Investor Update Untuk Meeting Mar2010 Rev2

Embed Size (px)

Citation preview

  • 8/7/2019 Investor Update Untuk Meeting Mar2010 Rev2

    1/32

    PT Perusahaan Listrik Negara (Persero)

    Investor Update Electricity for a Better Life

    STRICTLY CONFIDENTIAL

    Maret 2010

  • 8/7/2019 Investor Update Untuk Meeting Mar2010 Rev2

    2/32

    TABLE OF CONTENTS

    COMPANY OVERVIEW2

    INVESTMENT STORY3

    REGULATORY UPDATE4

    FINANCIAL UPDATE5

    1

    APPENDIX6

    PLN PROGRESS UPDATE1

  • 8/7/2019 Investor Update Untuk Meeting Mar2010 Rev2

    3/32

    PLN PROGRESS UPDATE

    2

  • 8/7/2019 Investor Update Untuk Meeting Mar2010 Rev2

    4/32

    PLN Progress Update

    3

    From H1 2008 to H1 2009, EBITDA has increased from Rp 8,690bn to Rp 12,578bn

    while the EBITDA margins increased from 11.1% to 18.3%

    The EBITDA interest coverage has also increased to 4.1x in H1 2009 from 2.8x in H1

    2008

    Improvements infinancial

    performance

    In October 2009, MoF issued letter for 5% margin in the 2009

    While 5% margin for 2010 has been approved and stipulated in the 2010 State Budget

    Law

    PLN continues to improve operations efficiency thereby reduce subsidy requirement

    Notable improvements include improvement in energy mix and reduction in system

    losses

    Approved 5%margin

    New ElectricityLaw

    ContinuedOperationalEfficiency

    improvement

    New capacitydevelopment

    Further significant progress has been made in the 10,000 MW Fast Track Program

    11 projects, equivalent to 6.2GW, have achieved 50% completion

    100% of the required funding for generation projects have been signed

    Law No. 30 of 2009 on Electricity (New Electricity Law) issued in Sept 2009

    Once implemented, private business enterprises, cooperatives and non-governmental

    enterprises will be permitted to participate in electricity generation, transmission and

    supply to customers

    However, PLN will retain first priority to be the electricity supplier for the public needs

    New Law will potentially support PLN to achieve a more solid financial position

    There have been a number of notable improvements and updates at PLN in the last few months

  • 8/7/2019 Investor Update Untuk Meeting Mar2010 Rev2

    5/32

    COMPANY OVERVIEW

    4

  • 8/7/2019 Investor Update Untuk Meeting Mar2010 Rev2

    6/32

    5

    PLN is the major electricity producer and supplier in Indonesia through its portfolio of Generation,Transmission and Distribution assets with generation capacity of about 25,611 MW1

    In accordance with the Law no.19/2003 governing SOEs, Government is under obligation to provide subsidy

    for PLN in carrying PSO mission

    Wholly-owned by Republic of Indonesia, supervised by MSOE, regulated by Ministry of Energy and Mineral

    Resources (MEMR) and monitored by the Ministry of Finance (MoF)

    Mandated to implement the Fast Track Program to build 10,000 MW of coal-fired generating plants(Presidential Decree No. 71/2006)

    Company Overview

    PLN is the only state-owned power utility company in Indonesia

    5

    Controls over 85%1 of nationalgeneration capacity

    Main purchaser of electricityfrom Independent PowerProducers (IPPs)

    Sole provider of powertransmission in Indonesia

    Transmission linesapproximately 34,000 kmcand 59,000 MVA of powertransformer capacity1

    Sole distributor of electricityto end customers in

    Indonesia Distribution lines of

    approximately 623,000 kmcand 34,000 MVA oftransformer capacity, serving39 million customers1

    Generation Transmission Distribution

    Note:

    1 As of June 30,2009

  • 8/7/2019 Investor Update Untuk Meeting Mar2010 Rev2

    7/32

    6

    100% Owned by GoI

    99.99% 99.99%

    99.99%99.99% 99.33%

    99.99% 99.97%

    Indonesia Power

    ElectricityGeneration

    PT PLN (Persero)

    99.99%

    PLN Geothermal

    Geothermal

    Ministry of State OwnedEnterprises (MSOE)

    Ministry of Energy andMineral Resources (MEMR)

    Ministry of Finance (MoF) Oversight

    Corporate Structure

    100%

    PLN Batu Bara

    Coal

    Majapahit Holding B.V.

