Upload
others
View
6
Download
0
Embed Size (px)
Citation preview
Internal Monitoring Report June 2017
AZE: Road Network Development Investment
Program, Project 1 and Project 3
Prepared by Azeravtoyol Open-Joint Stock Company for the Republic of Azerbaijan and the
Asian Development Bank.
This internal monitoring report is a document of the borrower. The views expressed herein do
not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be
preliminary in nature.
In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
REPUBLIC OF AZERBAIJAN AZERAVTOYOL OJSC
Road Network Development Program
Masalli–Astara Motorway Project
Tranche 1- L2354/2355 and Tranche3 - L2831
Sarcuvar-Girdani (Section A) Girdani- Penser (Section B) Penser -Astara (Section C)
LAND ACQUISITION AND RESETTLEMENT PLAN
INTERNAL MONITORING REPORT
January-June, 2017
1
ACRONYMS
ADB Asian Development Bank
SPS Safeguards Policy Statement
AP Affected Person
AAY AzerAvtoYol
AZN Azerbaijani Manat
DSC Design and Supervision Consultant
IMR Internal Monitoring Report
LAD Land Acquisition Department
LARF Land Acquisition and Resettlement Framework
LARP Land Acquisition and Resettlement Plan
NDP Network Development Program
NRS National Resettlement Specialist
PIU Project Implementation Unit
ROW Right of Way
TOR Terms of Reference
2
Table of Contents 1. Introduction ................................................................................................1
2. Objectives of the LARP Internal Monitoring ...............................................1
.
3. LARP Implementation Mechanism and Structure …………………………..1
4. Status of Land Acquisition and Compensation Payment...........................2
5. Temporary Impacts.....................................................................................3
6. Records of Grievances ..............................................................................3
3
1. Introduction
1. The Masalli-Astara Motorway, which is the southern section of the highway between
Alat and Astara, is a project financed under the Road Network Investment Program through
the Asian Development Bank’s (ADB) multi-tranche financing facility (MFF). The highway is
a 58.600 kilometer dual carriageway motorway section of the M3 highway corridor that links
the Baku City to the south of the country and the town of Astara, which straddles the Iranian
border. The construction of the Masalli-Astara Motorway Project, referred to below as the
‘sub-project’, is being financed through Loans 2354 and 2831. The sub-project starts at
Masalli (km 0.00) and ends at Astara (km 58.600) and is divided into three sections, A, B and
C (refer to Table 1).
Table 1: Sections of the Masalli-Astara Motorway Project
Section Section (from – to) Length
(Kms.) Km.Point
A (Project 1) Masalli–Girdani 22.15 0 – 22.15
B (Project 3) Girdani–Penser 19.35 22.15 – 41.50
C (Project 3) Penser–Astara 19.90 41.50 –58.6
2. Objectives of the LARP Internal Monitoring
2. The objectives of this internal monitoring assignment were to review, validate and
report on the status of the implementation during the reporting period, January-June 2017,of
the Land Acquisition and Resettlement Plans (LARPs) prepared for Sections A, B and C
within the Road Network Development Program (RNDP). The internal monitoring reports
(IMRs), which are submitted every 6 months to ADB, serve as updates on the implementation
of LARPs.
3. This IMR also includes an account of the grievances reported by project affected
people (APs) and addressed in line with policies and principles laid out in the resettlement
plans (RPs) and the ADB’s2009 Safeguards Policy Statement(SPS).
3. LARP Implementation Mechanism and Structure
4. AzerAvtoYol (AAY) of the Republic of Azerbaijan is the Executing Agency and has
overall responsibility for the sub-project including the preparation, implementation and
financing of all land acquisition and resettlement (LAR) related tasks as well ascross-agency
coordination. The Investment Unit of the AAYis carried out its function through its Project
Implementation Unit (PIU) which was established for the implementation of the Project. The
Project Implementation Unit (PIU), headed by a Director, is responsible for general project
4
execution, and is tasked with overall responsibility for the day-to-day implementation
activities.
