Upload
others
View
2
Download
0
Embed Size (px)
Citation preview
J.Monne – CCS Project ManagerTOTAL EP – R&D Division
Lacq CCS Integrated PilotA First
Green House Gas Emissions
The importance of CCS in the climate mitigation
Source : IEA WEO 2011
Limiting CO2 to 450 ppm in atmosphere to limit temperature increases to 1.5-2°C
CCS pilot, Lacq, France
Carbone Capture and Storage (CCS) is using an existing knowledge developpedby the Oil and Gas industry and by natural gas underground storage activity
Potentially this technology could be applied in 7,000 industrial sites in the world such as coal-fired power stations, steel works, refineries, petrochemical plants …
Total, a player in both R&D and operational projects in this technology for over more than 15 years :
- Sleipner, aquifer storage, 1 Mt/y, started in 1996,
- Snøhvit, aquifer storage, 0.8 Mt/y started in 2008,
- Lacq, gas depleted reservoir storage, 1 injection well, up to 60000 t/y, Total operator
Total participates in more than 14 National or International R&D projects on CCS
CCS is one of the available solution to be developed as soon as possible / optimized in term of efficiency and economics.
CCS pilot, Lacq, FranceAddressing Green House Gases emissions reduction
Lacq pilot project overview
Objectives
Acquire expertise and reduce costs for future industrial deployment
Flue gases treatment package
Lacq Field Test Compressor
To Demonstrate the technical feasibility and reliability of an integrated onshore Carbone Capture and Storage scheme for steam production.
To acquire operational experience and data to up-scale with cost reduction the oxy-combustion technology from pilot (30MWth) to industrial scale (200MWth).
To develop geological storage qualification methodologies
To develop monitoring methodologies on site to prepare future larger scale long term onshore storage projects. (Micro seismic monitoring, Environmental monitoring..)
CCS pilot, Lacq, France
Project description
This industrial operation is planned to capture and trap ~ 90,000 tonnes of CO2over a 3 1/2-year period (eq to the exhaust emissions of 30,000 cars on 2 Years)
Lacq site
800 km
Pont d’As
Saint-Faust
Lacq
5 km
Existing right of way
City of PAU
Rousse-1 injection well
27bar
TRANSPORT: 27km long pipe from Lacq to Rousse
A Full industrial integrated chain : 1st In Europe testing the Oxy-combustion technology on Gas boiler at 30Mwth.
Budget : CAPEX 60 M Euros
Financial Investment Décision end of 2006
Start-up of operational phase: July 3rd, 2009
First CO2 injection in Rousse reservoir: January 8th, 2010
End of injection: 8th July 2013
CCS pilot, Lacq, France
Permitting and public acceptance
Project information also available on www.total.com/corporate-social-responsibility
Permit obtained in may 2009 for capture, transportation and storage A « Regulatory » pilot, 1st in Europe
Public dialogue – transparency policy Identification of Stakeholders (ONG, mayors…) Early public meetings in 2007 (4 public meetings) Follow up information committee (7 meetings) Information letter every quarter (14 letters) Dedicated Hot line
Scientific Advisory Committee since 2007
Scientific collaboration program with National Institutes and Universities on Rousse storage
Project endorsed by the Carbon SequestrationLeadership Forum (CSLF)
CCS pilot, Lacq, France
Lacq pilot project technicaldescription
CCS pilot, Lacq, FranceA complete industrial chain
1010 Lacq deep gas reservoir
OxygenProduction
Unit
Lacq gas production
1
Natural gas inlet
2
Lacq gas treatment plant
3
Commercial gas
4
UtilitiesBoiler oxycombustion
5
CO2
6
CO2 Transportation
7
Compression
8CO2 injection
9
CO2 storage
10
4000 m
4500 m Natural gas
Steam
Purification / CO2 dehydration
Compression
Rousse reservoir
Industrial scale:30MWth oxycombustion60 000 t/year CO2Integrated within existing facilities
CO2 injection CO2 transport CO2 capture Natural Gasproduction
Air separation unit Oxycombustion Boiler Cooling water tower
Dehydration Unit
Capture, compression description
Lacq Compressor Rousse compressor
CCS pilot, Lacq, France
4 Pressure and Temperature sensorsObjectives :
Calibrate of reservoir models
Monitor of well injectivity
Micro-seismic sensorsObjectives
To assess the impact of the injection near the
wellbore
Top reservoir @ 4540m
Rousse well specific completionCCS pilot, Lacq, France
Microseismic equipment installed in 7shallow wells (TD: 200m/GL): 6 wells on a 2km radius circle around the
injection well;
1 well on the injection site.One seismometer for natural seismicity
Online information transmitted continouslyto a control center
In case of magnitude > 3, the injection isstopped
Events localized at +/- 250 m/magnitude - 2
Shallow well
Surface microseismic sensorsCCS pilot, Lacq, France
Subsurface Operational Feedback
Bottom hole P measurementSub-surface Feedback monitoring
Static reservoir pressure is increasing due to CO2 injection.