    SPC

    Icon+

    ICT

    PLN Enjiniring

    Engineering Services

    PembangkitanJawa Bali

    ElectricityGeneration

    PLN Batam

    Electric Utility

    PLN Tarakan

    Electric Utility

    6

  • 8/7/2019 Investor Update Untuk Meeting Mar2010 Rev2

    8/32

    7

    Strong Management TeamCombination of Technical, Operations and Business Competence

    Name Title Other/ Previous Experience

    Board of Commissioners

    Yogo Pratomo President CommissionerDaily Coordinating Team and formerly Director General ofElectricity and The Utilization

    Rahmat Waluyanto CommissionerDirector General of Debt Management, Ministry of FinanceRepublic of Indonesia

    Adang Firman Independent Commissioner Former Head of Metro Jaya Police Dept

    Wimpy S. Tjetjep CommissionerFormer Deputy of Energy, Mineral Resources and ForestryCoordination for Ministry of Economic Coordinator

    Lutfi Hamid Independent Commissioner Former Consultant in Civil Engineering

    Syahrial Loetan CommissionerFormer Secretary for State Minister of PPN/ Head ofSecretary for Bappenas

    Abdul Aziz CommissionerFormer Special Staff for Minister of State Owned

    Enterprises

  • 8/7/2019 Investor Update Untuk Meeting Mar2010 Rev2

    9/32

    8

    Strong Management TeamCombination of Technical, Operations and Business Competence

    Dahlan Iskan President Director

    Owner of Jawa Pos Group, President Director/ CEO of PT PWU

    Jatim Group, President Director of Power Plant - PT Cahaya FajarKaltim

    I.G.A. Ngurah Adnyana Director of Java Bali OperationFormer Deputy Director of Distribution and General Manager in PLNBali Distribution Unit.

    Harry Jaya Pahlawan Director of West Indonesian OperationFormer PLN Vice President of International Relations and CorporateSecretary

    Vickner S inaga Director of East Indonesian OperationFormer Vice President of IPP Construction Services of PLN HeadOffice

    Murtaqi Syamsudin Director of Business and Risk ManagementFormer PLN Director of Java Bali, Corporate Secretary and GeneralManager of PLN Banten and West Java Distribution Unit

    Nasri S ebayang Director of Planning & TechnologyFormer PLN Head of Primary Energy & Deputy Director ofIndependent Power Producers

    Nur Pamuji Director of Primary EnergyFormer General Manager of PLN Java-Bali Transmission and LoadDispatch Center

    Bagyo Riawan Director of Strategic Procurement Former PLN Deputy Director of Java-Bali Power Generation

    Eddy D. Erningpraja Director of HR and General Affairs Former PLN Deputy Director of HR System Development

    Setio Anggoro Dewo Director of Finance

    Former Independent Commissioner of Indonesia Power and Indosat,

    Chairman of Accounting Post Graduate Program and Senior Lecturerin Economics at University of Indonesia

    8

    Board of Directors

    Name Title Other Experience

  • 8/7/2019 Investor Update Untuk Meeting Mar2010 Rev2

    10/32

    INVESTMENT STORY

    9

  • 8/7/2019 Investor Update Untuk Meeting Mar2010 Rev2

    11/32

    Investment Story

    StrongGovernment

    Support

    FavourableDemand and

    Supply Dynamics

    1

    2

    Fast Trackand

    IPP Program

    3

    OperationalExcellence

    4

    10

  • 8/7/2019 Investor Update Untuk Meeting Mar2010 Rev2

    12/32

    MoF Decree No. 111/PMK.02/2007 and its amendments ensure the difference between revenues and

    costs are covered without being subject to a cap Continuous review to ensure adequacy and timely payments Rising subsidy trend under challenging operating conditions

    In 2008 subsidy over the budgeted amount had been revised three times (from IDR 29.8 tn to IDR80.42 tn, in the last revision) to cover energy price increase

