Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
1 INTRODUCTION
1.1 Tunnel at the outset
The Metropolitan Waterworks Authority (MWA) was one of leading firms in Thailand which had employed Tunnel Boring Machines (TBM) extensively in construction of its transmission system, throughout the past 30 years. Various TBM types, including, manual, semi-mechanical, mechanical and EPB were employed in tunneling projects with diameters of TBM ranging from 3.16 to 4.56 m., for the construction of tunnel ID ranging from 2.0 to 3.4 m. The tunnels were constructed mostly in a stiff clay layer at 17-20 m. from ground surface, but some went down to 30 m., when running across Chao Phraya River.
1.2 New Era of Water Transmission Tunnels
Tunnelling becomes a common practice for MWA. EPB (Earth Pressure Balanced) shield machines were employed, enabling excavation in all types of soil profile of Bangkok possible. Having been equipped with higher efficiency back-up system, such as GYRO, the excavated alignment could be easily controlled. Newly developed segments, both steel and RC, straight and tapered, facilitate tunneling through all radius of curvature, some cases, R < 50m. Recently, MWA succeeded in projects under the 7
th Bangkok Water Supply
Improvement Project with total length of 50 km. of tunnels constructed and 14 EPB TBMs adopted.
Large-Scale Transmission Tunnel Rehabilitation Project for Sustainable Water Supply Management in Bangkok Urban Area
A Case Study of Metropolitan Waterworks Authority Bangkok, Thailand
D.Klahan & B.Vongsa & M.Panaim & P.Traidate & W.Phakjarung Metropolitan Waterworks Authority, Bangkok, Thailand
ABSTRACT: Metropolitan Waterworks Authority (MWA) has been involving in the construction of underground tunnel using Tunnel Boring Machine (TBM) for more than 30 years. Treated water has been conveyed through the large-scale transmission tunnel networks, with the total length of 187 kilometers, to the distribution pumping stations around and inside the metropolitan boundary. At the outset, the typical tunnel sections, both primary and secondary linings, were designed to be reinforced concrete. Having been in use for long term, there are some leakages detected, which caused severe effect to the road surface and to some extents to the above ground structures. MWA, therefore, launched the tunnel rehabilitation project, comprising of 4 routes, with total length of 14 km, with an aim at surveying the leakage points by employing the so-called Geophysical Surveying Method, filling the voids detected along tunnel alignment with proper materials and installing Steel Pipes (MS-Tube) inside the existing tunnels as secondary lining to strengthen the structure and to increase water pressure resistant capability.
This paper is aimed at describing the method of Tunnel rehabilitation, which has been acceptably and technically proven to be one of the proper solutions for rehabilitation of large-scale tunnel, since it was once successfully adopted in the previous tunnel repair project from Bangkhen Water Treatment Plant to Pradipat Valve Chamber. Such repaired tunnel has been in use well until now without any leakage encountered. Pipes inserted inside of tunnel were electrically welded, then, infilling mortar was grouted into the annulus around the inside of tunnel and outside of inserted pipes, leading to final tunnel section with considerably higher sectional modulus. Some challenges, for example, when performing underground works nearby the MRT Tunnel and preventive measures to cope with which employed FEM analysis in conjunction with installation of a series of geotechnical instrumentation as well as setting out the Trigger Level for monitoring, were also discussed.
Keywords : Tunnel Boring Machine (TBM), Transmission Tunnel, Primary Lining, Secondary Lining, Rehabilitation, Geophysical Method, Steel Pipes, FEM Analysis, Instrumentation, Trigger Level
1.3 Background of the problems
The initial east-bank water transmission network consisted of tunnels built solely from Reinforced Concrete. Unlike the modern tunnels, olds tunnels were without internal steel linings. (Figure 1). A problem that may arise when an underground leakage enlarges, is Sink Hole underneath the roads (Figure 2) Sink Hole may cause the road’s structure or nearby buildings to collapse. It may also cause further damage to tunnel structure itself. Damage caused water loss accounted for millions bath per year. Most severely, water supply network may come to halt, bringing unpleasant effects on the capital
Figure 1 Typical Tunnel Section
Figure 2 Sink hole caused by water leakage
2 TUNNEL REHABILITATION PROJECT
2.1 Coping with problems
According to the leakage points recorded during operation, where there were up to 25 locations found and likely more without visible evident, MWA has planned for the measure to cope with such problems. Exact location of all possible leakage points, both visible and invisible, needed to be extensively surveyed. Since employing steel lining as a secondary lining is most optimised
technique for the construction of large-scale water tunnels, nowadays, and, since, MWA had experience in choosing to insert the steel lining for the rehabilitation of some early water tunnels with success. Thus, MWA is relying on the same technique for the rehabilitation of existing tunnels for the current project. MWA, Therefore, decided to launch a project namely G-TN-R2-7(R) under the 7
th
Bangkok Water Supply Improvement Project to rehabilitate the leaked Tunnels.
