Upload
moses-kaswa
View
219
Download
0
Embed Size (px)
Citation preview
7/30/2019 Kisse Project 2
1/35
PROJECT TITLE:UPGRADING OF AN EARTH ROADTO GRAVEL ROAD
CASE STUDY: KINONDONI MAKABURINI BURUNDI RNAME:
STEPHEN KISSE
ADM NO: 100101P7295
COURSE: ORDINARY DIPLOMA IN BUILDING AND CIVENGINEERING
7/30/2019 Kisse Project 2
2/35
INTRODUCTION:
Burundi Road is an Earth Road, located in Dar esalaam city at kinondoni District along Kinondonroad.From junction of Kinondoni Road and Ali HaMwinyi Road,Burundi Road are second Road in Rhand side a long Kinondoni Road and From KinonMakaburini station are second Road in left hand
7/30/2019 Kisse Project 2
3/35
DIRECTION OF BURUNDI ROAD
7/30/2019 Kisse Project 2
4/35
PROBLEM STATEMENT:
Poor surface condition of Burundi road due to difdefect like pot hole, corrugation and other on a Rsurface reduces efficiency performance of vehictime goes the problem become serious as resultroad user not be comfortable when using it.
7/30/2019 Kisse Project 2
5/35
Pot hole on the road surface
7/30/2019 Kisse Project 2
6/35
OBJECTIVE OF THE PROJECT:
To design gravel Road at Burundi Road
7/30/2019 Kisse Project 2
7/35
SPECIFIC OBJECTIVE
Determine soil test Determine traffic counting
Conducting survey data
7/30/2019 Kisse Project 2
8/35
SCOPE OF THE PROJECT
The scope of the project is to provide the designethickness of gravel Road of 800m at Burundi ro
7/30/2019 Kisse Project 2
9/35
EXPECPECTED OUTCOME :
The expected outcome of this project to improveroad to gravel Road.
7/30/2019 Kisse Project 2
10/35
METHODOLOGY:
Literature review Data collection
Survey data
Laboratory test
Traffic count
Rainfall intensity
Data analysis
7/30/2019 Kisse Project 2
11/35
LITERATURE REVIEW
GRAVEL ROADGravel road are the road that are constructed bgravel or crushed stone material to carry the hetraffic up to 100ADT(average daily traffic). Conssuperior as compared to an earth road. The camgravel road is 1:25 to 1:30.There are no specificthe material. Rounded stones and river gravel arpreferable as there is poor interlocking.
7/30/2019 Kisse Project 2
12/35
PROCEDURE OF CONSTRUCTION GRAVROAD
Material survey- Gravel to be used for the construction is stacked along
the sides of the proposed road.Moisture content W= (M2 M3)/ (M3 M1)*100%
Plastic index =liquid limit plastic limitLocation and dimensioning- marking road dimension and Width of the road
Range 3.5m to 5m and compaction.Preparation of subgradePavement construction crushed gravel aggregates are placed carefully in tto avoid segregation.0pening to traffic A few days after the final rolling and drying out, the roadto the traffic
7/30/2019 Kisse Project 2
13/35
FACTOR INFLUENCING SELECTION OF BASE COURSE AND SURFACINGDEPENDS
Amount of trafficType of traffic
Nature of sub grade soil and drainage condition
Availability of construction material
Climatic condition
Equipment available
Position of underground water table
Time available for completing the project
7/30/2019 Kisse Project 2
14/35
GENERAL FACTORS THAT CAUSES DEFECTS
Traffic volume -due to increasing number of vehusing the road
Within the designed period, hence the failure roa
Sub grade material when material is not suitabconstruction of
Road, absolute the road can fail for short Period o Water on the road surface due to poor design o
camber, during Heavy rainfall there is overflow oon the road surface.
Construction practice when there is no good
supervision during construction the road, Hence
7/30/2019 Kisse Project 2
15/35
STRENGH OF SUB GRADE SOIL
The strength of sub grade soil is measured by Cabearing ratio(CBR).CBR is normally a measure ostrength of the soil, required to take simple test taking sample of soil about 1m from the ground surface, sub grade sample are taken at interval
along chain age.
CBR value (in %) =P(100/13.2)
CBR value (in %) = P(100/20)
Where P is Plun er force in KN at 2.5mm and 5
7/30/2019 Kisse Project 2
16/35
TRAFFIC COUNTING
Traffic account is a system of accounting vehiclpassing on a road. During account vehicle you ccategories vehicle according to the weight of anindividual vehicle that is imposed on the road. bconducting by measure the standard of vehicle pon a road.
