Iron Ore 2009 McNab Jankovic David and Payne

Embed Size (px)

Citation preview

  • 8/3/2019 Iron Ore 2009 McNab Jankovic David and Payne

    1/12

    Processing of Magnetite Iron Ores Comparing GrindingOptions

    B McNab 1, A Jankovic 2, D David 3 and P Payne 4

    ABSTRACTAlthough the majority of current steel production is supported by iron oresourced from high0grade haemetite deposits, the long-term growingdemand for steel has led to higher raw material prices and opened theway for many new magnetite deposits to also be developed.

    There is a rich and long history of magnetite ore processing in Westerncountries, including large operations such as Cleveland Cliffs in the USAand LKAB in Sweden, as well as smaller operations like Savage River inTasmania. The challenge for virtually all magnetite operations is tominimise operating costs, which is dominated by the cost of powerrequired to fine grind the ore in order to achieve acceptable concentrateiron grade together with low impurity content. This remains the casetoday and will be even more important in the future when a carbon tax isexpected to become a significant addition to the operating costs formagnetite deposits.

    Historically, the lowest operating cost was achieved by multistage fullyautogenous grinding with integrated magnetic separation steps betweenthe stages. The major benefit of fully autogenous grinding is theelimination of steel grinding media costs and the need to discriminatebetween steel and magnetite in coarse magnetic separation. Theseparation step between grinding stages progressively reduces the amountof material to be ground.

    Application of more efficient grinding technologies developed in thelast 20 years, including high pressure grinding rolls (HPGR) for finecrushing and stirred milling for fine grinding, has provided opportunitiesto further reduce the operating costs associated with comminution. Bothtechnologies are already implemented in some magnetite processingoperations, although in limited capacity.

    The results of a theoretical option study for high capacity processing of a hard, fine-grained silica-rich magnetite ore is presented in this paper,

    with the emphasis on comminution circuit options. Several circuit optionsare ranked based on a net present value analysis incorporating an estimateof carbon tax added in the operating cost. The study demonstrates thesignificant advantages of applying more efficient autogenous grindingtechnologies.

    INTRODUCTION

    World iron ore resources are estimated to exceed 800 billiontonnes and world iron ore production in 2006 was 1690 Mt. Newiron ore mining capacity taken into operation in 2007 reachedalmost 130 Mt globally (United Nations Conference on Tradeand Development, 2008). In Australia, magnetite is mined at theSavage River mine with reserves of 22 Mt of magnetite ore at52 per cent Fe and the Iron Magnet deposit which has 300 Mt of magnetite ore reserves grading 37 per cent Fe. There are atleast 4.5 billion tonnes of magnetite resources grading 33.5 -36.5 per cent Fe in Western Australia, 1.5 billion tonnes at 31 -50 per cent Fe in South Australia and 700 Mt at 25 - 52 per centFe in Tasmania and Queensland (Clout et al , 2004).

    Compared to direct ship haemetite ores mined from the upperregolith, magnetite deposits require significant beneficiation,which typically involves grinding to a particle size wheremagnetite is liberated from its silicate matrix. Many banded ironformation deposits in the Pilbara and Yilgarn cratons withinWestern Australia and the Gawler craton within South Australiaare very fine grained, often requiring a final concentrate grindsize P 80 (80 per cent passing size) of 25 - 35 m. The amount of energy required to produce a magnetite product suitable for sale aspellet plant feed is substantially more than an equivalent directship lump (6 mm) and fines (

  • 8/3/2019 Iron Ore 2009 McNab Jankovic David and Payne

    2/12

    (HPGR) for fine crushing and stirred milling for fine grinding,has provided opportunities to further reduce the operating costsassociated with grinding. At Empire Mines a HPGR is installedfor processing crushed pebbles and its introduction has resultedin a primary AG mill throughput increase in the order of 20 per cent (Dowling et al , 2001). Application of Vertimill finegrinding technology at Hibbing Taconite Company enabledprocessing of lower grade ores and increased the concentrate

    production (Pforr, 2001).The Whyalla magnetite plant in South Australia is specificbecause it utilises the HPGR technology for comminution of theprimary ore. The HPGR circuit is closed with a 3 mm aperturewet screen with the undersize reporting to the rougher magneticseparators (RMS). Banded iron formation (BIF) ores at Whyallaallow a relatively large silica rejection to the RMS tailings streamand so are well suited to the particle size that can be effectivelygenerated by a commercial size closed circuit HPGR system.Figure 1 shows the plant feed bin (left of photo) and the highpressure grinding rolls.