5. The land acquisition and resettlement tasks are being carried out by AzerAvtoYol’s
Land Acquisition Department (LAD), which has organized and is internally monitoring the
LARP preparation and implementation (including surveys, asset valuation and community
consultation) and related cross-agency coordination. The LAD designated two engineers
from its Department for implementation of LAR activities at Lankaran and Astara Rayons.
The National Resettlement Specialist, Mr. Arastun Quliyev (NRS), collects and keeps the
records of APs, type of impacts, compensation amounts, payment dates and resolutions of
LAR-related conflicts and issues. The LARPs prepared for Sections A, B and C are being
implemented with support from the Design and Supervision Consultant (DSC).
6. The LARPs are being implemented by AAY-LAD in accordance with the following
policy frameworks:
i) ADB Safeguard Policy Statement Appendix 2: Safeguard Requirements 2:
ii) Involuntary Resettlement (June 2009);
iii) Applicable laws of the Republic of Azerbaijan;
iv) The Land Acquisition and Resettlement Framework (LARF) prepared for the
Road Network Development Program (RNDP); and,
(v) The terms and conditions of the Loan Agreements Nos. 2354 and 2831.
4. Status of Land Acquisition and Compensation Payment
Section A
7. Section A of the Masalli-Astara Motorway Project comprises 22.15 kms between Km
0+00 (Serchuvar-Masalli) and Km 22+150 (Girdani- Lenkaran). As of the current monitoring
period, there were no pending land acquisition issues.
8. The final Land Acquisition and Resettlement Plan (LARP) for this section was
prepared in June 2011. There were 605 APs recorded in the LARP. All but 12 APs had
received due compensation by June 2013. The External Monitoring Report dated June 2013
confirmed that all entitlements in accordance with the LARP provisions had been awarded to
the APs, with the exception of 12 pending cases. By January 2015, there were only nine
unresolved pending LAR cases. However, by the end of 2015, all the pending LAR issues
were resolved through negotiations with APs.
9. There have been no new negative impacts to the communities within and near the
road section during the reporting period (January-June 2017). Major construction works are
complete as the end of June 2017 and the Contractor is currently working on the finalization
of the works.
5
Section B
10. Road Section B of the Project covers km 22+150 at Girdani to km 41+500 at Penser,
with a total road length of 19.35 kilometers.
11. The final LARP for Section B was prepared in July 2011. Due to additional land
impacts, an Addendum to the LARP was prepared in November 2013. A total of 710 APs
were covered in the LARP and its addendum. By the end of 2013, all entitlements were
provided to APs, except for the acquisition of land plots owned by 11 APs, compensation for
affected municipality lands, compensation for severely affected APs, and those APs having
residual land parcels due to land acquisition. By the end of 2014, however, all compensation
for municipal lands and residual lands, as well as compensation for severely affected APs
were provided. Meanwhile, the number of pending land acquisition cases was only five by
the end of 2014. As of June 2016, there were only three LAR issues unresolved. Out of
these three cases, two were compensation issues, while one involved relocation of one
residential structure from the right-of-way (ROW). The two compensation issues were finally
resolved within the previous reporting period (January 2017).
12. With regards to the pending relocation issue, the Court has released its decision that
the residential structure shall be removed from the ROW, and relocated by its owner (Ayaz
Mammedov ) to a new site at his own expense. Since his house was constructed after the
LARP cut-off date, the owner has expressed his agreement with the Court’s decision with a request for partial assistance from AAY in the form of machinery and equipment to relocate
the said structure. Upon realizing that maintaining his house built within ROW is impossible,
Ayaz Mammedov purchased a new land plot about 200 meters away from his current house.
On 09 July 2017, he started the relocation of his house with the necessary assistance
provided by the Contractor (Figures 1 and 2). Further assistance was provided by the
Contractor in the construction of his new house. Figure 3 shows his new house’s foundation
being laid with concrete. All these works were carried out with Ayaz Mammedov’s consent.
