Upload
lengoc
View
215
Download
0
Embed Size (px)
Citation preview
Health and Safety Executive
Health and Safety Executive
Introduction to Excavation Safety
Luke Messenger HSE Construction Division, Birmingham
WWT Event 7th June 2015
What are the key issues?
Key Issues
• Collapse of excavations
• Undermining of adjacent structures
• Material falling into an excavation
• People, plant and equipment falling into excavation
• Buried Services
When it all goes wrong
Law
CDM 2015 Regulation 22(1) • All practicable steps must be taken “where necessary” to prevent danger
to any person to ensure that - • An excavation (or part of) does not collapse • No material is dislodged or falls • No person is buried or trapped
Also • Steps to be taken to prevent persons, equipment or materials falling in
(Reg 22(2)) • Prevent excavation or adjacent ground from being overloaded (Reg
22(3)) And • No work should be carried out unless the excavation, equipment and
materials have been inspected by a competent person (Reg 22(4))
Enforcement
In the last 5 years - • Average 3 trench collapse fatalities per year • 27 RIDDOR Major Injuries • 430 Notices (Mostly Prohibition Notices) covering
• Risk of collapse of excavation onto persons • Risk of collapse that would carry
person/plant/structure into excavation • Risk of falls into unguarded excavation
• Other Notices requiring daily inspection • Significant proportion during basement excavation
Enforcement Cont.
Prosecutions • 9 brought by HSE resulting in fines • 2012 one fine of £150K + £28K costs • 2014 two fines of £15k + £2k costs (Not including FFI) • 2011 Cotswold Geotechnical - Corporate Manslaughter Death of geologist in 3.5 m deep pit in 2008 Fined £385K • 2014 Site Manager jailed for 3 years 3 months Consultant jailed for 9 months Manslaughter charges following death of labourer in Fulham in 2010 – Basement Excavation
Excavation Safety Basics
You probably all know this…..
……..but
Excavation Safety Basics
• A cubic metre of soil weighs around 1.75 Tonnes.
• Any fall of material presents a risk. • Unless the excavation can be battered to
a safe slope, the sides will need supporting to prevent collapse and provide safe conditions for persons working in or adjacent to the excavation.
• Support enables work to be carried out without interruption and protect adjacent property and /or services.
Perception
• The importance and need to provide proper support to excavations is often hard to explain to site operatives.
• Clays, to the inexperienced, often look very stable when first excavated.
• They stand up vertically, in many cases, for a surprisingly long time and a false sense of security is built up.
• Remember, it’s not if? but when? an excavation face will collapse
Basic soil mechanics
• Sides relieved of lateral support from surrounding ground
• Becomes unstable
• Material above natural angle of repose will partially or totally collapse at any time
Angle of Repose
Soil poured from a container will stand in a heap, the slope of which is known as the “Angle of Repose.”
This is a stable slope in the soil
Temporary safe slopes of soils
Table from CIRIA Report 97 - Trenching Practice
Excavation of trench
Surcharge loading
Reaction to foundation loading
Load
Wedge of soil under foundation driven into
ground
Soil pushed out and driven
upwards
Ground heaves
Undermining doesn’t mean you have to dig directly beneath the foundation
Soil slips off stable material
Wedge of soil at angle of repose
Earth face
Foundation exerts vertical load on soil below
Wall
What will the inspector do?
Planning the work
• Company Standards for excavation work • Risk Assessment procedure • Consider underground services • Temporary works input (Calculations &
Drawings) • Production of Method Statements (safe system of work)
• Selection of right plant and equipment • Competent site management and supervision
(especially front line supervisors)
Method Statements
• Geotechnical information
• Method of construction and support of excavation
• Access/ egress and edge protection
• Plant/ equipment to be used
• Buried services • Adjacent structures • Supervision of work
Geotechnical Report – Starting point
• Ground conditions need to be known to design the permanent or finished works.
• Information can be found from desktop study or previous experience of local area.
• More complicated jobs will need a site investigation including a geotechnical report
• Information can also be used by contractor when devising construction method (including support of excavations)
Excavation Solutions
Trench Boxes
Close Boarded Trench Support
Design of trench box - access ladder and
edge protection attached to box
Waler Frames – For Medium Sized Trenches
Hydraulic / Mechanical Struts Strutting Frame
Control Measures - battering or stepping back
• Battering or stepped excavations
• Based on safe angle of repose
• However you need the space on site to do this.
