Lecture -1 to 3 (1. Proj Introduction, 2. Proj Definition & Life Cycle, 3. Proj Selection

Embed Size (px)

Citation preview

  • 8/11/2019 Lecture -1 to 3 (1. Proj Introduction, 2. Proj Definition & Life Cycle, 3. Proj Selection

    1/36

    Lecture1July 5th, 2014

    By : D N Banerjee

  • 8/11/2019 Lecture -1 to 3 (1. Proj Introduction, 2. Proj Definition & Life Cycle, 3. Proj Selection

    2/36

    2

    PROJECT M N GEMENT

    LECTURE-1

    PROJECTS CAN BE UNDERTAKEN BY:

    Individual i. Construction of Own House

    ii. Setting up a small or cottage

    industry

    iii. Organizing a Social Event

    iv. Etc.NGO Sector i. Social Activity - Say Setting up a

    Self Help Group

    ii. Organizing Relief Operation after

    calamity

    Corporate Sector (Large &Medium)

    i. Setting up Industrial Projects

    Government i. Infrastructure Projects

  • 8/11/2019 Lecture -1 to 3 (1. Proj Introduction, 2. Proj Definition & Life Cycle, 3. Proj Selection

    3/36

    3

    PROJECT M N GEMENT

    LECTURE-1

    EXAMPLES OF PROJECTS :

    CONSTRUCTION OF A HOUSE

    INTERIOR OF RESIDENCE/OFFICE

    SETTING UP A SHOP

    RAISING FUNDS FOR CHARITY

    PUTTING UP SMALL TO VERY LARGE

    MANUFACTURING UNIT

    INFRASTRUTURE DEVELOPMENT

    RETAIL MARKETING

  • 8/11/2019 Lecture -1 to 3 (1. Proj Introduction, 2. Proj Definition & Life Cycle, 3. Proj Selection

    4/36

    PROJECT M N GEMENT

    HOW A PROJECT IS CREATED & ACCOMPLISHED

    VISION TO CREATE

    MISSION TO ACHIEVE

    CREATING A TEAM TO WORK ON STRATEGIC

    BUSINESS PLAN

    FORMALIZE STRATEGY OF VISION

    CAPITAL OUTLAY

    RESOURCE PLANNING

    TIME SCHEDULE

    CAPACITY ASSESMENT

    ASSESSMENT OF OVERALL VIABILITY

    OF PLAN

    LECTURE-1

  • 8/11/2019 Lecture -1 to 3 (1. Proj Introduction, 2. Proj Definition & Life Cycle, 3. Proj Selection

    5/36

    5

    PROJECT M N GEMENT

    APPROVAL AND FINAL GO-AHEAD OF PLANBY APPROPRIATE SANCTIONING

    AUTHORITY

    VISION CONVERTED TO PROJECT

    LECTURE-1

  • 8/11/2019 Lecture -1 to 3 (1. Proj Introduction, 2. Proj Definition & Life Cycle, 3. Proj Selection

    6/36

    6

    PROJECT M N GEMENT

    LECTURE-1

    A PROJECT IS DIFFERENT FROM OTHER ACTIVITIES :

    A project is a combination of many activities carried

    out sequentially and is not an independent activity

    A project requires planning but activities need not

    require planningActivities could be carried out by individuals but a

    project cannot be carried out by one person.

    Activities could be repetitive in nature but in a

    project generally different activities are not repetitive

    A project has a definite start and a definite end while

    an activity may not necessarily have definite end

  • 8/11/2019 Lecture -1 to 3 (1. Proj Introduction, 2. Proj Definition & Life Cycle, 3. Proj Selection

    7/36

    Lecture2July 5th, 2014

    By : D N Banerjee

  • 8/11/2019 Lecture -1 to 3 (1. Proj Introduction, 2. Proj Definition & Life Cycle, 3. Proj Selection

    8/36

    8

    PROJECT M N GEMENT

    LECTURE-2

    DEFINITION OF PROJECT:

