    11/17

    welding length, joint length, and blocksweight.

    Fourth is shop type. For the assembly shop,select one of the following values: 3DS (three-dimensional shop), BOS (building outfittingshop), PBS (paneled-block shop), and A-7 (areacode no. 7). Whether it is indoor or outdoormust be considered for each shop. In total, weitalicized 10 candidate input variables: 4 cardi-nal- and 6 nominal-scale variables.

    To eliminate unnecessary variables, weadopted the stepwise regression approachwith four cardinal variables: (1) dead weight,(2) welding length, (3) joint length, and (4)block weight.

    We expected that multicollinear variableshad to be dropped to keep the model robust.In this manner, the joint length and the blockweight are finally selected. Thus, eight vari-

    ables are eventually selected as the input tothe neural network. Figure 11 shows a configu-ration of the neural network developed usingthe neural network developer UNIK-NEURO .

    To confirm whether the neural networkmodel significantly outperforms other possi-ble approaches, we compared it with twoapproaches: (1) multiple regression and (2)simple regression through origin. We madethe comparison using simple regression

    dure: (1) Select candidate input variables:Four categories of variables are selected withpossible values for each variable. (2) Elimi-nate unnecessary variables: Highly correlatedredundant cardinal variables are filtered outby stepwise regression as a preprocessor. (3)Train and test the network with and withoutthe preprocessing. (4) Compare the estima-tion performance by the neural network withone by the regression analysis.

    We selected four categories of variable thatinfluence the welding time. They are candidateinput variables of the neural network model.

    First is ship type. For use, select one of thefollowing values: VLCC (very large crude oilcarrier), OBO (ore bulk carrier), COT (crudeoil tanker), B/C (bulk carrier), CONT (con-tainer), P/C (product carrier), and so on. Thedead weight , the weight that the ship can car-

    ry, must also be considered.Second is block type. For locus, select oneof the following values: side-shell, bulbus-low, engine-room-side-upper, fore-deck, lon-gitudinal-bulk-head, transverse-bulk-head,transverse-noncorrugated-bulk-head, mid-ship-bottom, and so on. Whether it is a pan-eled or a curved bottom or a single or a dou-ble shell must also be considered.

    Third is a blocks physical characteristics:

    Articles

    88 AI MAGAZINE

    Figure 9. An Output Screen Showing a Dynamic Spatial Layout of a Work Plate in DAS-CURVE.

  • 8/14/2019 Intelligent Scheduling Systems for Shipbuildins

    12/17

  • 8/14/2019 Intelligent Scheduling Systems for Shipbuildins

    13/17

    fore, based on the data availability, the proto-type systems were degraded. However, man-agement was delighted because the systemscould run based on the currently availabledata, although they were not ideal. The sys-tems in the second stage were developedusing a C++ version of UNIK to enhance opera-tional speeds. The systems were installed inthe field in 1992 and tested under real-worldconditions.

    The third stage was prospective enhance-ment. During this stage, the systems devel-oped in the second stage were incrementallyenhanced. A difference is that the enhance-ment was oriented toward the target set atthe end of the first stage. The systems gradu-

    ally improved because more data becameavailable during 1993. This enhancement willcontinue as necessary data are collected.

    Project Work Group OrganizationThe project team consisted of both Daewooand KAIST personnel (table 2). We observedthat the roles of the project members evolvedaccording to the development phases, asshown in table 2. Working and communicat-

    face and coordination among multiple expertsystems and databases.

    These issues were explored during the pro-jects first year, 1991, and prototypes of theDAS systems were developed using UNIK. Theseprototypes could successfully demonstratethe vision, although they could not providethe satisfactory speed.

    The second stage was data-dependent real-ization. Daewoo employees were frustratedbecause they couldnt provide the data neces-sary to run the prototype systems. However, itwas a good point at which to identify whichdata were available and which were not. Thisprocess required close communication withthe design division because the initial proto-

    type required information about the designspecification from the computer-aided design(CAD) tools to automate the process planningand person-hour estimation. However, thesedata could not be provided until the currentCAD system was upgraded to a solid modeler,which was not technically feasible at the time.Other data that could not be supported werethe erection sequencedependent person-hourand the processing time requirements. There-

    Articles

    90 AI MAGAZINE

    Figure 11. A Neural Network Configuration for Person-Hour Estimation.

  • 8/14/2019 Intelligent Scheduling Systems for Shipbuildins

    14/17

    ing with management was smooth becausethe executives involved in the project did notchange until the end of the project.