The reservoir pressure increase is as per the predictive model. (Eclipse 300 compositional modeling)
System has been Calibrated by real shots
Mainly natural seismic activity linked to northern
front accident of Pyrenées mountain range has
been detected (between Iberic and Eurasian
plates).
From the beginning of injection, no significant
event linked with injection has been detected.
C02 Injection
No incidence on reservoir integrity
Microseismic monitoring
Rousse
Spain
France
30km
Sub-surface Feedback monitoring
Environmental Plan Monitoring and feedback
Soil gas (35): CO2 and CH4 concentration and flux. C isotopy. Inert gas. Autumn and winter.
Perched aquifer ( 4 springs) : Chemical and mineral content, every 6 months.Indicators: pH, conductivity, carbonates, bicarbonates.
Shallow and deep saline aquifers sampled at selected existing water wells (drinking water supply of Pau). Monitoring idem perched aquifer.
Surface water ( 5 small rivers): Standardized bio-indicators (diatoms and benthic macro invertebrates) and chemical and mineral content. Every 6 months.
Fauna and Flora: Annual inventory of:• Flora of representative ecosystems (33 sites)• Several amphibians and insects species (50 sites).
Environmental monitoring
30km
RSE-1
No deviation from Baseline surveys in 2009
Soil gas, Water, Fauna & flora
1 km
City of PAU
Economics of the CCS chain
What if CCS is delayed by 10 years?
Source : IEA WEO 2011
Additional cost > 1 T Euros if CCS is delayed to achieve the same objectives
CCS pilot, Lacq, France
Capture cost : From 50 U$D/t CO2 avoided to 100 U$D/t CO2 avoided depending on CO2 Concentration
=70 % of the total CCS chain cost
Transportation Cost : Pipeline /Ship depending on distance (1 or 2 U$D / 250 Km of pipe) =10 % of the total CCS chain cost
Storage cost : 5/15 U$D/t CO2 avoided (Onshore / offshore/acquifer/depleted) = 20 % of the total CCS chain cost
Economics of CCS for GasCCS pilot, Lacq, France
Still some critical issues regarding the economics of CCS chain
= Uncertainty regarding CO2 price( OCDE 2020 50 / 2030 110 ?)= Regulation is not yet defined in all countries = Uncertainty in appraising storage capacity for acquifer storage= Until now, no insurance product has been proposed in the event of CO2 Leakage
Economics of CCS for GasCCS pilot, Lacq, France
IGCC : Integrated Gazeification Combined Cycle ( hydro/coal gasified)NGCC : Natural Gaz Combined Cycle (Gaz and steam turbines)
Conclusion
Conclusion
At this stage of the pilot (45000 T Injected), the demonstration of the technical feasibility and reliabilityof an integrated onshore Carbon Capture and Storage scheme for steam production has been proved.
The design of 200 MWth oxyboiler should be finalized in 2013.
Geological storage qualification methodologies have been developed .
The long term CO2 storage monitoring program economically and technically viable is still to be developed.
The Lacq pilot is part of the larger Total CCS technological roadmap . CCS is considered as a valuable contribution to GHG reduction. The Lacq pilot demonstration project is an example of what kind of project contributes to the deployment of this technology by 2030.
For CO2 issue from combustion in O&G sector and power generation sector , current cost evaluations for industrial size capture unit are still high , even for oxycombustion. More R&D works and demonstrations are needed before upscaling and streamlining CCS installations.
“‘Transparency” in communication with the stakeholders is one of the key factor to reach the public acceptance. It remains a permanent “concern” to be taken into account during the whole life of a CCS experimentation and for the future industrial deployment of CCS..
“Innovation is one of the main drivers of sustainable growth in our production”
DISCLAIMER and COPYRIGHT RESERVATION
The TOTAL GROUP is defined as TOTAL S.A. and its affiliates and shall include theparty making the presentation.
Disclaimer
This presentation may include forward-looking statements within the meaning of thePrivate Securities Litigation Reform Act of 1995 with respect to the financial condition,results of operations, business, strategy and plans of TOTAL GROUP that are subjectto risk factors and uncertainties caused by changes in, without limitation, technologicaldevelopment and innovation, supply sources, legal framework, market conditions,political or economic events.
