Upload
others
View
9
Download
0
Embed Size (px)
Citation preview
Abdessalem RABHI, PhD.Programme Manager, IGES
JITMAP: Promoting Japanese low carbon technologies and best practices in India
The 2nd JITMAP dialogue meeting -18 Jan. 2018, MCCIA Trade Tower, Pune-
2 2
About IGES: Outline
• Name of the InstituteThe Institute for Global Environmental Strategies (IGES)
• EstablishmentMarch 31, 1998
• Location >Headquarter: Hayama, Kanagawa, Japan>Tokyo Office: Chiyoda-ku, Tokyo>Kitakyushu Office: Kitakyushu-city, Fukuoka>Kansai Research Centre (KRC): Kobe, Hyogo>Overseas Offices/Desks: Bangkok (Thailand), Beijing (China), Delhi (India).
IGES headquarters (Hayama, Kanagawa)
3
-Technology Assessment and Stakeholders’ Matchmaking-
IGES-TERI’s efforts to promote low carbon technologies and best practices in India
4
Overall process of intervention
JBIC, EESL funding?
JICA/JST Funding)(FY2010-2013)
MOEJ Funding (FY2014, 2015, 2016, 2017)
Feasibility Study
Technology Need
Assessment (TNA)
Evaluation
Demonstration
projects
Technology Availability Assessment
(TAA)
Capacity Building
5
FS on Gas Heat Pump (GHP)
B2B Matching: Feasibility studies
FS on Electric Heat Pump (EHP) FS on Compressed air (CA)
FS on Induction Furnace (IF) FS on Once Through Boiler (OTB) FS on Steam System Optimization (SSO)
6
Electric Heat Pump (EHP): 30%-40% energy saving due to reduction in fuel consumption of boiler and electricity consumption of chiller
Gas Heat Pump (GHP): 35%-45% energy saving due to switch from electricity to Natural Gas as source of energy
B2B Matching: Demonstration projects and impact evaluation
7 7
B2B Matching: Awareness creation and capacity building
In house trainings for energy auditors (TOT)On site trainings for plant engineers
Awareness creation and capacity buildings for businesses managers and/or owners
8
B2F Matching: Explore potential financing options Mtg. with Small Industries development bank in India (SIDBI)
Mtg. with JICA (India) Mtg. with JBIC (India)
9
B2P Matching: Explore supporting policy/programme optionse.g. mtg. with Central Boiler Inspectors regarding IBR
e.g. Mtg. with Gujarat Energy Development Agency (GEDA) e.g. mtg. with MCCIA
10
Case study1: Installing Electric Heat Pump in India
Insights and lessons learnt
ELECTRIC HEAT PUMP INSTALLED AT FOOD COMPLEX, MOGAR
YEARLY CO2 REDUCTION
Notes: • Average CO2 reduction is 180 ton/year (almost twice what was initially estimated)• Note: In Year 2013, EHP started operation in 23 Jul.• Year 2015, EHP was under breakdown for 4 months• Year 2017, the data was just until Mid July.
