21
LS1 activities J.M. Jimenez 4 th December’13

LS1 activities J.M. Jimenez 4 th December’ 13

  • Upload
    morey

  • View
    39

  • Download
    0

Embed Size (px)

DESCRIPTION

LS1 activities J.M. Jimenez 4 th December’ 13. LHC: A Marvel of Technology The LHC tunnel with dipole magnets . LHC: A Marvel of Technology Dipole Magnets: 1232 of them operating at 1.9K. 7 TeV 8.33 T 11850 A 7MJ. Contracts by 4.7cm during cool-down. - PowerPoint PPT Presentation

Citation preview

Page 1: LS1 activities J.M. Jimenez  4 th  December’ 13

LS1 activities

J.M. Jimenez 4th December’13

Page 2: LS1 activities J.M. Jimenez  4 th  December’ 13

2Introduction to LS1J.M. Jimenez 4th December 2013

Page 3: LS1 activities J.M. Jimenez  4 th  December’ 13

3Introduction to LS1J.M. Jimenez 4th December 2013

LHC: A Marvel of TechnologyThe LHC tunnel with dipole magnets

Page 4: LS1 activities J.M. Jimenez  4 th  December’ 13

4Introduction to LS1J.M. Jimenez 4th December 2013

LHC: A Marvel of TechnologyDipole Magnets: 1232 of them operating at 1.9K

7 TeV8.33 T11850 A7MJContracts by 4.7cm during

cool-down

Page 5: LS1 activities J.M. Jimenez  4 th  December’ 13

5Introduction to LS1J.M. Jimenez 4th December 2013

LHC: A Marvel of TechnologyThe LHC long straight sections

Page 6: LS1 activities J.M. Jimenez  4 th  December’ 13

6Introduction to LS1J.M. Jimenez 4th December 2013

LHC: A Marvel of Technology Challenges for 2012: increasing luminosity…

Objectives being achieved…!

Even if running at 50 ns butwith an optimised crossing angle

Page 7: LS1 activities J.M. Jimenez  4 th  December’ 13

7Introduction to LS1J.M. Jimenez 4th December 2013

LHC: A Marvel of TechnologySome technological challenges for next years…

Circumference (km) 26.7 100-150m underground

Number of Dipoles 1232 Cable Nb-Ti, cold mass 37million kg

Length of Dipole (m) 14.3

Dipole Field Strength (Tesla) 8.4 Results from the high beam energy needed

Operating Temperature (K) 1.9 Superconducting magnets needed for the high magnetic fieldSuper-fluid helium

Current in dipole sc coils (A) 13000 Results from the high magnetic field1ppm resolution

Beam Intensity (A) 0.5 2.2.10-6 loss causes quench

Beam Stored Energy (MJoules) 362 Results from high beam energy and high beam current1MJ melts 2kg Cu

Magnet Stored Energy (MJoules)/octant

1100 Results from the high magnetic field

Sector Powering Circuit 8 1612 different electrical circuits

Page 8: LS1 activities J.M. Jimenez  4 th  December’ 13

8Introduction to LS1J.M. Jimenez 4th December 2013

LHC: A Marvel of TechnologyLHC beam stored energy

Momentum at collision 7 TeV (1 eV = 1,6 × 10-19 Joule)

Number of bunches 2808Protons per bunch 1.15 1011

Total number of protons 6.5 x1014 (1 ng of H+) (for 2 beams)

700 MJ melt one ton of copper

Energy stored in the two beams: 724 MJouleEnergy to heat and melt one ton of copper: 700 MJoule

700 MJoule dissipated in 88 s

700.106 / 88.106 8 TW

World Electrical Installed Capacity 3.8 TW

90 kg of TNTper beam

Page 9: LS1 activities J.M. Jimenez  4 th  December’ 13

9Introduction to LS1J.M. Jimenez 4th December 2013

LHC: A Marvel of TechnologyLHC cryomagnets stored energy

10 GJoule flying 700 km/h

The energy stored in the LHC magnets corresponds

approximately to 8 such trains running at 300 km/h

1232 * 108 mH = 133 H ; ½ L . I2 ~ 10 GJ

• Energy stored in the magnet system: 10 GJoule• Energy stored in one (of 8) dipole circuit: 1.3 GJoule

Magnetic energy must be

discharged in around 40 seconds!

Page 10: LS1 activities J.M. Jimenez  4 th  December’ 13

10Introduction to LS1J.M. Jimenez 4th December 2013

301 ± 85pΩ

Rmax = 2.7nΩ

Rmax = 3.3nΩ

306** ± 313pΩ

(**) number of splices in the quads segments corrected, 1.3 added

Dipole Buses Quad Buses

12 23 34 45 56 67 78 81

Main Dipoles&Quads Bus, sorted by position, 2048 segmentsAll HWC pyramids and plus ~150 ramps to 3.5TeV analyzed

Top 10 Splice Resistances

2nΩ

LS1 activitiesLHC Main Splices: Busbars SC

Page 11: LS1 activities J.M. Jimenez  4 th  December’ 13

11Introduction to LS1J.M. Jimenez 4th December 2013

LS1 – magnet replacement

Finished SSS 233, with vacuum barrier: a long story of leaks and repairs (bulk material leak). Successful final pressure test !All dipoles ready, awaiting

diode installation

Cryo-BLM mounted on Q7R3

Only 1 more magnet to test (Q7R3) before the 2012 year end and cryo-shutdown in SM-18