    STUDY OPTIONS

    An option study for a 10 Mt/a ore processing plant for aconsistently hard, fine-grained silica-rich magnetite ore wascarried out, with the emphasis on comminution circuit options. Acapacity of 10 Mt/a was selected to simplify the comparison bykeeping within the current single processing line limitations of theworlds largest AG mill capabilities. In practice, GRD Minprochas undertaken studies of Australian concentrators from 10 Mt/aup to 80 Mt/a, whereby the level of design, layout and operationcomplexity significantly appreciates when multiple trains of

    worlds largest equipment need to be integrated.For the purpose of the study, the concentrator was assumed to

    be located in the Pilbara of Western Australia within 100 km of aport suitable for facilitating equipment delivery. It was assumedthat there were no restrictions on spatial layout and that theprocess facility would be built on ground of a sound geotechnicalcharacter. Any subsequent differences in tailings disposal, waterrecovery, operation and cost were not considered.

    The approach taken in comparing various flow sheet optionswas in line with GRD Minprocs typical conceptual or scopinglevel assessment methodology and delivers a plus or minus35 per cent capital and operating cost accuracy. Such an exerciseis recommended at the commencement or prior to theprefeasibility study phase of a magnetite project. To enable ameaningful study a minimum required level of comminution andbeneficiation test work should have been undertaken beforehand.

    A minimum set of ore comminution properties are required fora conceptual design. An example is provided in Table 1 and isused as the basis for this theoretical study.

    The magnetite concentrate weight recovery, specific gravity(SG), predicted Bond abrasion index (Ai), iron and silica contentwere based on the following relationships:

    Concentrate weight recovery % = 10.737 ln( P 80) - 3.0945

    Concentrate iron content Fe % = -8.4667 ln( P 80) + 98.455

    Concentrate SG = 0.84 ( )% . % .Fe Fe

    +

    518724

    13 0

    724

    Concentrate Ai = 0.05(% Si020.4332 )

    Concentrate silica content Si0 2 % = 9.6966 ln( P 80) - 29.571

    The fine-grained nature of this hypothetical ore results in arelatively late release or liberation curve as illustrated in Figure 2.This fundamental property of a magnetite ore is generally one of the most salient drivers of flow sheet design and therefore flowsheet option generation. For example, it is not uncommon formagnetite banded iron formation ores to exhibit two distinctliberation zones, a coarse size consistent with the inherent silicabanding width and a finer size related to the unlocking of silicates within the magnetite bands.

    For the ore considered, only 20 - 30 per cent of feed mass canbe rejected magnetically in the size range typical for closedcircuit HPGR operation. Conversely, significant mass up toapproximately 50 per cent can be rejected to tails at a P 80 of 150 m which could be achievable with a closed circuit AG milloperation.

    FLOW SHEET OPTIONSFour circuit options were considered for comparison with thefollowing acronyms used to identify the primary unit processwithin each:

    COS coarse ore stockpile, SC secondary crush, HPGR high pressure grinding roll, AGC autogenous mill in closed circuit with cyclones and

    pebble crusher,

    RMS rougher magnetic separation, CMS cleaner magnetic separation,

    CMS2 second cleaner magnetic separation,

    2 Perth, WA, 27 - 29 July 2009 Iron Ore Conference

    B McNAB et al

    FIG 1 - High pressure grinding rolls at Whyalla magnetiteconcentrator plant (Morgan, 2007).

