Life Cycle Cost Analysis for Bridges. In Search of Better Investment and Engineering Decisions. Presented by: Hank Bonstedt Executive Director Prestressed Concrete Association of Pennsylvania. What is Life Cycle Cost?. An economic analysis procedure that uses engineering inputs - PowerPoint PPT Presentation

Citation preview

Page 1: Life Cycle Cost Analysis for Bridges

Life Cycle Cost Analysis for Bridges

Life Cycle Cost Analysis for Bridges

In Search of Better Investment and

Engineering Decisions

In Search of Better Investment and

Engineering Decisions

Presented by: Hank BonstedtExecutive DirectorPrestressed Concrete Association of

Pennsylvania

Page 2: Life Cycle Cost Analysis for Bridges

What is Life Cycle Cost?

What is Life Cycle Cost?

• An economic analysis procedure that uses engineering inputs

• Compares competing alternatives considering all significant costs

• Expresses results in equivalent dollars (present worth)

• An economic analysis procedure that uses engineering inputs

• Compares competing alternatives considering all significant costs

• Expresses results in equivalent dollars (present worth)

Page 3: Life Cycle Cost Analysis for Bridges

Cost ConsiderationsCost Considerations

Maintenance and Inspection

Cost

Initial Cost

Costs

Present Worth

Years

Rehabilitation Cost

Salvage Value

Salvage Costs

Page 4: Life Cycle Cost Analysis for Bridges

Present Worth AnalysisPresent Worth Analysis

• Discounts all future costs and benefits to the present:

t=n

PW = FC + pwf [MC+IC+FRC+UC] + pwf [S] t=0

• Discounts all future costs and benefits to the present:

t=n

PW = FC + pwf [MC+IC+FRC+UC] + pwf [S] t=0

FC = First (Initial) Costt = Time Period of AnalysisMC = Maintenance CostsIC = Inspection CostsFRC = Future Rehabilitation CostsUC = Users CostsS = Salvage Values or Costspwf = Present Worth Factor

FC = First (Initial) Costt = Time Period of AnalysisMC = Maintenance CostsIC = Inspection CostsFRC = Future Rehabilitation CostsUC = Users CostsS = Salvage Values or Costspwf = Present Worth Factor

Page 5: Life Cycle Cost Analysis for Bridges

First (Initial) CostFirst (Initial) Cost

• Initial cost of structure

• Incentive/disincentive payments should not be included since they would reflect user benefits or costs prior to structure going into service

• Initial cost of structure

• Incentive/disincentive payments should not be included since they would reflect user benefits or costs prior to structure going into service

Page 6: Life Cycle Cost Analysis for Bridges

Time Period of AnalysisTime Period of Analysis

• Normally equal for all alternatives

• Should include at least one major rehabilitation– Needed to capture the true economic benefit

of each alternative

• Bridge design today is based on a probabilistic model of 100 years

• Normally equal for all alternatives

• Should include at least one major rehabilitation– Needed to capture the true economic benefit

of each alternative

• Bridge design today is based on a probabilistic model of 100 years

Page 7: Life Cycle Cost Analysis for Bridges

Maintenance CostsMaintenance Costs

• Annual cost associated with the upkeep of the structure

• Information is difficult to obtain for a given project

• Cost varies on the basis of size of the structure (sqft)

• Best Guess Values– Frequency - Annual– Concrete 0.05 % of Initial Cost– Structural Steel 0.05 % of Initial Cost

• Annual cost associated with the upkeep of the structure

• Information is difficult to obtain for a given project

• Cost varies on the basis of size of the structure (sqft)

• Best Guess Values– Frequency - Annual– Concrete 0.05 % of Initial Cost– Structural Steel 0.05 % of Initial Cost

Page 8: Life Cycle Cost Analysis for Bridges

Inspection CostsInspection Costs

• Requirements set forth in the National Bridge Inspection Standards (23 CFR 650.3)

• Occurs for all alternatives every two years• Cost varies on the basis of size of the

structure (sqft) and by construction material• Best Guess Values

– Frequency - Biannual– Concrete 0.15 % of Initial Cost– Structural Steel 0.20 % of Initial Cost

• Requirements set forth in the National Bridge Inspection Standards (23 CFR 650.3)

• Occurs for all alternatives every two years• Cost varies on the basis of size of the

structure (sqft) and by construction material• Best Guess Values

– Frequency - Biannual– Concrete 0.15 % of Initial Cost– Structural Steel 0.20 % of Initial Cost