    In October 2009, MoF issued letter for 5% margin in the 2009 While 5% margin for 2010 has been approved and stipulated in the 2010 State Budget Law

    GoI emphasizes the importance of PLNs financial soundness to ensure stable electricity supply

    Notes:

    1. PSO : Public Service Obligation

    2. Latest budgeted amount (November/December 2008)

    3. Government budgeted subsidy for 2009 based on a 61$US/barrel oil cost assumption and foreign exchange 10,500 IDR/USD

    4. 2004-2008 are total revenues from electricity subsidies recognized by PLN in its audited financial statements

    Total Government Subsidy to PLN4

    Strong Government Support

    Extended government loan maturities, converted overdue interest and penalty charges into equity duringfinancial crisis

    Waived interest on certain tax payment deferrals and channels 2-step loans to PLN but remains theprimary obligor to lenders

    Law no. 19/2003 demonstrates GoIs willingness to support PLN through legislative provisions which cover

    the shortfall between revenues and costs for doing PSO1

    Government availability to inject equity in PLN in accordance with the prevailing laws to fund thedevelopment plan

    GovernmentFinancial

    Assistance

    GoI is involved in almost every critical stage of PLNs operations

    Budget setting, capex plans, IPP developments, primary energy supplyGovernment

    Close Involvement

    Provision of Timelyand Adequate

    Subsidies

    11

    1

    3.512.5

    32.9 36.6

    78.6

    45.03

    0

    30

    60

    90

    2004 2005 2006 2007 2008 2009E

    (Rptrillion)

  • 8/7/2019 Investor Update Untuk Meeting Mar2010 Rev2

    13/32

    Clear Legal Framework to Support PLN Subsidy Mechanism

    Mechanism based on the Ministry of Finance Regulation No. 111/PMK.02/2007 and its amendmentsensures certainty of the subsidy amount and timely cost recovery...

    Costs covered by Subsidy

    Power purchase

    Fuel

    Maintenance

    Personnel

    Administration

    Depreciation

    Interest and financingcosts

    1

    Note:

    1 Public Service Obligation 12

    Cost of Supply in Gov Budget Un-Audited Cost of Supply

    Audited Cost of Supply

    MOF Regulation No. 111/PMK.02/2007 and No. 162/PMK.02/2007

    95%

    Dec

    95%

    Dec

    95%

    Jan

    95%

    Feb

    95%

    Mar

    95%

    Apr

    95%

    May

    95%

    Jun

    95%

    Jul

    95%

    Aug

    95%

    Sep

    95%

    Oct

    2008

    Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

    Assumption

    Exchange rate Rp/USD

    Oil price, coal price

    Fuel mix

    Average selling price

    T&D losses

    etc

    Cost of Supply

    LV, MV, HV

    PSO1

    Jan

    100%

    1Q 100%

    2Q

    100%

    3Q

    100%

    PSO1

    2007

    95%

    Nov

    2009

    95%

    Jan

    95%

    Feb

    Feb Mar Apr

    95%

    Jan

    95%

    Jan

    95%

    Oct

    95%

    Jul

    95%

    Mar

    May

    Quarterly adjustment

    95%

    Apr

    Jun

    100%

    1Q

  • 8/7/2019 Investor Update Untuk Meeting Mar2010 Rev2

    14/32

    Favourable Demand / Supply DynamicsBacked by strong macro indicators, energy demand in Indonesia is expected to grow at more than9% p.a. in next few years1

    with planned capacity additions from the Fast Track Program to address the rise in demand

    2

    Projected Indonesian Energy Demand 2009 2018

    Low electrification ratio (62%) underlines the undersupply of electricity in Indonesia and shows the intrinsic growth potential forPLN

    More than 9% p.a. is projected demand growth over the next few years

    Urgent need for new generation capacity due to frequent power outages in recent years

    PLNs diversified asset base is located across Indonesia, with a large portion serving the most populated area of Indonesia, theJava-Bali region

    60% of the population in Indonesia (140 million) live on the island of Java, with nearly 1,000 people per square kilometer

    Java-Bali represents ~80% of energy demand requirements in Indonesia, with nearly of total generating capacity located there