    Ore grade % FeT 32.2

    Drop weight index (DWi) kWh/m 3 11.1Ore specific gravity 3.40

    Concentrate specific gravity 4.30

    Bulk density t/m 3 2.01

    Bond ball mill work index (BBWi) kWh/t 17.2

    Bond abrasion index (BAi) 0.3

    Bond rod mill work index (BRWi) kWh/t 17.7

    Bond crushing work index (BCWi) kWh/t 20.6

    Point load index (PLI) MPa 14.8

    Unconfined compressive strength (UCS) MPa 355

    Fibrous mineral content Nil

    TABLE 1Ore design parameters.

  • 8/3/2019 Iron Ore 2009 McNab Jankovic David and Payne

    3/12

    PM pebble mill, PC primary crusher, SM stirred mill, and TSF tailings storage facility.

    Option 1 PC/AGC/RMS/PM/CMSPrimary crushing AG milling in closed circuit withhydrocyclones and pebble crushing rougher magnetic separation pebble milling cleaner magnetic separation (see Figure 3).

    Option 1 resembles the well known fully autogenous LKABand Cleveland Cliffs style operations. Absence of steel grindingmedia significantly reduces the operating cost. Pebble millcontrol and pebble transport and handling requirements addcomplexity to the design and operation. A P 80 of 250 m wasnominated for the RMS feed.

    Option 2 PC/AGC/RMS/BM/CMS/SM/CMS2Primary crushing AG milling in closed circuit withhydrocyclones and pebble crushing rougher magneticseparation ball milling cleaner magnetic separation tertiarymilling using stirred mills second cleaner magnetic separation.(see Figure 4)

    Option 2 has an additional grinding and magnetic separationstage compared to Option 1 and is considered to be simple indesign and operation. In respect to the grinding flow sheet, it is

    similar to the Savage River operation although the AG mill isclosed with hydrocyclones rather than screens, there is nohydroseparator and a third stage of comminution has been addedin respect of the finer liberation requirement. For reasons of costestimation and layout simplicity hydrocyclones have beenselected rather than screens to close the AG mill circuit for bothOptions 1 and 2.

    A P 80 of 250 m was nominated for the RMS feed, 75 m forthe CMS feed and 30 m for the CMS2 feed.

    Option 3 PC/C SC/C HPGR/RMS/BM/CMS1/SM/ CMS2Primary crushing closed circuit secondary crushing closedcircuit HPGR rougher magnetic separation ball milling firstcleaner magnetic separation tertiary milling using stirred mills second cleaner magnetic separation (see Figure 5).

    In Option 3 secondary crushing and HPGR effectively replaceAG milling with pebble crushing. Application of HPGR, stirredmilling and additional magnetic separation stage reduces thepower requirements compared to Options 1 and 2. The flow sheetis similar to that applied at Project Magnet south of Whyalla inSouth Australia and the proposed Gindalbie Project east of Geraldton in Western Australia.

    A P80 of 2300 m was nominated for the RMS feed, 75 m forthe CMS feed and 30 m for the CMS2 feed. This wouldnecessitate wet screening to close the HPGR circuit.

    Option 4 PC/SC/O HPGR/PM1/RMS/PM2/CMS1/

    SM/CMS2Primary crushing secondary crushing screening openHPGR coarse pebble milling rougher magnetic separation fine pebble milling first cleaner magnetic separation tertiarymilling using autogenous stirred mills second cleaner magneticseparation (see Figure 6).

    Option 4 is an attempt to design a circuit with the lowestoperating cost through increased grinding energy efficiencyusing three stages of magnetic separation, traditionalautogenous milling, HPGR and stirred milling technology. Inthis conceptual flow sheet steel grinding media is eliminated.Circuit complexity is partially reduced by open secondarycrushing, HPGR grinding and stirred milling operation althoughrecovery, storage and control of three separate sized media

    streams is introduced. It is assumed that a magnetic selectionprocess is applied to collect each media stream therebymaximising the power drawn thus capability of the downstreamautogenous grinding unit.

    A P 80 of 500 m was nominated for the RMS feed, 75 m forthe CMS feed and 30 m for the CMS2 feed.

    ENERGY COMPARISON

    With the exception of the primary crushing module, which isconsistent between options, estimates were developed for thetotal power drawn in the comminution, classification andmagnetic separation areas of each circuit. Energy consumed bymaterial transport machinery related to pumping between areaswas not considered at this level of study. A summary of theresultant unit circuit energy for each option is shown in Figure 7.