    A SEQUENCE OF ACTIVITIESSTRATEGICALLY PLANNED AND

    EXECUTED WITHIN A PRE-DETERMINED

    TIME FRAME & COST SCHEDULE TO

    ACHIEVE A TARGETED GOAL IN

    FULFILMENT OF A VISION

  • 8/11/2019 Lecture -1 to 3 (1. Proj Introduction, 2. Proj Definition & Life Cycle, 3. Proj Selection

    9/36

    9

    PROJECT M N GEMENT

    DEFINITION OF MANAGEMENT:

    MANAGEMENT IS MANAGING CERTAIN ACTIVITIES THROUGH

    PROPER PLANNING TO ATTAIN A

    DEFINITE GOAL

    LECTURE-2

    Management deals with framing policies and formulating

    guidelines. These are implemented or executed by

    executives or administrators. Hence Administration is

    different from Management

    Administration is administering or implementing

    policies, guidelines framed by the Management.

  • 8/11/2019 Lecture -1 to 3 (1. Proj Introduction, 2. Proj Definition & Life Cycle, 3. Proj Selection

    10/36

    10

    PROJECT M N GEMENT

    LECTURE-2

    SO WHAT IS PROJECT MANAGEMENT:

    PROJECT MANAGEMENT IS FRAMINGPOLICIES, GUIDELINES AND PLANS FOR

    CONVERTING THE VISION OR GOAL OF

    THE PROMOTOR INTO REALITY.

    The Senior Members of the Project Management

    Team creates the policies, guidelines and plans

    and these are executed through theadministrators, engineers, technicians who are

    also part of the team.

  • 8/11/2019 Lecture -1 to 3 (1. Proj Introduction, 2. Proj Definition & Life Cycle, 3. Proj Selection

    11/36

    11

    Phase-1

    Concept

    Phase-2

    Planning

    Phase-3

    Execution

    Phase-4

    Winding-Up

    Identify need Put a project team

    in place

    Procurement action Handing over of

    project

    Develop capital

    outlay

    Garner external

    support if need be

    Placement of

    implementation and quality

    management team

    Taking clearances on

    zero

    deficiencies/defects

    Scheduling and

    fixing important

    milestones

    Design

    Engineering

    with BOQ and

    Specification

    Supervision of work,

    monitoring progress and

    taking corrective actions to

    achieve milestones

    Demobilization and

    redeployment of

    manpower

    Establish

    feasibility

    PERT-CPM

    scheduling

    Reporting progress (PMIS) Reconciliation of all

    material

    Identify

    alternatives

    Finalize Project

    Cost based on

    final design

    Holding Regular review

    meetings internally &

    externally

    Transfer of material

    and clearing out of

    site

    Finalize strategic

    business plan

    Inter disciplinary

    co-ordination

    Inter disciplinary co-

    ordination

    Closing Accounts and

    Winding-Up

    PROJECT M N GEMENT

    LECTURE-2

    PROJECT LIFE CYCLE

  • 8/11/2019 Lecture -1 to 3 (1. Proj Introduction, 2. Proj Definition & Life Cycle, 3. Proj Selection

    12/3612Phase-1 Phase-2 Phase-3 Phase-4Concept Planning Execution Winding-up

    Le

    velofresourcerequired

    GRAPHICAL REPRESENATATION OF

    PROJECT LIFE-CYCLE

    PROJECT M N GEMENT

    LECTURE-2

  • 8/11/2019 Lecture -1 to 3 (1. Proj Introduction, 2. Proj Definition & Life Cycle, 3. Proj Selection

    13/36

    13Phase-1 Phase-2 Phase-3 Phase-4Concept Planning Execution Winding-up

    Le

    velofresourc

    erequired

    GRAPHICAL REPRESENATATION OF RESOURCE

    REQUIREMNET IN PROJECT LIFE-CYCLE

    PROJECT M N GEMENT

    LECTURE-2

  • 8/11/2019 Lecture -1 to 3 (1. Proj Introduction, 2. Proj Definition & Life Cycle, 3. Proj Selection

    14/36

    14

    INTRODUCTION TO PMBOK

    LECTURE-2

  • 8/11/2019 Lecture -1 to 3 (1. Proj Introduction, 2. Proj Definition & Life Cycle, 3. Proj Selection

    15/36

    PMBOK stands for Project Management Body of Knowledge.