Average Daily Traffic(ADT) =(total number of vpassing for 7 day)/(7 day)
Equivalent standard axle(ESA)= (load/8.16)4.55 tim
of vehicle
7/30/2019 Kisse Project 2
17/35
DATA COLLECTION
Data collection required are:
Survey data
Traffic counting
Rainfall intensity
Laboratory Soil Test
Sieve analysiscompaction test
CBR Test
Atterberg test
7/30/2019 Kisse Project 2
18/35
SURVEY DATA
CHAINAGE BS IS FS RISE FALL
1.685
1.530 0.155
1.620 0.09
0+125 1.751 0.131
1.521 0.073
1.678 0.157
1.866 0.188
1.232 1.602
1.563 0.331
1.587 0.024
7/30/2019 Kisse Project 2
19/35
SURVEY DATA
CHAINAGE BS IS FS RISE FALL
1.342 1.523 0.055
1.751 0.409
1.756 0.005
0+500 1.653 0.103
1.564 0.089
1.882 0.318
1.702 0.18
1.541 1.625
1.605 0.064
1.625 0.02
7/30/2019 Kisse Project 2
20/35
LONGITUDINAL SECTION
7/30/2019 Kisse Project 2
21/35
SIEVE ANALYSIS RESULTS
Bs test sieve Mass ofpan +soil
MassRetained
MassRetainedcorrection
%retained
Total %passing
Mass of pan 229.22mm - - - - 1001.18mm 236.7 7.5 7.6 2.8 97.2
600micro 279.4 50.2 50.7 18.8 78.4425micro 279.4 47.7 48.2 17.9 60.5300micro 260.5 31.3 31.6 11.7 48.8212micro 251.3 22.1 22.3 8.4 40.4150micro 246.8 17.6 17.8 6.6 33.863micro 246.4 17.2 17.4 6.4 27.4Passing - 73.4 17.1 27.4 0
Total - 267 269.7 100 0
7/30/2019 Kisse Project 2
22/35
SUMMARY OF LABORATORY TESTS FOR DESIGN
LABORATORY TEST RESULTS
Pit No: 1 Pit No: 2 Pit No: 3
Atterbergs limit
Liquid limit 31 29 30.5
Plastic limit 17 16 14
Plastic index 14 13 12
Compaction test
MDD(kg/m3) 1908 1945 1992
OMC(%) 7.8 8.2 7.5
CBR test
4.5kg/5layer/62blows
8 10 9
4.5kg/5layer/30blows
3 4 8
7/30/2019 Kisse Project 2
23/35
TRAFFIC COUNTCar Pick up
& vansLightlorriesunder 5tons
Busesunder25 seats
Mediumlorriesover 5tons
Heavylorries
Veryheavylorries
Busoveseat
17.12.2012
89 12 2 3 0 0 0 0
18.12.2012
96 15 3 5 0 0 0 0
19.12.2012
102 9 5 2 2 0 0 0
2.1.201
3
88 20 2 3 0 0 0 0
3.1.2012
98 22 7 3 0 0 0 0
4.1.2013
110 25 0 5 0 0 0 0
5.1.2013
92 15 6 3 2 2 0 0
7.1.2013
87 27 5 2 2 0 0 1
7/30/2019 Kisse Project 2
24/35
RAINFALL INTENSITY
- 15
MIN
- 1 HR 2
HRS
3 HRS 6 HRS 12
HRS H
2 YRS 92.08 65.04 42.78 23.66 16.62 9.50 4.99
5 YRS 117.4
8
84.18 57.02 31.61 21.92 12.77 7.49
10
YRS
134.3
2
96.84 66.44 36.87 25.42 14.93 7.91
25
YRS
155.6
0
112.8
4
78.35 43.52 29.85 17.67 9.37
50
YRS
171.4
0
124.7
2
87.19 48.45 33.13 19.70 10.46
100
YRS
187.0
8
136.5
0
95.96 53.34 36.39 21.71 11.54
7/30/2019 Kisse Project 2
25/35
RAINFALL CURVE
7/30/2019 Kisse Project 2
26/35
GRAPH OF SIEVE
7/30/2019 Kisse Project 2
27/35
GRAPH OF ATTERBEG
7/30/2019 Kisse Project 2
28/35
GRAPH OF COMPACTION
7/30/2019 Kisse Project 2
29/35
DATA ANALYSIS FOR SOILLABORATORY TEST
Classification of soil
according to the data are collected,
From AASHTO SOIL CLASSIFICATION
Group A-2, A-2-6
Usual type of significant
Constituent material = silty or clayey grand sand
General rating as subgrade = Fair to poor
7/30/2019 Kisse Project 2
30/35
CALCULATION OF VEHICLE
tones Mid point Equivalent
factor(L/8.2)4.5
Number of
vehicles
Number of
axle
N
s
3-5 4 0.0395 144 288 1
5-7 6 0.2452 6 12 2
Total 150 300 1
7/30/2019 Kisse Project 2
31/35
DATA ANALYSIS FOR TRAFFICCOUNTING Determination of CESAL
n= design life =3%r= growth rate= 6% =0.06
Total number of commercial vehicle =14.3184 Total number of standard axle per day = Total number of standa
axle/Number of days
= 14.3184/7
=2.045485714
CESAL =365*2.04585714*(1+0.06)3 -1
0.06
CESAL = 237731.2982
CESAL = 0.24*106
According to (Pavement design manual 199traffic load class for CESAL
I obtained is 0.234*10
6
is TLC 05
7/30/2019 Kisse Project 2
32/35
Calculation of finding CBRdesign
CBR Result
PIT No 1 = 4
PIT No 2 = 6
PIT No 3 = 8
n =3,d =0.1*(n-1)
d=0.1*(3-1)
d=0.2
7/30/2019 Kisse Project 2
33/35
DESIGN CBR
CBR(%)8
6
4
2
1 2 3 4 5TEST NUMBER
= 4%
7/30/2019 Kisse Project 2
34/35
DESIGN OF THICKNESS
According to the strength of CBR required by mapavement design is 15%.
But l found that CBR is 4%,improvement ofsubgrade is required.
Also according to the pavement and manual dematerial(1999).
The thickness layer require according to the daabove
150mm thick G80 CBR base course.
150mm thick G45 sub base course.
7/30/2019 Kisse Project 2
35/35
REFERENCE;
Ministry of work Tanzania (1999) Pavement Mateand Design Manual.
Graham E. Barnes (2000) Soil Mechanics (PrincipPractices)
Central material laboratory manual(2000)Tanzannational road agency
S.K.Khanna and C.E.G.Justo (1991) Highway eng(7th edition) Nem Chand and Bros, India
Dares salaam institute of technology (25th Feb, 1Manual for Traffic, Transportation and Highway
Engineering Book11-volume 2&3