Upload
christian-sutton
View
218
Download
0
Tags:
Embed Size (px)
Citation preview
DD
Kurt Krempetz (Director's Review - Dec. 7, 99)
1
Mechanical Infrastructure
Kurt Krempetz
Introduction
Existing Systems
New Systems
Schedule
Manpower
Conclusions
DD
Kurt Krempetz (Director's Review - Dec. 7, 99)
2
Introduction
Definitions:
Mechanical/Cryo/Gas Infrastructure- Components/systems which are needed to
operate the D0 detector and subdetectors. These are cooling systems, Heating, Ventilation, Air, Conditioning(HVAC) systems, andhoisting/drive systems.
Installation-
Placing components in their proper positions and performing a minimal testing program. Minimal testing includes pressure testing, leak testing, and a checkout of the basic operation of the component.
Commissioning-First time operation of the system which includes obtaining safety approvals, pump and purging of systems, developing process operations,and debugging. This does not include operations.
DD
Kurt Krempetz (Director's Review - Dec. 7, 99)
3
Existing Systems
Liquid Helium(LHe)System Solenoid system; commissioned. Visible Light Photon Counters(VLPC) system;
commissioned to cryostats.
DD
Kurt Krempetz (Director's Review - Dec. 7, 99)
4
Existing Systems
DD
Kurt Krempetz (Director's Review - Dec. 7, 99)
5
Existing Systems
DD
Kurt Krempetz (Director's Review - Dec. 7, 99)
6
Existing Systems
DD
Kurt Krempetz (Director's Review - Dec. 7, 99)
7
Existing Systems
DD
Kurt Krempetz (Director's Review - Dec. 7, 99)
8
Existing Systems
DD
Kurt Krempetz (Director's Review - Dec. 7, 99)
9
Existing Systems
Liquid Nitrogen (LN2) System Solenoid and VLPC; commissioned. Calorimeters; in partial operation.
Liquid Argon(LAr) System Storage of LAr; in operation. Reconnect transfer lines to calorimeters.
Vacuum System Solenoid,VLPC, and Calorimeters; in operation.
LAr Safety Spill System Disconnected;South End Calorimeter(EC) off
center beam.
DD
Kurt Krempetz (Director's Review - Dec. 7, 99)
10
Existing Systems
ODH System Solenoid,VLPC,and Calorimeters; in operation.
Control Air System Dry air for valves in the cryo/gas system; in
operation. Purge Air System
Dry air for purge of Calorimeter preamp boxes and EC beam hole; in operation.
Water Systems Pond Water System; in operation. Chilled Water System; in partial operation. De-ionized Chilled Water System.
Cools Electronics; in partial operation. Low Conductivity Water System.
Cools End Iron Magnet(EF), Central Iron Magnet (CF) and Magnet Power Supplies;commissioned
Heat Pump Water System Cools the D0 Assemble Building (DAB);in
operation
DD
Kurt Krempetz (Director's Review - Dec. 7, 99)
11
Existing Systems
DD
Kurt Krempetz (Director's Review - Dec. 7, 99)
12
Existing Systems
HVAC Systems HVAC Collision Hall System ;in operation. HVAC Assembly Hall System; in operation. HVAC Detector System;disassembled.HVAC Detector System;disassembled.
Drive/Hoisting Systems EC Drive System.
SEC drive system; disconnected. NEC drive system; in operation.
CF Drive System; in operation. EF Drive System; in operation. Platform Drive System; disassembled. EC Cable Winders
NEC winder; in operation. SEC winder; disassembled.