    Innovations at the SiteThe innovations made possible by using theDAS systems can be summarized as follows:

    Reengineering of the planning and work-ing processes: The aim of DAS was notautomating the existing processes but inno-vating the old processes using AI technology.We present three examples of these innova-tions (Kim 1994). First is the product-mixcase-selection process. Before using DAS-LPP,the loads of the plants were calculated after

    product-mix cases were selected. Now, we canselect good product-mix cases considering thefuture loads of the plants. Second is the spa-tial scheduling process. Before using the spa-tial scheduling expert systems such as DAS-CURVE , the spatial allocation plan was madeafter temporal allocation planning. Now, theintegration of two scheduling processes savesmuch time and effort and enhances the quali-ty of the schedule. Third is the expected per-

    son-hour calculation process. The previousinaccurate and heuristic unit method wasreplaced by the neural networkbased estima-tion method.

    Selection of the best schedule from simu-lation: The speedup of the schedule-genera-tion time enabled the field scheduler to trymultiple scheduling strategies and select thebest schedule among the simulation results.

    Move of the scheduling effort fromsimultaneous and centered scheduling: Thenetworked scheduling expert systems in ahierarchical architecture enabled the produc-tion management department to plan andcontrol the plants, reducing the negotiationefforts among plants.

    Visual production management and con-trol by graphic output: The graphic outputscreens generated from systems such as DAS-CURVE improved the planning and work pro-ductivity using clear communication betweenmanagement and workers.

    Technology transfer from university toindustry: The DAS Project is famous in Koreaas a typical success story of the cooperationbetween university and industry. Now Dae-

    Articles

    WINTER 1995 91

    Figure 12. A Cumulative Load Curve (S-curve) Used in DAS- LPP .

  • 8/14/2019 Intelligent Scheduling Systems for Shipbuildins

    15/17

    MaintenanceThe systems are maintained by the program-

    mers and knowledge engineers who weretrained during the project. The schedulers canset the contingent scheduling strategy byestablishing the parameters for the constraintbase and the rule base. For flexible systemmaintenance based on the change of plant lay-out and facilities, KAIST and Daewoo are cur-rently conducting research on the schedulingsystem generator as part of the DAS-II Project.

    AcknowledgmentsThis research is funded by Daewoo HeavyIndustries Ltd. in Korea. We are particularlygrateful to Vice-President Dong Kyu Park,Executive Directors Wan Chul Suh, Yang BinCho, and Hee Gyu Kim, Department ManagerSe Jin Jang, Section Manager Gwang Joo Lee,and Sang Soon Im and Yong Chul Kim fortheir cooperation during knowledge acquisi-tion. We also would like to thank members of the DAS Project team at KAIST and Daewoo:

    Jae Wook Kim, Jeong Seung Lee, Jae HoChun, and Seok Jun Byun.

    woo has the ability to develop expert systemsby itself.

    Development CostThe development costs for the three yearswere calculated at approximately $159,000for the hardware and $675,000 for theresearch and one developer from each organi-zation. The total cost was about $834,000.

    Estimate of Payoff Although the revenue implication for theproject is not easy to calculate, the company

    estimates were based on the expected con-tributing rates of the production productivityand planning productivity improvements.Because the estimated contribution rate of DAS to the yearly production productivityimprovement (15 percent) is 30 percent andto the planning productivity improvement is50 percent, the expected annual benefit of the DAS Project is about $4 million.

    Articles

    92 AI MAGAZINE

    First Year, 1991 Second Year, 1992 Third Year, 1993DAS-ERECT Research on constraint-

    directed graph searchSpatial scheduling inpreerection shop,system implementation,graphic user interfaceimplementation

    Experiments, graphicuser interfacedevelopment, systemupgrade andmaintenance

    DAS-CURVE Research on spatialscheduling

    System implementation,graphic user interfaceimplementation

    DAS-PANEL Research on linebalancing with dynamiccycle time

    Rule base and inferenceengine construction,system and graphic userinterfaceimplementation

    DAS-MH Tool ( UNIK -NEURO )development

    Neural networkmodeling and systemdevelopment

    Experiment and modelselection

    DAS-LPP Research on CSP and LPmodeling of S-curve

    Interactive planningprototype

    ImplementationLanguage and Tool

    Lisp version prototype Operational system ( Cconversion)

    Installed in field

    Development Phase Vision revelation Data-dependentrealization

    Prospectiveenhancement

    Table 1. Development Process.