Preparing for higher intensities

Q5 and Q7, built for the first time

at CERN

Page 12: LS1 activities J.M. Jimenez  4 th  December’ 13

12Introduction to LS1J.M. Jimenez 4th December 2013

LS1 activities Splices & Copper stabilizers

Splices

Splice join

Copper stabiliser joins

Page 13: LS1 activities J.M. Jimenez  4 th  December’ 13

13Introduction to LS1J.M. Jimenez 4th December 2013

LS1 activities Splices & Copper stabilizers

• Despite correct splice resistance between SC cables, a 13 kA joint can burn-out in case of a quench, if there would be a bad bonding between the SC cable and the copper bus, coinciding with a discontinuity in the copper stabilizer

• Resistance measurements and g-ray pictures have shown the presence of many of such defective joints in the machine, limiting the safe operating current

Page 14: LS1 activities J.M. Jimenez  4 th  December’ 13

14Introduction to LS1J.M. Jimenez 4th December 2013

LS1 activities 13kA splices consolidation

Welds cutting with orbital cutting machine in placeSleeve slidingBus bars machiningShunts positioning and solderingKapton foil insulation along 250mmInjection envelopes in placeLower insulation cover insertionUpper insulation cover insertionInsulation covers FixationResin injection into the envelopesSpider insulation in place

Page 15: LS1 activities J.M. Jimenez  4 th  December’ 13

15Introduction to LS1J.M. Jimenez 4th December 2013

LS1 activities Cryo-feedbox consolidation

Page 16: LS1 activities J.M. Jimenez  4 th  December’ 13

16Introduction to LS1J.M. Jimenez 4th December 2013

TE-VSC

LS1 activities Radiation to Electronic in LHC tunnel: a concern…

UJ76

UJ14/16RR13/17

UJ56RR53/57

US85

Page 17: LS1 activities J.M. Jimenez  4 th  December’ 13

17Introduction to LS1J.M. Jimenez 4th December 2013

Overall additional number of persons at CERN during LS1 per status

Page 18: LS1 activities J.M. Jimenez  4 th  December’ 13

18Introduction to LS1J.M. Jimenez 4th December 2013

LS1 activities Dashboard…

Page 19: LS1 activities J.M. Jimenez  4 th  December’ 13

19Introduction to LS1J.M. Jimenez 4th December 2013

Resuming Operation

from mid February 2013 to end December 2014

F M A M J J A S O N D J F J FM A M J J A S O N D

2013 2014 2015

M A

LHC

SPS

PS

PS Booster

beam to beam

PhysicsBeam commissioningShutdownTests

Courtesy Katy Foraz

Page 20: LS1 activities J.M. Jimenez  4 th  December’ 13

20Introduction to LS1J.M. Jimenez 4th December 2013

December 4, 2012 Roberto Saban 20

LS1LS1LS1LS1LS1LS1LS1LS1LS1LS1LS1LS1LS1LS1LS1LS1LS1LS1

LS1LS1LS1LS1LS1LS1LS1LS1LS1LS1LS1LS1LS1LS1LS1LS1LS1LS1

LS1LS1LS1LS1LS1LS1LS1LS1LS1LS1LS1LS1LS1LS1LS1LS1LS1LS1

LS1LS1LS1LS1LS1LS1LS1LS1LS1LS1LS1LS1LS1LS1LS1LS1LS1LS1

LS1LS1LS1LS1LS1LS1LS1LS1LS1LS1LS1LS1LS1LS1LS1LS1LS1LS1

LS1LS1LS1LS1LS1LS1LS1LS1LS1LS1LS1LS1LS1LS1LS1LS1LS1LS1

LS1LS1LS1LS1LS1LS1LS1LS1LS1LS1LS1LS1LS1LS1LS1LS1LS1LS1

LS1LS1LS1LS1LS1LS1LS1LS1LS1LS1LS1LS1LS1LS1LS1LS1LS1LS1

LS1LS1LS1LS1LS1LS1LS1LS1LS1LS1LS1LS1LS1LS1LS1LS1LS1LS1

LS1LS1LS1LS1LS1LS1LS1LS1LS1LS1LS1LS1LS1LS1LS1LS1LS1LS1

LS1LS1LS1LS1LS1LS1LS1LS1LS1LS1LS1LS1LS1LS1LS1LS1LS1LS1

LS1LS1LS1LS1LS1LS1LS1LS1LS1LS1LS1LS1LS1LS1LS1LS1LS1LS1

LS1LS1LS1LS1LS1LS1LS1LS1LS1LS1LS1LS1LS1LS1LS1LS1LS1LS1

LS1LS1LS1LS1LS1LS1LS1LS1LS1LS1LS1LS1LS1LS1LS1LS1LS1LS1

LS1LS1LS1LS1LS1LS1LS1LS1LS1LS1LS1LS1LS1LS1LS1LS1LS1LS1

LS1LS1LS1LS1LS1LS1LS1LS1LS1LS1LS1LS1LS1LS1LS1LS1LS1LS1

LS1LS1LS1LS1LS1LS1LS1LS1LS1LS1LS1LS1LS1LS1LS1LS1LS1LS1

Long Shutdown 1(13th Feb. 2013 to Dec. 2014) – Beam Commissioning Jan.-Apr. 2015)

A very busy period – Safety, Quality, Schedule

Page 21: LS1 activities J.M. Jimenez  4 th  December’ 13