    Peak load of 16.3 GW in Java-Bali in 2008 represents ~75% of overall Indonesia demand (Indonesia 22 GW)

    Reserve Margin of Java-Bali system in 2008 was 28%

    Unit 2009 2010 2012 2014 2018

    1.Energy Demand

    - Indonesia TWh 137.9 149.3 179.2 215.6 309.4

    - Java-Bali TWh 107.0 115.3 137.5 165.0 235.3

    - Outside Java-Bali TWh 30.9 34.0 41.7 50.6 74.1

    2.Electrification Ratio

    - Indonesia % 66.9 69.3 75.0 81.2 93.6

    - Java-Bali % 70.0 72.6 78.7 85.4 97.9

    - Outside Java-Bali % 61.3 63.2 68.3 73.6 86.1

    13

    0

    50

    100150

    200

    250

    300

    350

    2007 2009 2011 2013 2015 2017

    T

    Wh

    Indonesia Jawa Bali Outside Jawa Bali

    Note:1 Based on RUPTL (Long Term Power System Expansion Plan) endorsed by Ministry of Energy Mineral Resources Decree No. 2780.K/21/MEM/2009 dated

    December 19, 2008

  • 8/7/2019 Investor Update Untuk Meeting Mar2010 Rev2

    15/32

    14

    JavaBali Generation Development

    To meet growing electricity demand, Indonesia has plans to develop a further 35.7 GW by 2018

    3

    2009 2018 JavaBali Development Plan1

    Note:1 Minister of Energy and Mineral Resources Decree No. 2780.K/21/MEM/2008 dated 19 December 2008, with updated COD schedule on the projects

    currently under construction/process

    which will be initially achieved via the Fast Track program and IPP developments

    0

    1,000

    2,000

    3,000

    4,000

    5,000

    6,000

    2009 2010 2011 2012 2013 2014 2015 2016 2017 2018

    Capacityad

    dition(MW)

    PLN IPP

  • 8/7/2019 Investor Update Untuk Meeting Mar2010 Rev2

    16/32

    Shortage of electricity in Indonesia

    Abundance of coal in Indonesia Electricity generation with coal is much cheaper than with oil fuel

    Long term strategy to replace oil fuel generation with coal fuel generation to lower fuel costs

    Key Drivers

    Overview ofFast TrackProgram

    Formalised through Presidential Regulation no. 71/2006 in which PLN was mandated by GoIto build coal-fired power plants throughout Indonesia

    To reduce subsidy burden for the GoI, to reduce PLNs costs and to meet rising domestic

    electricity demand

    A Committee is set up through Presidential Regulation No. 72/2006, whose membersinclude Coordinating Minister of Economics, MOF, MSOE, MEMR and BAPPENAS

    Develop 10 coal-fired power plants in Java-Bali and 25 coal-fired power plants outside Java-Bali totaling of approx. 9.5 GW, to be largely completed by 2011

    Once completed, significantly reduce oil fuel as a proportion of total fuel from 35.2%1 in 2008to below 10%1 in 2012

    All new IPP power plants will continue to be based on non-oil fuel

    ProgramDescription

    15% equity funding from PLN already committed

    85% bank financing guaranteed by the GOI already committedFinancing

    Fast Track Program Overview3

    15

    Note:1 Excludes IPPs and it is expressed in terms of percentage of total kilowatt hours generated by each fuel source

  • 8/7/2019 Investor Update Untuk Meeting Mar2010 Rev2

    17/32

    221 210 268

    1,391 1,461

    2,359

    1,314

    167 174 249366

    367

    0

    500

    1,000

    1,500

    2,000

    2,500

    2006 2007 2008 H1 2009

    (Rp/kWh)

    Coal Natural Gas Oil Fuel

    Breakdown of Fuel and Lubricants CostsBreakdown of Total Operating Expenses

    As a material portion of PLN's generation capacity is oil fuel fired, increasing oil fuel pricessignificantly increased operating expenses....

