Loc Process

Embed Size (px)

Citation preview

  • 8/10/2019 Loc Process

    1/76

    LOSS OF CONTAINMENT - PROCESS

    Source of Hazard Initiators Risk Evaluation Risk Management

    Measures

    Performance

    Standards

    HS1 - Pressure

    Vessels (inc

    Columns)

    G1 - Corrosion:

    Internal / External

    Frequency F14 - Inherent

    Safety

    - fully rated

    vessels,

    Vessels,

    pipework,

    tubing, tanks,

    risers

    1. Scope

    This section provides guidance for the assessment of safety case content with respect to the loss of

    containment from process plant and process operations, from hazard identification through to

    elements of consequence determination, including risk management measures. However it

    excludes assessment of the consequences of ignition of any release. This is considered separately

    in Section 2.3.3.

    2. Assessment of Adequacy of Demonstration

    The evaluation of risk that might stem from each major accident hazard is to be assessed by

    identification of the factors that might result in an adverse combination of a source of hazard and

    initiator, together with identification and evaluation of escalation paths that might result. Potential

    sources of hazard, initiators etc, are shown in Section 4 below. Assessors should ensure that,

    where relevant, safety cases contain appropriate consideration of each of these factors.

    3. Depth of Assessment

    This section gives guidance on the depth of assessment required to determine the adequacy of the

    demonstration that measures have been or will be taken to ensure compliance with the relevant

    statutory provisions.

    Where safety case contents match with good practice identified in the assessment sheets for a

    particular element associated with a major accident, there will usually be no need for an assessor to

    probe into the details of how the good practice is applied. This may, however, be a suitable issue

    for follow-up by inspection.

    4. The assessor should examine the adequacy of the hazard identification, risk evaluation and

    management in conjunction with the contents of the Categorisation Table below:

    Loss of Containment - Process

  • 8/10/2019 Loc Process

    2/76

    pipework,

    pipelines, risers,

    etc

    -large segregation

    distances

    - separate

    accommodation

    jacket

    - inventory

    minimisation

    - Temperature &

    pressure rating

    - Material

    specification

    - Corrosion

    allowance

    - Fatigue life

    - Frequency of

    inspection

    - Relief

    arrangements

    and capacity

    - Reliability of

    protective

    systems

    - Adequacy of

    supports

    - Fire protection

    HS2 - Heat

    Exchangers

    G2 - Erosion F1 - Generic

    historical data

    F15 - Relief

    systems Heat

    Exchangers

    - Thermal rating

    - Temperature

    and pressurerating

    - Shell and tube-

    side flowrates

    - Material

    specification

    - Fatigue life

  • 8/10/2019 Loc Process

    3/76

    - Frequency of

    inspection

    - Relief

    arrangements

    and capacity

    HS3 -

    AtmosphericVessels [eg

    Wemcos, tilted

    plate separators,

    deck tanks]

    G3 -

    Overpressure

    F2 - Company &

    installation data

    F16 - HIPS

    systems Atmosphericvessels

    - Temperature &

    pressure rating

    - Material

    specification

    - Corrosionallowance

    - Relief

    arrangements

    and capacity

    HS4 -

    Centrifuges /

    Hydrocyclones

    G4 - Internal

    explosion

    F3 - Installation

    specific hazard

    studies

    - HAZOPs

    - FMEAs

    - Design reviews

    F18 - Shutdown

    systems

    Centrifuges/

    hydrocyclones

    - Temperature &

    pressure rating

    - Material

    specification

    - Corrosion

    allowance

    - Separation

    efficiency

    - Vibration

    (centrifuges)

    HS5 Piping and

    piping

    components

    G5 - Under

    pressurisation

    F4 - Layout F19 - Alarms /

    Trips Piping

  • 8/10/2019 Loc Process

    4/76

    - Temperature &

    pressure rating

    - Material

    specification

    - Corrosion

    allowance

    HS6 - Smallbore

    tubing

    G6 - Fatigue /

    vibration cracking

    F5 - Company

    standards /

    procedures

    F20 - Good

    procedures

    - operational

    - maintenance

    Tubing

    - Temperature &

    pressure rating

    - Material

    specification

    HS7 - Pipeline

    Risers (see

    section 2.3.2)

    G7 - Fire F6 - Corrosion /

    erosion policy

    F21 - Competent

    personnel

    HS8 - Flexible

    hoses

    G8 - Seal failure F7 - Operational

    reviews

    [procedures]

    F22 - Monitoring

    & audit systems Flexible hoses

    - Temperature &

    pressure rating

    - Material

    specification

    - Corrosion

    allowance

    - Fatigue life

    - Frequency of

    inspection

    - Integrity of

    connections

    HS9 - Pumps G9 - Turret

    failure

    F8 - SIL

    standards

    F23 - Isolations

    compressors,

    turbines

  • 8/10/2019 Loc Process

    5/76

    HS10 -

    Compressors

    G10 - Inadequate

    installation

    F9 - Equipment

    selection [eg weld

    or flange]

    - Flowrate

    - Head/pressure

    - Shut-in pressure

    - NPSH

    - Turndown

    Minimum flow

    - Sealing system

    HS11 - Turbines G11 - Operator

    error: inadequate

    Training

    F10 - Concept

    selection

    F24 - Gas

    detection (see

    section 2.3.3)

    HS12 - Valves G12 - Operator

    error: inadequate

    competency

    Consequences: F25 - Fire

    detection (see

    section 2.3.3)

    Valves

    - Temperature &

    pressure rating

    - Material

    specification

    - Corrosion

    allowance

    - Closure mode

    - Fire protection

    - Integrty of seals

    - Leakage rate

    H13 Gas

    treatment plant

    G13 - Violation

    F11 - Size of

    release

    - speed &

    effectiveness of

    detection

    response

    - blowdown

    system

    Gas treatment

    plant

    - Temperature &

    pressure rating

    - Material

    specification

    - Corrosion

    allowance

    - Performance

    specification

  • 8/10/2019 Loc Process

    6/76

    HS14 - Marine

    storage tanks

    G14 - Deficient

    procedures:

    operational

    F12 Dispension

    - open / closed

    modules /

    ventilation rates

    Marine tanks

    - Pressure rating

    - Fatigue life

    - Frequency of

    inspection

    - Relief

    arrangements

    and capacity

    - Reliability of

    protective

    systems

    HS15 -

    Hazardous

    drains / caissons

    G15 - Deficient

    procedures:

    maintenance

    F13 - Toxicity of

    release

    HS16 - Integral

    storage cells

    G16 - Ship

    collision

    HS17 Flare and

    vent towers

    G17 - Dropped

    object

    Flare and vent

    systems

    - Temperature &

    pressure rating

    - Material

    specification

    - Corrosion

    allowance

    - Separation

    efficiency

    - Gas dispersion

    - Thermal

    radiation

    - Noise level

  • 8/10/2019 Loc Process

    7/76

    HS1 Pressure Vessels (including Columns)

    HS5 Piping and Piping Components

    - Turndown

    HS18 - Turrets G18 - Seismic

    event

    HS19 -

    Temporary

    Equipment

    G19 - Missile [eg

    turbine blade]

    G20 - Ageing /mechanical

    degradation

    G21 - External

    loads [eg stood

    on, struck by

    scaffold pole]

    G22 - Helicopter

    collision / rollover

    G23 - Inadequate

    design

    G24 - Incorrect

    material

    specification

    G25 - Incorrect

    material usage

    G26 - Thermal

    radiation

    G27 - Slugging /

    water hammer

    G28 - Sloshing /

    slam liquid loads

    G29 - Structural

    failure

  • 8/10/2019 Loc Process

    8/76

    HS12 Valves

    [Relevant Sheets: G17, G18, G20, G21, G29, G3, G5, G6, G8, G10, G27, F15, F18]

    1. This sheet is generally applicable to the mechanical integrity of static components that form the

    boundary of a hydrocarbon containment system; ie pressure vessels and piping etc. It is also of

    relevance to rotating equipment, in so far as these also have pressure boundaries. Aspects specific

    to machinery and rotating equipment are dealt with elsewhere. Similarly, process control and plant

    isolation requirements are not dealt with here.

    This sheet is not intended to limit the scope of an assessor to pursue any aspect of safety that they

    believe is important to a particular safety case, within the remit provided by the safety case

    regulations. It is though intended to provide guidance as to the minimum acceptable demonstration

    of safety that a duty holder should be able to provide. As with all safety assessment work, there is a

    need for HSE assessors to concentrate on areas where there are grounds for believing the safety

    demonstration may be weakest. Knowledge of such areas comes from HSEs collective experience,

    as well as that of the wider engineering community. This document is intended to provide pointerstowards what are believed to be the most pressing concerns. Conversely, it is not considered

    necessary or practical for a particular safety case to mention explicitly all of the aspects of design

    and operational concerns identified below. However the duty holder should in principle be able to

    address all such concerns and hence provide an adequate demonstration of integrity. Therefore, it

    is reasonable for an assessor to question a duty holder on any aspect of the integrity justification.

    Confirmation should be obtained that the pressure system elements have been designed,

    constructed, installed, and operated in accordance with a recognised standard or code of practice.

