IT Project Management: Chapter 5 Risk Managemnt

Embed Size (px)

Citation preview

  • 8/18/2019 IT Project Management: Chapter 5 Risk Managemnt

    1/31

    IT PROJECT MANAGEMENTDr. Zeeshan BhattiMPhil (IT)Chapter 4

    Institute of Information and Communication TechnologyUniversity of Sindh, Jamshoro

    Risk Management

    BY: DR. ZEESHAN BHATTI 1

  • 8/18/2019 IT Project Management: Chapter 5 Risk Managemnt

    2/31

    ShareLessonsLearned

    EvaluateSuccess

    ConductClose-Out

    Meeting

    Roadmap to Project Management Success

    FormProject

    Team

    Statementof WorkPurpose

    Project Background

    Project Deliverables

    WorkBreakdownStructure

    ResponsibilityMatrix

    R A

    A

    S SR

    Network Gantt ResourcePlan

    UpdatePlan

    ResolveIssues

    ManageChange

    TrackProgress

    PerformTasks

    Budget

    TIME

    LEADERSHIP

    COMMUNICATION

    P R O J E

    C T N

    O T E B O O K M E E

    T I N G S

    R E P O

    R T S

    L E S S O N S L E A R N E D

    P L A N

    I M P L E

    M E N T

    C L O S E

    - O U T

    BY: DR. ZEESHAN BHATTI 2

  • 8/18/2019 IT Project Management: Chapter 5 Risk Managemnt

    3/31

    WHAT IS RISK?

    Risk can be defined as:

    “Any threat to project success.”

    BY: DR. ZEESHAN BHATTI 3

  • 8/18/2019 IT Project Management: Chapter 5 Risk Managemnt

    4/31

    Schedule

    Within

    AvailableResources

    Project Scope

    Project Risk

    BY: DR. ZEESHAN BHATTI 4

  • 8/18/2019 IT Project Management: Chapter 5 Risk Managemnt

    5/31

    RISK MANAGEMENT PROCESS

    RiskUncertain or chance events that planning can not overcome or control.

    Risk ManagementA proactive attempt to recognize and manage internal events and external threatsthat affect the likelihood of a project’s success.

    What can go wrong (risk event).

    How to minimize the risk event’s impact (consequences).

    What can be done before an event occurs (anticipation).

    What to do when an event occurs (contingency plans).

    BY: DR. ZEESHAN BHATTI

  • 8/18/2019 IT Project Management: Chapter 5 Risk Managemnt

    6/31

    THE RISK EVENT GRAPH

    FIGURE 7.1

    BY: DR. ZEESHAN BHATTI

  • 8/18/2019 IT Project Management: Chapter 5 Risk Managemnt

    7/31

    RISK MANAGEMENT’S BENEFITSA proactive rather than reactive approach.

    Reduces surprises and negative consequences.

    Prepares the project manager to take advantage

    of appropriate risks.Provides better control over the future.

    Improves chances of reaching project performance objectives within budget andon time.

    BY: DR. ZEESHAN BHATTI

  • 8/18/2019 IT Project Management: Chapter 5 Risk Managemnt

    8/31

    THE RISK MANAGEMENPROCESS

    FIGURE 7.2

    BY: DR. ZEESHAN BHATTI

  • 8/18/2019 IT Project Management: Chapter 5 Risk Managemnt

    9/31

    MANAGING RISK

    Step 1: Risk IdentificationGenerate a list of possible risks through brainstorming, problemidentification and risk profiling.

    Macro risks first, then specific events

    Step 2: Risk AssessmentScenario analysis for event probability and impactRisk assessment matrix

    Failure Mode and Effects Analysis (FMEA)Probability analysis

    Decision trees, NPV, and PERT

    Semiquantitative scenario analysis

    BY: DR. ZEESHAN BHATTI

  • 8/18/2019 IT Project Management: Chapter 5 Risk Managemnt

    10/31

    THE RISK BREAKDOWN STRUCTURE (RBS)