    Iron Ore Conference Perth, WA, 27 - 29 July 2009 3

    PROCESSING OF MAGNETITE IRON ORES COMPARING GRINDING OPTIONS

    y = 10.737ln(x) - 3.0945R = 0.9705

    30

    40

    50

    60

    70

    80

    90

    10 100 1000 10000

    P80 Size (m)

    M a s s

    % o f

    f e e d

    t o m a

    g n e t i c

    c o n c e n t r a t e

    FIG 2 - Grind versus liberation.

  • 8/3/2019 Iron Ore 2009 McNab Jankovic David and Payne

    4/12

    4 Perth, WA, 27 - 29 July 2009 Iron Ore Conference

    B McNAB et al

    FIG 3 - Option 1 flow sheet.

    FIG 4 - Option 2 flow sheet.

  • 8/3/2019 Iron Ore 2009 McNab Jankovic David and Payne

    5/12

    Iron Ore Conference Perth, WA, 27 - 29 July 2009 5

    PROCESSING OF MAGNETITE IRON ORES COMPARING GRINDING OPTIONS

    FIG 5 - Option 3 flow sheet.

    FIG 6 - Option 4 flow sheet.

  • 8/3/2019 Iron Ore 2009 McNab Jankovic David and Payne

    6/12

    A significant circuit energy reduction is predicted withOptions 3 and 4, which include HPGR and stirred milling. Some

    33 per cent of additional energy separates the most energyefficient option (Option 4) from the least efficient, the twostage AGC Pebble circuit, Option 1. In todays market and theprojected energy market during the life cycle of a typicalmagnetite concentrator the magnitude of this difference issignificant unless the cost of power is negligible (

  • 8/3/2019 Iron Ore 2009 McNab Jankovic David and Payne

    7/12

    is from electrical energy consumption while indirect contributionfrom steel consumption (dominated by grinding media) is inthe order of five to 16 per cent for Options 2 and 3 that utiliseball milling.

    PROCESS CAPITAL COST

    The scope of the estimates follows the work breakdown structuredeveloped specifically for the study and considers each flowsheet from the COS reclaim feeders to either the final magneticseparator concentrate discharge or the magnetic separator tailingsdischarge. As such, no concentrate or tailings handling, filtrationor storage was considered. For simplicity some equipment orcosts considered common to all options have been omitted.

    The estimate is developed based on the premise that the processis located inland in north-west Western Australia. All costs areestimated in Australian dollars and are presented as first quarter2009 costs. They are judged to have an accuracy of 35 per cent,which is commensurate with the accuracy requirements for a highlevel options study of this nature.

    The capital cost estimates have been structured into threemajor categories, detailed below.

    Direct costsDirect costs are those expenditures that include supply of equipment and materials, freight to site and construction labourrelevant to the particular option.

    Indirect costsIndirect costs are those expenditures covering engineering,procurement and construction management (EPCM) servicestogether with the supervision of the commissioning of the works.Contract works and goods in transit insurance have also beenincluded. Temporary construction facilities have been included inIndirects.

    Contingencies (growth allowance)Contingencies have been assigned as an overall percentage to thetotal estimate. Contingency has been applied to the estimate tomake allowance for the following risks:

    minimal design input, preliminary scope definition, quantity survey errors and omissions, material and labour rate accuracy, equipment budget costing, and incorrect bulks factor application.

    Estimation methodologyAn industry standard methodology for a conceptual level

    estimate has been applied for the cost comparison and includes,bulk quantities, equipment and platework, freight, capitalspares, temporary facilities, indirect costs, temporary facilitiesand EPCM and contingencies (growth allowance).

    A detailed equipment list has been prepared and imported intothe estimate. For each item of equipment costs have been enteredas per the basis outlined above. Budget quotes have been receivedfor certain items of major equipment. GRD Minprocs databaseinformation (or allowances) has been used for other equipmentitems appropriately factored and escalated where necessary.