Page 9: Life Cycle Cost Analysis for Bridges

Future Painting CostsFuture Painting Costs

• Only applies to structural steel structures but excludes weathering steel

• Should occur every 20 years• Cost varies on the basis of size of the

structure (sqft)• Best Guess Values

– Frequency – every 20 years– Concrete 0.0 % of Initial Cost– Structural Steel 7.0 % of Initial Cost

• Only applies to structural steel structures but excludes weathering steel

• Should occur every 20 years• Cost varies on the basis of size of the

structure (sqft)• Best Guess Values

– Frequency – every 20 years– Concrete 0.0 % of Initial Cost– Structural Steel 7.0 % of Initial Cost

Page 10: Life Cycle Cost Analysis for Bridges

Future Rehabilitation Costs

Future Rehabilitation Costs

• The frequency is not only a function of time but also the growing traffic volume and the structural beam system

• Cost varies on the basis of size of the structure (sqft) and structural beam system

• Best Guess Values– Frequency

• First occurrence – Concrete 40 years• First occurrence – Structural Steel 35 years• Annual traffic growth rate .75 % (shortens rehab

cycles)– Concrete 20.0 % of Initial Cost– Structural Steel 22.0 % of Initial Cost

• The frequency is not only a function of time but also the growing traffic volume and the structural beam system

• Cost varies on the basis of size of the structure (sqft) and structural beam system

• Best Guess Values– Frequency

• First occurrence – Concrete 40 years• First occurrence – Structural Steel 35 years• Annual traffic growth rate .75 % (shortens rehab

cycles)– Concrete 20.0 % of Initial Cost– Structural Steel 22.0 % of Initial Cost

Page 11: Life Cycle Cost Analysis for Bridges

Salvage Value/CostsSalvage Value/Costs

• Occurs once at end of life of structure

• Difference between– Removal cost– Salvage value

• Best Guess Values– Removal cost 10 % of Initial Cost– Salvage Value – Concrete - 0 % of Initial Cost– Salvage Value – Structural Steel - 2 % of Initial

Cost

• Occurs once at end of life of structure

• Difference between– Removal cost– Salvage value

• Best Guess Values– Removal cost 10 % of Initial Cost– Salvage Value – Concrete - 0 % of Initial Cost– Salvage Value – Structural Steel - 2 % of Initial

Cost

Page 12: Life Cycle Cost Analysis for Bridges

Users CostsUsers Costs

• For early construction completion, maintenance and rehabilitations only

• Delay-of-use• Time delay• Fuel consumption• Driver discomfort

• Vehicle operating costs

• Accidents

• For early construction completion, maintenance and rehabilitations only

• Delay-of-use• Time delay• Fuel consumption• Driver discomfort

• Vehicle operating costs

• Accidents

Page 13: Life Cycle Cost Analysis for Bridges

Users CostsUsers Costs

• Pros– Users pay for transportation system– Drives the results

• Cons– Owner can not recoup costs– Not in my budget– Drives the results

• Pros– Users pay for transportation system– Drives the results

• Cons– Owner can not recoup costs– Not in my budget– Drives the results

Page 14: Life Cycle Cost Analysis for Bridges

Users CostsUsers Costs

• Driver Delay Costs:

DDC = (L/Sa-L/Sn) x ADT x N x w

L = Length of affected road waySa = Traffic speed during maintenance activitySn = Normal traffic speedADT = Average daily traffic (vehicles per day)N = number of days of maintenance activityw = Hourly time value of drivers

• Driver Delay Costs:

DDC = (L/Sa-L/Sn) x ADT x N x w

L = Length of affected road waySa = Traffic speed during maintenance activitySn = Normal traffic speedADT = Average daily traffic (vehicles per day)N = number of days of maintenance activityw = Hourly time value of drivers

Page 15: Life Cycle Cost Analysis for Bridges

Users CostsUsers Costs

• Vehicle Operating Costs:

VOC = (L/Sa-L/Sn) x ADT x N x r

L = Length of affected road waySa = Traffic speed during maintenance activitySn = Normal traffic speedADT = Average daily traffic (vehicles per day)N = number of days of maintenance activityr = weighted-average vehicle cost

• Vehicle Operating Costs:

VOC = (L/Sa-L/Sn) x ADT x N x r

L = Length of affected road waySa = Traffic speed during maintenance activitySn = Normal traffic speedADT = Average daily traffic (vehicles per day)N = number of days of maintenance activityr = weighted-average vehicle cost

Page 16: Life Cycle Cost Analysis for Bridges

Users CostsUsers Costs

• Accident Costs:

AC = L x ADT x N x (Aa-An) x ca

L = Length of affected road wayADT = Average daily traffic (vehicles per day)N = number of days of maintenance activityAa = Accident rate during maintenance activityAn = Normal accident rateca = Cost per accident