  • 8/14/2019 Intelligent Scheduling Systems for Shipbuildins

    16/17

    ReferencesHong, J. S.; Kim, E. Y.; and Lee, J. K. 1993. AssemblyLine Scheduling Expert Systems in Shipbuilding:DAS-PANEL. In Proceedings of the Korean Expert Sys-tems Society Conference (in Korean), 147158.Seoul, Korea: Korean Expert Systems Society.Kim, E. Y. 1994. CIM in Shipbuilding: A Case Study.

    In Proceedings of the Korean Expert Systems Soci-ety Conference (in Korean), 8198. Seoul, Korea:Korean Expert Systems Society.Lee, J. K. 1993. Phased Development Strategy forComplex Expert Systems: A Shipbuilding Schedul-ing Case. In Proceedings of 93 Pan Pacific Confer-ence on Information Systems, 255257. Taiwan,Republic of China: PACIS.Lee, J. K., and Kim, H. D. 1994. Man-Hour Require-ment Estimation for Assemblies Using Neural Net-works. In Proceedings of 94 Japan/Korea JointConference on Expert Systems, 203206. Tokyo,

    Japan: Japanese Society for Artificial Intelligence.Lee, K. J., and Lee, J. K. 1995. The Dominance andPreference of Search Space in Dynamic Spatial Lay-out, Working Paper, KAIST-MIS-WP-9503-01, Depart-ment of Management Information Systems, KoreanAdvanced Institute of Science and Technology.Lee, K. J., and Lee, J. K. 1992. Spatial Schedulingand Its Application to Shipbuilding. In Proceedingsof the Second Pacific Rim Conference on ArtificialIntelligence, 11831189. Seoul, Korea: KoreanInformation Science Society.Lee, K. J.; Lee, J. K.; and Choi, S. Y. 1995. A SpatialScheduling System and Its Application to Ship-

    building: DAS-CURVE . Robotics and Computer Integrat-ed Manufacturing . Forthcoming.Lee, K. J.; Lee, J. K.; and Choi, S. Y. 1994. SpatialScheduling Expert Systems for Shipbuilding. In Pro-ceedings of the Second World Congress on ExpertSystems, 243249. New York: Cognizant Communi-cation Corporation.Lee, J. K.; Suh, M. S.; and Fox, M. S. 1993. Contin-gencies for the Design of Scheduling Expert Sys-tems. Expert Systems with Applications 6:219230.Lee, J. K.; Choi, H. R.; Yang, O. R.; and Kim, H. D.1994. Scheduling Shipbuilding Using a Constraint-Directed Graph Search: DAS-ERECT. Intelligent Systemsin Accounting, Finance, and Management 3:111125.Lozano-Prez, T. 1983. Spatial Planning: A Configu-ration Space Approach. IEEE Transactions on Com-

    puters 32(2): 108120.Nilsson, N. J. 1980. Principles of Artificial Intelligence .San Francisco, Calif.: Morgan Kaufmann.ORourke, J.; Chien, C.; Olson, T.; and Naddor, D.1982. A New Linear Algorithm for IntersectingConvex Polygons. Computer Graphics and Image Pro-

    cessing 19:384391.Preparata, F. P., and Shamos, M. 1985. Computation-al Geometry: An Introduction. Reading, N.Y.: SpringerVerlag.Yang, O. R., and Choi, S. Y. 1994. An Expert Systemwith Optimization Model: DAS-LPP. In Proceedingsof Korean Expert Systems Society Conference (inKorean), 241251. Seoul, Korea: Korean Expert Sys-tems Society.Zhu, D., and Latombe, J. C. 1991. Mechanization of

    Articles

    WINTER 1995 93

    First Year, 1991 Second Year, 1992 Third Year, 1993 RolesUniversity(KAIST)

    9 persons 9 persons 6 persons Research anddevelopment,

    Research andprototypedevelopment,

    knowledgeengineering

    Inference enginedevelopment, tooland system

    conversion (Lisp toC)

    Advancedimplementationand experiment

    technologytransfer

    People fromcompany

    3 persons 3 persons 5 persons 3-year residence atthe university

    Specification,transfer, learning,and training

    Rule base andgraphic userinterfacedevelopment

    Maintenance andgraphic userinterfacedevelopment

    Management 4 persons 4 persons Coordination,team in thecompany

    ProjectManagement

    Data Support andTraining

    on-the-jobtraining

    Domain experts 11 persons 17 persons In-house training,Knowledge transferand feedback,prototype testing

    Use learning andsystem testing

    practice, andtesting, support of scheduling masters

    Table 2. The Number of Members in Each Group and Their Changing Roles.