    ...creating the need for PLN to replace oil fuel fired facilities with coal fired power stations

    Rationale for Fast Track Program Fuel Mix Improvement3

    Fuel Cost Comparison

    16

    0

    30,000

    60,000

    90,000

    120,000

    2006 2007 2008 H1 2008 H1 2009

    (Rpbn)

    Oil Fuel Natural Gas Coal

    Geothermal Lubricants Water

    63,401 65,560

    107,783

    34,30751,271

    0

    50,000

    100,000

    150,000

    200,000

    2006 2007 2008 H1 2008 H1 2009

    (Rpbn)

    Fuel and Lubricants Electricity Purchase Maintenance

    Personnel Depreciation Others

    105,228111,506

    160,598

    62,81275,490

  • 8/7/2019 Investor Update Untuk Meeting Mar2010 Rev2

    18/32

    Fast Track Program in Progress Overview

    Project progress varies, 11 projects, equivalent to 6.2GW, have achieved more than 50%progress

    - 3 power plants, equivalent to approximately 1.0GW, are expected to be commissioned by

    end of 2009- The remainder will be largely completed by 2011

    ProjectConstruction

    33 EPCContracts

    signed

    33 EPC contracts signed including 10 locations in Java-Bali (7.5GW) and 23 locationsoutside Java-Bali (2.0GW)

    Total capacity of approximately 9.5 GW if all 33 locations are built

    More than half of coal requirements have been secured by long term coal supply contracts(20 years)

    Most of the remaining balance is under contract finalization process while the rest of thebalance will be tendered out

    Coal Supply

    Transmission is being developed in parallel with the power station construction

    Total investment estimate is USD 2.2 billion

    Transmissionsystem

    17

    3

  • 8/7/2019 Investor Update Untuk Meeting Mar2010 Rev2

    19/32

    Funding for Fast Track Program

    PLN has made significant progress in securing the required funding for the Fast Track Program

    Transmission

    Generation

    3

    Disbursement as of 31 December 2009

    As of February 2010

  • 8/7/2019 Investor Update Untuk Meeting Mar2010 Rev2

    20/32

    Coal

    68%

    Geothermal

    15%

    Gas

    16%

    Oil

    1%

    17 IPPs totaling 4,247MW currently under development

    23 small IPPs (less than 50MW) totaling 227MW currently under development

    Underdevelopment

    In Operation 4,568 MW in operation or about 15% of total national capacity

    Supplied by 21 IPPs

    IPP Program Overview3

    19

    Under Development (4,474 MW)1In Operation (4,568 MW)1

    Coal

    74%

    Geothermal

    17%

    Hydro

    9%

    Note:

    1 As of June 30 2009

    The Fast Track Program is complimented by a strong pipeline of IPP developments

  • 8/7/2019 Investor Update Untuk Meeting Mar2010 Rev2

    21/32

    Corporate Strategy Clear Roadmap Ahead for PLN

    Corporate Strategy to maximize achievement of PLNs Strategic Objectives

    4

    Price restructuring

    Margin optimization

    Sales optimization

    Margin optimization

    Increase sales

    Immediate (2009) Mid Term (2010-2011) Long Term (> 2011)

    Fuel mix improvement

    Continuous efficiencyimprovement

    Demand Side Management

    Continuous efficiencyimprovement

    10,000 MW Fast TrackProgram

    Maximize asset utilization

    Accelerate IPP participation

    Maximize assetutilization

    Operational Excellenceimprovement

    Corporate wide onlinesystem information

    Competency basedHRM

    B2B initiatives

    Pre-paid meter

    Demand-Side Management

    Business process improvement

    GCG/Compliance (ERM)

    HR competencies

    ICT system improvement (ERP, EAM, CCB)

    Subsidiaries/ affiliates alignment

    Securing Primary Energy

    Fuel mix improvement

    Efficiency program: eg Reduce Losses,

    Maintenance, Adm. costs

    10,000 MW Fast Track Program

    Increase T&D capacity

    Capacity optimization

    Connection cost paid by customers

    Improve operating procedures

    Availability and reliability improvement

    RevenueManagement

    CostManagement

    CapacityManagement

    OperationalPerformance

    Management

    Supporting /Enabler

    20

    Operational Excellenceimplementation

    System & organizationrevitalization

    Competencies based HRM

    Continuous ERMimprovement

    Continuous ICT systemimprovement

  • 8/7/2019 Investor Update Untuk Meeting Mar2010 Rev2

    22/32

    48.0% 48.9% 50.6% 50.2%

    2006 2007 2008 H1 2009

    Operations Efficiency Program

    System (Transmission & Distribution) Losses Collection Period (days)

