TESTING & COMMISSIONING REPORT FOR
SWITCHYARD EQUIPMENTS &SWITHGEARS
PROCEDURE NO:T&C/T& C P/AIS-GIS/001Rev-3
PROJECT-765/400 KV UNNAO PROJECT
CLIENT-CROMPTON GREAVES LMITED
OWNERUTTAR PRDESH POWER TRANSMISSION
CORPORATION LIMITED
Page 1 of 3
EXECUTED BY-LARSEN & TOUBRO LIMITED-ECC DIVISIONPre Commissioning Tests For Lightning or Surge Arrester
Bay/Feeder No-801 1BEquipment Identification-LADate-2-2-2012
PRE COMMISSIONING TESTS FOR LIGHTNING ARRESTER OR SURGE ARRESTER
DETAILS OF EQUIPMENT:
LOA No. : EPU/RA/UPPTCL/CA-02
Make : XIAN XD ARRESTER CO LTD
Type: : METAL OXIDE SURGE ARRESTER
Sl. No. : R-Phase: 8830 Y-Phase: 8936 B-Phase: 8834
Year of manufacture: R-Phase: 2010 Y-Phase: 2010 B-Phase: 2010
Feeder Name : BAY-1B
Voltage Rating : 765kV
Post Installation check listS.
No.
Description Status Remarks, Record
discrepancies, if anyYes No
1. Equipment is cleaned and free from dust / dirt, foreign
materials etc.
Yes
2. Equipment is free from all visible defects on physical
inspection
Yes
3. Support structure and surge counter has been provided
with double earth
Yes
4. All nuts and bolts are tightened correctly as per specified
torque
Yes
5. Equipment erection is complete in all respect Yes
6. Permanent Labeling and identification is done Yes
7. Leveling and alignment of structure and base frame is
checked
Yes
8. All insulators and surge counter are free from any
physical defect
Yes
9. Tightness of nuts bolts of terminal connectors arechecked
Yes
10. Erection completion certificate along with list of
outstanding activities reviewed
Yes
11. Check one end of surge counter is connected to the
bottom of LA stack and one end of surge counter hasbeen earthed
Yes
12. The direction of the exhaust vent ports away from the
protected equipment and other arrester poles
Yes
13. Clearance from the arrester to earthed objects and from
the arrester pole to another arrester pole maintained as
per outline drawing and all erection has been done as per
drawing issued by Engg. Deptt.
Yes
14. Serial number and sequence of LA parts for erection of
multi stack LA is checked
Yes
8/2/2019 LA-Bay-1B
2/3
TESTING & COMMISSIONING REPORT FOR
SWITCHYARD EQUIPMENTS &SWITHGEARS
PROCEDURE NO:T&C/T& C P/AIS-GIS/001Rev-3
PROJECT-765/400 KV UNNAO PROJECT
CLIENT-CROMPTON GREAVES LMITED
OWNERUTTAR PRDESH POWER TRANSMISSION
CORPORATION LIMITED
Page 2 of 3
EXECUTED BY-LARSEN & TOUBRO LIMITED-ECC DIVISIONPre Commissioning Tests For Lightning or Surge Arrester
Bay/Feeder No-801 1BEquipment Identification-LADate-2-2-2012
VOLTECH L&T CGL UPPTCL
15. Alignment of corona rings are checked
16. After charging, leakage current on the surge counter is
checked within safe limits
Yes
IR VALUE TEST
Insulation resistance measurement using 5 kV Megger: (min. >1000M )
Surge counter reading:
Sl. No. Reading Phase
R-Phase Y-Phase B-Phase
1. Counter Reading 1 to 3 3 to 5 1 to 3
CALIBRATION STATUS TABLETEST INSTRUMENT DETAILS:
Sl. No. Between PhaseR- Phase Y- Phase B-Phase
1 1st stack and Earth >1T >1T
2 2nd stack and Earth 173G 203G
3 3rd stack and Earth 298G 385G
4 4th stack and Earth 648G 417G
5 Support Insulator to
Earth
388G 239G
8/2/2019 LA-Bay-1B
3/3
TESTING & COMMISSIONING REPORT FOR
SWITCHYARD EQUIPMENTS &SWITHGEARS
PROCEDURE NO:T&C/T& C P/AIS-GIS/001Rev-3
PROJECT-765/400 KV UNNAO PROJECT
CLIENT-CROMPTON GREAVES LMITED
OWNERUTTAR PRDESH POWER TRANSMISSION
CORPORATION LIMITED
Page 3 of 3
EXECUTED BY-LARSEN & TOUBRO LIMITED-ECC DIVISIONPre Commissioning Tests For Lightning or Surge Arrester
Bay/Feeder No-801 1BEquipment Identification-LADate-2-2-2012
VOLTECH L&T CGL UPPTCL
Sl.no Instrument description Range Calibration status
1. LT MEGGER (Analog) 500 V DC 05/07/2012
2. HT MEGGER (Analog) (2.5-5.0) KV DC 06/07/2012
3. DIGITAL MULTIMETER (0-1000) V AC 16/05/2012
4. AC CURRENT LEAKAGE TESTER (0-100) A 17/06/2012
5. CONTACT RESISTANCE KIT 100 A 23/06/2012
6. DIGITAL HT MEGGER (0.5-5) KV DC 18/06/2012
7. DIGITAL CLAMPMETER (0-2000) A 20/06/2012
FINAL DOCUMENTATION REVIEW :
A. Final documents of Pre-Commissioning Checks Reviewed and Approved YES / NOB. Documents regarding Spares, Equipment ,O&M Manuals etc available YES / NO
at site for O&M purpose
C. After Modification, If Any, AS BUILT DRAWINGS are available at site YES / NO