    As a general principle, HSE accepts that codes, standards published by BSI, ASME, API and

    others, are for the most part well founded, in that they have been written to encompass the present

    best knowledge and advice available. However adherence to a code is not in itself a demonstration

    of safety. There are several reasons for this. Not only are some codes inherently goal oriented

    themselves, but there are also some matters which are the subject of technical uncertainty, or

    indeed where current code provisions appear to be inadequate or may not reflect the state of the

    art. The safety case assessment process may therefore include questioning as to the detailed

    application or adequacy of parts of codes. A typical, but non-exhaustive, list of standards and codes

    of practice would include:

    PD5500: 2009+A3:2011 Specification for unfired fusion welded pressure vessels

    ASME VIII Boiler and pressure vessel code

    BPVC Section VIII-Rules for Construction of Pressure Vessels Division 1 (BPVC-VIII-1 -

    2010)

  • 8/10/2019 Loc Process

    9/76

    BPVC Section VIII-Rules for Construction of Pressure Vessels Division 2-Alternative Rules

    (BPVC-VIII-2 - 2010)

    BPVC Section VIII-Rules for Construction of Pressure Vessels Division 3-Alternative Rules

    for Construction of High Pressure Vessels (BPVC-VIII-3 - 2010)

    BS EN 13445 Unfired pressure vessels

    BS EN 13445-1:2009 Unfired pressure vessels. General

    BS EN 13445-2:2009 Unfired pressure vessels. Materials

    BS EN 13445-3:2009 Unfired pressure vessels. Design

    BS EN 13445-4:2009 Unfired pressure vessels. Fabrication

    BS EN 13445-5:2009+A3:2011 Unfired pressure vessels. Inspection and testing

    BS EN 13445-6:2009 Unfired pressure vessels. Requirements for the design and fabrication

    of pressure vessels and pressure parts constructed from spheroidal graphite cast iron

    BS EN 13445-8:2009 Unfired pressure vessels. Additional requirements for pressure vesselsof aluminium and aluminium alloys

    Part 7 isn't published as a "British Standard" but as a "Published Document"

    PD CR 13445-7:2002 Unfired pressure vessels. Guidance on the use of the conformity

    procedures

    PD CEN TR 13445-9:2011 Unfired Pressure Vessels Conformance of the EN 13445 series

    to ISO 16528

    ASME B31.3 2010 Process piping

    ISO13703 2000 [API 14E] Petroleum and natural gas industries. Design and installation of

    piping systems on offshore production platforms. BS equivalent is BS EN ISO 13703:2000

    ISO 15649 2001 Petroleum and natural gas industries. Piping. BS equivalent is BS ISO

    15649:2001

    PD CEN/TR 14549 2004 Guide to the use of ISO 15649 and ANSI/ASME B31.3 2010 for

    piping in Europe in compliance with the Pressure Equipment Directive

    ISO 14692 Parts 1 to 4 Petroleum and natural gas industries. Glass-reinforced plastics

    (GRP) piping. Current versions are from 2002, BS equivalent;

    BS EN ISO 14692-1:2002

    BS EN ISO 14692-2:2002

    BS EN ISO 14692-3:2002

    BS EN ISO 14692-4:2002

  • 8/10/2019 Loc Process

    10/76

    BS 4994 1987 Specification for design and construction of vessels and tanks in reinforced

    plastics. Replaced by BS EN 13923:2005 and BS EN 13121-3:2008+A1:2010

    Codes to assist in-service integrity:

    A typical but non-exhaustive list of relevant standards would include:

    ASME Boiler and Pressure Vessel Code Series Please see BPVC-VIII-1 2010, BPVC-VIII-

    2 - 2010and BPVC-VIII-3 - 2010

    Inspection:

    API 510 Pressure vessel inspection code: Maintenance inspection: In-service inspection,

    rating, repair, and alteration current version is 9th edition 2006

    API 570 Piping Inspection Code: In-service Inspection rating, repair and alteration of piping

    systems current version is 3rd edition 2009

    API RP 574 Inspection practices for piping system components current version is 3rd edition

    2009

    EEMUA Standards

    API RP 580 Risk based inspection. Current version is 2nd edition 2009

    API 581 Risk based inspection technology. Current version is 2nd edition 2008

    Flaw assessment:

    BS 7910 2005 Guide to methods for assessing the acceptability of flaws in metallic

    structures Fitness for purpose:

    Fitness for service

    API 579-1 Fitness for Service current version is 2nd edition, 2007

    DNV RP F101 Corroded pipelines. Current version 2010

    The emerging ASME Post Construction codes are likely to provide useful benchmarks for

    inspection planning, flaw evaluation, repair, and testing.

    2. Where a standard or code of practice other than those listed above has been employed,

    udgement as to the adequacy of alternative measures can only be assessed on an individual basis,and the duty holder should be required to provide an engineering justification of how an equivalent

    level of health and safety performance is delivered.

    The avoidance of loss of containment relies primarily on the integrity of the containment in which

    the hydrocarbons are held. The issue of mechanical integrity can itself be subdivided into issues of

    initial integrity and continuing integrity.

    2.1 Initial integrity

  • 8/10/2019 Loc Process

    11/76

    Adequate initial integrity is delivered by adherence to suitable design principles, often embodied in

    codes and standards. Full consideration should be taken of design details, operating and fault

    conditions, material properties and potential failure modes. Related issues include the provision of

    protective systems. Delivery of the design intent is provided by suitable quality controls on

    manufacture followed by appropriate inspection and testing.

    Adequate initial integrity is ensured by adherence to the following engineering principles.

    Risks implicit in the design should be identified. [APOSC 91]

    Engineering design should seek to minimise risk and adopt a hierarchical approach [APOSC

    92 & 98]

    Appropriate industry standards should be used.

    Engineering structures important to safety should maintain their integrity through life,

    requiring a demonstration that normal operating loads and foreseeable extreme loads have

    been quantified.

    The materials used should be suitable. [APOSC 95]

    Active safety features should have demonstrably adequate reliability, availability and

    survivability

    2.2 In-service Integrity

    Following a consideration of the initial integrity, attention must be turned to the continuing integrity

    of the containment, throughout its service life. This is ensured by; operating the plant within the

    limits for which it was designed; by carrying out appropriate maintenance and through periodicexamination by a competent person, to identify significant inservice degradation. Also, procedures

    must be in place to ensure that modifications to the plant will not compromise the integrity of the

    containment. Finally, the duty holder needs to be sure that the assumptions made at the design

    stage are still valid. For example, a change of usage may lead to faster corrosion/erosion rates and

    different applied loads may invalidate the design fatigue assessment. The effects of ageing need to

    be considered to ensure that the inspection regime addresses all of the deterioration modes taking

    place.

    3. Relevant Legislation, ACOP and Guidance includes:

    Offshore Installations (Safety Case) Regulations 2005, Regulations 12(1)(c) & 12(1)(d) &

    Schedules

    Offshore Installations (Prevention of Fire and Explosion, and Emergency Response)

    Regulations 1995, Regulations 9 and 19

    Provision and Use of Work Equipment Regulations 1998, Regulations 4, 5 and 6

    Lifting Operations and Lifting Equipment Regulations 1998, Regulations 8 and 9

  • 8/10/2019 Loc Process

    12/76

    Pressure Equipment Regulations 1999, Regulations 7 and 10

    Assessment Principles for Offshore Safety Cases [APOSC] 14, 16, 35, 41, 91, 92, 95, & 98

    4. Specific technical issues:

    Relevant initiators and potential failure mechanisms are identified below:

    4.1 Primary & Secondary Loads

    Primary loads typically include design pressure and self-weight etc. Secondary loads typically

    include thermal loads and equipment displacements etc. Adherence to the relevant design codes

    and standards should ensure that the pressure systems are adequately designed for primary and

    secondary loads.

    4.1.1 Overpressure [Initiator G3]

    Pressure system should be designed for maximum and, where relevant, the minimum anticipated

    operating pressure under all modes of operation. It needs to be borne in mind that the maximumoperating pressure may not occur during the normal mode of operation. Designing equipment and

    systems to the maximum pressure to which it can be subjected can have advantages in simplifying

    plant by reducing or eliminating protection or relief systems. Based on established design

    pressures, the facilities should be protected with recognised relief devices discharging to suitable

    disposal or an instrumented high integrity protection system or a combination of both. The latter

    subject is covered in F16. Possible sources of overpressure need to be identified and allowed for.

    Issues for Safety Case Assessment

    It should be established whether provision against over pressurisation is provided by active

    measures, such as pressure relief and control systems, or is dependent upon the strength of the

    component itself. Later in life, plant changes may necessitate reassessment.

    When overpressurisation is a foreseeable event, the consequences should be considered. The

    nature of the failure should be determinable, ie whether a leak or a catastrophic failure could result.

    Further assessment of consequence could include assessment of the hazards posed by any

    release.

    4.1.2 Risers and Topsides Pressure Rating [Initiator F15]

    It is normal practice in offshore industry to use different design codes for the design of topside

    piping and risers. Risers are normally designed to pipeline design codes, such as BS 8010 and

    topside piping is normally designed to piping code ASME B31.3 2010. Both the codes use different

    factor of safety in the design of pressure systems for primary and secondary loads. Hence it is

    important that at the specification break between riser and topside piping the pressure rating on

    both sides, ie riser and topside, is compatible.

  • 8/10/2019 Loc Process

    13/76

    Issues for Safety Case Assessment

    It should be established that specification break made between topside piping and a riser is made

    at appropriate location so that the design requirements of respective design codes are satisfied.

    4.1.3 Under-Pressurisation [Initiator G5]

    Underpressure events also have the potential to cause failures i.e. by implosion if the under-

    pressure that results is below atmospheric pressure [vacuum conditions]. Normally, integrity isassured by adherence to a recognised design code.