    Reducing System Losses1

    Implementing Efficiency Drive Program2

    Improving Operation and Maintenance System3

    4 Reducing Collection Period

    Efficiency ProgramCapacity Factor

    21

    4

    Effective revenue and cost management provided for improved profitability in 2008

    10.9 10.8

    8.4 8.6

    2006 2007 2008 H1 2009

    11.5% 11.1% 10.5% 10.1%

    0%

    5%

    10%

    15%

    2006 2007 2008 H1 2009

    Transmission Losses Distribution Losses System Losses

  • 8/7/2019 Investor Update Untuk Meeting Mar2010 Rev2

    23/32

    REGULATORY UPDATE

    22

  • 8/7/2019 Investor Update Untuk Meeting Mar2010 Rev2

    24/32

    Regulatory update

    Private business enterprises, cooperatives and non-governmental enterprises are allowed

    to participate in the electricity supply business under the New Electricity Law However, PLN still has a first priority to be the electricity supplier for the public needs1

    Industry

    framework

    Overview

    On 23 September 2009, the Government issued Law No. 30 of 2009 on Electricity (New

    Electricity Law) which replaces Law No. 15 of 1985 (Old Electricity Law)

    The implementing regulations of the New Electricity Law shall be issued within one yearafter its enactment, before which the implementing regulations of the Old Electricity Law stillis still deemed valid

    Allows differentiation of tariffs across regions

    Parliament approval will be required for tariff settingTariff structure

    No specific provisions concerning PLNs Government subsidies has been provided

    PLN believes that the subsidy policy will remain in forceSubsidies

    Electricity supply business now requires Electricity Supply Business License (IUPTL) for

    the purpose of supplying electricity for public use

    PLN is deemed as having already obtained the IUPTL

    Licensing

    23

    The New Electricity Law will open up the Indonesian electricity supply market to new participants

    Note:

    1 The new law does not specifically state that the priority is given to PLN, but given to state owned enterprise (which PLN is one of them)

  • 8/7/2019 Investor Update Untuk Meeting Mar2010 Rev2

    25/32

    FINANCIAL UPDATE

    24

  • 8/7/2019 Investor Update Untuk Meeting Mar2010 Rev2

    26/32

    Strong Financial Profile

    EBITDA and EBITDA Margin

    EBITDA to Interest

    Sales and GoI Subsidy

    Total Debt and Cash

    PLN enjoys positive cash flows and EBITDA and a healthy balance sheet

    25

    53,382 66,482

    93,809 97,896

    12,968 16,2916,388 9,637

    0

    30,000

    60,000

    90,000

    120,000

    2006 2007 2008 H1 2009

    (Rpbn

    )

    Debt Cash

    4.4x

    3.0x 2.4x

    4.1x

    2006 2007 2008 H1 2009

    0

    45,000

    90,000

    135,000

    180,000

    2006 2007 2008 H1 2008 H1 2009

    (Rpbn)

    Sales Government Subsidy

    103,644 112,891

    162,827

    68,19477,282

    10,827

    14,32116,109

    12,5788,690

    10.3%12.6%

    9.8%

    11.1%

    18.3%

    2006 2007 2008 H1 2008 H1 2009

    (Rpbn)

    EBITDA EBITDA Margin (%)

  • 8/7/2019 Investor Update Untuk Meeting Mar2010 Rev2

    27/32

    4.9x4.6x

    5.8x

    3.9x

    2006 2007 2008 H1 2009

    Strong Financial Profile

    Debt to EBITDA

    Debt to Equity Ratio

    Net Debt / EBITDA

    Total Debt / Total Capitalization

    The Company has sustainable gearing and good cash flow coverage

    26

    Note:

