Large Rehabilitation ProjectsLarge Rehabilitation ProjectsCase Study fromNikola Tesla ‘A’, Serbia.
D Spalding and J Beaton
Power Plants 2010, Serbia
Nikola Tesla A4 – A6 Boiler Rehabilitations
Doosan Power Systems have participated in the rehabilitation of the boilers on units A4, A5 & A6.
Unit Year Role Description Funded by
Unit A5 2004 Main Contractor Full boiler island rehabilitation EAR
Unit A4 2007 Main Contractor Boiler pressure parts, steam lines EPSand ancillaries, chemical clean & steam blow& steam blow.
Unit A6 2008 Main Contractor Boiler pressure parts & ancillaries EPS
Unit A6 2010 Main Contractor Boiler pressure parts & ancillaries EPSchemical clean & steam blow.
Power Plants 2010, Serbia 1
Nikola Tesla A4 – A6 Boiler Rehabilitations
Nikola Tesla Boilers Units A3 – A5
• Benson type once through lignite fired tower boiler with spiral furnace and steam flow of 920 T /H (305MW )920 Tonnes/Hour (305MWe).
• Supplied by SES Tlmace Slovakia.
Nikola Tesla Unit A6Nikola Tesla Unit A6
• Sulzer type once through lignite fired tower boiler with vertical tube furnace and steam flow of 930 Tonnes/hour (308MWe)of 930 Tonnes/hour (308MWe).
• Supplied by Rafako Poland.
Power Plants 2010, Serbia 2
Nikola Tesla A4 – A6 Boiler Rehabilitations
Units A3 – A6 History and Condition (Prior to Rehabilitation)
• Units A3 – A6 were commissioned between 1976 and 1979.
• No major investment for many yearsNo major investment for many years.
• Boiler tube degradation due to off-line corrosion.
• Suffering reduced output and large efficiency lossesand forced outages
• All units in need of major rehabilitation• All units in need of major rehabilitation.
Power Plants 2010, Serbia 3
Nikola Tesla A4 – A6 Boiler Rehabilitations
UNIT A5 Rehabilitation
• Works split into 3 main lots, Boiler Island, Turbine Island and E,C&I.• Project funded by the European Agency for Reconstruction (EAR).• Project management by TENT and Vattenfall Powerconsult
• DPS awarded Boiler Island in March 2004 after international competitive tender• DPS awarded Boiler Island in March 2004 after international competitive tender.• Remarkable outage programme of 270 days to synchronisation achieved.• Over 750,000 manhours expended on Boiler Island Works.• 44,600 site butt welds with weld repair rate < 2%., p
Power Plants 2010, Serbia 4
Nikola Tesla A4 – A6 Boiler Rehabilitations
UNIT A5 W kUNIT A5 Workscope
• 1000 tonnes of pressure parts to replace.• 44 600 site butt welds to complete• 44,600 site butt welds to complete.• HP & IP Steam lines to replace• New Atomising steam fuel oil system• New sootblowing system• Coal and Ash plant refurbishment• Draught plant refurbishment.• Coal mill refurbishment.• Boiler Valves and damper replacemento e a es a d da pe ep ace e t• Insulation and refractory replacement• Chemical clean and steam blow.
Power Plants 2010, Serbia 5
Local Laydown Area Allowed Efficient Stockpiling, Smooth Movement and Pre-Assembly of Pressure Parts.
Power Plants 2010, Serbia 6
Temporary Support Structures Developed for Lower Furnace Removal
Lower Furnace Structural supports tied back to the Upper Furnace and
Roof allowed safe removal of
Power Plants 2010, Serbia 7
Roof allowed safe removal of Evaporator Tubing
Furnace Removed from the Hopper to 56m level
Power Plants 2010, Serbia 8
Replacement Superheater Elements Lifting Process
Runway Beam usedRunway Beam usedto accelerate liftingprocess
Power Plants 2010, Serbia 9
Transition Panel Datum Position Critical Phase in Furnace Re-tube
Power Plants 2010, Serbia 10
The upper furnace walls and superheater elements can then be installed
Power Plants 2010, Serbia 11
The lower furnace follows - 1
Power Plants 2010, Serbia 12
The lower furnace follows - 2
Replacement of furnace sidewalls
Power Plants 2010, Serbia 13
Use of hand welded corner tubes in-situ to accelerate replacement of evaporator walls
Power Plants 2010, Serbia 14
Coal Burner Panel Replacement
Power Plants 2010, Serbia 15
Rehabilitation of the Economiser Outlet Flue to the Chimney
Power Plants 2010, Serbia 16
Before After
Rehabilitation of the Heavy Fuel Oil handling System and Burners
New HFO Pumps Installed New Atomising Fuel Oil
Power Plants 2010, Serbia 17
New Atomising Fuel Oil Burners
Rehabilitation of the Lignite Beater Mills During Furnace Modernisation
I t ll ti f Mill C i d Mill i t l
Power Plants 2010, Serbia 18
Installation of Mill Casing and Mill internals
Nikola Tesla A4 – A6 Boiler Rehabilitations
UNIT A4 Rehabilitation
• Works split into a greater number of lots, with more local contractors directly engaged by TENTTENT.