• Accident Costs:

AC = L x ADT x N x (Aa-An) x ca

L = Length of affected road wayADT = Average daily traffic (vehicles per day)N = number of days of maintenance activityAa = Accident rate during maintenance activityAn = Normal accident rateca = Cost per accident

Page 17: Life Cycle Cost Analysis for Bridges

Present Worth FactorPresent Worth Factor

1pwf =

(1 + i)n

1pwf =

(1 + i)n

pwf = Present Worth Factor for discount rate i and year n

i = Discount raten = Number of years when cost

(benefit) will occur

pwf = Present Worth Factor for discount rate i and year n

i = Discount raten = Number of years when cost

(benefit) will occur

Page 18: Life Cycle Cost Analysis for Bridges

Discount RateDiscount Rate

Interest - Inflationi =

1 + Inflation

Interest - Inflationi =

1 + Inflation

Interest – The return of an investment that raises the future value of an invested dollar

Inflation – The erosion of a dollar’s value that raises any future expenses

Use of a discount rate allows for the use of constant dollars in the analysis

Interest – The return of an investment that raises the future value of an invested dollar

Inflation – The erosion of a dollar’s value that raises any future expenses

Use of a discount rate allows for the use of constant dollars in the analysis

Page 19: Life Cycle Cost Analysis for Bridges

Process And Approach Limits

Process And Approach Limits

• Government does not invest money to gain cash benefits (interest)

• Government money is generally invested only in depreciating assets

• Anything not bought this year costs more next year (inflation)

• Government does not invest money to gain cash benefits (interest)

• Government money is generally invested only in depreciating assets

• Anything not bought this year costs more next year (inflation)

Page 20: Life Cycle Cost Analysis for Bridges

User Costs InputUser Costs InputUser Costs Inputs Alternative 1

Prestressed Concrete

Length of affected roadway * 2.00 2.00 miles

ADT * 5,000 5,000 vehicles per day

Normal traffic speed 45 45 mph

Construction traffic speed 20 20 mph

Normal accident rate 1.9 1.9 /million vehicle miles

Construction accident rate 2.2 2.2 /million vehicle miles

Number of construction days

Early Construction Completion 90 0 days

Maintenance 10 10 days/occurrence

Inspection 5 8 days/occurrence

Painting 0 90 days/occurrence

Rehabilitation 120 120 days/occurrence

Hourly time value of drivers 6.25 6.25 $/hour

Weighted average vehicle cost 8.00 8.00 $/hour

Cost per accident 100,000 100,000 $/occurrence

Note*: Total traffic affected by Maintenance, Inspection, Painting, and Rehabilitation activity over and under structure

Alternative 2Structural Steel

User Costs Inputs Alternative 1 Prestressed Concrete

Length of affected roadway * 2.00 2.00 miles

ADT * 5,000 5,000 vehicles per day

Normal traffic speed 45 45 mph

Construction traffic speed 20 20 mph

Normal accident rate 1.9 1.9 /million vehicle miles

Construction accident rate 2.2 2.2 /million vehicle miles

Number of construction days

Early Construction Completion 90 0 days

Maintenance 10 10 days/occurrence

Inspection 5 8 days/occurrence

Painting 0 90 days/occurrence

Rehabilitation 120 120 days/occurrence

Hourly time value of drivers 6.25 6.25 $/hour

Weighted average vehicle cost 8.00 8.00 $/hour

Cost per accident 100,000 100,000 $/occurrence

Note*: Total traffic affected by Maintenance, Inspection, Painting, and Rehabilitation activity over and under structure

Alternative 2Structural Steel

Page 21: Life Cycle Cost Analysis for Bridges

Discount Rate InputsDiscount Rate Inputs

Present Worth Factors For All AlternativesDiscount Rate 0.00%Inflation Rate 2.00%

Present Worth Factors For All AlternativesDiscount Rate 0.00%Inflation Rate 2.00%

Page 22: Life Cycle Cost Analysis for Bridges

Structure Costs InputStructure Costs InputInitial Cost of Structure 7,000,000

Analysis Period 100

Frequency (Years)

Cost Factor

Per Occurrence Cost

Maintenance Costs 1 0.05% 3,500Inspection Costs 2 0.15% 10,500Painting Costs 0 0.00% 0Rehabilitation Costs

• First Rehabilitation 40 20.00% 1,400,000Annual Traffic Growth Rate * 0.75%Salvage Costs/Value

• Demolition Costs 100 10.00% 700,000• Salvage Value 100 0.00% 0• Net Salvage Costs 700,000