    The estimates are summarised and tabulated in Table 4:

    Option 1 $346.6 M, Option 2 $356.9 M, Option 3 $321.3 M, and Option 4 $312.6 M.

    Iron Ore Conference Perth, WA, 27 - 29 July 2009 7

    PROCESSING OF MAGNETITE IRON ORES COMPARING GRINDING OPTIONS

    Option 1 Option 2 Option 3 Option 4

    Power CO 2 t/a 329 503 315 768 248 757 238 328

    Steel CO 2 t/a 5804 18 256 37 300 8306

    Total CO 2 t/a 335 307 334 023 286 057 246 634

    CO2 tax $/t 0.77 0.77 0.66 0.57

    OPEX $/t (no CO 2 tax) 6.17 6.42 6.66 5.38

    CO2 tax % OPEX 11.1 10.7 9.0 9.3

    TABLE 3Carbon emissions and carbon tax summary.

    Option 1Option 2

    Option 3

    Option 4

    Option 1 Option 2 Option 3 Option 4

    MISCELLANEOUS 0.17 0.18 0.17 0.17

    LABOUR 0.80 0.85 0.87 0.90

    MAINTENANCE MATERIALS 0.83 0.86 0.81 0.79

    GRINDING MEDIA & WEAR LINERS 0.41 0.74 1.82 0.66

    POWER 3.95 3.79 2.99 2.86

    0 . 0 0

    1 . 0 0

    2 . 0 0

    3 . 0 0

    4 . 0 0

    5 . 0 0

    6 . 0 0

    7 . 0 0

    O p e r a t i n g C o s t s ( $ / f e e d t )

    FIG 8 - Operating cost comparison.

  • 8/3/2019 Iron Ore 2009 McNab Jankovic David and Payne

    8/12

    Total estimated capital costs for each circuit are within 14 percent, which does not infer any one option is a standout from acapital cost perspective. Due to the higher power drawn byOptions 1 and 2, which include AG mill circuits, a lower capitalcost to power consumption ratio results. Option 1 offers thelowest ratio with $8.4 k/kW consumed, Option 2 has $9.0 k/kWconsumed and Options 3 and 4 with $10.3 k/kW $10.1 k/kWrespectively (refer Table 4).

    FINANCIAL COMPARISONApplying a ten per cent discount rate over 12 years of operation,high level, pre-tax, net present value (NPV) determinations werecalculated for Options 1 to 3 relative to the base case, Option 4,which returned the lowest capital and operating cost. Figure 9compares these outcomes.

    Options 1 and 3 have a similar NPV outcome ranging betweennegative $94 - 95 M relative to Option 4. A $1 M variance isviewed as being immaterial relative to the accuracy of the study.Option 2 shows the least favourable outcome with a $118 M NPV

    deficit relative to Option 4. This option is disadvantaged by bothhigh capital and operating cost.

    The all autogenous Option 4 flow sheet is $94 M lower thanthe next best option, Option 1. The conclusion drawn from thisfinancial evaluation is that highly energy efficient autogenousprocessing routes can offer significant benefits for competentmagnetite ores requiring fine grinding. Were this hypotheticalprocess design to be advanced, piloting test work would be well

    justified to explore the validity of the key autogenous unitprocesses proposed within Option 4.Having established a relative NPV comparison a variability

    analysis was undertaken to understand each flow sheet optionssensitivity to two key operating cost inputs namely power andball mill media. The outcomes are presented graphically inFigures 10 and 11.

    Not surprisingly, Options 1 and 2, which are the most energyintensive circuits, are found to be highly sensitive to power costwhen compared relative to Option 4. Only in the case that powercould be supplied at a zero cost could Option 1 (AGC/RMS/ PM/CMS) approach the NPV value of Option 4.