2.2 Details and scope of the project
The works under this contract are consisted of
rehabilitating 4 sections of existing tunnels as shown
in Figure 3 including;
Section 1: Tunnel Diameter 2.5 meters, from
Si Phraya Valve Chamber to Lumpini Valve Chamber
with approximate length of 2.4 kilometers.
Section 2: Tunnel Diameter 2.8 meters, from
Pradipat Valve Chamber to Si Phraya Valve Chamber
with approximate length of 7.5 kilometers.
Section 3: Tunnel Diameter 2.0 meters, from Lad
Ya Riser Structure to Tha Phra Riser Structure with
approximate length of 3.7 kilometers.
Section 4: Tunnel Diameter 2.0 meters, from
Lumpini Valve Chamber to Lumpini Drop Structure
with approximate length of 0.2 kilometers.
Figure 3 Project location map
The construction period started from November
2010 to October 2013. First, works in section 1 in
conjunction with section 3 were performed at the
same time, followed by works in section 2 and
finally works in section 4.
The total contract price is 762,189,530 Baht.
The Contractor is Italian-Thai Development Public
Company Limited. Construction is supervised
jointly by MWA and the specialized consultant
including Asdecon Corporation and Geotechnical
and Foundation Engineering co.ltd. The scopes of the works are as follows;
1. To locate the leakage points along the whole
tunnel line using the geophysical method and to fill
the voids caused by leaked water with appropriate
materials. Two alternatives of geophysical methods
including Ground Penetration and Resistivity Test
were considered. The latter was selected to survey
the voids along the tunnel line since it could provide
more accurate information for the specific depth of
tunnel (approximately 17-20 m. from surface) This
method adopted the concept of difference electric
current measured in the different media. The area
where there was leakage (high moisture content)
would show lower Resistivity value than those
measured from soil or sand. Conventionally, the
Resistivity (Ohm-m) got from measurement through
soil ranged from 1-1,000, while the value got from
sand ranged from 1-100 and value got from ground
water ranged from 0.5 – 300. When plotted as
detour, lower Resistivity zone (higher moisture
content) would give blue color. The measuring
equipment and example of results are as shown in
Figure 4.
Figure 4 Resistivity test for leakage point
Figure 5 Example of the leakage survey result
From Figure 5, it was found that Resistivity test
gave the result with acceptably good agreement with
the existing leakage point information. Having done
all survey along the route line, total 27 leakage
points were found. After the area with high tendency
to have tunnel leakage was primarily located, then,
Soil Boring Investigation was performed at every
leakage point. It was obvious that, the location of
tunnel leakage would give the higher moisture
content and lower SPT-N value.
At the design stage, the Consultant, Asdecon
Corporation and Geotechnical and Foundation
Engineering co.ltd (Asdecon & GFE), had
performed the FEM analysis, and found that there
was significant effect from void around the tunnel to
the settlement of the ground and nearby structures
when shutting down the transmission system leading
to decreased pressure inside MWA tunnel. Thus,
such voids were needed to be filled before tunnel’s
shut-down. The FEM analysis was as shown in
figure 6.
Figure 6 FEM analysis to study the effect of
void when shutting down the transmission system
The schematic diagram of void filling process is
shown in Figure 7. One of materials used for filling
the voids was cement base with conventional
proportion per m3 as shown in Table 1. Such
proportion might be particularly adjusted to suit with
ground condition. In some cases, other appropriate
materials were used.
Figure 7 Void filling process
Material Weight (kg)
Cement
Bentonite
Water
350
52.5
870
Table 1 Typical void filling proportion (kg/m3)
2. To excavate and get the existing construction
shafts and valve chambers modified in order to give
ease for installation of Steel Pipes inside tunnels.
Some shafts that were backfilled and restored, were
modified and used as construction shafts for
Av
At
Medium
Clay
Stiff
Clay
Dense Sand
supplying pipes and grout car for secondary lining.
When all works finished, those shafts were again
restored to the existing condition (Figure 8).
