1 Irwin/McGraw-Hill The McGraw-Hill Companies, Inc. 2004 Materials Requirements Materials Requirements Planning Planning Chapter 16 Chapter 16

Irwin/McGraw-Hill The McGraw-Hill Companies, Inc. 2004 1 Materials Requirements Planning Chapter 16

Embed Size (px)

Citation preview

Page 1: Irwin/McGraw-Hill  The McGraw-Hill Companies, Inc. 2004 1 Materials Requirements Planning Chapter 16

11Irwin/McGraw-Hill The McGraw-Hill Companies,

Inc. 2004

Materials Requirements Materials Requirements PlanningPlanning

Chapter 16Chapter 16

Page 2: Irwin/McGraw-Hill  The McGraw-Hill Companies, Inc. 2004 1 Materials Requirements Planning Chapter 16

22Irwin/McGraw-Hill The McGraw-Hill Companies,

Inc. 2004

OutlineOutline

Definition of MRP SystemsDefinition of MRP Systems

MRP versus Order-Point SystemsMRP versus Order-Point Systems

MRP ExampleMRP Example

MRP ElementsMRP Elements

Operating an MRP SystemOperating an MRP System

The Successful MRP SystemThe Successful MRP System

Page 3: Irwin/McGraw-Hill  The McGraw-Hill Companies, Inc. 2004 1 Materials Requirements Planning Chapter 16

33Irwin/McGraw-Hill The McGraw-Hill Companies,

Inc. 2004

Definitions of MRP SystemsDefinitions of MRP Systems

““Closed-loop” MRP System (See Figure 16.1)Closed-loop” MRP System (See Figure 16.1)

Three principal functions of MRP (Orlicky):Three principal functions of MRP (Orlicky):– InventoryInventory– PrioritiesPriorities– CapacityCapacity

Types of MRP:Types of MRP:– Type I. An inventory control systemType I. An inventory control system– Type II. A production and inventory control systemType II. A production and inventory control system– Type III. An Enterprise Resource Planning (ERP) systemType III. An Enterprise Resource Planning (ERP) system

Page 4: Irwin/McGraw-Hill  The McGraw-Hill Companies, Inc. 2004 1 Materials Requirements Planning Chapter 16

44Irwin/McGraw-Hill The McGraw-Hill Companies,

Inc. 2004

Attribute MRP Order Point

Demand Dependent Independent

Order philosophy Requirements Replenishment

Forecast Based on master schedule Based on past demand

Control concept Control all items ABC

Objectives Meet manufacturing needs Meet customer needs

Lot sizing Discrete EOQ

Demand pattern Lumpy but predictable Random

Types of inventory Work in process and rawmaterials

Finished goods and spareparts

Attribute MRP Order Point

Demand Dependent Independent

Order philosophy Requirements Replenishment

Forecast Based on master schedule Based on past demand

Control concept Control all items ABC

Objectives Meet manufacturing needs Meet customer needs

Lot sizing Discrete EOQ

Demand pattern Lumpy but predictable Random

Types of inventory Work in process and rawmaterials

Finished goods and spareparts

MRP versus Order-Point Systems (Table 16.2)MRP versus Order-Point Systems (Table 16.2)

Page 5: Irwin/McGraw-Hill  The McGraw-Hill Companies, Inc. 2004 1 Materials Requirements Planning Chapter 16

55Irwin/McGraw-Hill The McGraw-Hill Companies,

Inc. 2004

BOM (Table Example)BOM (Table Example)

Top

Leg

Long Rail

Short Rail

Page 6: Irwin/McGraw-Hill  The McGraw-Hill Companies, Inc. 2004 1 Materials Requirements Planning Chapter 16

66Irwin/McGraw-Hill The McGraw-Hill Companies,

Inc. 2004

BOM (Product Structure)BOM (Product Structure)

Short Rails(2)

Table(End Item)

Long Rails(2)

Legs(4)

Top(1)

Leg Assembly(1)

Page 7: Irwin/McGraw-Hill  The McGraw-Hill Companies, Inc. 2004 1 Materials Requirements Planning Chapter 16

77Irwin/McGraw-Hill The McGraw-Hill Companies,

Inc. 2004

Indented BOMIndented BOMLevel CodeLevel Code ComponentComponent

00 Table (end-item)Table (end-item)

11 Leg assembly (1)Leg assembly (1)

22 Short rails (2)Short rails (2)

22 Long rails (2)Long rails (2)

22 Legs (4)Legs (4)

11 Top(1)Top(1)

Page 8: Irwin/McGraw-Hill  The McGraw-Hill Companies, Inc. 2004 1 Materials Requirements Planning Chapter 16

88Irwin/McGraw-Hill The McGraw-Hill Companies,

Inc. 2004

MRP ElementsMRP Elements

Bill of Materials (BOM)Bill of Materials (BOM)

Master SchedulingMaster Scheduling

Inventory RecordsInventory Records

Capacity PlanningCapacity Planning

PurchasingPurchasing

Shop Floor ControlShop Floor Control

Page 9: Irwin/McGraw-Hill  The McGraw-Hill Companies, Inc. 2004 1 Materials Requirements Planning Chapter 16

99Irwin/McGraw-Hill The McGraw-Hill Companies,

Inc. 2004

Operating an MRP SystemOperating an MRP System

Should MRP carry “safety stock”?Should MRP carry “safety stock”?

How much “safety stock” should be carried?How much “safety stock” should be carried?

Issue of “safety lead time”Issue of “safety lead time”

Danger of “informal” system driving out the Danger of “informal” system driving out the “formal” system“formal” system

Expansion of MRP to other functions (finance, Expansion of MRP to other functions (finance, HRM, etc.) of businessHRM, etc.) of business

Page 10: Irwin/McGraw-Hill  The McGraw-Hill Companies, Inc. 2004 1 Materials Requirements Planning Chapter 16

1010Irwin/McGraw-Hill The McGraw-Hill Companies,

Inc. 2004

Elements of Success in MRPElements of Success in MRP

Implementation planningImplementation planning

Adequate computer supportAdequate computer support

Accurate dataAccurate data

Management supportManagement support

User knowledgeUser knowledge