    4.1.4 External Loads and Structural Support Failure [Initiators G21 & G29]

    Lack of consideration of pipe supports and movement of piping and connected equipment at the

    design phase can result in failure of supports, leakage at flanged joints and overloading of sensitive

    equipment such as pumps and compressors etc.

    External loads could come from a disturbance of the structure itself, ie a partial failure or relativedisplacements. External movements may result from vessel movements [FPSO] or wind sway, eg

    piping supported from a tall slender tower or temperature changes in connected equipment. Loads

    due to such movements need to be considered and adequate flexibility should be provided within

    the pipework.

    For floating vessels, the motion may well contribute significantly to the fatigue load

    Issues for Safety Case Assessment

    Confirmation that external loads acting on the pressure system have been considered and allowed

    for in the mechanical design.

    4.1.5 Inadequate Installation [Initiator G10]

    Inadequate installation of plant is a significant source of engineering failure. Deficiencies include

    misalignment of mating parts, incorrect welding and jointing procedures, inadequate inspection, and

    the omission of certain parts of the overall commissioning process, such as pressure testing.

    Commissioning procedures should be in place to ensure that installed pressure equipment is

    inspected before use to identify any design faults that may have been introduced at the construction

    stage and to confirm suitability for use.

    Issues for Safety Case Assessment

    Does the duty holder have an effective safety management system for installation and modification

    of plant.

    4.1.6 Seismic Event [Initiator G18]

  • 8/10/2019 Loc Process

    14/76

    If seismic events are deemed a possibility, then in principle the effects can be included as a design

    load case. In such a situation, the response of the structure will have been calculated and the

    resultant motion would have to be imposed on the hydrocarbon containment system.

    Issues for Safety Case Assessment

    Whether seismic assessment has been carried out at the design stage.

    4.2 Occasional Loads

    These include slugging, water hammer, wind, sloshing and liquid slam, etc [G27 & G28].

    During design, the operation of each piping system needs to be clearly understood not only under

    normal conditions but also those conditions arising during start up, shutdown and as a result of

    process upsets.

    The dynamic loads produced by the movement of fluids within a pressurised system can be

    considerable. Excitation from valve slams or from flow instabilities has been known to be a sourceof severe vibration.

    Issues for Safety Case Assessment

    The safety case should make it clear that occasional loads have been considered during the design

    phase.

    4.3 Degradation in Service

    4.3.1 Corrosion

    Please refer to generic sheets G1 Parts 1 & 2 & F6.

    Piping containing hydrocarbons should avoid 'dead legs' and be designed to facilitate drainage to

    prevent trapping of fluid.

    4.3.2 Erosion

    Please refer to generic sheets G2 & F6.

    4.3.3 Fatigue/Vibration Cracking G6]

    Fatigue is a damage mechanism by which cracks can propagate in a structure under the influence

    of repeated cycles of stress well below the level capable of causing general yielding. Fatigue is

    often characterised as occurring in two phases, the first is that of initiation, i.e. from manufacture up

    to the point where a detectable crack is present. The second is the phase of defect growth, where

    propagation from the point of detectability to the point of failure occurs.

  • 8/10/2019 Loc Process

    15/76

    Fatigue is addressed initially at the design stage. There are a number of methodologies by which

    this can be done. However we note that for plant with a limited fatigue load, the codes normally

    provide for the exclusion of a full analysis, providing that certain preconditions can be met, i.e. it is

    established that there will only be a limited number of full pressure cycles etc.

    In general though, the fatigue loads from all sources of repetitive stress have to be characterised

    both in terms of the stress amplitude and their number. This can be used to determine a fatigue

    lifetime for the component.

    Issues for Safety Case Assessment

    The importance of fatigue as a potential failure mechanism varies greatly according to the type of

    duty a pressure vessel or piping system is subjected to. However, in an environment where

    installations are increasingly being used beyond its original design lifetime, there are important

    issues as to whether the plant is still within its original fatigue life. For older plant, the duty holder

    could be questioned as to the current validity of the original fatigue calculations.

    Experience has shown that fluid induced vibration is a significant cause of failure in offshore

    pressure systems, affecting both vessels and piping. Such type of vibration is perhaps somewhat

    difficult to treat within design codes. Further guidance on this topic is provided in:

    Guidelines for the avoidance of vibration induced fatigue failure in process pipework published by

    the Energy Institute

    It is a reasonable question to ask how the duty holder assures the integrity of plant against this

    source of fatigue.

    4.3.4 Seal/Gasket/Compression Fitting Failure G8]

    A suitable demonstration should be provided for the integrity of joints and seals where failure could

    lead to a release of hydrocarbons. General information should be provided to indicate that flanges

    and other joints have been adequately designed and properly made to avoid flammable and toxic

    hazards. Further guidance is available in Guidelines for the management of the integrity of bolted

    oints for pressurised systems published by the Energy Institute.

    4.3.5 Fully Welded Topside Pipework in Critical Areas [F18 & F9]

    The use of fully welded pipework topside is one of the approaches to adhere to the principle of

    inherently safer design. However, for ease of access for operation, inspection, maintenance and

    repairs, it is not possible to have fully welded pipework everywhere on topside plant. The duty

    holder should avoid routing of pipework containing hazardous fluid through non hazardous area. If

    this is unavoidable then pipework shall be all welded [no flanges] and not located in a vulnerable

    position where it may be mechanically damaged.

  • 8/10/2019 Loc Process

    16/76

    Issues for Safety Case Assessment

    It should be established in the safety case that as far as possible hydrocarbon pipework in non-

    hazardous areas is fully welded.

    4.4 Materials

    Materials chosen should be suitable for the application in terms of the process fluid, environment

    and applied loading.

    4.4.1 Incorrect Material Specification

    Please refer to G24 regarding issues relating to incorrect material specification. Issues relating to

    incorrect material usage [G25] are addressed by ensuring that pressurised equipment is designed

    and manufactured in accordance with a recognised design standard as indicated in Section

    1above.

    4.4.2 Brittle Fracture

    The prevention of brittle fracture is addressed within design codes. Prevention involves the correct

    choice of materials, operation within strict temperature/pressure limits and monitoring ageing

    phenomena such as embrittlement. Ferritic steels are subject to a ductile to brittle transition as

    temperature decreases, rendering them highly vulnerable to brittle fracture when cold. Transition

    temperatures vary, but are typically below ambient values for offshore applications. Ageing though

    can lead to a shift in the transition temperature and render components more susceptible to brittle

    fracture. Austenitic steels remain ductile at low temperatures and may be preferred for application

    such as blowdown lines.

    Brittle fracture is possible whenever low temperatures are involved, in particular low temperatures

    associated with gas expansion. This is particularly the case when systems are still pressurised,

    although in some circumstances, the differential stresses through the wall of a vessel by sudden

    cooling could lead to crack propagation.

    Issues for Safety Case Assessment

    Choice of materials.

    Identification of vulnerable components.

    4.4.3 Ageing/Mechanical Degradation [G20]

    The effect of ageing is undoubtedly one of the major integrity issues facing the older installations.

    Ageing encompasses degradation mechanisms such as fatigue and corrosion. There are also some

    other phenomena, for example creep and the deterioration in mechanical properties such as

    fracture toughness. The latter phenomenon is associated with changes in transition temperatures.

  • 8/10/2019 Loc Process

    17/76

    Provision against these mechanisms is explicitly required, as part of the design criteria and

    operational monitoring exists for the express purpose of detecting these phenomena.

    Nevertheless, ageing related failures are occurring. The implication of this is that either plant is

    being operated beyond its original design life, that conditions have changed because modification

    has rendered the initial assumptions invalid or that inspection regimes are inadequate.

    In recent years, the popularity of risk-based inspection schemes has led to situations where

    inspection intervals have been lengthened for some plant. Where such decisions have been made,

    the requirements on the knowledge about plant state are high.

    Issues for Safety Case Assessment

    As for fatigue, corrosion and other degradation phenomena above; including:

    Whether initial design assumptions are still valid.

    Whether modifications have had their implications on lifetime assessed.

    Whether the inspection regime is adequate.

    The adequacy of the duty holders piping repair policy to take account of HSE Safety Notice 4/2005

    Weldless repair of safety critical piping and ISO TS 24817 Composite repairs for pipework

    Qualification and design, installation, testing and inspection for composite repairs.

    4.5 Dropped Loads G17]

    Major hazards assessed are the impact of dropped loads onto hydrocarbon containment plant and

    or accommodation areas. Protection essentially relies upon having an effective safety management

    system.

    Typical benchmarks employed include:

    HSG221 Technical guidance on the safe use of lifting equipment offshore

    BS 7121-2 & 11 Code of practice for the safe use of cranes

    Step Change lifting and mechanical handling guidelines

    OGP 376 Lifting and hoisting safety recommended practice

    OPITO Training and competency assessment standards for crane operators, riggers, and

    banksmen / slingers

    OMHEC Practical guidance on communications for safe lifting and hoisting operations

    HSE Safety Notice 2/2005 Single line components in the hoisting and braking systems of

    offshore cranes

  • 8/10/2019 Loc Process

    18/76

    Issues for Safety Case Assessment

    Plans showing crane over sail area and identification of areas where pipelines, HC piping and

    vessels and accommodation units are vulnerable to dropped loads and or boom collapse.

    References to dropped object/load impact studies and their conclusions. Provision of protective

    barriers on vulnerable areas.