Figure 8 Modification of existing shafts
3. To construct the by-pass piping systems at Si
Phraya and Lumpini Valve Chambers, in order to
cope with the shortage of water during shutting-
down of the transmission system and distribution
pumping stations for works under section 2 and 4
4. To install Steel Pipes inside the repaired tunnels
using electrical welding method, pour the infilling
mortar around the tunnel and pipe annulus and get
all the systems tested and disinfected before putting
in service. After tunnel’s shut-down, water inside
tunnel was drained out and tunnel’s inner surface
was thoroughly clean. It was found that, after being
used for years, the RC lining (secondary lining) of
the existing tunnel was in considerably good
conditions. There was an obvious de-scaling of
surface due to abrasion, but not very deep. The
previously repaired cracks which employed portion
of steel segment bolted and sealed to tunnel surface
were in good condition without severe damage and
excessive corrosion found (see figure 9). The cracks
were then surveyed and repaired by adopting PU
Foam, which could efficiently stop water from
outside of the tunnel. The application of PU Foam to
stop water is as shown in Figure 10. The ventilation
system, lighting system with emergency lights,
communication system and rails were, then, installed
inside the tunnel (Figure 11). In this project, the
Contractor decided to use low voltage electricity
system (380 V) instead of conventional high voltage
system (6.6 kV) inside tunnel. The advantage was
that it was unnecessary to provide transformer inside
tunnel, but required larger diameter of wire, leading
to higher installation cost, but with higher safety in
exchange.
Figure 9 Existing tunnel’s conditions after
draining out the water
Figure 10 Application of PU Foam to stop water
at existing tunnel’s cracks
Figure 11 Installation of ventilation & lighting
MS Tube was transported into tunnel on rail via
locomotive. Selection of proper rail type and size was
also of importance. Since clearance was limited, this
made conventional rail unsuitable. The channels (100 x
50) were adopted (see figure 12). Two types of
locomotives were used including electrical locomotive
and modified tow tractor (see figure 13). At the outset
of project, pipe carrier was designed to be carriage-like
which was very rigid (see figure 14). The carriage was
durable, but it took time to install pipe and rather made
some visible damage to inside surface of pipe. Later, it
was decided to change to simple roller-like carrier,
which could serve well, but needed more frequent
maintenance in exchange (see figure 15)
Figure 12 Rail made from channel 100x50
Figure 13 Modified tow tractor (Top) and conventional
electric locomotive (Bottom)
Figure 14 Pipe carriage
Figure 15 Roller-like pipe carriers
Prefabricated Pipes were transported to the
position where they would be electrically welded (see
figure 16). The annulus between outside of the pipes
and inside of tunnel was grouted by infilling mortar
(see figure 17). This mortar, when got harden, would
provide corrosion protection to the pipe as pH around
the pipe surface was increased in the same manner as
concrete providing the thin film protection for re-bar.
Tunnel’s sectional modulus was also significantly
increased.
Figure 16 Pipe transportation inside tunnel
Figure 17 Grouting of infilling mortar
Mortar grouting was controlled by pressure in
conjunction with volume measurement in order to
ensure that the annulus was filled completely. Grouting
material was specially mixed so that it could maintain
adequate workability at placing after being transported
inside tunnel and re-mixed by re-mixer car (see figure
18).
Figure 18 Set of equipment for infilling mortar
The mortar was designed to have slump flow more
than 60 cm. in diameter and target strength of 200 ksc.
The typical proportions of infilling mortar are as
shown in Table 2.
Material Weight (kg)
Cement
PFA (Fly Ash)
Water
Sand
Admixture
275
275
295
1460
45 (cc)
Table 2 Typical infilling mortar proportion (kg/m3)
MS Tubes (pipes) were connected through electrical
welding. The welded joints were tested by dyke
Penetrant test. After welding, joints needed to be
repaired and O\QC checked to ensure that same quality
as shop fabrication could be achieved. Tests, including;
Holliday detection test (2,000 v), Dolly Test (Epoxy
lining’s adhesion test) and Dry Film Thickness Test
(not less than 406 microns), were performed. Details
are as shown in figure 19.
Figure 19 On-site testing of MS tube’s internal lining
After passing pressure and disinfection tests by
MWA’s Water Quality Control Department, the
rehabilitated tunnel was ready to transmit water.
Tunnel repaired and inserted by MS tube is as shown
in figure 20.
Figure 20 Tunnel ready to be used
The average rate of pipes insertion, installation and
infill mortar grouting was 10.77 m./day for section 1
and 3, 13.56 m./day for section 2 and 11.80 m./day for
section 4. The rate of work of section 1 and 3 seemed
to be comparatively lower than those of the other two
sections because the works started first. At the outset,
the contractor encountered the problems in various
aspects, including; suitability of pipe carriage, grouting
equipment, suitability and size of steel made for rails,
maintenance of rails and locomotives and, of most
significance, the skills of workers and labors. Having
experienced the learning curve of methodology, the
rate was found to increase when undergoing works of
section 2 and 4.