    PMBOK standardizes the processes or phases involved in Project

    Management, which we have seen in Project Life Cycle. It also

    standardizes the knowledge areas accepted as best practice for the

    project management profession.

    There are various types of projects such asconstruction,

    engineering, automotive, defence; software or even disaster

    management. PMBOK while standardizing the Processesand

    Knowledge Areas,it provides the fundamentals of ProjectManagement irrespective of the type of project.

    LECTURE-2

  • 8/11/2019 Lecture -1 to 3 (1. Proj Introduction, 2. Proj Definition & Life Cycle, 3. Proj Selection

    16/36

    It is now an internationally recognised standard (ANSI/PMI 99-

    001-2008 and IEEE 1490-2011). It is published from time to time

    by PMI and is currently in its 5th

    edition.

    LECTURE-2

    ANSI - American National Standards Institute

    PMI - Project Management Institute

    IEEE - Institute of Electrical and Electronics Engineers.

  • 8/11/2019 Lecture -1 to 3 (1. Proj Introduction, 2. Proj Definition & Life Cycle, 3. Proj Selection

    17/36

    PMBOK recognises 5 basic process groups or Phases

    1. Initiating ( Concept)2. Planning

    3. Executing

    4. Monitoring and Controlling (Newly Introduced )

    5. Closing (Winding-up)

    Processes overlap and interact throughout a project or phase.

    Processes are described in terms of:

    Inputs - documents, plans, designs, etc.Tools and Techniques - mechanisms applied to inputs

    Outputs - documents, products, etc.

    LECTURE-2

  • 8/11/2019 Lecture -1 to 3 (1. Proj Introduction, 2. Proj Definition & Life Cycle, 3. Proj Selection

    18/36

    Besides the process groups or phases PMBOK also recognises

    10 knowledge areas typical of almost all projects.

    The 10 knowledge areas are:

    1. Project Integration Management

    2. Project Scope Management

    3. Project Time Management4. Project Cost Management

    5. Project Quality Management

    6. Project Human Resource Management

    7. Project Communications Management8. Project Risk Management

    9. Project Procurement Management

    10. Project Stakeholder Management (added in the 5th edition)

    LECTURE-2

  • 8/11/2019 Lecture -1 to 3 (1. Proj Introduction, 2. Proj Definition & Life Cycle, 3. Proj Selection

    19/36

    Each knowledge area contains some or all of the project

    management processes or groups such as

    Plan say for Time Management

    Conduct say for Time Management

    Administer say for Time Management

    Close say for Time Management

    It would typically be same for all the above mentioned knowledge

    areas

    PMBOK can be adopted for General Management also which

    could include planning, organising, staffing, executing and

    controlling the operations of an organisation. Financial forecasting,

    organisational behaviour and planning techniques are also similar.

    LECTURE-2

  • 8/11/2019 Lecture -1 to 3 (1. Proj Introduction, 2. Proj Definition & Life Cycle, 3. Proj Selection

    20/36

    Lecture3July 5th, 2014

    By : D N Banerjee

  • 8/11/2019 Lecture -1 to 3 (1. Proj Introduction, 2. Proj Definition & Life Cycle, 3. Proj Selection

    21/36

    21

    PROJECT M N GEMENT

    LECTURE-3

    PROJECT SELECTION

    PROJECT SELECTION LECTURE 3

  • 8/11/2019 Lecture -1 to 3 (1. Proj Introduction, 2. Proj Definition & Life Cycle, 3. Proj Selection

    22/36

    22

    PROJECT SELECTION

    To get a Market Research conducted on the products for gettingauthentic data on short and long term effects the products or goodsmay have on the demand-supply pattern and to get authentic data onthe prevalent market prices of the products in various regions.