DD
Kurt Krempetz (Director's Review - Dec. 7, 99)
13
New Systems
At the Design stage LHe Systems
Transfer lines through Shielding Wall Jumper Connections Installing VLPC Cryostats
DD
Kurt Krempetz (Director's Review - Dec. 7, 99)
14
New Systems
Silicon Cooling Chillers/pumps Piping Controls and Instrumentation
WAMUS Gas System(Dirty) Pumps Purifiers Piping Controls and Instrumentation
WAMUS Gas System Pumps Purifiers Piping Controls and Instrumentation
DD
Kurt Krempetz (Director's Review - Dec. 7, 99)
15
New Systems
Tracker Purge System Silicon Purge
– dry air– moisture barriers
Fiber Tracker Purge– dry air– dry nitrogen– temperature control
Access Hardware scaffolding temporary floors hoists
MDT Gas System Pumps Purifiers Piping Controls and Instrumentation
Preshower Cable Winder
DD
Kurt Krempetz (Director's Review - Dec. 7, 99)
16
New Systems
DD
Kurt Krempetz (Director's Review - Dec. 7, 99)
17
Schedule
Summary (detailed version enclosed)
Wamus Gas Systems 11/17/99-2/15/00 Preshower Cable Winder 11/15/99-3/15/00 Tracker Purge Gas 12/1/99-5/11/00 LHe/VLPC Cryostat 12/6/99-6/12/00 Silicon Cooling 7/15/99-7/15/00 MDT Gas System 2/28/00-7/28/00 LAr/LAr Safety Spill Line 8/01/00-9/08/00
Tuning up all systems 11/01/00-2/06/01
DD
Kurt Krempetz (Director's Review - Dec. 7, 99)
18
Manpower
Summary (detailed version enclosed)
Engineering 80w Designer 55w Super Tech 65w Tech 150w Welder 35w Plant Maintenance
People 10w
DD
Kurt Krempetz (Director's Review - Dec. 7, 99)
19
Schedule/ManpowerDetails
System Details(existing)
System Start End Resources LHe system
Dis/reconnect Refrigeration Plant* 12/6/00 12/15/00 .5w Markley,1w TechRoll in Commissioning(Cooldown) 2/5/01 2/20/01 1w Markley,1wRucinski,1w Krempetz,1w Barger,2wTech
LN2 SystemReconnect Jumper Connections 1/16/01 1/16/01 .1w Markley,.1w Barger,.2w TechRoll in Commissioning 1/16/01 1/18/01 .1w Markley,.1w Barger,.1w Tech
LAr SystemCooldown/Fill CC 9/1/00 9/8/00 .5w Markley,.5 Rucinski,.5 Krempetz,.5w Barger,1w TechReconnect Jumper Connections 1/16/01 1/16/01 .1w Markley,.1w Barger,.2w TechRoll in CommissioningCooldown and fill EC and CC 1/16/01 2/5/01 2w Markley,.2wRucinski,.1w Krempetz,.2w Barger,4Tech
Vacuum SystemReconnect Jumper Connections 1/16/01 1/16/01 .1w Markley,.1w Barger,.2w Tech Modifying Vacuum Instrumentation 8/1/00 8/15/00 1w Markley, 1 w TechRoll in Commissioning 1/16/01 1/18/01 .1w Markley,.1w Barger,1w Tech
LAr Spill SystemInstalling Spill Line(temp) 8/1/00 9/1/00 1w Miller,4w Tech,1w welderInstallingSpill Line 12/1/00 1/1/00 1w Miller,4w Tech,1w welderReconnecting Spill Line 1/16/01 1/17/01 .1w Simon,.2 Tech
ODH SystemReplace Heads 12/01/00 12/02/00 .1w Markley,.1w TechRoll in Commissioning 1/16/01 1/18/01 .1w Markley,.1w Barger,.1w Tech
Control Air SystemMaintenance 11/1/00 11/15/00 .1w Barger,.5w Tech
Purge Air SystemMaintenance 11/1/00 11/15/00 .1w Barger,.5w Tech
Pond Water SystemMaintenance 10/1/00 11/1/00 .2w Simon, 4w Plant Maintenance Tech
Chilled Water SystemMaintenance 10/1/00 11/1/00 .2w Simon, 4w Plant
Maintenance Tech
DD
Kurt Krempetz (Director's Review - Dec. 7, 99)
20
Schedule/ManpowerDetails
De-ionized Chilled Water System
Maintenance 8/1/00 9/1/00 .1w Simon, .25w Tech
Testing Run 9/1/00 9/15/00 .1w Simon, .25w Tech
Roll in Commissioning 2/6/01 2/30/01 .1w Simon, .25w Tech Low Conductivity Water System
Maintenance 10/1/00 11/1/00 .2w Simon, 1w Tech
Roll in Commissioning 2/6/01 2/30/01 .1w Simon, .25w Tech HVAC Collision Hall System