    Description of cranes and lifting machinery including safe working load, de-rating for prevailing sea

    state, and rated capacity indicator.

    Details of the arrangements for maintenance and thorough examination of cranes including details

    of structured engineering studies (e.g. FMECA) to give assurance that maintenance address ageing

    issues

    Details of how competence is assessed for crane operators, banskmen, slingers and for those

    responsible for planning lifting operations.

    Evidence that lifting operations are planned and assistance is available to identify and plan non-

    routine lifts.

    Personnel transfer using cranes and carriers

    Some designs of carriers used for personnel transfer between an installation and vessel can

    accommodate more than four persons. This introduces a new major accident hazard that must be

    addressed in the safety case.

    Typical benchmarks employed include:

    HSE Offshore Information Sheet 1/2007 Guidance on procedures for the transfer of

    personnel by carriers

    Emerging guidance on lifting of persons from OMHEC

    Issues for Safety Case Assessment

    An assessment of how this major accident risk is addressed describing the control measures

    in place to ensure the suitability of crane, suitability of the carrier, procedural controlsincluding recovery from the sea and competency.

    5. Other Related Assessment Sheets in this Section are:

    G1 Part 1 Corrosion: Internal

    G1 Part 2 Corrosion: External

    G2 Erosion

    G18 Seismic Event

    F16 High Integrity Protection Systems [HIPS]

  • 8/10/2019 Loc Process

    19/76

    HS2 Heat Exchangers

    6. Cross-Referenced Sections and Sheets are:

    Section 2.3.2 Loss of Containment - Pipelines

    1. Confirmation should be obtained that heat exchangers have been designed, constructed in

    accordance with recognised standards or codes of practice. Recognised standards/codes of

    practice would include:

    BS EN ISO 16812:2007 and API Standard 660 for shell & tube exchangers

    BS EN ISO 15547-1:2005 and API Standard 662 for plate type heat exchangers

    BS EN ISO 13706:2011 and API Std 661 for air cooled heat exchangers

    BS EN ISO 13705:2006 and API Std 560 for fired heaters

    TEMA Standards of the Tubular Exchanger Manufacturers Association are applicable for

    tubular heat exchangers.

    Pressure Vessel Design Codes applicable to heat exchangers:

    PD 5500:2009 + A3: 2011 Specification for unfired fusion welded pressure vessels

    BS EN 13445 Unfired pressure vessels

    ASME VIII Boiler and pressure vessel code

    Printed circuit heat exchangers [PCHEs] are normally designed to ASME VIII Division 1 but

    other design codes such as PD 5500 can be employed as required by the purchaser.

    API SPEC 12K Specification for Indirect Type Oil Field Heaters

    2. Where a standard/code of practice other than those listed above has been employed,

    udgement as to the adequacy of the heat exchange equipment can only be assessed on an

    individual basis and the duty holder should be required to justify that the applied standard/code will

    be equally effective.

    3. Relevant Legislation, ACOP and Guidance includes:

    Offshore Installations (Safety Case) Regulations 2005, Regulation 12(1)(c)

    Assessment Principles for Offshore Safety Cases [APOSC] paras 14 and 35

    Provision and Use of Work Equipment Regulations 1998 Regulation 4

    4. Technical Issues:

  • 8/10/2019 Loc Process

    20/76

    4.1 Shell and Tube Heat Exchangers

    Flow induced tube vibration which results in thinning of the tubes can occur where the tubes pass

    through the tube sheets. The possibility of this occurring should have been examined as part of the

    design.

    The provision of overpressure relief for tube failure should be considered when the design pressure

    for the low pressure side of the exchanger is low compared to the design pressure of the high

    pressure side. A specific 2/3 rule is no longer contained in API 521. 5 thedition - section 5.19 (Heat

    transfer equipment failure). The section now states Loss of containment of the low pressure side to

    atmosphere is unlikely to result from a tube rupture where the pressure in the low pressure side

    (including upstream and downstream systems) during the tube rupture does not exceed the

    corrected hydrotest pressure.

    [NB: Old 2/3 rule The provision of overpressure relief for tube failure should be considered when

    the design pressure for the low pressure side of the heat exchanger is less than 2/3 of the design

    pressure of the high pressure side. The 2/3 rule was written in the context of ASME pressure

    vessel codes for which the test pressure was typically 150% of the design pressure . The 2/3 rule

    was dependent on the hydrotest pressure being typically 150% of the design pressure, some

    vessels are now hydrotested to 130% of the design pressure when the rule would become the

    10/13 rule].

    Related guidance:

    API RP 521 Guide for Pressure Relieving and Depressuring Systems. 5 th

    ed, 2007 (includes2008 addendum). ISO 23251.

    Guidelines for the Design and Safe Operation of Shell and Tube Heat Exchangers to

    Withstand the Impact of Tube Failure, September 2000, ISBN 9780852932865

    4.2 Printed Circuit Heat Exchangers

    For PHCEs there is an issue with thermal cycling which has been known to have caused failure of

    the integrity of the heat exchange matrix. This phenomenon is most likely to occur when the unit is

    subjected to frequent start-ups and shutdowns. Confirmation should be sought that this has been

    taken into account as part of the design process.

    4.3 Gasketed Plate Heat Exchangers

    There is a likelihood of significant hydrocarbon release to the atmosphere on gasket failure. Shields

    should normally be fitted to prevent fluids from contacting personnel in the event of gasket failure.

    There is a working pressure limitation for gasketed plate heat exchanger of approx 25 barg.

    4.4 Brittle failure due to the formation of titanium hydrides

  • 8/10/2019 Loc Process

    21/76

    HS3 Atmospheric Vessels (eg Wemcos, Tilted Plate Separators, Deck Tanks)

    A particular design of shell and tube cooler with the tubesheet manufactured from titanium sheet

    explosively bonded to steel suffered catastrophic failure due to the formation of titanium hydrides

    when the interface was exposed to wet gas. HSE Safety Alert SA 1/2005 Catastrophic failure of

    shell and tube production cooler.

    4.5 Design Requirements for Heat Exchangers

    The following would be expected in heat exchanger design:

    a. protection against high internal pressure, e.g. tube failure,

    b. appropriate design, selection and location of PSVs and bursting discs,

    c. detection system for hydrocarbon leaks into heating or cooling medium,

    d. safe discharge/disposal of leaking material,

    5. Other Related Assessment Sheets in this Section are:

    2.3.1.HS1 Pressure Vessels (Including Columns)

    6. Cross-Referenced Sections and Sheets are:

    None

    1. Confirmation should be obtained that atmospheric vessels and their accessories have been

    designed and constructed in accordance with recognised standards or codes of practice.

    Recognised standards/codes of practice would include:

    API Standard 2000 Venting Atmospheric and Low Pressure Storage Tanks; Non

    Refrigerated and Refrigerated, 6th Edition, November 2009 (ISO 28300:2008 identical)

    API Publication 2210 Flame Arresters for Vents of Tanks Storing Petroleum Products

    BS EN ISO 16852:2010 Flame arrestors Performance requirements, test methods and

    limits for use

    API Bulletin 2521 Use of Pressure-Vacuum Vent Valves for Atmospheric Pressure Tanks to

    Reduce Evaporation Loss

    API Standard 620 Design and Construction of Large, Welded, Low Pressure Storage Tanks

    API Standard 650 Welded Steel Tanks for Oil Storage

  • 8/10/2019 Loc Process

    22/76

    API SPEC 12D Specification for Field Welded Tanks for Storage Production Liquids

    API SPEC 12F Specification for Shop Welded Tanks for Storage of Production Liquids

    API SPEC 12B Specification for Bolted Tanks for Storage of Production Liquids

    API SPEC 12P Specification for Fibreglass Reinforced Plastic Tanks

    BS 1564:1975 Specification for pressed steel sectional rectangular tanks

    BS EN 14015:2004 Specification for the design and manufacture of site built, vertical,

    cylindrical, flat-bottomed, above ground, welded, steel tanks for the storage of liquids at

    ambient temperature and above (replaces BS 2654:1989)

    Withdrawn BS 2654:1989 Specification for the manufacture of vertical steel welded non-

    refrigerated storage tanks with butt-welded shells for the petroleum industry

    3. Where a standard/code of practice other than those listed above has been employed,

    udgement as to the adequacy of the atmospheric vessel can only be assessed on an individual

    basis and the duty holder should be required to justify that the applied standard/code will be equally

    effective.

    4. Relevant Legislation, ACOP and Guidance includes:

    Offshore Installations (Safety Case) Regulations 2005, Regulation 12(1)(c)

    Assessment Principles for Offshore Safety Cases [APOSC] paras 14, 16 and 35

    Provision and Use of Work Equipment Regulations 1998, Regulation 4

    Offshore Information Sheet No 2/2010 - Reducing the risks of hazardous accumulations of

    flammable/toxic gases in tanks and voids adjacent to cargo tanks on FPSO and FSU

    installations

    Loss of Containment Manual Part 9.4 - Inert Gas Controls/Cargo Tank Blanketing

    5. Specific Technical Issues:

    4.1 Venting for Fire Exposure and In/Out Breathing

    It is likely that tanks installed on offshore installations will not be fitted with a frangible roof-to-shell

    attachment for fire venting purposes. Where this is the case, confirmation should be sought that

    venting capacity is adequate for fire exposure conditions.

