Upload
claudiotomas
View
6
Download
0
Embed Size (px)
DESCRIPTION
Large Shaft - Circular Diaphragm Wall
Citation preview
ZEEBRUGGE GAS TERMINALZEEBRUGGE - BELGIUM
Construction of a circular shaft to take a gas reservoir
A s part of the extensionproject at the Zeebruggegas terminal, Fontec,the Belgian subsidiary ofSoltanche Bachy, was awardedthe contract for the diaphragmwall works for a Liquid NaturalGas reservoir. Soltanche Bachycarried out the work as the leadcontractor in partnership withTechnigaz and MBG workingunder a design and buildcontract.
The reservoir is a shaft with aninternal diameter of 90.50mand a storage capacity of140,000m3. The other three
Large shaftCircular diaphragm wall
A507
CLIENT: FLUXYS LNG N.VSUPERVISING ENGINEER: FLUXYS LNG-TRACTEBELCONTRACTORS: TECHNIGAZ - FONTEC - MBGDURATION OF THE DIAPHRAGM WALL WORKS: OCTOBER 2004 TO FEBRUARY 2005
MAIN QUANTITIES:
Diaphragm wall: 11,300m2
Diaphragm wall depth: 39,5m Earthmoving: 166,000m3
Reservoir storage capacity: 140,000m3
Overview of the terminal
A507
reservoirs were constructed bySoltanche Bachy in 1982 using a1,5m thick diaphragm wall and a800mm thick inner wall. Advances indesign methodology made possible alighter structural solution for thisnew reservoir : it uses a 1.20m thickdiaphragm wall down to a depth of39.50m, with an excavated depth of25m (in part of 28m) .
As the project is located on a gasstorage site, particular attention waspaid to safety and procedures weretightened as a consequence. There were further challengingrequirements: a minimum concretestrength of 40MPa was needed tomeet the calculated stress levels inthe arch form wall. This, in turn was
dependent on a 0.5% verticalitytolerance and perfect wall continuitybetween panels. These requirementsgave rise to a need for increasedquality control to monitor the workson a continuous and daily basis.
The walls were constructed using aKS3/2 steerable hydraulic grab and amechanical grab, both equipped withvertical alignment recording systems.The circular diaphragm wall construc-tion comprised 43 panels measuring6.68m in length and 39.5m in depth(the walls developed length along thecircular wall axis = 287m). The exca-vation of the diaphragm walls passedthrough fill, clayey sand and compactsand with a 3m minimum embedmentinto clay.
EarthmovingConstruction of the diaphragm wall
Overview of the terminal 3D study of movement as the diaphragm wall buckles
CWS joints (stop end with waterstop)were used for the connection betweenpanels. Vertical alignment, includingany twisting, was very closely monito-red in order to ensure good circularwall continuity. Once the diaphragm wall had beencompleted, the construction of theconcrete capping beam was commen-ced, followed by bulk excavation insi-de the wall. Nine inclinometer tubes and 24 straingauges were integrated into the wallfor the purpose of monitoring itsbehaviour during the bulk excavationinside the shaft and during construc-tion of the LNG tank.