Maintenance 11/1/00 12/1/00 .2w Simon, 1w Tech HVAC Detector System
Reconnect** 1/24/01 1/30/01 .2w Simon,.2 Markley,1w Tech
Roll in Commissioning 1/30/01 2/15/01 .1w Simon, .25w Tech EC Drive System
Reconnect 10/31/00 11/2/00 .1w Krempetz,.2w
Miller, 2w Tech
Commissioning 11/2/00 11/15/00 .2w Miller, .5 Tech Platform Drive System
Reconnect** 12/6/00 12/28/00 1w Miller, 4w Tech
Commissioning 12/28/00 1/1/00 .1w Krempetz,1w Miller,
4w Tech
System Details(New)
LHe Transfer Line through Shielding Wall
Design 5/1/00 6/15/00 4w Rucinski,6w Friend
Fabricate 6/15/00 7/15/00 3w Barger, 4w Tech,
1w welder
Install 2/1/01 2/1/01 .1w Barger,.1w Tech
Commission 2/5/01 2/12/01 .1w Rucinski,.1w
Markley,.1Barger,.1Tech LHe Jumpers Connections
Design 6/15/00 7/15/00 2w Rucinski,4w Friend
Partial Fabrication 7/15/00 8/15/00 2w Barger, 4w Tech, 2w Welder
Final Fabrication/Install* 2/1/01 2/5/01 .6 Rucinski, .4 Barger,2w Tech, .6w Welder Commission 2/5/01 2/12/01 .1w Rucinski,.1w
Markley,.1Barger,.1Tech
DD
Kurt Krempetz (Director's Review - Dec. 7, 99)
21
Schedule/ManpowerDetails
VLPC Cryostat Installation Fixture
Design* 12/6/99 1/14/00 2w Rucinski,3w ArnoldFabrication* 1/17/00 3/10/00 2.4w Rucinski,1w Miller,7w
TechInstallation** 4/10/00 4/28/00 .3w Rusinski,1w Miller,5w
Tech,1w Welder Commissioning*4/17/00 6/12/00 5w Rusinski,5w Markley, 2w
Krempetz,8w Barger,8w Tech
Silicon Cooling SystemDesign** 7/15/99 2/20/00 11.5w Squires, 12w Trotter,
3w Markley Installation** 1/20/00 6/20/00 8w Barger, 24w Tech,8w
Welder Commissioning 6/20/00 7/15/00 2w Squires,2w Markley,
2w Barger, 4w Tech WAMUS Gas System (Dirty)
Design*** 11/17/99 1/1/00 2w Olis, 2w Krempetz
4w Friend,2w MarkleyInstallation*** 12/1/99 1/27/00 1w Olis, 4w Barger,
8w Tech,4w Welder Commissioning*** 1/27/00 2/15/00 2w Olis,2w Markley,
2w Barger, 2w Tech WAMUS Gas System
Design*** 11/17/99 1/1/00 2w Olis, 2w Krempetz
4w Friend,2w MarkleyInstallation*** 12/1/99 1/27/00 1w Olis, 4w Barger,
8w Tech,4w WelderCommissioning*** 1/27/00 2/15/00 2w Olis,2w Markley,
2w Barger, 2w Tech MDT Gas System
Design* 2/28/00 4/28/00 1w Olis,1w Rucinski,6w Friend,2w MarkleyInstallation* 4/28/00 6/28/00 1w Rucinski, 4w Barger,
10w Tech,4w WelderCommissioning* 6/28/00 7/28/00 2w Rucinski,2w Markley,2w Barger,2Tech
DD
Kurt Krempetz (Director's Review - Dec. 7, 99)
22
Schedule/ManpowerDetails
Tracker Purge System Design*** 12/1/99 2/28/00 2w Olis, 4w Cease,
2w Krempetz, 6w Friend,2w MarkleyInstallation*** 2/28/00 4/28/00 2w Cease, 4w Simon,
12w TechCommissioning*** 4/28/00 5/11/00 2w Cease,2w Markley,2w
Tech Preshower Cable Winder
Design 11/15/99 12/15/99 .5 Krempetz,2w MateskiInstallation 2/15/00 3/15/00 .1w Krempetz, 1wSimon, 4w Tech,1w Welder
Access HardwareDesign 11/1/00 1/6/00 6w Cease, 2w Krempetz
6w Mateski,2w RucinskiInstallation 12/1/00 1/20/01 2w Cease, 4w Simon,
10w Tech,4w WelderCommissioning 1/20/01 2/6/01 2w Cease,2w Simon, 2w
Tech
*=In current schedule **=In current schedule but modified ***=In current schedule and schedule probable to slip
DD
Kurt Krempetz (Director's Review - Dec. 7, 99)
23
Conclusions
Existing System are in need of some maintenance but basically in good condition.
New systems are not needed yet but will be very soon.
Manpower for the new systems has been under estimated.
Limited manpower has been available to work on new systems.
Manpower must be available to work on these new systems or the current schedule will not be met.