    8 Perth, WA, 27 - 29 July 2009 Iron Ore Conference

    B McNAB et al

    Area number Area description Option 1 Option 2 Option 3 Option 4

    Direct costs $ $ $ $

    001 Coarse ore feed 7 237 040 7 237 040 7 151 313 6 241 940

    002 AG mill grinding 80 068 915 88 965 461

    002 Secondary crushing 18 809 132 13 923 099

    002A Tertiary crushing 11 969 442

    003 Pebble recycle crushing 17 704 056 14 972 636

    003 HPGR circuit 34 215 535 20 430 750

    003A Pebble mill grinding and pebble storage 36 389 765

    004 Rougher magnetic separation 2 272 362 2 272 362 3 282 300 2 524 846

    005 Ball mill grinding 18 264 249 48 448 884005 Pebble mill grinding 90 872 360 27 801 316

    006 Concentrate separation and fine milling 76 680 928 76 680 928 66 959 736

    006 Concentrate separation 2 758 989

    Total process plant 200 913 722 208 392 675 188 588 092 186 240 895

    Site preparation and improvements 2 098 103 2 083 927 1 885 881 1 862 409

    Control aystems 4 552 915 4 586 582 3 668 577 3 463 224

    Total plant infrastructure 6 651 018 6 670 509 5 554 458 5 325 633

    First fill reagents and consumables (allowance) 0 2 646 705 3 413 705 0

    Ocean freight 10 180 855 10 095 453 7 373 659 7 405 066

    Spares 5 630 444 5 612 860 4 325 727 4 219 437

    Mobilisation/demobilisation and preliminaries 6 447 027 6 287 927 6 554 941 6 759 735

    Commissioning assistance 2 098 103 2 083 927 1 885 881 1 862 409

    Total miscellaneous 24 356 429 26 726 872 23 553 914 20 246 647

    Total direct cost 231 921 169 241 790 056 217 696 463 211 813 176

    Indirect costs

    Temporary facilities 19 265 417 19 343 204 17 415 717 16 945 054

    EPCM 36 122 657 36 268 508 32 654 469 31 771 976

    Total indirect costs 55 388 074 55 611 713 50 070 186 48 717 031

    Total costs (net) 287 309 243 297 401 769 267 766 649 260 530 207

    Growth, contingency, risk 59 241 158 59 480 354 53 553 330 52 106 041

    Total costs (overall) 346 550 401 356 882 123 321 319 979 312 636 248

    Delta total cost relative to Option 4 33 914 153 44 245 875 8 683 731 0

    Total cost/kW drawn 8414 9041 10 289 10 108

    TABLE 4

    Capital cost comparison.

  • 8/3/2019 Iron Ore 2009 McNab Jankovic David and Payne

    9/12

    Iron Ore Conference Perth, WA, 27 - 29 July 2009 9

    PROCESSING OF MAGNETITE IRON ORES COMPARING GRINDING OPTIONS

    -$140,000,000

    -$120,000,000

    -$100,000,000

    -$80,000,000

    -$60,000,000

    -$40,000,000

    -$20,000,000

    $0

    700 800 900 1000 1100 1200 1300 1400 1500 1600 1700

    Ball Mill Media Cost ($/t)

    Option 1

    Option 2

    Option 3

    D e

    l t a

    N P V R e

    l a t i v e t o O p t i o n

    4 ( $ )

    FIG 11 - Net present value sensitivity to ball mill media cost.

    -$160,000,000

    -$140,000,000

    -$120,000,000

    -$100,000,000

    -$80,000,000

    -$60,000,000

    -$40,000,000

    -$20,000,000

    $0

    0 20 40 60 80 100 120 140 160 180 200

    D e

    l t a

    N P

    V R e

    l a t i

    v e t o O p

    t i o

    n 4

    ( $ )

    Power Cost ($/MWh)

    Option 1

    Option 2

    Option 3

    FIG 10 - Net present value sensitivity to power cost.

    -94

    -118

    -95

    -140

    -120

    -100

    -80

    -60

    -40

    -20

    0

    Option 1 Option 2 Option 3

    C i r c u i t

    E n e r g y

    ( k W h / f e e d

    t o n n e )

    FIG 9 - Net present value (comparison).