    API 2000 6th edition now includes new, more accurate, equations for normal venting as opposed to

    fire exposure where the equations stay the same. The new normal venting equations deal with

    inbreathing and outbreathing caused by liquid movements and thermal effects. However the old

    normal venting methods are still valid and appear as an Annex of API 2000.

    4.2 Bunding

  • 8/10/2019 Loc Process

    23/76

    HS4 Centrifuges / Hydrocyclones

    It should be clear that any decision as to whether tanks should be bunded or not has been made in

    the light of a corresponding fire analysis.

    4.3 The emergency dumping/draining of the flammable content of large tanks should have been

    considered.

    4.4 Consideration should have been given to minimising storage tank sizes and inventories as

    part of a wider consideration of an inherently safer design features.

    4.5 Methanol Storage Tanks

    Provision should be made to limit the discharge of methanol vapour to atmosphere. For large

    storage tanks, the provision of an inert gas blanket should have been considered.

    4.6 Design Requirements for Atmospheric Vessels

    The following would be expected in atmospheric vessel design:

    a. appropriate venting arrangements, e.g. two independent adequately sized vents,

    b. appropriate and adequate bunding.

    6. Other Related Assessment Sheets in this Section are:

    2.3.1.F14 Inherent Safety

    7. Cross-Referenced Sections and Sheets are:

    None

    1. Confirmation should be obtained that centrifuges and hydrocyclones have been designed, and

    constructed, in accordance with recognised standards or codes of practice. Recognised

    standards/codes of practice would include:

    PD 5500:2003 Specification for unfired fusion welded pressure vessels

    BS EN 13445 Unfired pressure vessels

    ASME VIII Boiler and pressure vessel code

    2. Where a standard/code of practice other than those listed above has been employed,

    udgement as to the adequacy of the centrifuge or hydrocyclone can only be assessed on an

  • 8/10/2019 Loc Process

    24/76

    HS6 Smallbore Tubing

    individual basis and the duty holder should be required to justify that the applied standard/code will

    be equally effective.

    3. Relevant Legislation, ACOP and Guidance includes:

    Offshore Installations (Safety Case) Regulations 2005, Regulation 12(1)(c)

    Assessment Principles for Offshore Safety Cases [APOSC] paras 14 and 35

    Provision and Use of Work Equipment Regulations 1998, Regulation 4

    4. Technical Issues:

    None

    5. Other Related Assessment Sheets in this Section are:

    2.3.1.HS1 Pressure Vessels (Including Columns)

    6. Cross-Referenced Sections and Sheets are:

    None

    1. Confirmation should be obtained that the design, installation and maintenance of smallbore

    tubing is in accordance with recognised standards or codes of practice. Recognised

    standards/codes of practice would include:

    Guidelines for the management, design, installation and maintenance of small bore tubing

    assemblies: Energy Institute.

    2. Where a standard/code of practice other than that listed above has been employed, judgement

    as to the adequacy can only be made on an individual basis and the duty holder should be required

    to justify why equivalent standards of safety should result.

    3. Relevant Legislation, ACOP and Guidance includes:

    Offshore Installations (Safety Case) Regulations 2005, Regulation 12(1)(c)

    Assessment Principles for Offshore Safety Cases [APOSC] paras 14 and 35

    Provision and Use of Work Equipment Regulations 1998, Regulation 4

    Loss of Containment Manual Part 2 Small bore piping and tubing systems

    4. Specific Technical Issues:

    None over and above those described in the referenced standard.

  • 8/10/2019 Loc Process

    25/76

    HS8 Flexible Hoses

    HS9 Pumps

    HS10 Compressors

    5. Other Related Assessment Sheets in this Section are:

    None

    6. Cross-Referenced Sections and Sheets are:

    None

    1. Confirmation should be sought that the design, specification and usage of flexible hoses used on

    the installation is in accordance with a recognised standard or code of practice. Recognised

    standards/codes of practice include:

    Guidelines for the management of flexible hose assemblies: Energy Institute, Oil and Gas UK, HSE,

    2nd edition, February 2011

    2. Where a standard/code of practice other than that listed above has been employed, judgement

    as to the adequacy can only be made on an individual basis and the duty holder should be required

    to justify why equivalent standards of safety should result.

    3. Relevant Legislation, ACOP and Guidance includes:

    Offshore Installations (Safety Case) Regulations 2005, Regulation 12(1)(c)

    Assessment Principles for Offshore Safety Cases [APOSC] paras 14 and 35

    Loss of Containment Manual Part 2 Small bore piping and tubing systems

    4. Specific Technical Issues:

    None over and above those described in the referenced standard.

    5. Other Related Assessment Sheets in this Section are:

    None

    6. Cross-referenced Sections and Sheets are:

    None

  • 8/10/2019 Loc Process

    26/76

    HS11 Turbines

    [Relevant Sheets:G7, G19]

    1. Introduction

    This sheet is to provide guidance for safety case assessment for areas dealt with by the Mechanical

    Systems Team OSD3.4. What follows is therefore generally applicable to the mechanical integrity

    of machinery and rotating equipment. Aspects specific to hydrocarbon containment are dealt with

    elsewhere. Similarly, process control and plant isolation requirements are not dealt with here.

    The document is not intended to limit the scope of an assessor to pursue any aspect of safety that

    they believe is important to a particular safety case, within the remit provided by the Safety Case

    Regulations. It is though intended to provide guidance as to the minimum acceptable demonstration

    of safety that a duty holder should be able to provide. As with all safety case assessment work,

    there is a need for HSE assessors to concentrate on areas where there are grounds for believing

    the safety demonstration may be weakest. Knowledge of such areas comes from HSEs collective

    experience, as well as that of the wider engineering community. There is some guidance below that

    provides pointers towards what are believed to be the most pressing concerns. Conversely, it is not

    considered necessary or practical for a particular safety case to mention explicitly all of the aspects

    of design and operational concerns identified below. However, the duty holder should in principle be

    able to address all such concerns and hence provide an adequate demonstration of integrity.

    Therefore, in the last resort, it is reasonable for an assessor to question a duty holder on any

    aspect of the integrity justification.

    2. Machinery and Rotating Equipment Integrity

    Machinery and rotating equipment is often packaged together to form a single system. The

    packages employ a combination of rotating equipment such as pumps, compressors and

    generators, driven by a gas turbine or electric motor. Typical applications include:

    Process and export gas compression

    Oil export pumping

    Fire water pumping

    Utilities [electricity generation/compressed air]

    Our main source of reference is HSEs Inspection Guidance Notes [IGN]: HSE Research report

    076 Machinery and Rotating Equipment Integrity Inspection Guidance Notes.

    The IGN provides technical guidance that focuses on commonly used equipment such as gas

    compression and oil export packages, typical machinery including turbines, motors and diesel

    engines, and rotating equipment such as pumps and compressors etc. The IGN provides an

  • 8/10/2019 Loc Process

    27/76

    HS13 Gas Treatment Plant

    understanding of the technology used and considers those aspects of design, operation and

    maintenance that could contribute to a major offshore incident. The report also includes a

    structured review to assist Inspectors gauge compliance with statutory requirements and it gives

    examples of poor practice to look out for.

    A comprehensive list of relevant standards is provided in Section 5.15 of the IGN.

    Our main references for gas turbine safety include:

    ISO 21789 Gas turbine applications - Safety

    Offshore gas turbines (and major driven equipment) integrity and inspection guidance notes

    HSE Research Report 430

    Fire and explosion hazards in offshore gas turbines HSE Offshore Information Sheet

    10/2008

    3. Relevant Legislation, ACOP and Guidance Includes:

    Offshore Installations (Safety Case) Regulations 2005, Regulation 12(1)(c)

    Assessment Principles for Offshore Safety Cases [APOSC] paras 14 and 35

    4. Specific Technical Issues:

    None over and above those described in the referenced standard.

    5. Other Related Assessment Sheets in this Section are:

    None

    6. Cross-Referenced Sections and Sheets are:

    None

    1. Confirmation should be obtained that gas (and oil) treatment processes and plant have been

    designed and constructed in accordance with recognised standards or codes of practice.

    Recognised standards/codes of practice for design of vessels, piping, valves, etc are given in other

    sections of this chapter. However specific standards for treatment processes includes:

    API RP 55 Conducting oil and gas producing and gas processing plant operations involving

    hydrogen sulphide.

  • 8/10/2019 Loc Process

    28/76

    EFC Pub 16 Guidelines on materials for carbon and low alloy steels for H2S containing

    environments in oil and gas production

    EFC Pub 17 Corrosion resistant alloys for oil and gas production Guidance on general

    requirements and test methods for H2S service

    EFC Pub 23 CO2corrosion control in oil and gas production

    NACE MR0175 Sulphide stress cracking resistant materials for Oilfield Equipment

    2. Where a standard/code of practice other than that listed above has been employed, judgement

    as to the adequacy of the system can only be assessed on an individual basis and the duty holder

    should be required to justify that the applied standard/code will be equally effective.

    3. Relevant Legislation, ACOP and Guidance includes:

    Offshore Installations (Safety Case) Regulations 2005, Regulations 12(1)(c)

    Assessment Principles for Offshore Safety Cases [APOSC] Principle 4

    Provision and use of Work Equipment Regulations 1998, Regulation 4

    4. Specific Technical Issues:

    4.1 Materials of construction, appropriate to the service conditions and composition of the

    fluids, should be specified and used.

    4.2 The consequences of a release of toxic material should be addressed and appropriate

    control and mitigation measures should be outlined.