The TOTAL GROUP does not assume any obligation to update publicly any forward-looking statement, whether as a result of new information, future events or otherwise.Further information on factors which could affect the company’s financial results isprovided in documents filed by TOTAL GROUP with the French Autorité des MarchésFinanciers and the US Securities and Exchange Commission.
Accordingly, no reliance may be placed on the accuracy or correctness of any suchstatements.
Copyright
All rights are reserved and all material in this presentation may not be reproducedwithout the express written permission of the TOTAL GROUP.
ASAP, ICO2N HARP & WASP
CO2 ReMoVECO2 Care
CO2Store
ANR CO2Geocarbone
Ademe – TotalAir Liquide
IPGP – ADEME –Schlumberger - TOTAL
ReGaSeq (IFP)
ANR CO2 2006-07-08CRISCO2SOCECO2
GazAnnexesProchePuits
Sentinelle / Carmex
AGI Alberta
Montmiral
Izaute & LussagnetLacq CO2
WeyburnR&D phase 1
Sleipner Snøhvit
ENCAP
Lessons learned fromoperational projects
Studies of natural analoguesand reinjection processes
R&D programs(solo or in partnership)
BigCO2Big CCS
CO2H2O+
West Texas EOR
Operational and research projects on CO2Worldwide Climate Change Context
CO2CRC
How to communicate in case of accident happening in another pilot plant and/or in existing injection sites ?How to communicate on geosciences ?How to classify the level of risk ‘’public acceptance’’among different
projects ?How to set up an independent body to review site qualification studies and
monitoring data ?How to demonstrate that CCS is not against new and renewable energies ?How to prove that CO2 will be trapped for ever?
Public dialog : Still some remaining questions CCS pilot, Lacq, France
A very fast growing activity
Source IEA
CCS pilot, Lacq, France
Start-up of operational phase: July 3rd, 2009First CO2 injection in Rousse reservoir: January 8th, 2010
End of injection: 8th July 2013
Project phasingCCS pilot, Lacq, France
Site screening and conceptual studies
Basic engineering studies
Detailed engineering and procurement
Construction works
Injection well work over
Facilities running (capture)
Injection
Environemental & seismic base line surveys
Monitoring
Information to stakeholders
Public inquiry
Permitting process / regulatory agencies
Injection schedule
Reporting to regulatory agencies
20112006 2007 2008 2009 2010 2012 2013
Start of injection8th Jan. 2010
End of injection July 2013
Official authorization05/2009
Official authorization for 18 month prolongation
11/2011
Chemistry
Bio-indicators
Phreatic aquifer (springs) Chemistry
Grounwater Chemistry
FaunaFlora
Soil gas
Res. & Caprock Microseismic + P&T
CO2 sensors at injection pad
Well annulii
P & T Flowrate, Composition
Soil gas C isotopy, Inert gas, radon
6 m deep shallow well Chemistry
80 m deep shallow well Chemistry, water level
Springs Chemistry,
Flux tower
Infra red and lidar
Phreatic aquifer
Permanent
Permanent
Permanent
Atmospheric CO2 concentration
Permanent
In test
Additional R&D (French National
Research Agency, Paris & Nancy Univ.,
INERIS, IFPEN, BRGM, IPGP etc.)
SiteInjection well
Permanent
Permanent
Permanent
Permanent
Permanent
Winter Spring Summer Autumn
Environment
Water quality
Surface water (rivers)
Ecosystems
Environmental monitoringSoil gas, Water, Fauna & flora
Injection well
Tertiary
Upper Cretaceous
Low Cretaceous
Mano - Rousse depleted gas field
S N
CO2 storage into Rousse
Geological cross – section (S – N)
CCS pilot, Lacq, France
Jurassic fractured dolomitic
reservoir
Depth # 4500m/MSL
Temp. # 150 C
Initial P: 485 bars
P before inj: # 40 bars
Final pressure: # 100 bars
Initial CO2 = 4,6%
Initial H2S < 1%
Av. Porosity: 3%
Av. Perm. = 5mD
Av. Water saturation: 30%-
40%
Only one well: RSE-1,
producing from 1972 to
2008, 0.9 GSM3 .
Why Oxycombustion technology for Lacq ?
Air boiler without CO2 Capture
Oxy-combustion is a solution to drastically reduce the Carbon footprint on gas boilers
Oxy boiler with CO2 Capture and electricity fromGRID
Oxy boiler with CO2 Capture and electricityproduced by oxy boiler
Air boiler with CO2 Post-Capture and electricityfrom the GRID
Air boiler with CO2 Post-Capture and electricityproduced by the boiler
CCS pilot, Lacq, France
The overall “ Carbon footprint ” for oxycombustion is excellent even in comparison with Amine post capture
1166
326
434
Carbon Footprint / year for an oxyboiler of 600 Mwth / 200 MWe