    T3A INDUSTRIAL

    Doc # AP-01-1099 Issue # 05 Page 1 of 4

    STANDARD OPERATING PROCEDURE

    Title: KEY PERSONS AND THEIR BACKUP PERSONS

    ASSIGNEE NAME TITLE SIGN./DATE

    PREPARED BY AYMAN SALAMA QA OFFICER

    REVIEWED BY MOHAMED ELASSADY QA OFFICER

    APPROVED BY MOHAMED ELSAADYQA SECTION

    HEAD

    HISTORY OF CHANGE

    ISSUE # ISSUE DATE PAGE # SUMMARY OF CHANGE

    From Issue 001 to

    Issue 00220/10/2002

    Page 1,2&4

    1- Change in assignee persons

    2- Change in responsibilities

    3- Add responsibility no.3.3

    4- Change in attachment 5.2.

    From Issue 002 to

    Issue 0311/05/04 Page 1 1- Change inassignee persons

    From Issue 03 toIssue 04

    21/05/06 All Pages

    1- Change inassignee persons

    2- Change in Objective.

    3- Change in responsibilities

    4- Change in Procedures

    5- Change in attachment 5.2.

    From Issue 04 to

    Issue 0515/10/06 All Pages

    1- Change in assignee persons

    2- Change in responsibility

    3- Change in procedures

    4- Change in attachment 5.1 , 5.2

    ISSUE DATE: //. EFFECTIVE DATE: //. REVISION DATE: //.

  • 7/30/2019 Key Persons and Their Backup Persons 05

    2/4

    T3A INDUSTRIAL

    Doc # AP-01-1099 Issue # 05 Page 2 of 4

    1. OBJECTIVE:

    1.1. To establish a procedure for preparing list of approved signatures of key persons and those

    backup persons of T3A factory.

    2. SCOPE:

    1.1. Applies to all departments in T3A factory.

    3. RESPONSIBILITY:

    1.1. Each Department manager determining his/ her backup person in case of his absence &this shall be approved by the Plant manager or his designee.

    1.2. The Planet manager determining the qualified person in the factory and his backup person.

    1.3. QA Documentation officer or his designee checking on the signatures list.

    3.4. Quality Assurance Manager or designee: review, approval and system compliance

    4. PROCEDURES:

    1.1.Each Department manager shall determine his/her backup person in case of his/her absence

    and make a delegation for the same in the prescribed form (See attachment 5.1.).

    1.2.The attachment 5.1. Shall be approved by plant manager or his designee before the concernedperson proceeds on his vacation.

    1.3. List of approved signatures of key persons and those backup persons for all departments shall

    be approved by plant manager or his designee.

    1.4.QA Department shall maintain the list of approved signatures of all key persons and those

    backup persons of T3A factory.

    1.5.QA Documentation officer or his designee checking on the signatures list for all key persons

    and those backup persons each 6 months.

    5. ATTACHMENTS:

    5.1. Delegation form

    5.2. List of approved signatures of key persons and those backup persons.

    PREPARED BY: REVIEWED BY: ... APPROVED BY: ..

  • 7/30/2019 Key Persons and Their Backup Persons 05

    3/4

    T3A INDUSTRIAL

    Doc # AP-01-1099 Issue # 05 Page 3 of 4

    5.1. Delegation form:

    DELEGATION

    From: [department name/manager name]

    To: All Department Managers

    CC: [Top manager name]

    Subject: Delegation process

    Date: From -------------- To ---------------

    Please kindly be informed that [------------------------------------- ] is in charge of [department name]

    during the above mentioned period to act as a department manager

    Thanks and best regards

    --------------- Manager Plant Manager

    Name: -------------------- Name: --------------------

    Signature: ---------------- Signature: ----------------

    PREPARED BY: REVIEWED BY: ... APPROVED BY: ..

  • 7/30/2019 Key Persons and Their Backup Persons 05

    4/4

    T3A INDUSTRIAL

    Doc # AP-01-1099 Issue # 05 Page 4 of 4

    5.2. List of approved signatures of key persons and those backup persons:

    Date: ../../

    Department Name: .

    Key person Name Designation Signature Backup person name Designation Signature

    Approved by: Plant Manager

    Name: --------------------

    Signature: ----------------

    PREPARED BY: REVIEWED BY: ... APPROVED BY: ..