    4.2 Adsorbent and absorbent materials may be used to treat the gas stream. These

    substances (e.g. amine) may themselves give rise to hazards. The consequences of

    breakthrough of substances (e.g. elevated levels of H2S) on the downstream plant should be

    addressed.

    5. Other Related Assessment Sheets in this Section are:

    2.3.1.HS1 Pressure vessels

    2.3.1.HS2 Heat exchangers

    2.3.1.HS5 Piping

    2.3.1.HS6 Small bore tubing

    HS8 Flexible hoses

  • 8/10/2019 Loc Process

    29/76

    HS15 Hazardous Drains / Caisson

    HS9 Pumps

    HS10 Compressors

    HS17 Flare and vent towers

    G1 Corrosion

    G20 Ageing / material degradation

    G24/25 Incorrect material specification and usage

    F11 Size of release, speed of detection and effectiveness

    F12 Dispersion

    6. Cross-Referenced Sections and Sheets are:

    None.

    1. Confirmation should be obtained that the hazardous drains system and disposal caisson have

    been designed and constructed in accordance with recognised standards or codes of practice.

    Recognised standards/codes of practice include:

    Pipework:

    ANSI B31.3 Petroleum refinery piping

    Sump Tanks & Disposal Caisson:

    API Standard 2000 Venting Atmospheric and Low Pressure Storage Tanks; Non Refrigerated

    and Refrigerated, 6th Edition, November 2009 (ISO 28300:2008 identical)

    API Publication 2210 Flame Arrestors for vents of tanks Storing Petroleum products

    2. Where a standard/code of practice other than that listed above has been employed, judgement

    as to the adequacy of the hazardous drains system and disposal caisson can only be assessed on

    an individual basis and the duty holder should be required to justify that the applied standard/code

    will be equally effective.

    3. Relevant Legislation, ACOP and Guidance includes:

    Offshore Installations (Safety Case) Regulations 2005, Regulation 12(1)(c)

  • 8/10/2019 Loc Process

    30/76

    Assessment Principles for Offshore Safety Cases [APOSC] paras 14 and 35

    Loss of Containment Manual Part 8.6 Segregation of hazardous drains

    4. Specific Technical Issues:

    4.1 Flame Arrester

    The hazardous drains sump tanks and disposal caisson will generally be vented to the atmospheric

    vent header although, in some cases, a dedicated vent may be provided. In either case, the vent

    should be fitted with a flame arrester designed to API 2210, ISO 16852 or equivalent.

    4.2 Wave Action

    The drains sump vent should be of sufficient capacity to accommodate the inbreathing and

    outbreathing due to the rise and fall in liquid level as a result of wave action.

    Dip pipes, within the caisson, should terminate at sufficient depth to ensure that they are

    submerged at all times.

    4.3 Dip Pipe Perforation

    Dip pipes can be subjected to accelerated rates of corrosion at, or just below, the liquid level in the

    caisson. Perforation resulting from such corrosion may result in the migration of hydrocarbon

    vapour from the caisson into the drains system, [this has resulted in a number of hydrocarbon

    releases]. Confirmation should be obtained that there is an inspection scheme in place to address

    this phenomenon.

    4.4 Inappropriate inter-connections

    A number of hydrocarbon releases have resulted from poor design involving inappropriate

    interconnections between the closed/flare system and the open drains. Plant blowdown then

    causes gas to discharge from the open drains. Confirmation should be sought that this possibility

    has been examined during the plant HAZOP studies.

    4.5 Design Requirements for Open and Closed Drains

    The following would be expected in open and closed drains design:

    a. segregation of open and closed drains,

    b. open drain systems are typically classified as hazardous and non-hazardous. It is important

    that segregation of the drain systems is maintained at times and under all foreseeable

    conditions to prevent migration of hydrocarbons into safe areas where they may present an

    ignition risk,

  • 8/10/2019 Loc Process

    31/76

    HS17 Flare and Vent Towers

    c. maintaining appropriate slopes to achieve drainage,

    d. dedicated closed drain vessel or appropriate integrity and segregation if flare vessel is used

    as a drain drum,

    e. isolation of drain points to prevent over-pressurisation of drain system from HP process

    plants, e.g. spades or locked valves.

    5. Other Related Assessment Sheets in this Section are:

    None

    6. Cross-Referenced Sections and Sheets are:

    None

    1. Confirmation should be obtained that flare towers have been designed and constructed in

    accordance with recognised standards or code of practice. Recognised standards/codes of practice

    include:

    API Standard 521 American Petroleum Institute [5th edition January 2007] Pressure

    Relieving and Depressurising Systems (ISO 23251 identical)

    BS EN ISO 25457:2008: Flare details for general refinery and petrochemical service

    The Institute of Petroleum [2001] Guidelines for the Safe and Optimum Design of

    Hydrocarbon Pressure Relief and Blowdown Systems ISBN 0 85293 287 1

    The above codes, standards and guidance are applicable to flare towers on both fixed installations

    and FPSOs. Well test equipment on drilling installations is likely to have dedicated well test flare

    booms.

    2. Where a standard/code of practice other than that listed above has been employed, judgement

    as to the adequacy of the flare tower can only be assessed on an individual basis, and the duty

    holder should be required to justify why its procedures/practices in the relevant areas will deliver an

    equivalent level of health and safety performance.

    3. Relevant Legislation, ACOP and Guidance includes:

    Offshore Installations (Safety Case) Regulations 2005, Regulation 12(1)(c)

    Assessment Principles for Offshore Safety Cases [APOSC] paras 14 and 35

    Loss of Containment Manual Part 5.5 Relief/blowdown/flare system integrity

  • 8/10/2019 Loc Process

    32/76

    HS18 Mechanical Integrity of FPSO Mooring Turrets

    4. Specific Technical Issues:

    A review of lessons learned from past incidents is given in Section 6 of Institute of Petroleum

    Guidelines for the Safe and Optimum Design of Hydrocarbon Pressure Relief and Blowdown

    Systems. This guide includes checklists for assessment of relief and blowdown systems [pp 100-

    102] for both designers and operators. The guide should be included as part of the assessment

    process.

    An overview of radiation exposure levels is given in Section 5.8 of theInstituteofPetroleum

    Guidelinesfor the Safe and Optimum Design of Hydrocarbon Pressure Relief and Blowdown

    Systems. Confirmation should be obtained that the suggested limits are not exceeded.

    The Design Requirements for Relief, Vent and Flare Systems are covered as a specific technical

    issue in section 2.3.1 F15 Relief Systems.

    5. Other Related Assessment Sheets in this Section are:

    2.3.1.F15 Relief Systems

    6. Cross-Referenced Sections and Sheets are:

    None.

    [Relevant Sheets: G.9]

    Introduction

    1. Many floating production storage and offtake facilities [FPSOs] employ the principal of free

    weathervaning of the hull round a geostationary mooring spread. For this purpose, the hull structure

    is designed or modified to accommodate an internal turret to which static mooring lines are fixed

    permitting unrestricted rotation of the vessel about that axis of fixation. The turret incorporates a

    bearing arrangement similar to a crane slew ring to reduce friction and, also usually a high pressure

    swivel system to permit and control the transfer of fluids from the stationary risers to the rotating

    vessel and its processing and storage facilities.

    The design and operational safety/integrity of the bearing and swivel arrangements are matters for

    technical assessment by OSD Mechanical Specialists at the design safety case and operational

    safety case stages. Other aspects such as integration of the turret with the hull structure and the

    design/integrity of flowlines and flexible risers need to be addressed by respective specialist

    sections.

    2. Assessment Principles:

  • 8/10/2019 Loc Process

    33/76

    i. There are no national or international standards or formal codes for the design of turrets or

    swivels, although they draw heavily upon existing large low speed bearing design and fluid/gas

    sealing technology. Each example to date is a bespoke engineering solution and the most

    appropriate method of assessment therefore involves the basic principals of hazard identification,

    FMEA, Risk Assessment and whether risks are controlled to ensure compliance with the relevant

    statutory provisions.

    ii. OSD3.4, to obtain the information necessary to approach the assessment task in a competent

    and consistent manner, commissioned a technical survey of published information covering all

    FPSO and FSO installations in theUKsector. From this information a practical and comprehensive

    database was created called:

    The FPSO Turret and Swivel Interactive Knowledge Base

    The IKB provides the following principal reference facilities:

    i. General description of turret systems

    Ship structures

    General systems and arrangements

    Mooring systems and turret loadings

    Scaffolding and support systems

    Personnel

    Construction standards

    ii. Turret system design

    Major components and boundaries

    Turret transfer systems

    Interfacing systems

    iii. Fluid transfer systems

    iv. Failure modes

    v. Inspection and maintenance

    vi. Examples of good and bad practice

    This extensive register encompasses detail of all existing turret mooring designs and arrangements

    existing inUKwaters. In addition it discusses in appropriate technical language the merits and

  • 8/10/2019 Loc Process

    34/76

    weaknesses of respective systems and guides the reader first toward an appreciation of the

    broader aspects of the technology, hazard identification and risk recognition processes, to a

    position where specific examples may be subject to comparative appraisal against a cross industry

    selection of design types and their operational characteristics and histories.