    1 On annualised basis

    27.6%32.8%

    42.5% 42.3%

    2006 2007 2008 H1 2009

    38.2%

    48.7%

    73.9% 73.2%

    2006 2007 2008 H1 2009

    3.7x3.5x

    5.4x

    3.5x

    2006 2007 2008 H1 2009

  • 8/7/2019 Investor Update Untuk Meeting Mar2010 Rev2

    28/32

    THANK YOU

    27

  • 8/7/2019 Investor Update Untuk Meeting Mar2010 Rev2

    29/32

    APPENDIX

    28

  • 8/7/2019 Investor Update Untuk Meeting Mar2010 Rev2

    30/32

    Fast Track Program Status Update Java Bali Island3

    29

    Size Total(MW) (MW) (millions) *) Bank (billions) *) Bank 2009 2010 2011 2012 2013

    1 Labuan, Banten 2 x 300 600 289 BNI 1,189 BCA 300 300 - - -

    2 Rembang, Jateng 2 x 315 630 262 CDB / Barclays 1,911 Mandiri - 630 - - -

    3 Suralaya, Banten 1 x 625 625 284 CEXIM 735 Mega - 625 - - -

    4 Indramayu, Jabar 3 x 330 990 592 BOC 1,273 BNI - 990 - - -

    5 Paiton, Jatim 1 x 660 660 331 CEXIM 601 Mega - 660 - - -

    6 Pacitan, Jatim 2 x 315 630 293 CEXIM 1,046 Bukopin - - 630 - -

    7 Teluk Naga, Banten 3 x 315 945 455 BOC 1,607 Bukopin - - 945 - -

    8 Pelabuhan Ratu, Jabar 3 x 350 1,050 482 CEXIM 1,874 Mega - - 700 350

    9 Tanjung Awar2, Jatim 2 x 350 700 372 BOC 1,155 BNI - - - 700

    10 Adipala, Jateng 1 x 660 660 468 CDB / ICBC 1,890 CDB / ICBC - - - - 660

    7,490 3,828 13,281 300 3,205 2,275 1,050 660

    Loan effective Note: *) Status as of 15 Feb 2010

    Loan signed but not effective yet

    Total

    No Project USD Portion IDR Portion Expected capacity in the year commercial

  • 8/7/2019 Investor Update Untuk Meeting Mar2010 Rev2

    31/32

    Fast Track Program Status Update Other Islands3

    30

    Size Total

    (MW) (MW) (millions) *) Bank (billions) *) Bank 2010 2011 2012

    1 Ende, East Nusa Tenggara 2 X 7 14 8 Asbanda 73 Mega 14 - -

    2 Tjg Bale Karimun, Riau Islands 2 X 7 14 7 BRI 71 Mega 7 7 -3 Kendari, Southeast Sulawesi 2 X 10 20 10 Asbanda 97 Mega 10 10 -