• A lot of sites maximise the footprint and hence no option to batter or step excavation
• Easier if new build • Still need to batter back
or provide support
Hit and miss or close boarding required
Stiff clay Sandy silty clay
Stiff Clays and soils
Open or hit and miss shoring
Soft Clays, Gravels & Sands
Close boarding or interlocked sheets
clay
Sand/ gravels
Soil types – layered strata
Layered soil strata can be very unstable
Therefore close support system with possible groundwater control required
Clay over Sandy/Gravel Fatality
Corner sheared off Clay layer
Void where gravel layer fell away
Presence of water
• Water table (geotechnical report)
• Ingress of water (e.g. broken water main)
• Affects stability of excavated face
• Washes out granular soils
• Soften clay soils
Use equipment properly
Don’t forget adjacent structures
Unsupported clay face and risk of undermining adjacent structure
Boundary wall can slip or overturn
Unsupported clay face
Protection for the public
Underpinning
Technique devised to treat subsidence now also used to form basements
Excavate below existing foundation
Form new pin or foundation
Heel can be designed out
Underpinning 2 – Schedule
Typical underpinning schedule drawn up by competent person
Should there be a requirement to support face of underpin section?
Need to consider sacrificial face support – usually steel sheet piles
Clay face starting to fail
Support of existing foundation
Underpinning – failure to survey existing wall and to prop
Basement Construction
• High Risk Work – needs careful planning before work starts on site
• Need Temporary works engineering input - can be an engineer or an experienced person.
• Method Statement should be in place, e.g. a clear method of how work is to be undertaken including shoring of excavations and support of existing or adjacent structures.
• Shoring material/ equipment is on site • Competent site supervision
Supporting existing structure above basement
Prohibition Notice served – temp wks engineer came back with props at 200mm centres below main walls of house
EOT starts to lean towards road
Emergency works by LA contractor
Excavator for sale - collection only!
Buried Services
• Plan the Work
• Obtain cable plans – only an indication
• Use cable locating devices – essential – Locate, identify and mark – Training – Check and maintain equipment
• Safe digging practices – Trial holes, horizontal digging,
insulated tools
Buried Services
Further information
• HSE Website http://www.hse.gov.uk/electricity/information/excavations.htm
• HSG47 ‘Avoiding Danger from Underground Services’
• Busy Builder CIS65
Information & Guidance
• Guidance concerned with Groundworks/ Excavations
• HSE Website ‘Structural Stability During Excavations’ www.hse.gov.uk/construction/safetytopics/excavations
• HSE Busy Builder Leaflets CIS64 on Excavation and CIS66 on Domestic Basement Construction
• HSE Website ‘Excavation and Underground Services’
www.hse.gov.uk/electricity/information/excavations.htm
Information & Guidance
• Construction Plant-Hire Association (CPA) – Shoring Technology Interest Group Publications
www.cpa.uk.net/shoring -technology-interest-group-stig-publications/ (Guidance on Management of Shoring in Excavations, Selection of shoring equipment) • Association of Specialist Underpinning
Contractors (ASUC) www.asuc.org.uk (Guidance on Underpinning, Basement
Extensions)
So what are temporary works?
Temporary Works is defined in BS5975 : 2008 as
“parts of the works that allow or enable construction of, protect, support or provide access to the
permanent works and which might or might not remain in place at the completion of the works“
Temporary Works (BS 5975:2008)
• Anything and everything used to assist with construction of the permanent works.
• An engineered design used to assist with construction and which may be removed; or left in situ (abandoned); or may be reused to become part of the permanent works.
• Includes basic excavation support
• Procedures for management and coordination are required
Small builders get confused……..
Remember
• Temporary condition is the problem
• Temporary Works is the solution
Also
• Decisions about build sequence, time allocation, construction method, const materials – all influence scale, complexity, cost and criticality of TW needed
Procedures for dealing effectively with TW
Small or simple job (SME / Micro dutyholder)
• Developer / contractor coordinates TW – paperwork to suit type & structure of company
• Subcontractor/s given lead within their specialism
• TW engineer used for bespoke or complex areas with independent design check on complexity / risk basis
• Installation / alterations / loading / unloading / dismantling overseen by main contractor working with subcontractor
Procedures for dealing effectively with TW
Big or complex job
• Appointment of TW coordinator & fine tuning of existing company paperwork procedures
• Appointment of TW designer
• Independent design check especially where complex / high risk
• Appointment of TW contractor
• Appointment of TW supervisor/s
• Full control of implementation – installation, alterations, loading, unloading, dismantling