    3. Relevant Legislation, ACOP and Guidance includes:

    Offshore Installations (Safety Case) Regulations 2005, Regulation 12

    Offshore Installations (Prevention of Fire and Explosion, and Emergency Response) Regulations

    1995, Regulations 4, 5, 9 & 19

    Offshore Installations and Wells (Design and Construction, etc) Regulations 1996, Regulations 4, 5,

    6, 7 & 8

    Failure modes, reliability and integrity of floating storage unit (FPSO,FSU) turret and swivel

    systems HSE research report OTO 2001/073

    4. For marginal field development the turret moored FPSO offers commercial attractions. Mooring

    turrets clearly embody major hazard potentials including both the control of the transient hazardous

    inventories within them and station keeping of the parent vessel. Full and intelligent use of the

    FPSO turret database and application of its reflective appraisal procedures are the best means

    available for assessing and evaluating both the design and the lifetime operational integrity of this

    advanced production technology.

    5. Other Related Assessment Sheets in this Section are:

    For the purpose of this manual mooring turrets have been assigned to Section 2.3.1 - Loss of

    Containment - Process. However, the turret is a multi functional design feature, its construction and

    housing form an integral part of the vessel primary structure and the mooring system. Whilst these

    considerations are the responsibility of structural and marine specialists, structural strength and

    especially stiffness are of paramount importance to the performance of the turret bearings, seals

    and flanged joints. Consequently there are at least three safety critical elements to be assessed in

    relation to the turret, namely integrity of primary and support structure, mooring integrity and the

    integrity of fluid paths [flexible risers, swivels and rigid pipework]. It is therefore desirable that the

    assessment of turret design and operational issues should be undertaken on a multi discipline basis

    with input from OSD5 and other OSD3 Specialist Teams.

    6. Cross-Referenced Sections and Sheets are:

    None

  • 8/10/2019 Loc Process

    35/76

    HS19 Temporary Equipment

    1. Confirmation should be obtained that systems and procedures are in place to manage the risks

    associated with the use of temporary equipment. These should be broadly in line with the guidance

    given in SPC/TECH/OSD/25.

    Confirmation should also be obtained that all temporary equipment has been designed and

    constructed in accordance with recognised standards or codes of practice, or if not, justification

    sought as to why the standard(s) employed should result in equivalent levels of safety.

    2. Where systems and procedures differ markedly from those recommended in

    SPC/TECH/OSD/25, judgement as to the adequacy of the management of risks associated with the

    temporary equipment can only be assessed on an individual basis and the duty holder should be

    required to justify that the applied systems and procedures will be equally effective.

    3. Relevant Legislation, ACOP and Guidance includes:

    Offshore Installations (Safety Case) Regulations 2005, Regulation 12(1)(c)

    Assessment Principles for Offshore Safety Cases [APOSC], paras 14 and 35

    Provision and Use of Work Equipment Regulations 1998, Regulation 4

    4. Specific Technical Issues:

    4.1 Deciding what is, and is not, temporary equipment

    Essentially Temporary Equipment compromises equipment which is not a permanent part of the

    installation, and which is intended to be removed after a finite period of time.

    4.2 Impact of temporary equipment on existing plant/systems

    A HAZID and HAZOP should have been conducted to ensure that the Temporary Equipment will

    not compromise the integrity of the existing plant and systems [and vice versa].

    4.3 Control of Change

    There should be systems/procedures in place to control short term amendments to existing

    procedures/documentation. The systems/procedures should cover the re-instatement of amended

    material.

    4.4 Competence and Training

    Temporary training requirements need to be identified, recorded and implemented. Contractor

    competence and training should be verified by the duty holder.

  • 8/10/2019 Loc Process

    36/76

    G1 Part 1 Corrosion: Internal

    4.5 Control of Contractors

    The integration of systems/procedures will be required where the Contractors have their own

    systems/procedures for the operation, control and maintenance of the temporary equipment.

    5. Other Related Assessment Sheets in this Section are:

    None

    6. Cross-Referenced Sections and Sheets are:

    None

    Topsides Plant

    1. Confirmation should be obtained that internal corrosion is being managed through

    implementation of a corrosion management system. There are no recognised standards or codes of

    practice that deal with the corrosion management system. Hence in co-operation with the offshore

    industry CAPCIS have prepared the research report OTO 2001/044 Review of Corrosion

    Management for Offshore Oil and Gas Processing for HSE, which provides guidance and examples

    of best practice. This is considered to be the benchmark that duty holders corrosion management

    system should satisfy. Recognised standards and codes of practice dealing with certain specificelements of corrosion management include:

    DnV RP G-101 Risk Based Inspection of Topsides Static Mechanical Equipment

    API Publication 581 Risk Based Inspection

    HSE RR363/2001 Best Practice for risk based inspection as part of integrity management

    RIMAP Generic Risk Based Inspection and Maintenance Planning

    NORSOK standard M-506 CO2 Corrosion Rate Calculation Model

    NORSOK Standard M-CR-505 Corrosion Monitoring Design

    NACE Standard RP0775 Preparation and Installation of Corrosion Coupons and

    Interpretation of Test Data in Oil Field Operations

    NACE Standard RP0497 Field Corrosion Evaluation Using Metallic Test Specimens

    NACE Standard RP0192 Monitoring Corrosion In Oil & Gas Production with Iron Counts

    ASTM G4 Standard Guide for Conducting Corrosion Coupon Tests in Field Application

  • 8/10/2019 Loc Process

    37/76

    ASTM G96 Standard Guide for On-line Monitoring of Corrosion in Plant Equipment

    [Electrical and Electrochemical Methods]

    InstituteofPetroleumModel Code of Safe Practice for Petroleum Industry Part 13: Pressure

    Piping Systems Examination

    InstituteofPetroleumModel Code of Safe Practice for Petroleum Industry Part 12: Pressure

    Vessel Systems Examination

    EEMUA 193 Recommendations for the Training, Development and CompetencyAssessment of Inspection Personnel

    EEMUA 179 A Working Guide for Carbon Steel Equipment in Wet H2S Service [Developed

    largely from Oil Refinery experience]

    API RP574 Inspection Practices for Piping System Codes

    API RP570 Piping Inspection Code: Inspection, repair, alteration and re-rating of in-service

    piping systems

    API RP510 Pressure vessel inspection code: Maintenance inspection, rating, repair, and

    alteration

    2. Where a standard/code of practice other than those listed above has been employed,

    udgement as to the adequacy of corrosion management can only be assessed on an individual

    basis, and the duty holder should be required to justify why its procedures/practices in the relevant

    areas will deliver an equivalent level of health and safety performance.

    3. Relevant Legislation, ACOP and Guidance includes:

    Offshore Installations (Safety Case) Regulations 2005, Regulations12(1)(c) and 12(1)(d)

    Assessment Principles for Offshore Safety Cases [APOSC], paras 95, 98 and 102

    Offshore Installations (Prevention of Fire and Explosion, and Emergency Response)

    Regulations 1995, Regulations 4(1)(a); 9(b) and 12

    Pressure Equipment Regulations 1999

    4. Specific Technical Issues:

    The safety case assessment should seek to establish to what extent aspects of the corrosion

    management system listed below have been addressed particularly because experience has shown

    them to be contributory factors in corrosion incidents:

    Clear, explicit policy governing corrosion and plant monitoring.

    Sufficient inhouse expertise, clear allocation of responsibilities and involvement of offshore

    staff to enable delivery of the policy.

  • 8/10/2019 Loc Process

    38/76

    Better analysis and integration of inspection and monitoring data including use of statistical

    techniques to allow for uncertainties resulting from limitations of inspection techniques and

    coverage.

    Better use of opportunistic inspection.

    Better documentation of system.

    Increased utilisation of platform staff knowledge and raised awareness.

    Widen scope of inspection plans that includes certain amount of speculative inspection.

    Improved identification of corrosion hot spots based on plant walkabout rather then

    examination of drawings.

    Increased system performance monitoring and improved failure investigations that identify

    underlying system failures.

    Regular system reviews that includes assessment of system performance against set

    criteria, evaluation of system failures and identification of areas to be improved.

    Regular independent audits of the corrosion management system.

    Ensuring high availability of inhibitor injection system.

    Consideration of enhanced degradation near injection points due to local flow/environmental

    conditions.

    Planning of non-invasive inspection [NII] scheme based on considerations outlined in JIP

    reports HOIS NII Decision Guidance, Mitsui Babcock GSP 235, Recommended Practice

    for NII.

    Minimisation of deadlegs and where unavoidable implementation of targeted inspection

    scheme.

    Identification of areas prone to pitting and application of the most appropriate inspection

    techniques and prevention schemes including designing them out.

    Identification of components that could suffer preferential weld corrosion and application of

    appropriate specialised inspection techniques and prevention strategies. Further guidance in

    JIP report Risk of preferential weldment corrosion of ferritic steels in CO2 containing

    environments and the Guidelines for the prevention, control and monitoring of preferential

    weld corrosion of ferritic steels in wet hydrocarbon production systems containing CO2.

    Level of attention given to the hydrocarbon drains systems integrity management.

    Special consideration of the failure mechanisms of smallbore piping [3 and below] and

    application of appropriate inspection techniques.

  • 8/10/2019 Loc Process

    39/76

  • 8/10/2019 Loc Process

    40/76

    NORSOK standard M-501 Surface preparation and protective coatings

    ISO 12944 Paints and Varnishes Corrosion Protection of Steel Structures

    85 5493: 1977 Protective coating of iron and steel structures against corrosion.

    EN ISO 14713: Protection against corrosion of iron and steel in structures - Metal coatings -

    Guide.

    EN ISO 1461: Hot dip galvanized coatings on fabricated products.

    EN 10240: (Draft) Coatings for steel tubes: Specification for hot dip galvanized coatings.