    LECTURE-3

    To identify various potential business ventures for vertical growth of

    the existing business or for First Timers - New line of products

    To gather authentic data on the prevailing technology being used bycompetitors and the latest technologies available internationaly

    PRELIMINARY ACTIVITIES

    To identify various potential business ventures having synergy with

    the existing business activities for strategic horizontal growth of the

    business - Expansion; Backward Integration; Forward Integration;

    Conversion of By-Products and / or Waste into saleable products

    LECTURE 3PROJECT SELECTION

  • 8/11/2019 Lecture -1 to 3 (1. Proj Introduction, 2. Proj Definition & Life Cycle, 3. Proj Selection

    23/36

    23

    LECTURE-3

    INTERMEDIATE ACTIVITIES

    Based on the Preliminary Activities to narrow down theinitially identified ventures for further study

    To establish the preliminary viability of the selected

    ventures based on the following criterion:

    Approx. Project Cost

    Cost of Product vis--vis the standard selling price

    expected to prevail in the market when ready

    Investment Recovery Period

    Time schedule to complete the project and starting of

    commercial production

    Expected Profitability

    PROJECT SELECTION

    LECTURE 3PROJECT SELECTION

  • 8/11/2019 Lecture -1 to 3 (1. Proj Introduction, 2. Proj Definition & Life Cycle, 3. Proj Selection

    24/36

    24

    LECTURE-3

    FINAL ACTIVITIES

    Based on the Preliminary viability studies to identify oneor two business proposals for further detailed study

    The viability study is conducted in more detail to arrive at

    a more authentic and as near to reality figures as

    possible

    Based on the above finally one business proposal is

    selected

    Once the SELECTION process is overPHASE-1 of the

    Project Management Life Cycle is launched

    PROJECT SELECTION

    LECTURE 3BENIFIT

  • 8/11/2019 Lecture -1 to 3 (1. Proj Introduction, 2. Proj Definition & Life Cycle, 3. Proj Selection

    25/36

    25

    LECTURE-3BENIFIT

    BENEFITS OF PROJECT MANAGEMENT FOR COMPANY

    Planned and organized approach

    Setting standards and specifications and norms

    Budget formulation and effective cost control

    Planned and effective scheduling

    Effective and close monitoring at every stage and phase

    Constant evaluation and taking corrective measures

    Completing the project within the planned parameters of cost

    and time

    Effective Statutory Compliances

    LECTURE 3LIVE PROJECT

  • 8/11/2019 Lecture -1 to 3 (1. Proj Introduction, 2. Proj Definition & Life Cycle, 3. Proj Selection

    26/36

    26

    LECTURE-3LIVE PROJECT

    VIEWS FROM A LIVE PROJECT

    FROM GROUND TO FINISHEDSTRUCTURE PROGRESSIVELY

  • 8/11/2019 Lecture -1 to 3 (1. Proj Introduction, 2. Proj Definition & Life Cycle, 3. Proj Selection

    27/36

    GROUND WHERE

    PROJECT TO BE

    CONSTRUCTED

    EXISTING

    ASH SILO

    2 NOS

    CHIMNEY

  • 8/11/2019 Lecture -1 to 3 (1. Proj Introduction, 2. Proj Definition & Life Cycle, 3. Proj Selection

    28/36

  • 8/11/2019 Lecture -1 to 3 (1. Proj Introduction, 2. Proj Definition & Life Cycle, 3. Proj Selection

    29/36

  • 8/11/2019 Lecture -1 to 3 (1. Proj Introduction, 2. Proj Definition & Life Cycle, 3. Proj Selection

    30/36

  • 8/11/2019 Lecture -1 to 3 (1. Proj Introduction, 2. Proj Definition & Life Cycle, 3. Proj Selection

    31/36

  • 8/11/2019 Lecture -1 to 3 (1. Proj Introduction, 2. Proj Definition & Life Cycle, 3. Proj Selection

    32/36

    32

  • 8/11/2019 Lecture -1 to 3 (1. Proj Introduction, 2. Proj Definition & Life Cycle, 3. Proj Selection

    33/36

  • 8/11/2019 Lecture -1 to 3 (1. Proj Introduction, 2. Proj Definition & Life Cycle, 3. Proj Selection

    34/36

  • 8/11/2019 Lecture -1 to 3 (1. Proj Introduction, 2. Proj Definition & Life Cycle, 3. Proj Selection

    35/36

  • 8/11/2019 Lecture -1 to 3 (1. Proj Introduction, 2. Proj Definition & Life Cycle, 3. Proj Selection

    36/36

    EXISTING

    ASH SILO

    2 NOS

    CHIMNEY