    BY: DR. ZEESHAN BHATTI

  • 8/18/2019 IT Project Management: Chapter 5 Risk Managemnt

    11/31

    PARTIAL RISK PROFILE FOR PRODUCT DEVELOPMENT PROJECT

    FIGURE 7.4

    BY: DR. ZEESHAN BHATTI

  • 8/18/2019 IT Project Management: Chapter 5 Risk Managemnt

    12/31

    DEFINED CONDITIONS FOR IMPACT SCALES OF A RISK ON MAJOROBJECTIVES (EXAMPLES FOR NEGATIVE IMPACTS ONLY)

    FIGURE 7.5

    BY: DR. ZEESHAN BHATTI

  • 8/18/2019 IT Project Management: Chapter 5 Risk Managemnt

    13/31

    RISK ASSESSMENT FORM

    FIGURE 7.6

    Failure Mode and Effects Analysis (FMEA)Impact × Probability × Detection = Risk Value

    BY: DR. ZEESHAN BHATTI

  • 8/18/2019 IT Project Management: Chapter 5 Risk Managemnt

    14/31

    RISK SEVERITY MATRIX

    Failure Mode and Effects Analysis (FMEA)

    Impact × Probability × Detection = Risk Value

    BY: DR. ZEESHAN BHATTI

  • 8/18/2019 IT Project Management: Chapter 5 Risk Managemnt

    15/31

    MANAGING RISK (CONT’D)

    Step 3: Risk Response DevelopmentMitigating Risk

    Reducing the likelihood an adverse event will occur.

    Reducing impact of adverse event.

    Avoiding RiskChanging the project plan to eliminate the risk or condition.

    Transferring RiskPaying a premium to pass the risk to another party.

    Requiring Build-Own-Operate-Transfer (BOOT) provisions.

    Retaining RiskMaking a conscious decision to accept the risk.

    BY: DR. ZEESHAN BHATTI

  • 8/18/2019 IT Project Management: Chapter 5 Risk Managemnt

    16/31

    CONTINGENCY PLANNING

    Contingency PlanAn alternative plan that will be used if a possible foreseen risk event actually occurs.

    A plan of actions that will reduce or mitigate the negative impact (consequences) of arisk event.

    Risks of Not Having a Contingency PlanHaving no plan may slow managerial response.

    Decisions made under pressure can be potentially dangerous and costly.

    BY: DR. ZEESHAN BHATTI

  • 8/18/2019 IT Project Management: Chapter 5 Risk Managemnt

    17/31

    RISK AND CONTINGENCY PLANNING

    Technical RisksBackup strategies if chosen technology fails.Assessing whether technical uncertaintiescan be resolved.

    Schedule RisksUse of slack increases the risk of a late project finish.Imposed duration dates (absolute project finish date)Compression of project schedules due to a shortened project duration date.

    BY: DR. ZEESHAN BHATTI

  • 8/18/2019 IT Project Management: Chapter 5 Risk Managemnt

    18/31

    RISK RESPONSE MATRIX

    BY: DR. ZEESHAN BHATTI

  • 8/18/2019 IT Project Management: Chapter 5 Risk Managemnt

    19/31

    RISK AND CONTINGENCY PLANNING

    (CONT’D)Costs Risks

    Time/cost dependency links: costs increase when problems take longer to solve thanexpected.

    Deciding to use the schedule to solve cash flow problems should be avoided.

    Price protection risks (a rise in input costs) increase if the duration of a project isincreased.

    Funding RisksChanges in the supply of funds for the project can dramatically affect the likelihoodof implementation or successful completion of a project.

    BY: DR. ZEESHAN BHATTI

  • 8/18/2019 IT Project Management: Chapter 5 Risk Managemnt

    20/31

    OPPORTUNITY MANAGEMENT TACT

    ExploitSeeking to eliminate the uncertainty associated with an opportunity toensure that it definitely happens.

    ShareAllocating some or all of the ownership of an opportunity to anotherparty who is best able to capture the opportunity for the benefit of theproject.

    EnhanceTaking action to increase the probability and/or the positive impact ofan opportunity.

    AcceptBeing willing to take advantage of an opportunity if it occurs, but nottaking action to pursue it.