6
Figure 1. Roof Dismantling of Ayaz Mammedov’s House within the ROW
Figure 2. Total Demolition of Ayaz Mammedov’s House Within the ROW
7
Figure 3. Concrete Foundation Laying of Ayaz Mammedov`s New House
Section C
13. Road Section C covers km 41+500 to km 58+600 with a total length of 17.1 kilometers.
14. The LARP for this section was prepared in July 2011. There were 433 APs covered
by the LARP. However, with the changes in the alignment of road sections according to
construction arrangements, additional APs were identified. Hence, an addendum to the
LARP was prepared in October 2013. The LARP and its addendum eventually covered a
total of 578 APs within Section C. By the end of January 2015, there were only nine pending
LAR issues remaining . As of June 2016, according to the previous LARP internal monitoring,
there were only six pending issues . All those pending LAR-cases were resolved as of the
previous reporting period (January 2017). These included a complaint regarding the
compensation amount awarded to Guliyev Imran & Kamran brothers, which was settled
during a final negotiation with AAY on 6 January 2017.
15. To conclude, all LAR-related activities on Road Section B &C have been completed.
4. Temporary impacts
16. During the reporting period, there were no temporary impacts on land plots.
8
5. Records of Grievances
17. The status of the Grievance Redress Management (GRM) is indicated by the
documentation of the received grievances and complaints, and the corresponding actions
and measures done to address them. Grievance Log Book is used to document the received
grievances and complaints, so that corresponding actions and measures may be taken to
resolve them. In order to ensure transparency and facilitation of community residents’ applications, the contact details of the GRM committee representative tasked to register the
complaints were shared with the residents and the officials of concerned and affected
municipalities. Grievances registered in the Log Book for the period of July – December 2016
had been resolved and information was provided in the previous reporting period.
18. The grievances and complaints from the communities with regards to the construction
of Road Sections B and C recorded in the Log Book, with corresponding solutions
undertaken, are presented in the following Grievance Registers (Table 1 and 2). For the
period covering this report (January-June 2017), there were no grievances filed by the
community residents with regards to the construction of Road Section A. For road Section B,
one grievance (Dashdaligjar village) was lodged during the reporting period. The complaint
was related to deterioration of local roads, and the grievance was addressed by the
Contractor. Three complaints (1.Kolatan, Sahagaci and Kakalos villages, 2.Siyekeran village
3.Erchivan village,) recorded with regards to Road Section C construction during the same
reporting period involved blocking of access by the works. The arisen issues in that three
grievances were examined and now they are being solved. That access roads which provide
people to reach their ploughed field parallel with road alignments are under construction
process and are in the final stage of completion.
9
Grievance Registers for Road Sections B and C
10
Table 1: Grievance Register – Section B
No Tranch
e Location
Date Receive
d
How grieva
nce was
received
Complainant
Description of the issues/complaints
Contact details
Notes, undertaken actions
Status
1 Section B
Dasdaligjar village
02 March 2017
In meeting
Nazim Emenulla
yev
When will contractor repair the Dasdaligjar village road near the Bridge No 8?
050-343-00-
45
The Dasdaligjar village road near the Bridge No was repaired.
Solved
11
Table 6: Grievance Register – Section C
No Tranche Locatio
n
Date Receive
d
How grievance was receive
d
Complainant
Description of the
issues/complaints
Contact details
Notes, undertaken
actions Status
1 Section C
Kolatan, Sahagaci and Kakalos villages
10 June 2017
By local Municipality on behalf of local villages` people
Local people
People needs access road to reach their ploughed field parallel with road alignment
Local Municipality
The arisen issue in the grievance was reviewed and that access road is under construction process and is in the final stage of completion.
In the solution stage
2 Section C
Siyekeran village
10 June 2017
By local Municipality on behalf of local village people
Local people
People needs access road to reach their ploughed field parallel with road alignment
Local Municipality
The arisen issue in the grievance was reviewed and that access road is under construction process and is in the final stage of completion.
In the solution stage
3 Section C
Ercivan village
10 June 2017
By local people letter No 758
A group of village people
People needs access road to reach their ploughed field parallel with road alignment
Local Municipality
The arisen issue in the grievance was reviewed and that access road is under construction process and is in the final stage of completion.
In the solution stage