9
UNCLASSIFIED UNCLASSIFIED JTEN Reduction Plan Mr. Steve Kostoff DD JS J7 JCW Environment Development 15 February 2012

JTEN Reduction Plan

Embed Size (px)

DESCRIPTION

JTEN Reduction Plan. Mr. Steve Kostoff DD JS J7 JCW Environment Development 15 February 2012. Abstract. In response to budgetary pressure, ED asked to consider ways to reduce costs accrued by JNTC technical infrastructure JTEN one of the largest JNTC cost drivers - PowerPoint PPT Presentation

Citation preview

Page 1: JTEN Reduction Plan

UNCLASSIFIED

UNCLASSIFIED

JTEN Reduction Plan

Mr. Steve Kostoff

DD JS J7 JCW

Environment Development

15 February 2012

Page 2: JTEN Reduction Plan

UNCLASSIFIED

UNCLASSIFIED

Abstract

• In response to budgetary pressure, ED asked to consider ways to reduce costs accrued by JNTC technical infrastructure– JTEN one of the largest JNTC cost drivers

• As a result of previous budget cuts, most cost reductions taken with regard to JTEN have already been taken

• Therefore the best place to consider cost reductions now is in the size of the network itself

2

Page 3: JTEN Reduction Plan

UNCLASSIFIED

UNCLASSIFIED

Method

• Based on work begun 2 years ago in the JTEN Recapitalization project, there are a number of sites on the JTEN that have low utilization rates

• These sites could be removed to save equipment maintenance costs and their needs for JTEN satisfied by the deployment of a JTEN pod

• Recommended cut list based on JTEN Recapitalization metrics• Projected savings by proposed reduction approx. $750,000 OM/

year

3

Page 4: JTEN Reduction Plan

UNCLASSIFIED

UNCLASSIFIED

JTEN Reduction List

Number Site Total Exercise

Days

Oct 2010-Present

Remarks

1 Keesler AFB N/A Hub site –not needed w/ 2.0 2 Camp Roberts

(HUB)N/A Hub site –not needed w/ 2.0

3 Orlando (JDIF) 765 Recommend backside connection to JCW/McDill

4 Schofield Barracks

591 Recommend backside connection to Pearl Harbor

5 Camp Courtney 137 Recommend backside connection to Pearl Harbor

6 Shaw AFB 267 Fort Belvoir 0

8 Fallon NAS 0 moving to NCTE

9 Ft Sam Houston 12

10 SOUTHCOM 16

11 Fort Stewart 29

12 Ft Campbell 32

13Davis-Monthan AFB 36

14 Ft. Sill 48

15Des Moines ANG – DTOC 61

No connections to ARCNET permitted, thus no reason for JTEN

4

Page 5: JTEN Reduction Plan

UNCLASSIFIED

UNCLASSIFIED

• Two sites will be eliminated as no longer necessary under JTEN 2.0 (JTEN 1.0 hubs without local customers)

• Several sites can be made local backside connections to nearby JTEN nodes – JTEN node at such a site is eliminated and local network connected as backside to neighbor node– SITE PICKS UP REMAINING COSTS

• Remaining sites nominated on basis of low utilization, except in cases of special interest (link to another network, etc.)

5

Page 6: JTEN Reduction Plan

UNCLASSIFIED

UNCLASSIFIED

Deployment

• Deployment phase begins upon completion of the Operational Acceptance Test in April assuming test is passed– Site surveys begin in April– Site installations begin in June– JTEN 2.0 upgrade complete June 2013 if schedule holds

6

Page 7: JTEN Reduction Plan

UNCLASSIFIED

UNCLASSIFIED7

Page 8: JTEN Reduction Plan

UNCLASSIFIED

UNCLASSIFIED8

Page 9: JTEN Reduction Plan

UNCLASSIFIED

UNCLASSIFIED9