2
ZEEBRUGGE GAS TERMINAL ZEEBRUGGE - BELGIUM Construction of a circular shaft to take a gas reservoir A s part of the extension project at the Zeebrugge gas terminal, Fontec, the Belgian subsidiary of Solétanche Bachy, was awarded the contract for the diaphragm wall works for a Liquid Natural Gas reservoir. Solétanche Bachy carried out the work as the lead contractor in partnership with Technigaz and MBG working under a design and build contract. The reservoir is a shaft with an internal diameter of 90.50m and a storage capacity of 140,000m 3 . The other three Large shaft Circular diaphragm wall A507 CLIENT: FLUXYS LNG N.V SUPERVISING ENGINEER: FLUXYS LNG-TRACTEBEL CONTRACTORS: TECHNIGAZ - FONTEC - MBG DURATION OF THE DIAPHRAGM WALL WORKS: OCTOBER 2004 TO FEBRUARY 2005 MAIN QUANTITIES : Diaphragm wall: 11,300m 2 Diaphragm wall depth: 39,5m Earthmoving: 166,000m 3 Reservoir storage capacity: 140,000m 3 Overview of the terminal

Large Shaft - Circular Diaphragm Wall

Embed Size (px)

DESCRIPTION

Large Shaft - Circular Diaphragm Wall

Citation preview

  • ZEEBRUGGE GAS TERMINALZEEBRUGGE - BELGIUM

    Construction of a circular shaft to take a gas reservoir

    A s part of the extensionproject at the Zeebruggegas terminal, Fontec,the Belgian subsidiary ofSoltanche Bachy, was awardedthe contract for the diaphragmwall works for a Liquid NaturalGas reservoir. Soltanche Bachycarried out the work as the leadcontractor in partnership withTechnigaz and MBG workingunder a design and buildcontract.

    The reservoir is a shaft with aninternal diameter of 90.50mand a storage capacity of140,000m3. The other three

    Large shaftCircular diaphragm wall

    A507

    CLIENT: FLUXYS LNG N.VSUPERVISING ENGINEER: FLUXYS LNG-TRACTEBELCONTRACTORS: TECHNIGAZ - FONTEC - MBGDURATION OF THE DIAPHRAGM WALL WORKS: OCTOBER 2004 TO FEBRUARY 2005

    MAIN QUANTITIES:

    Diaphragm wall: 11,300m2

    Diaphragm wall depth: 39,5m Earthmoving: 166,000m3

    Reservoir storage capacity: 140,000m3

    Overview of the terminal

  • A507

    reservoirs were constructed bySoltanche Bachy in 1982 using a1,5m thick diaphragm wall and a800mm thick inner wall. Advances indesign methodology made possible alighter structural solution for thisnew reservoir : it uses a 1.20m thickdiaphragm wall down to a depth of39.50m, with an excavated depth of25m (in part of 28m) .

    As the project is located on a gasstorage site, particular attention waspaid to safety and procedures weretightened as a consequence. There were further challengingrequirements: a minimum concretestrength of 40MPa was needed tomeet the calculated stress levels inthe arch form wall. This, in turn was

    dependent on a 0.5% verticalitytolerance and perfect wall continuitybetween panels. These requirementsgave rise to a need for increasedquality control to monitor the workson a continuous and daily basis.

    The walls were constructed using aKS3/2 steerable hydraulic grab and amechanical grab, both equipped withvertical alignment recording systems.The circular diaphragm wall construc-tion comprised 43 panels measuring6.68m in length and 39.5m in depth(the walls developed length along thecircular wall axis = 287m). The exca-vation of the diaphragm walls passedthrough fill, clayey sand and compactsand with a 3m minimum embedmentinto clay.

    EarthmovingConstruction of the diaphragm wall

    Overview of the terminal 3D study of movement as the diaphragm wall buckles

    CWS joints (stop end with waterstop)were used for the connection betweenpanels. Vertical alignment, includingany twisting, was very closely monito-red in order to ensure good circularwall continuity. Once the diaphragm wall had beencompleted, the construction of theconcrete capping beam was commen-ced, followed by bulk excavation insi-de the wall. Nine inclinometer tubes and 24 straingauges were integrated into the wallfor the purpose of monitoring itsbehaviour during the bulk excavationinside the shaft and during construc-tion of the LNG tank.