    BY: DR. ZEESHAN BHATTI

  • 8/18/2019 IT Project Management: Chapter 5 Risk Managemnt

    21/31

    MANAGING RISK (CONT’D)

    Step 4: Risk Response ControlRisk control

    Execution of the risk response strategy

    Monitoring of triggering events

    Initiating contingency plans

    Watching for new risks

    Establishing a Change Management SystemMonitoring, tracking, and reporting risk

    Fostering an open organization environment

    Repeating risk identification/assessment exercises

    Assigning and documenting responsibility for managing risk

    BY: DR. ZEESHAN BHATTI

  • 8/18/2019 IT Project Management: Chapter 5 Risk Managemnt

    22/31

    CHANGE MANAGEMENT CONTROL

    Sources of ChangeProject scope changes

    Implementation of contingency plansImprovement changes

    BY: DR. ZEESHAN BHATTI

  • 8/18/2019 IT Project Management: Chapter 5 Risk Managemnt

    23/31

    CHANGE CONTROL SYSTEM PROCES1. Identify proposed changes.2. List expected effects of proposed changes

    on schedule and budget.

    3. Review, evaluate, and approve or disapproveof changes formally.

    4. Negotiate and resolve conflicts of change, condition,and cost.

    5. Communicate changes to parties affected.

    6. Assign responsibility for implementing change.7. Adjust master schedule and budget.

    8. Track all changes that are to be implemented

    BY: DR. ZEESHAN BHATTI

  • 8/18/2019 IT Project Management: Chapter 5 Risk Managemnt

    24/31

    THE CHANGE CONTROL PROCESS

    FIGURE 7.9

    BY: DR. ZEESHAN BHATTI

  • 8/18/2019 IT Project Management: Chapter 5 Risk Managemnt

    25/31

    BENEFITS OF A CHANGE CONTROL S1. Inconsequential changes are discouraged

    by the formal process.2. Costs of changes are maintained in a log.

    3. Integrity of the WBS and performance measuresis maintained.

    4. Allocation and use of budget and management reserve fundsare tracked.

    5. Responsibility for implementation is clarified.

    6. Effect of changes is visible to all parties involved.

    7. Implementation of change is monitored.

    8. Scope changes will be quickly reflected in baseline andperformance measures.

    BY: DR. ZEESHAN BHATTI

  • 8/18/2019 IT Project Management: Chapter 5 Risk Managemnt

    26/31

    SAMPLE CHANGEREQUEST FORM

    FIGURE 7.10

    BY: DR. ZEESHAN BHATTI

  • 8/18/2019 IT Project Management: Chapter 5 Risk Managemnt

    27/31

    CHANGE REQUESTLOG

    FIGURE 7.11

    BY: DR. ZEESHAN BHATTI

  • 8/18/2019 IT Project Management: Chapter 5 Risk Managemnt

    28/31

    KEY TERMSAvoiding risk

    Budget reserve

    Change management system

    Contingency plan

    Management reserve

    Mitigating risk

    OpportunityRisk

    Risk breakdown structure (RBS)

    Risk register

    Risk profile

    Risk severity matrix

    Scenario analysis

    Sharing risk

    Time buffer

    Transferring risk

    BY: DR. ZEESHAN BHATTI

  • 8/18/2019 IT Project Management: Chapter 5 Risk Managemnt

    29/31

    ShareLessonsLearned

    EvaluateSuccess

    ConductClose-Out

    Meeting

    Roadmap to Project Management Success

    FormProjectTeam

    Statementof Work

    ResponsibilityMatrix

    Purpose

    Project Background

    Project Deliverables

    WorkBreakdownStructure

    R A

    A

    SS

    R

    Network Gantt BudgetResourcePlan

    UpdatePlan

    ResolveIssues

    ManageChange

    TrackProgress

    PerformTasks

    LEADERSHIP

    COMMUNICATION

    TIME

    P R O J E C

    T N O

    T E B O O K

    M E E T I N

    G S

    R E P O R T S

    L E S S O

    N S L E A R N E D

    P L A N

    I M P L E

    M E N T

    C L

    O S E - O U T

    BY: DR. ZEESHAN BHATTI 29

  • 8/18/2019 IT Project Management: Chapter 5 Risk Managemnt

    30/31

    REFERRED NOTESA Short Course in ProjectManagement, by Nayda G.Santiago

    REFERRED BOOK

    BY: DR. ZEESHAN BHATTI 30

  • 8/18/2019 IT Project Management: Chapter 5 Risk Managemnt

    31/31

    THANK YOU!!!!

    BY DR ZEESHAN BHATTI 31