Alternative 1 - Prestressed Concrete

Initial Cost of Structure 7,000,000

Analysis Period 100

Frequency (Years)

Cost Factor

Per Occurrence Cost

Maintenance Costs 1 0.05% 3,500Inspection Costs 2 0.15% 10,500Painting Costs 0 0.00% 0Rehabilitation Costs

• First Rehabilitation 40 20.00% 1,400,000Annual Traffic Growth Rate * 0.75%Salvage Costs/Value

• Demolition Costs 100 10.00% 700,000• Salvage Value 100 0.00% 0• Net Salvage Costs 700,000

Alternative 1 - Prestressed Concrete

Page 23: Life Cycle Cost Analysis for Bridges

Structure Costs InputStructure Costs InputInitial Cost of Structure 7,000,000

Analysis Period 100

Frequency (Years)

Cost Factor

Per Occurrence Cost

Maintenance Costs 1 0.05% 3,500Inspection Costs 2 0.20% 14,000Painting Costs 20 7.00% 490,000Rehabilitation Costs

• First Rehabilitation 35 22.00% 1,540,000Annual Traffic Growth Rate * 0.75%Salvage Costs/Value

• Demolition Costs 100 10.00% 700,000• Salvage Value 100 2.00% 140,000• Net Salvage Costs 560,000

Alternative 2 - Structural Steel

Initial Cost of Structure 7,000,000

Analysis Period 100

Frequency (Years)

Cost Factor

Per Occurrence Cost

Maintenance Costs 1 0.05% 3,500Inspection Costs 2 0.20% 14,000Painting Costs 20 7.00% 490,000Rehabilitation Costs

• First Rehabilitation 35 22.00% 1,540,000Annual Traffic Growth Rate * 0.75%Salvage Costs/Value

• Demolition Costs 100 10.00% 700,000• Salvage Value 100 2.00% 140,000• Net Salvage Costs 560,000

Alternative 2 - Structural Steel

Page 24: Life Cycle Cost Analysis for Bridges

Life Cycle Costs ResultsLife Cycle Costs Results

Costs User Costs Total

Construction 7,000,000 (383,250) 6,616,750

Maintenance 346,500 4,215,750 4,562,250

Inspection 514,500 1,043,292 1,557,792

Painting 0 0 0

Rehabilitation 4,200,000 1,533,000 5,733,000

Salvage 700,000 700,000

Total Constant Dollars 12,761,000 6,408,792 19,169,792

Present Worth 30,235,675 21,746,666 51,982,341

Alternative 1 - Prestressed ConcreteCosts User Costs Total

Construction 7,000,000 (383,250) 6,616,750

Maintenance 346,500 4,215,750 4,562,250

Inspection 514,500 1,043,292 1,557,792

Painting 0 0 0

Rehabilitation 4,200,000 1,533,000 5,733,000

Salvage 700,000 700,000

Total Constant Dollars 12,761,000 6,408,792 19,169,792

Present Worth 30,235,675 21,746,666 51,982,341

Alternative 1 - Prestressed Concrete

Page 25: Life Cycle Cost Analysis for Bridges

Life Cycle Costs ResultsLife Cycle Costs Results

Costs User Costs Total

Construction 7,000,000 0 7,000,000

Maintenance 346,500 4,215,750 4,562,250

Inspection 686,000 1,669,267 2,355,267

Painting 1,960,000 1,533,000 3,493,000

Rehabilitation 6,160,000 2,044,000 8,204,000

Salvage 560,000 560,000

Total Constant Dollars 16,712,500 9,462,017 26,174,517

Present Worth 48,910,066 31,365,348 80,275,414

Alternative 2 - Structural SteelCosts User Costs Total

Construction 7,000,000 0 7,000,000

Maintenance 346,500 4,215,750 4,562,250

Inspection 686,000 1,669,267 2,355,267

Painting 1,960,000 1,533,000 3,493,000

Rehabilitation 6,160,000 2,044,000 8,204,000

Salvage 560,000 560,000

Total Constant Dollars 16,712,500 9,462,017 26,174,517

Present Worth 48,910,066 31,365,348 80,275,414

Alternative 2 - Structural Steel

Page 26: Life Cycle Cost Analysis for Bridges

Life Cycle Costs Comparisons

Life Cycle Costs Comparisons

Prestressed Concrete Savings

Costs User Costs Total

Constant Dollars 31% 48% 37%

Present Worth 62% 44% 54%

Prestressed Concrete Savings

Costs User Costs Total

Constant Dollars 31% 48% 37%

Present Worth 62% 44% 54%