72.77
174
123
181
97.78
020406080
100120140160180200
2013 2014 2015 2016 2017
CO2 REDUCTION IN Ton/Year
181 181180
97,78
72.77
Vasundhara Award -2015
Recognitions from Energy and Environmental Savings
Golden Peacock Award- 2016(National Level)
Recognitions from Energy Savings and Innovations
15
Key insights based on the EHP case study
1) Implementing demonstration project “show case” is needed towards green technology transfer;
2) Continuous and timely technical assistance/follow up is needed to ensure the success of the demonstration project;
3) Technology transfer is a continuous process where synergy among efforts/stakeholders is needed;
16
Case study2: Investigation on compressed air system
Insights and lessons learnt
Installation of new receiver and new air compressors (not inverter type) Adjusting pressure setting
Reduce air leakage through installing foot switch Reconsider pipe size and design Start the use of efficient air gun
Expected benefits of improving compressed air system: Energy saving: 20% -30%
Example of identified potentialsSites Proposals for
hardware/equipements installation
Estimated Energy saving (kWh/year)
Estimated emission reduction (Ton/year)
Estimated operation cost saving (Million JPY/year)
Initial cost (in Japan market) (1000JPY)
Estimated Pay back period (Year)
Install Inverter A.C(NL-0)
308,160 302 3,513,024 7,000 2.0
Install Inverter A.C(NL-1)
308,160 302 3,513,024 7,000 2.0
Install Inverter A.C(NL-2)
256,543 251 2,924,592 5,000 1.7
Install two stages A.C 391,500 384 4,463,100 30,000 6.7
Install Booster 108,864 106 1,241,050 3,000 2.4
Install Inverter A.C 350,000 343 3,990,000 10,000 2.5
Install 2 stage A.C 130,500 128 1,487,700 10,000 6.7
Bombay Dyeing Co. Ltd.
Install Inverter A.C 60,830 56 693,462 3,000 4.3
Install Inverter A.C 660,200 647 7,526,280 12,000 1.6
Install high-efficiency drain trap
158,000 155 1,801,200 4500 2.5
Install Inverter A.C 660,200 647 7,526,280 12,000 1.6
Install Booster 109,000 107 1,242,600 1,400 1.1
Install Inverter A.C 660,200 647 7,526,280 12,000 1.6
Install high-efficiency drain trap
63,200 62 720,480 1,800 2.5
Ahmednagar Forging Co. Ltd.
Raymond UCO textile
Arvind Textile Co. Ltd.
Mahindra Hinoday Co. Ltd
Morarjee Textile Co. Ltd.
Sheet1
Summary of Proposals about hardware/equipements to Improve compressed air system
SitesProposals for hardware/equipements installationEstimated Energy saving (kWh/year)Estimated emission reduction (Ton/year)Estimated operation cost saving (Million JPY/year)Initial cost (in Japan market) (1000JPY)Estimated Pay back period (Year)
Mahindra Hinoday Co. LtdInstall Inverter A.C(NL-0)308,1603023,513,0247,0002.0
Install Inverter A.C(NL-1)308,1603023,513,0247,0002.0
Install Inverter A.C(NL-2)256,5432512,924,5925,0001.7
Install two stages A.C391,5003844,463,10030,0006.7
Install Booster 108,8641061,241,0503,0002.4
Ahmednagar Forging Co. Ltd.Install Inverter A.C350,0003433,990,00010,0002.5
Install 2 stage A.C130,5001281,487,70010,0006.7
Bombay Dyeing Co. Ltd.Install Inverter A.C60,83056693,4623,0004.3
Arvind Textile Co. Ltd.Install Inverter A.C660,2006477,526,28012,0001.6
Install high-efficiency drain trap158,0001551,801,20045002.5
Morarjee Textile Co. Ltd.Install Inverter A.C660,2006477,526,28012,0001.6
Install Booster 109,0001071,242,6001,4001.1
Raymond UCO textileInstall Inverter A.C660,2006477,526,28012,0001.6
Install high-efficiency drain trap63,20062720,4801,8002.5
1919
Financial capacity
Technical capacityMaximum Own
Capacity
Maximum Own Capacity
Matching B2B is sufficient
Matching B2F is also required
Matching B2P is also required
Matching B2F and B2P is also required
e.g.: Install one efficient standard air compressor
e.g.: Install several efficient standard air compressors
e.g.: Install oil free inverter type air compressor
e.g.: Install Inverter type oil injected air compressor
Required capacity through training programme
Required project funding
Note:B= BusinessF= FinanceP= Policy/programme
Current “Appropriate technology” Zone?
Key question: What kind of support is actually needed?
20
Key insight based on compressed air case study
1) What kind of support is actually required: Awareness creation, financial, or technical?
