Lecture 10- Project Planning and Scheduling

Embed Size (px)

Citation preview

  • 8/16/2019 Lecture 10- Project Planning and Scheduling

    1/26

    Construction

    Project Planning and Scheduling

    CE142

    Dr. J. Berlin P. Juanzon CE, MBA,MSCM

    LECTURE 10

  • 8/16/2019 Lecture 10- Project Planning and Scheduling

    2/26

    2

     A project is a collection of tasks that must be

    completed in minimum time or at minimal cost.

    Objectives of Project Scheduling

    Completing the project as early as possible bydetermining the earliest start and finish of each

    activity.

    Calculating the likelihood a project will be

    completed within a certain time period. inding the minimum cost schedule needed to

    complete the project by a certain date.

    !ntroduction

  • 8/16/2019 Lecture 10- Project Planning and Scheduling

    3/26

    "

    Objectives of Project Scheduling

    !ntroduction

     – !nvestigating the results of possible delays in

    activity#s completion time.

     – Progress control.

     – Smoothing out resource allocation over theduration of the project.

  • 8/16/2019 Lecture 10- Project Planning and Scheduling

    4/26

    Steps in the Planning Process

    1) Identify the tasks.

    2) Clearly state the objective of each task.

    3) Estiate the Personnel! "ie and #eso$rces toeet objectives.

    %) &evelop a task se'$ence.

    () Estiate the ork ite developent costs.

  • 8/16/2019 Lecture 10- Project Planning and Scheduling

    5/26

    Steps in the Planning Process

    1) Identify the tasks. "asks bring the project fro a proble to a prod$ct.

    Initially activities to be perfored

    Start ith ajor developent activities

    *reak don into saller tasks

    2) Clearly state the objective of each task. "asks refined to here res$lts of the activities are stated

    objectives. Easily $nderstood by entire design tea

    Specific as to hat info is to be developed

    +easible

    ,iven tie! personnel! e'$ipent

  • 8/16/2019 Lecture 10- Project Planning and Scheduling

    6/26

    Steps in the Planning Process

    3) Estiate the Personnel! "ie and #eso$rces to eet

    objectives.

    Estiates are alays diffic$lt as design takes tie. - variety of schees are $sed to estiate! all are based on

    ass$ptions. "rack record ithin copanies is alays the

     best indicator.

  • 8/16/2019 Lecture 10- Project Planning and Scheduling

    7/26

    Steps in the Planning Process

    %) &evelop a task se'$ence. Se'$ential "asks

    Parallel tasks Co$pled

    nco$pled

    &evelop a planning/sched$ling chart ilestone or ,antt chart

    PE#"

  • 8/16/2019 Lecture 10- Project Planning and Scheduling

    8/26

    Steps in the Planning Process

    %) &evelop a task se'$ence. &esign Str$ct$re 0atri Shos &ependency of tasks)

    A B C D E F G

    Moiliza!ion A  A

    La"ou!in# an$ S!a%in# B $ %

    E&'a(a!ion o) Colu*n Foo!in# C $ C

    Fari'a!e Foo!in# + Colu*n Rear D $ &

    Fari'a!e Colu*n For* E $ '

    -n!all Colu*n + Foo!in# Rear F $ $

    Con're!in# o) Colu*n Foo!in# G $ (() Estiate the prod$ct developent costs.

  • 8/16/2019 Lecture 10- Project Planning and Scheduling

    9/26

    Planning and Scheduling

      Gan!! Car! The bar or Gantt Chart is a widely used simple project scheduling

    technique. Advantages include:

    Direct correlation with time. Straight orward relationship with projects involving a limited

    number o tas!s. Straight orward integration o subtas!s having separate scheduling

    charts. Time schedule is le"ible and is e"panded to show tas!s o shorter

    nature. #rogress against the plan is easily relected.

    Disadvantage includes: That it does not convey the comple" interrelationships that may

    occur between tas!s.

  • 8/16/2019 Lecture 10- Project Planning and Scheduling

    10/26

    (antt Chart

  • 8/16/2019 Lecture 10- Project Planning and Scheduling

    11/26

    Planning and Scheduling

     Mile!one Car! A Mile!one 'ar! i i*ilar !o a Gan!! Car! /i! !e

    e*ai la'e$ on !a% 'o*le!ion.

    -! e*o$ie !e a*e i*li)ie$ !e'niue a $oe !e

    Gan!! 'ar!. -! $oe no! or!ra" !e in!errela!ioni

    e!/een !a% an$ en'e $oe no! i$en!i)" !e 'ri!i'al

    a!.

  • 8/16/2019 Lecture 10- Project Planning and Scheduling

    12/26

    )ilestone Chart

  • 8/16/2019 Lecture 10- Project Planning and Scheduling

    13/26

    Planning and Scheduling

    PERT {Program Evaluation and Review Technique}

    The PERT chart has distinct advantages forcomplex projects with interrelated tasks.

    PERT due to its complexit! of timeestimations has given wa! to more popular"P# methods.

