13
LADWP WATER SYSTEM CAPITAL PROGRAM UPDATE July 25 th 2013

LADWP WATER SYSTEM CAPITAL PROGRAM UPDATE July 25 th 2013

Embed Size (px)

Citation preview

Page 1: LADWP WATER SYSTEM CAPITAL PROGRAM UPDATE July 25 th 2013

LADWP WATER SYSTEM CAPITAL

PROGRAM UPDATEJuly 25th 2013

Page 2: LADWP WATER SYSTEM CAPITAL PROGRAM UPDATE July 25 th 2013

2

Los Angeles’ Water System

Established in 1902 Largest municipally-

owned utility in the U.S. Operating Revenue = $ 1.08 billion (FY2012/13)

3.86 million customers within 473 sq. mi. service area 679,000 active metered services Service elevation from sea level to over 2,400 feet 7,225 miles of pipeline, 114 tanks & reservoirs,

78 pump stations, 421 regulator stations 340-mile long Los Angeles Aqueduct System

The Los Angeles Aqueduct

Page 3: LADWP WATER SYSTEM CAPITAL PROGRAM UPDATE July 25 th 2013

3

Water System Priorities

Regulatory ComplianceSafe Water Supply and Compliance with Regulatory Requirements

Infrastructure ReliabilitySustainable Infrastructure Replacementand Upgrade

Sustainable Water SupplyIncrease Local Supply and Protect theEnvironment

Investments that address these priorities are interdependent and interconnected.

Los Angeles Aqueduct Cascades

Page 4: LADWP WATER SYSTEM CAPITAL PROGRAM UPDATE July 25 th 2013

4

Current and Projected Capital Expenditures

Next 10 yearsCAPITAL $ in millions

Total $8.5BTotal $484M

Page 5: LADWP WATER SYSTEM CAPITAL PROGRAM UPDATE July 25 th 2013

5

Water System Priority:Regulatory Compliance

Safety of the water we provide to our customers is LADWP’s #1 Priority

Drinking Water Regulations Require Major Investment in Water Infrastructure – two major water initiatives:

1) Open Reservoirs: cover, replace, or provide add. treatment

Regulation: Long Term 2 Surface Water Treatment Rule (LT2, April 1, 2014)

2) Chloramine Disinfection: system-wide change will reduce harmful disinfection byproducts

Regulation: Stage 2 Disinfection By-Products Rule (DBP2, June 30, 2021)

Failure to comply with regulatory requirements is NOT an option.

Page 6: LADWP WATER SYSTEM CAPITAL PROGRAM UPDATE July 25 th 2013

6

Shallow flooding dust mitigation

Gravel dust mitigation

Water System Priority:Regulatory Compliance

Owens Lake Dust Mitigation Project

• 90% of dust is controlled and Owens Lake is no longer in the top 10 list of PM10 (dust) emissions

• 42 square miles of dust control in operation

• Over $1.2 billion spent to date in capital (since Sep. 2000); $72 million in annual O&M (including cost of replacement water)

• Using up to 95,000 acre-feet per year of water from Los Angeles Aqueduct

Page 7: LADWP WATER SYSTEM CAPITAL PROGRAM UPDATE July 25 th 2013

7

Water System Priority:Regulatory Compliance

2012/13Next

10 yearsCapital Investment

Reservoirs & Trunk Lines $ 159.0 $1,337.6

Chlorine to Chloramine 26.8

100.5

Water Treatment 13.2

265.2

Owens Lake Dust Mitigation 49.4 337.3

Total $248.4 $2,040.6

Current and Projected Expenditures:($ in Millions)

Includes Water Quality Improvement Program and Owens Lake Dust Mitigation Project

Page 8: LADWP WATER SYSTEM CAPITAL PROGRAM UPDATE July 25 th 2013

8

Water System Priority:Infrastructure Reliability

LADWP’s Water System is large and complex Continually aging (233 miles of pipe are over a century old and 70% of pipes

are more than 50 years old)Maintenance and replacement is an ongoing and continuous effort

Water System Annual Leak Rate

15 leaks per 100-miles is below N. America

average of 25 leaks per 100-miles of pipe

Current 315-year Pipe Replacement

Cycle - severely deficient of frequency

required for continued reliabilityOur 7,200 miles of water distribution pipeline is the backbone of

our delivery infrastructure – we work very hard to keep its service reliability

Page 9: LADWP WATER SYSTEM CAPITAL PROGRAM UPDATE July 25 th 2013

9

Water System Priority:Infrastructure Reliability

Water Main Replacement Program

Page 10: LADWP WATER SYSTEM CAPITAL PROGRAM UPDATE July 25 th 2013

10

Water System Priority:Infrastructure Reliability

2012/13Next

10 yearsCapital Investment

Mainlines & Trunk Lines $ 63.2 $ 1,619.6

Reservoir, Pump, & Reg. Stations 21.2

634.1

Meters, Services, Hydrants 40.4

521.8

Seismic, Facilities, Equip., IT, Other 18.4 690.9

L.A. Aqueduct System 11.5 188.3

Total $154.7 $ 3,654.8

Current and Projected Expenditures:($ in Millions)

Page 11: LADWP WATER SYSTEM CAPITAL PROGRAM UPDATE July 25 th 2013

11

Water System Priority:Sustainable Water

SupplyThe City of Los Angeles plans to meet all new water demands through local resource development.

Environmental regulatory challenges and impacts of climate change requires continued focus on four major water initiatives:

1)Stormwater Capture2)Water Conservation2)Water Recycling3)San Fernando Basin Groundwater Remediation

Page 12: LADWP WATER SYSTEM CAPITAL PROGRAM UPDATE July 25 th 2013

1212

Water System Priority:Sustainable Water

Supply

FYE 2008 – 2012 Average Total: 574,600 AFY

Fiscal Year 2034 – 35 Total: 711,000 AFY

LA Aqueduct 206,81537%

Local GW64,46611%

Recycled Water6,7061%

MWD 297,94551%

Goal is to reduce our dependence on purchased supplemental imported water by 50 percent by 2035 or sooner

Charts do not reflect 100,000 AF of existing conservation

Page 13: LADWP WATER SYSTEM CAPITAL PROGRAM UPDATE July 25 th 2013

13

Water System Priority:Sustainable Water

Supply

2012/13Next

10 yearsCapital Investment

Groundwater Management & Remediation $ 12.9 $1,561.9

Water Recycling 27.9

814.3

Stormwater Capture 25.1

156.8

Water Conservation 15.1 217.3

Total $ 81.0 $ 2,750.3

Current and Projected Expenditures:($ in Millions)