2) Which specific stakeholder has/able to provide such support?
3) To address the above, mapping; matching, follow-up are key activities to be considered.
21
Key findings from IGES-TERI’s activities in India
Huge potential/market for Japanese technologies deployment in India,however:High upfront cost of Japanese technologies;Significant information/knowledge gap exists;Incomplete, fragmented, and uncoordinated efforts to tap
opportunities;Communication barriers (mindset, language, etc.).
>> It was concluded that there is a need to initiate a stakeholders'matchmaking platform to address all the above challenges in practicaland systematic manner.
22
Initiating Japan-India Technology Matchmaking Platform (JITMAP)
232323
Key feature of the platform
Bilateral: Specific focus on Japan and India;
Practical: unique forum where matching B2B, B2F and B2P can occur on the ground as well as online in faster way;
Comprehensive: Information and knowledge sharing about various aspects (technologies data base, policies data base, financing options data base, etc). not just about one of them as in most existing platforms;
Systematic: It addresses all the stages of Technology Transfer process, with special focus given to follow up activities;
Ultimate goal is to materialize the opportunities rather than just identifying them; Develop information rather than just collect and share it;
It is not an alternative option to existing platforms, but rather a complementary one to them.
24
JITMAP was initiated/launched as a trial basis on Jul. 13th, 2016. IGES and TERI as core members.
Leading Indian organizations has joined as dialogues members, namely: GEDA, MEDA, MCCIA, GITCO. Others are also expressing interests, from India and Japan.
Japan-India Technology Matchmaking Platform (JITMAP)
25
Key activities under JITMAPIGES and TERI, in coordination with JITMAP Dialogue Members, enable matchmaking of B2B,
B2F and B2P through the following activities:
Information collection, management and assessment
=>Develop database on “Seeds” and “Needs” (technologies, stimulating policies & regulations,
stimulating financing schemes, etc.)
Stakeholders matching (B2B, B2F and B2P)
Feasibility studies, project proposals, bankable proposals, project
implementation, follow-up activities, etc
“Online” Information and knowledge sharing
through JITMAP websitehttp://jitmap.org
Stakeholders’ awareness creation and capacity buildingTechnical and financial assistances,
Workshops, Trainings, joint planning for replication at wider level, etc.
-JITMAP m
embers dialogue m
eetings-Experts consultation m
eetings
“Online” Information and
knowledge sharing
“On the ground”
matchmaking
Mapping for matching
Databases, directories, case studies, proposals (projects/strategies/roadmaps), training materials, etc.
“Outputs
26
Japan-India Technology Matchmaking Platform (JITMAP)http://jitmap.org (PW: asdf1234)
http://jitmap.org/
27
Conclusion There is no shortage of technologies, no shortage of funding, no shortage of
initiatives, but there is shortfall in coordination/synergy among efforts to develop and implement projects;
Key challenges to promote green technology transfer include: -High upfront cost of Japanese technologies;-Significant information/knowledge gap exists;-Incomplete, fragmented, and uncoordinated efforts;-Communication barriers (mindset, language, etc.).
Successfully matching B2B, B2F, and B2P creates synergy among efforts, fills part of the information/knowledge gap, reduce communication barriers, and ultimately alleviates part of overall business cost (reduction of transaction cost, information cost, etc.);
Bilateral matchmaking platforms could be considered as innovative business model assuming that they include the “Appropriate” matchmakers.
28
Thank you for your kind attention
スライド番号 1About IGES: Outlineスライド番号 3スライド番号 4スライド番号 5スライド番号 6スライド番号 7スライド番号 8スライド番号 9スライド番号 10スライド番号 11スライド番号 12スライド番号 13スライド番号 14スライド番号 15スライド番号 16スライド番号 17スライド番号 18スライド番号 19スライド番号 20スライド番号 21スライド番号 22スライド番号 23スライド番号 24スライド番号 25スライド番号 26スライド番号 27スライド番号 28