    ISO 4628-3: 1982 Paints and varnishes - Evaluation of degradation of paint coatings -

    Designation of intensity, quantity and size of common types of defect - Part 3: Designation of

    degree of rusting.

    BS 7079: Part Al Preparation of steel substrates before application of paints and related

    products - Visual assessment of surface cleanliness - Part 1: Rust grades and preparation

    grades of uncoated steel substrates and of steel substrates after overall removal of previous

    coatings.

    ISO 9223: 1992 Corrosion of metals and alloys - Corrosivity of atmospheres - Classification.

    ISO 11303:2002 Corrosion of metals and alloys - Guidelines for selection of protection

    methods against atmospheric corrosion

    EN 22063: 1993 Metallic and Other Inorganic Coatings - Thermal Spraying - Zinc, Aluminium

    and Their Alloys

    EEMUA 200 Guide to the specification, installation, maintenance of spring supports of piping

    ISO CD 19902 Petroleum and natural gas industries Fixed offshore structures

    2. Where a standard/code of practice other than those listed above has been employed,

    udgement as to the adequacy of corrosion management system can only be assessed on an

    individual basis, and the duty holder should be required to justify why its procedures/practices in the

    relevant areas will deliver an equivalent level of health and safety performance.

    3. Relevant Legislation, ACOP and Guidance includes:

    Offshore Installations (Safety Case) Regulations 2005, Regulations 12(1)(c) and 12(1)(d

    Assessment Principles for Offshore Safety Cases [APOSC] paras 95, 98 and 102

    Offshore Installations (Prevention of Fire and Explosion, and Emergency Response) Regulations

    1995, Regulations 4(1)(a), 9(b) & 12

    Pressure Equipment Regulations 1999

    4. Specific Technical Issues:

  • 8/10/2019 Loc Process

    41/76

    G2 Erosion

    External corrosion of topsides on an ageing installation does not usually receive the same degree

    of attention as the management of the internal corrosion with the result that on a number of

    installations the primary threat of hydrocarbon release is from external corrosion. In addition a

    significant number of personnel injuries on such installations are due to falls and trips resulting from

    failure of corroded members used as temporary supports or steps. Corroded walkways have also

    featured in a number of incidents. Particular issues that should be probed as part of the safety case

    assessment include:

    Management of process plant integrity around corrosion traps such as pipe supports,

    penetrations, saddles, etc.

    Management of the risks associated with surface preparation and painting on live plant.

    Management of corrosion under insulation.

    Management of bolt corrosion.

    Management of pitting and stress corrosion cracking in corrosion resistant alloy piping and

    tubing operating in areas exposed to sea spray/deluge. See RR129 Review of externalStress Corrosion Cracking of 22% Cr Duplex Stainless Steel for further guidance.

    Painting and refurbishment planning systems and performance standards including short

    term remedies.

    Maintenance of spring supports.

    Corrosion management of walkways, hand railings, escape equipment attachment points

    and other similar secondary structural components.

    5. Other Related Assessment Sheets in this Section are:

    G15 Deficient Procedures: Maintenance

    G20 Ageing/Mechanical Degradation

    G24 Incorrect Material Specification

    G25 Incorrect Material Usage

    6. Cross-Referenced Sections and Sheets are:

    None

  • 8/10/2019 Loc Process

    42/76

    1. Confirmation should be obtained that erosion is being managed through implementation of an

    erosion management system that includes amongst other things selection of appropriate materials

    and coatings, control of fluid velocities, removal/prevention of solid particles, effective detection

    systems, plant design that minimises changes in flow direction and erosion resistant valve design.

    Recognised standards/codes of practice dealing with erosion include:

    DNV Recommended Practice RP 0501 Erosive Wear in Piping Systems

    ISO 13703 Offshore Piping Systems

    API RP14E Design and Installation of Offshore Production Platform Piping Systems

    2. Where a standard/code of practice other than those listed above has been employed,

    udgement as to the adequacy of erosion management system can only be assessed on an

    individual basis, and the duty holder should be required to demonstrate its procedures/practices in

    the relevant areas will deliver an equivalent level of health and safety performance.

    3. Relevant Legislation, ACOP and Guidance includes:

    Offshore Installations (Safety Case) Regulations 2005, Regulations 12(1)(c) and 12(1)(d)

    Assessment Principles for Offshore Safety Cases [APOSC], paras 95, 98 and 102

    Offshore Installations (Prevention of Fire and Explosion, and Emergency Response) Regulations

    1995, Regulations 4(1)(a), 9(b) and 12

    Pressure Equipment Regulations 1999

    4. Specific Technical Issues:

    There have been a number of major hydrocarbon releases recently caused by solids particle

    erosion where failure of a number of crucial control measures had occurred. Wall thinning is usually

    very rapid and hence prevention rather then control should be the guiding principle. Operations staff

    do not always appreciate the impact of the production rate on erosion risk. Prevention of erosion in

    the production plant can be achieved by design whereas for well servicing and drilling operations

    process management is usually the only available option. Erosion tends to be a localised effect

    which means that a very good knowledge of the local rather then global flow velocities is required in

    order to assess erosion risks. Sand detection systems have proved to have varying reliability and

    hence their effectiveness should be explored as part of the assessment process.

    Relevant guidance documents include:

    RR115 Erosion in Elbows in Hydrocarbon Production systems: Review Document

    SPC/TECH/OSD/19 Offshore Produced Sand Management

  • 8/10/2019 Loc Process

    43/76

    G4 Internal explosion

    5. Other Related Assessment Sheets in this Section are:

    G1 Part 1 Corrosion: Internal

    G1 Part 2 Corrosion: External

    6. Cross-Referenced Sections and Sheets are:

    None

    1. Confirmation should be obtained that internal explosions have been assessed in accordance

    with a recognised standard or code of practice. Recognised standards/codes of practice would

    include:

    HS025 Fire and Explosion Guidance, Oil and Gas UK/HSE 2007

    Spouge, J, A Guide to Quantitative Risk Assessment for Offshore Installations, CMPT

    (Centre for Marine and Petroleum Technology), 1999, Appendix IV Hydrocarbon event

    consequence modelling (old)

    BS EN ISO 13702:1999 Petroleum and Natural Gas Industries Control and Mitigation of

    Fires and Explosions on Offshore Production Requirements and Guidelines.

    The following document provides useful information but is based on a different regulatory regime,

    so should be used with care to ensure consistency withUKlegislation:

    VROM, Guidelines for quantitative risk assessment, Purple Book section 5, 2005

    2. Where a standard/code of practice other than those listed above has been employed,

    udgement as to the adequacy of the evaluation of the internal explosion hazard can only be

    assessed on an individual basis, and the duty holder should be required to justify why its

    procedures/ practices in the relevant areas will deliver an equivalent level of health and safety

    performance.

    3. Relevant Legislation, ACOP and Guidance include:

    Offshore Installations (Safety Case) Regulations 2005

    Offshore Installations (Prevention of Fire and Explosion, and Emergency Response)

    Regulations 1995

    Fire, Explosion and Risk Assessment Topic Guidance

    http://www.hse.gov.uk/foi/internalops/hid/manuals/pmtech12.pdf

  • 8/10/2019 Loc Process

    44/76G7 Fire

    Fire and Explosion Strategy Document http://www.hse.gov.uk/offshore/strategy/index.htm

    OTN 95 196 1995 Gas explosion handbook HSE-OSD report

    Loss Of Containment Manual Part 8.5 Air ingress and flammable mixtures

    http://www.hse.gov.uk/offshore/loss-of-containment-manual%202012.pdf

    4. Specific Technical Issues:

    4.1 Internal explosions are regarded as a lower risk factor in comparison to topsides external

    explosions. Specific attention should be paid to situations whereby air could ingress into a

    hydrocarbon-saturated atmosphere and form a flammable air/vapour mixture. The risk from a gas

    turbine sourced internal explosion should be assessed with particular emphasis on fuel/air control,

    emergency shutdown control and internal conditions that could give rise to volumes of un-ignited

    fuel air mixtures.

    The adequacy of Internal Explosion venting available in each engine installation should also be

    investigated.

    4.2 Protection against air ingress and flammable mixtures in process

    Flammable mixtures can form in piping, plant and equipment when air enters systems that normally

    contain hydrocarbon, as a result of operational or maintenance activities. Correct purging and

    operational procedures will ensure that the risks are minimised.

    5. Other related assessment sheets in this Section are:

    None

    6. Cross-referenced Sections and sheets are:

    Sheet HS9 Pumps

    Sheet HS10 Compressors

    Sheet HS11 Turbines

    Sheet F3 Installation Specific Hazard Studies

    Sheet F8 Safety Integrity Levels Standards

    Sheet F23 Fire/Smoke/Gas/Flame Detectors/Alarms

  • 8/10/2019 Loc Process

    45/76

    1. Confirmation should be obtained that requirements for the identification of fire hazards as

    initiators to other hazardous events have been analysed in accordance with recognised standards

    or codes of practice that would be used for a manned installation. Recognised standards/codes of

    practice would include:

    BS EN ISO 13702:1999 Petroleum and Natural Gas Industries Control and mitigation of

    fires and explosions on offshore production installations requirements and guidelines.

    Spouge, J, A Guide to Quantitative Risk Assessment for Offshore Installations, CMPT(Centre for Marine and Petroleum Technology), 1999, Appendix IV Hydrocarbon event

    consequence modelling (old)

    The following document provides useful information but is based on a different regulatory

    regime, so should be used with care to en