  • 8/16/2019 Lecture 10- Project Planning and Scheduling

    14/26

    Planning and Scheduling

    PERT "hart

    Three Time Estimates$

    %PT&'T&" ( 'hortest time) to

    #%'T *&+E*, ( -est Estimate) t#

    PE''&'T&" ( *ongest time) tp

  • 8/16/2019 Lecture 10- Project Planning and Scheduling

    15/26

    Planning and Scheduling

    Critical Path )ethod *as some common characteristics with P'+,

    &efined by activities and events  An activity is a time-consuming effort that is reuired

    to complete part of a project. Shown as an arrow on

    the diagram

     An event is denoted by a circle and defines the end

    of one activity and beginning of the ne/t. An event

    may be a decision point.

    -ctivity Event

  • 8/16/2019 Lecture 10- Project Planning and Scheduling

    16/26

    DEF--T-3 3F TERMS - A ET3R5 ctivit! $ any portions of project (tasks) which required

    by project, uses up resource and consumestime – may involve labor, paper work,

    contractual negotiations, machinery operationsActivity on Arrow (AOA) showed as arrow, AO – Activityon ode

    Event $ beginning or ending points of one or more

    activities, instantaneous point in time, also called!nodes"

    /etwork  # $ombination of all project activities and theevents

    ACT-6-T7

    PRECEED-G SUCCESS3R

    E6ET

     A

    ES LS

    %

    EF LF

    C

    ES LSD D

  • 8/16/2019 Lecture 10- Project Planning and Scheduling

    17/26

    Planning and Scheduling

    Critical Path )ethod ,erminology

    'arliest Start time 0'S1

    atest Start time 0S1

    'arliest inish time 0'13

    &uration 0&1 ' 4 'S 5 &

    atest inish 01 4 S 5 &

    ,otal loat 0,1 , 4 S - 'S 0Slack between the earliest and latest start times1

    On CP3 the total float is 6ero.

  • 8/16/2019 Lecture 10- Project Planning and Scheduling

    18/26

    Critical Path )ethod

    C#$ %"ample

  • 8/16/2019 Lecture 10- Project Planning and Scheduling

    19/26

    Critical Path )ethod

    Earliest Start "ies Established

    ACT-6-T73.

    ACT-6-T701RT&%/

    PREDECESS3R

    7 %obili&ation ' day

    2 ayout and taking ' day '

    " *+cavate ooting - days .

    8 abricate ootingrebar

    . days '

    9 abricate $olumn/ebar

    0 days -

    :1nstall ooting /ebars ' day 0,-

    ; 1nstall $olumn /ebars - days 2,3

    < $oncreting of ooting ' day 4

    = abricate $olumnorms

    3 days .

    7> 1nstall $olumn orms . days 5,6

  • 8/16/2019 Lecture 10- Project Planning and Scheduling

    20/26

    Critical Path )ethod

    ?',@O+ &!A(+A)

    7 2 8 9 ;

    " :

    =

    <)O%)O% B S

    A%

    ,?(

    +'%

    A%

    CO.

    +'%

    '$C

    ,?(

    !?S,

    ,?(

    +'%

    !?S,

    CO

    +'%

    CO?C

    ,?(

    A%

    O+)

    CO

    7>

    !?S,

    CO

    +'%

    !?S,

    CO

    O+)

    77

    CO?C

    CO

  • 8/16/2019 Lecture 10- Project Planning and Scheduling

    21/26

    CP) Calculations

    ,he calculations of the critical path and theproject duration is relatively simple3 reuiring

    only addition and subtraction.

    orward Pass,he first step in the calculations is to perform a

    forward pass. !n this step3 the early start and early

    finish of each activity are calculated. ,he early start

    0'S1 is the earliest time as activity may start. ,he

    early finish 0'1 is the earliest point at which an

    activity can be completed.4 5

  • 8/16/2019 Lecture 10- Project Planning and Scheduling

    22/26

    CP) Calculations

    %ackward Pass,he second stage is to move backward through the

    network and determine the late finish and late start

    times of each activity. ,he late finish 01 for theactivity in the network is asimed to be eual to the

    early finish calculated in the forward pass. !f there

    are multiple closing activities3 the greatest early

    finish is used. All other nodes are calculated using 4 )inimum S of all following activities

    ,hen the late start 0S1 can be calculated as

    S 4 - &

  • 8/16/2019 Lecture 10- Project Planning and Scheduling

    23/26

    CP) Calculations

    CP) loatCritical activities cannot be delayed or else the

    duration of the project will be longer. Activities with

    eual 'S and ' or 6ero float are considered criticalactivities and belongs to the critical path.

     

    ,hose activities that are not critical path will have

    scheduling leeway3 meaning that their start times canbe adjusted within limits that will not affect the

    duration of the project. !n construction industry3 this

    scheduling leeway is commonly called as total float.

  • 8/16/2019 Lecture 10- Project Planning and Scheduling

    24/26

    CP) Calculations

    ,O,A OA,

    , 4 D '

    4 S D 'S

    +'' OA,

    ree float is the minimum early start of

    all the following activities less the earlyfinish

    4 'S)!? D 0'S 5 &E+A,!O?1

  • 8/16/2019 Lecture 10- Project Planning and Scheduling

    25/26

    DATA SHEET:

    ACT-6-T7

    PREDESESS3R

    DURAT-3

    START F--S8 FL3ATCR-T-CA

    LACT-6-T7'S S ' ,

     A - 2

    % A "

    C % 8

    & A3% 2

    ' C "

    & 7

  • 8/16/2019 Lecture 10- Project Planning and Scheduling

    26/26