2.3 Challenges and Findings : Rehabilitation nearby MRT’s Tunnels
The Effect of Rehabilitation Works to MRT Tunnels in adjacent area was taken into consideration very seriously. Prior to commence-ment of rehabilitation project, MWA needed to prove that its working conditions met the specified safety provision and tolerance of MRT. This is in accordance with MRT’s Act, that required other agencies to get permission to work in the MRT’s safety zone. Figure 21 shows that there are two MRT tunnels constructed on top and bottom of previously built MWA tunnel. At the time of construction of MRT project, ground improvement had extensively been carried out around MWA tunnel to mitigate the adverse effect from TBM’s driving. This time, there was a need to take water out of the MWA tunnel, so proper preventive measures were required to mitigate risk that might arise to MRT tunnels instead.
Place the cursor on the T of Title at the top of your newly named file an
Figure 21 Layout of MRT and MWA tunnels
The Consultant (Asdecon & GFE), as a designer, had performed extensive study using Finite Element Method (FEM) and found that, reducing pressure in-side MWA tunnel by draining water out such tunnel did not significantly affect the soil around and near-by both MWA and MRT’s tunnels (figure 22). The deformation and movement of MRT’s Tunnels was considerably small in such a way that it did not affect the serviceability of MRT’s Tunnels. It was found that the differential principle stress and differ-ential radial deformation were in acceptable limit (less than 25 kPa and less than 3 mm.). A series of instrumentation was requested to install to continual-ly monitor the ground movement both before and af-ter working. Trigger levels were set so that immedi-ate actions could be taken appropriately to tackle with problems that might arise.
Figure 22 FEM model & analysis to study effect of MWA tunnel when releasing pressure to MRT tunnels
3 CONCLUSIONS
Conclusions from the experience from this tunnel rehabilitation project can be drawn as follows;
3.1 Employing steel lining as secondary tunnel lining is considerably and acceptably optimised technique for the construction and rehabilitation of large-scale water tunnel.
3.2 Voids around tunnel at leakage points are likely the area which are soft and have higher moisture content. They are likely the small voids connected to one another rather than large single voids.
3.3 Taking into account of durability, primary lining of tunnel which was made of RC, in overall, was in acceptably good condition without severe damage, except where there were small cracks.
3.4 Geophysical method was effective way to indicate the area where are likely to have high moisture content. It can’t be employed to specifically locate the exact position of voids, but extended measures might be needed, such as boring.
3.5 This tunnel rehabilitation project, when finished,
could significantly reduce the volume of water
leakage and considerably increase the stability of
water transmission system enabling MWA to
manage the water supply to cover all service area
with higher efficiency and effectiveness. This would
make MWA to be in agreement with the ministry of
interior’s policy as well as to accomplish its mission
which is to provide “Quality Water for Quality Life”.
4. ACKNOWLEDGEMENT
The Authors would like express their sincerest gratitude and deepest appreciation to MWA Governors, Mr. Charoen Passara and Mr. Thanasak Watanathana and Deputy Governors (Engineering and Construction), Mr. Luechai Deethavorn and Mr. Vitaya Intachit for their supervision, guidance,
encouragement and leadership during the project duration.
Sincere thanks are also extended to Italian-Thai Development Public Company Limited, especially, Mr.Supak Khunviriya, Prject Manager, for good cooperation throughout the project.
The Author would like to thank Asdecon and GFE, as Consultant, for their assistance in design checking, performing FEM analysis and remedying the technical problems encountered during the project.
Finally, the authors would like to record their appreciation to the Metropolitan Waterworks Authority (MWA) for supporting this project.
5. REFERENCES
Thailand Underground and Tunnelling Group, 2012.
Tunnelling and deep excavation works in Thailand.
N. Phienwej & Z.Z. Aye & A. Sramoon & T.Juirnarongrit
& T. Srisirirojanakorn & A. Asanprakit., (eds.).,
International tunneling and Underground Space
Association, World Tunnel Congress 2012 & 38th General
Assembly, Underground Space for a Global Society,
Bangkok, 18-23 May 2012.
Thailand Underground and Tunnelling Group, 2012. Water
Supply Tunnels. T. Kongsomboon (ed)., Tunneling and
Underground Spaces in Thailand.
17.0
0 m
.
24
.00
m.
10
.5 m
.
Fill
Soft Clay
Medium Clay
Stiff Clay
Dense Sand
Stiff Clay
Medium Dense Sand 1
Stiff Clay
Medium Dense Sand 2
Medium Dense Sand 2
Hard Clay
MRT
MRT
MWA
3.0 m.
7.5 m.
3.6 m.
5.3 m.
1.2 m.
3.4 m.
1.1 m.
4.6 m.
1.2 m.
6.1 m.
4.0 m.
7.3 m.