• Project funded by Elektroprivreda Srbija (EPS).• Project management by TENT.
• DPS awarded Boiler Island in March 2007 after international competitive tender.• Greater intensity of pressure part works. 54,000 site butt welds.• Hydraulic test achieved in just 28 weeks from commencement.• Weld repair rate maintained at a remarkable level of just 2%.
Power Plants 2010, Serbia 19
Nikola Tesla A4 – A6 Boiler Rehabilitations
UNIT A4 Workscope
• 1700 tonnes of pressure parts to replace.• 54,000 site butt welds to complete.• HP & IP Steam lines to replace• Ash plant refurbishment• Boiler Valves and damper replacement• Boiler Valves and damper replacement• Insulation replacement• Chemical clean and steam blow.
Power Plants 2010, Serbia 20
A4 Lessons Learned – Hopper Removed Last to Improve Safety
Power Plants 2010, Serbia 21
A4 Steamlines being lifted into place
Power Plants 2010, Serbia 22
Hopper Pre-assembly to Accelerate Programme Completion
Power Plants 2010, Serbia 23
A4 Job Nearly Done! - Steam Blow after the Chemical Clean
Mov03679.mpg
Power Plants 2010, Serbia 24
Nikola Tesla A4 – A6 Boiler Rehabilitations
Unit A6 Rehabilitation 434 element/panel lifts through a narrow boiler furnaceopening with afterburner
• Works carried out in 2 phases,– 2008– 2010.
opening with afterburnergrates in place.
• Upgrade of unit output to 348MWe• Replacement of virtually all boiler pressure
parts.• Very challenging programmes inVery challenging programmes in,
– 2008 only 189 days to completion and– 2010 only 203 days.
• Detailed planning and lifting studies iti l t hi th 2008critical to achieve the 2008 programme.
A clever lifting solution was developed
Power Plants 2010, Serbia 25
Nikola Tesla A4 – A6 Boiler Rehabilitations
UNIT A6 Workscope – Phase 1 - 2008
• 1057 Tonnes of pressure parts and26 000 it b tt ld i l di26,000 site butt welds including
• Upper Furnace Front & Rear Walls• Superheater 1
R h t 1• Reheater 1• Triflux Elements• Superheater 2
R h t 2• Reheater 2• Superheater 4• Superheater 5
Power Plants 2010, Serbia 26
A6 Rehabilitation Phase 1 - Limited to above the 47.5m Level
Power Plants 2010, Serbia 27
A6 Rehabilitation Phase 1 - Superheaters and Reheaters Being Lifted into Place
Power Plants 2010, Serbia 28
Nikola Tesla A4 – A6 Boiler Rehabilitations
UNIT A6 W k Ph 2 2010UNIT A6 Workscope – Phase 2 – 2010
• 1038 tonnes of pressure parts with 17,500site butt welds includingg
• Upper Furnace side walls• Superheater 3• Evaporator• Economiser• Afterburner Grates Renewal• Chemical Clean and steam blow
Power Plants 2010, Serbia 29
A6 Rehabilitation Phase 2 – Replacement of Membrane Walls and wall superheater below 47.5m Level
Power Plants 2010, Serbia 30
A6 Rehabilitation Phase 2 – Positioning of Wall Superheater
Power Plants 2010, Serbia 31
Nikola Tesla A4 – A6 Boiler Rehabilitations - Achievements
• A remarkable series of Major Boiler Rehabilitations where all key j yprogramme milestones were achieved.
• Despite the pace at which the works were carried out strong project management ensured very high Quality Assurance levels.
• Strong on-site management and decision making enabled continuous progress.
• A strong client contractor relationship was developed which ensured rapid on site dispute resolutionrapid on-site dispute resolution.
• Great cooperation with sub-contractors resulted in eliminating potential delays.
• The contract model evolved from a full boiler island rehabilitation on A5• The contract model evolved from a full boiler island rehabilitation on A5 to a highly customised workscope on A6.
• This allowed TENT to secure greater value by sub-contracting lower risk activities and DPS to focus on core boiler works
Power Plants 2010, Serbia 32
Conclusions
• Units A5, A4 and A6 boilers were successfully rehabilitated meeting all programme and technical requirements.
• Completion to programme allowed EPS to continue to supply electricity to theCompletion to programme allowed EPS to continue to supply electricity to the region and minimise energy imports over the winter months.
• Even though the scope of work on each project was extensive,exceptional quality standards were achieved,Th b il k l t d i ll l t i ifi t k th b l• The boiler works were completed in parallel to significant works on the balance of plant and turbine while the other units remained operational
• Full engagement with the local supply chain and solving problems directly with the client and the client’s advisor were critical to success.
• Effective application of a full range of project management skills was demonstrated at all levels from site and supplier management through to client relationships.
Power Plants 2010, Serbia 33
Acknowledgements
Doosan Babcock would like to acknowledge and thank EPS/TENT, Vattenfall Powerconsult and all our partners for their support in
making Nikola Tesla A4 to A6 units such exemplary large h bilit ti j trehabilitation projects.
Power Plants 2010, Serbia 34
Thank You – Any Questions?