    4 Amurang Baru, North Sulawesi 2 X 25 50 27 Asbanda 305 Mega - 50 -

    5 Bangka Baru, Bangka Belitung 2 X 30 60 23 BRI 317 BRI 30 30 -

    6 Gorontalo Baru, Gorontalo 2 X 25 50 26 Asbanda 265 Mega - 50 -

    7 Pangkalan Susu, North Sumatera 2 X 220 440 209 BRI 781 Mega - 440 -

    8 Barru, South Sulawesi 2 X 50 100 52 BRI 380 BRI - 100 -

    9 Tarahan, Lampung 2 X 100 200 119 BRI 460 Mega - 200 -

    10 Meulaboh, Nanggroe Aceh D. 2 X 110 220 124 CEXIM 614 Asbanda - 220 -

    11 Tidore, North Maluku 2 X 7 14 10 Asbanda 100 Asbanda - 14 -12 Jayapura, Papua 2 X 10 20 14 BRI 141 BRI - 20 -

    13 Kupang, East Nusa Tenggara 2 X 16.5 33 23 Asbanda 135 Asbanda - 33 -

    14 Asam-Asam, South Kalimantan 2 X 65 130 84 BRI 313 BRI - 130 -

    15 Bima, West Nusa Tenggara 2 X 10 20 8 Asbanda 120 Asbanda - 20 -

    16 Belitung Baru, Bangka Belitung 2 X 16.5 33 24 Asbanda 142 Asbanda - 33 -

    17 Teluk Sirih, West Sumatera 2 X 112 224 138 CDB 521 Asbanda - - 224

    18 Lombok, West Nusa Tenggara 2 X 25 50 24 Asbanda 274 Mega - 50 -

    19 Bengkalis, Riau 2 X 10 20 8 BRI 132 BRI - 20 -

    20 Pulang Pisau, Central Kalimantan 2 X 60 120 62 Asbanda 414 Mega - 120 -

    21Singkawang Baru, West

    Kalimantan2 X 27.5 55 31 Asbanda 172 Asbanda - 55 -

    22 Selat Panjang, Riau 2 X 7 14 9 BRI 111 BRI - 14 -

    23 Parit Baru, West Kalimantan 2 X 50 100 62 BRI 392 BRI - - 100

    2,001 1,102 6,330 61 1,616 324

    Loan effective Note: *) Status as of 15 Feb 2010

    Loan signed but not effective yet

    Total

    No ProjectExpected capacity in theUSD Portion IDR Portion

  • 8/7/2019 Investor Update Untuk Meeting Mar2010 Rev2

    32/32

    Indonesia remains in strong position to continue the improvement in its economy

    Steady Economic Prospect

    Indonesias economic momentum was better than

    expected in Q2 2009. Private consumption andinvestment continued to lead GDP growth in Q22009 (4.0% YoY) and for 1H2009 (4.2% YoY)

    Indonesias GDP in Q2 2009 is one of the highest

    in Asia, if this momentum is maintained, there willlikely be upward revisions to consensusexpectations for GDP forecast of 4.0% in 2009

    Stable government and stable economicdevelopment will likely to continue given that theincumbent president, SBY, will run the office for

    the next 5 years

    Improved Investment Climate

    Foreign capital continues to pour into thedomestic market while adding to foreign exchangesupply on the money market.

    Capital inflows in Indonesia are supported byoptimism for global and domestic economicrecovery, attractive yields on Rupiah instrumentsand improving perceptions of risk.

    Moodys upgraded Indonesias rating to Ba2 inSeptember 2009 which was prompted by theIndonesian economy's relatively strong resilienceto the global recession as well as its healthy

    medium-term growth prospects

    Solid Current Account & FX Reserves

    Support

    FX reserves stood at US$62.3 billion as ofSeptember 2009; equivalent to a healthy 6.2months import and government debt payments

    Structural improvement on non-oil trade trends,spurred by mining, plantation and commoditiesproducts

    Govt budget deficit is expected to expand fromUS$0.4bn to US$11.8bn (2.5% of GDP) in 2009,which can be sufficiently funded by 2008 financingsurplus, standby loans from multilateral partner,planned samurai and sukuk bonds issuance

    2009 Government Fiscal Stimulus

    Accelerate job and small business creationthrough peoples empowerment (PNPM),expansion credit programs (KUR) and newinfrastructure projects

    Increase purchasing power through basic goods

    (medicine, cooking oil) subsidies, direct cash andnon-cash subsidies for low income householdsand subsidies for health and education sectors

    Stimulate trade through import duty facilities,export financing, tax rate reductions and discounton peak electricity and diesel cost

    Source: Bank Indonesia, Ministry of Finance

    Reduced Risk to Inflation

    The ongoing downward trend in core inflation isbolstered by appreciation in the exchange rate,low imported inflation and declining public inflationexpectations.

    Volatile food inflation is down significantly

    consistent with the ongoing decline ininternational commodity prices

    September 2009 inflation eased to 2.8% from ahigh of 12.1% in September 2008

    The annual rate of inflation for 2009 is predictedto maintain a downward trend.

    Interest Rate Easing

    BI remains focused on easing liquidity tightnessby lowering BI interbank rate. Interbank rateshave come down by 225bps YTD and arecurrently at 6.50%

    BI will continue to monitor and respond in order to

    maintain currency strength and anchor inflationaryexpectations

    The Indonesian banking system remains in strongcondition with the CAR and NPLs within safelimits and generally CAR higher than mostregional banks

    PLN Backed by Resilience of the Indonesian Economy

    32