  • 8/3/2019 Iron Ore 2009 McNab Jankovic David and Payne

    10/12

    Ball mill media cost is only relevant to Options 2 and 3 as theother circuits include autogenous grinding. Figure 11 highlightsthe high NPV sensitivity to ball mill media cost for Option 3,which considers the largest ball milling duty. Although the NPVrelationship shown is steep, Option 3 would not becomeeconomically equivalent to Option 4 even at a zero ball millmedia cost.

    DISCUSSIONSome clear understanding of the economic merits of processcircuit options can be gleaned by developing a comparative studyas illustrated by this paper. In this case it was found that highlyenergy efficient autogenous processing routes can offersignificant benefits for fine-grained competent magnetite ores.The traditional AG mill and pebble mill style comminutioncircuit or those requiring significant steel grinding media tooperate have been found to be suboptimal from a pure economicperspective. Circuit options favouring multistage magneticseparation and with energy efficient autogenous comminutionequipment are more likely to add project value.

    The approach taken in this paper to compare flow sheetoptions was purely economic and to a large degree simplified byassumptions. In practice there are many other flow sheetselection drivers that can become relevant or even exclusivelydominant. Some examples of these from recent GRD Minprocexperience include:

    the identification of fibrous minerals within the ore; the availability/cost of water; the capability of the project owner to accept risk; spatial layout constraints, ground slope and geotechnical

    characteristics;

    a prescribed study and development schedule that does notallow sufficient time or budget for comparative test work programs;

    variability in rock competency or magnetite liberation;

    social and environmental risks relating to dust and the costsassociated in dust collection and control; the effect of moisture on HPGR performance and caking

    properties of HPGR product;

    long-term predictions for the cost of power and grindingmedia; and

    the cost impacts of tailings including capital, operating costand environmental risks.

    To expand further on the final point other capital and operatingcosts components related to different options for tails disposalwould need evaluation in the next phase of study. Options whichallow coarse RMS tailings, such as Options 3 and 4 in this paper,offer the potential to be inexpensively dewatered and eitherconveyed or transported by dump truck to be either comingledwith mining waste or dumped in a separate tailings storagefacility (TSF). Cost savings in process water consumption andTSF capital may be realised with this approach.

    The justification and value of this type of evaluation process isreflected by the magnitude of the NPV delta produced. In thiscase a $118 M delta resulted between the options considered. Itis therefore not unreasonable to expect that flow sheet selectionhas the potential to vary project value by up to one billion dollarsfor the worlds largest scale magnetite projects being considered.In comparison, the total cost of sample collection, metallurgicalbench and pilot scale test work and engineering studies becomesinconsequential for such projects.

    GRD Minproc places a high importance on developing andunderstanding geometallurgical relationships during the projectevaluation phase and as such would recommend that the

    requisite test work is completed prior to undertaking comparativeconceptual or prefeasibility studies. This approach infers testwork and study planning need to be suitably timed to ensure anadequate basis is available at the commencement of a studyperiod. The rapid pace of project evaluation and developmentexperienced during the 2006 to 2008 mining boom did notalways permit this strategy and in many cases has led to higherproject risk, inefficient engineering practices and slow

    commissioning and ramp up. Further information describingGRD Minprocs approach to geometallurgy and analysis can bereferenced in David (2007).

    CONCLUSION

    The primary conclusion drawn from this financial evaluation isthat highly energy efficient autogenous processing routes withmultiple separation stages offer significant financial benefits forfine-grained hard magnetite ores. For the ore type evaluated, theapplication of HPGR and stirred mill technology is indicated toreduce energy consumption by up to 25 per cent compared toconventional flow sheets with wet tumbling mills.

    Flow sheet design and option selection should be tailored tothe magnetite ore comminution and liberation characteristics. Forfine-grained ores the addition of a third grinding stage whichutilises energy efficient stirred milling benefits the economics intwo ways: reducing the amount of material that need to be fineground and grinding at high energy efficiency. The application of HPGR technology significantly reduces the energy consumptioncompared to AG milling. A synergy of HPGR and primarypebble milling as proposed for Option 4 and can result in a veryeffective circuit from a capital and operating point of view withHPGR working in open circuit feeding the primary pebble millwhich in addition to grinding, generates grinding media(pebbles) for the secondary pebble milling circuit. The productfrom the primary pebble mill is much finer than what can bepractically obtained from a closed HPGR circuit and thus the tailrejection at the RMS is higher which significantly reduces the

    duty of the following pebble milling stage.The magnetite market in general and the required scale of

    magnetite concentrator capacity is rapidly expanding and as aresult will amplify the importance and value of soundmetallurgical investigation and process design. To this end a wellstructured and scheduled study and evaluation period is of considerable importance if the objective is to maximise life cycleproject value and mitigate financial and stakeholder risk.

    An introduction of a carbon tax at levels indicated by theAustralian government is predicted to increase the operating costfor this type of operation significantly, in the order of nine to11 per cent or $0.57 - $0.77/t of ore.

    ACKNOWLEDGEMENT

    The authors acknowledge the permission of GRD Minproc topublish this paper and the assistance of James Higgie incompiling flow sheets and operating costs during his studentvacation work period.

    REFERENCESAustralian Government, 2008. Carbon Pollution Reduction Scheme:

    Australias Low Pollution Future White Paper , volume 1,December.

    Clout, J M F, Trudu, A, Zhu, D, Holmes, R J and Young, J, 2004.Australian magnetite resources and pellet plants, in Proceedings2004 Pelletizing Conference , Dalian, China, 19 - 22 August.

    David, D, 2007. The importance of geometallurgical analysis in plantstudy, design and operational phases, in Proceedings Ninth MillOperators Conference 2007 , pp 241-248 (The Australasian Instituteof Mining and Metallurgy: Melbourne).

    10 Perth, WA, 27 - 29 July 2009 Iron Ore Conference

    B McNAB et al

  • 8/3/2019 Iron Ore 2009 McNab Jankovic David and Payne

    11/12

    Dowling, E C, Corpi, P A, McIvor, R E and Rose, D J, 2001. Applicationof high pressure grinding rolls in an autogenous Pebble millingcircuit, in Proceedings SAG 2001 Conference , Vancouver, vol III,pp 194-201.

    Government of India, 2007. Comprehensive industry document on ironore mining, Ministry of Environment and Forest, Government of India [online]. Available from: [Accessed:2007-08].

    Hahne, R, Palsson, B I and Samskog, P O, 2003. Ore characterization for

    and simulation of primary autogenous grinding, Minerals Engineering , 16:13-19.Koivistoinen, P, Virtanen, M, Eerola, P and Kalapudas, R, 1989. A

    comminution cost comparison of traditional metallic grinding,semiautogenous grinding (SAG) and two stage autogenous grinding,in Proceedings SAG 1989 Conference , Vancouver.

    Morgan, A, 2007. Project Magnet HPGRs [online]. Available from:.

    Price, L, Sinton, J, Worrell, E, Phylipsen, D, Huc, X and Li, J, 2002.Energy use and carbon dioxide emissions from steel production inChina, Energy, 27(2002):429-446.

    Pforr, B, 2001. Fine screen oversize grinding at Hibbing TaconiteCompany, SME Annual Meeting, Denver, February.

    Rajala, G, Suardini, G and Walqui, H, 2007. Improving secondarygrinding capacity at Empire Concentrator, SME Annual Meeting,Denver, 25 - 28 February.

    Seidel, J, Logan, T C, LeVier, K M and Veillette, G, 2006. Case study Investigation of HPGR suitability for two gold/copper prospects, inProceedings SAG 2006 Conference , Vancouver, vol IV, pp 140-153.

    Tano, K T, Plsson, B I, Alatalo, J and Lindquist, L, 2006. The use of process simulation technology in process design when time andperformance is critical, SME Annual Meeting, Denver, February.

    United Nations Conference on Trade and Development, 2008. The IronOre Market 2007 - 2009 [online]. Available from: .

    Iron Ore Conference Perth, WA, 27 - 29 July 2009 11

    PROCESSING OF MAGNETITE IRON ORES COMPARING GRINDING OPTIONS

  • 8/3/2019 Iron Ore 2009 McNab Jankovic David and Payne

    12/12

    12 Perth, WA, 27 - 29 July 2009 Iron Ore Conference