Major Power Grid Blackouts in North America and Europe

Embed Size (px)

Citation preview

  • 8/12/2019 Major Power Grid Blackouts in North America and Europe

    1/32

    1539pk

    Copyright P. Kundur

    This material should not be used without the author's consent

  • 8/12/2019 Major Power Grid Blackouts in North America and Europe

    2/32

    1539pkMPB- 1

  • 8/12/2019 Major Power Grid Blackouts in North America and Europe

    3/32

    1539pkMPB- 2

    ! Approximately 50 million peoplein 8 states in theUS and 2 Canadian provinces affected

    " 63 GW of load interrupted (11% of total loadsupplied by Eastern North AmericanInterconnected System)

    ! During this disturbance, over 400 transmission linesand 531 generatingunits at 261 power plants tripped

    ! For details refer to: "Final Report of Aug 14, 2003Blackout in the US and Canada: Causes and

    Recommendations", US-Canada Power System

    Outage Task Force, April 5, 2004. www.NERC.com

  • 8/12/2019 Major Power Grid Blackouts in North America and Europe

    4/32

    1539pkMPB- 3

  • 8/12/2019 Major Power Grid Blackouts in North America and Europe

    5/32

    1539pkMPB- 4

    ! Electricity demand high but not unusually high! Power transfer levels high, but within established

    limits and previous operating conditions

    ! Planned outages of generating units in the affectedarea: Cook 2, Davis Bess plant, East Lake 4, Sammis

    3 and Monroe 1

    ! Reactive power supply problems in the regions ofIndiana and Ohio prior to noon

    ! Operators took actions to boost voltages" voltages within limits

    ! System operating in compliance with NERCoperating policies prior to 15:05 Eastern Daylight

    Time

    Aug 14, 2003 US-Canada Blackout

  • 8/12/2019 Major Power Grid Blackouts in North America and Europe

    6/32

    1539pkMPB- 5

  • 8/12/2019 Major Power Grid Blackouts in North America and Europe

    7/32

    1539pkMPB- 6

    ! The Midwest ISO (MISO) state estimator and real-time contingency analysis (RTCA) software not

    functioning properly from 12:15 to 16:04

    " prevented MISO from performing proper "earlywarning" assessments as the events wereunfolding

    ! At the First Energy (FE) Control Center, a number ofcomputer software problems occurred on the

    Energy Management System (EMS) starting at 14:14

    " contributed to inadequate situation awarenessat FE until 15:45

    ! The first significant event was the outage of EastLake generating unit #5 in the FE system at 13:31:34

    " producing high reactive power output" voltage regulator tripped to manual on

    overexcitation

    " unit tripped when operator tried to restore AVRcont'd

    Aug 14, 2003 US-Canada Blackout

  • 8/12/2019 Major Power Grid Blackouts in North America and Europe

    8/32

    1539pkMPB- 7

    ONTARIO

    2

    1

    ONTARIO

  • 8/12/2019 Major Power Grid Blackouts in North America and Europe

    9/32

    1539pkMPB- 8

    ! Initial line trips in Ohio, all due to tree contact:" Chamberlin-Harding 345 kV line at 15:05:41" Hanna-Juniper 345 kV line at 15:32:03" Star-South Canton 345 kV line at 15:41:35

    ! Due to EMS failures at FE and MISO control centers,no proper actions (such as load shedding) taken

    ! Critical event leading to widespread cascadingoutages in Ohio and beyond was tripping of

    Sammis-Star 345 kV line at 16:05:57

    " Zone 3 relay operation due to low voltage andhigh power flow! Load shedding in northeast Ohio at this stage could

    have prevented cascading outages that following

    Aug 14, 2003 US-Canada Blackout

  • 8/12/2019 Major Power Grid Blackouts in North America and Europe

    10/32

    1539pkMPB- 9

    (3:05:41)(3:32:03)

    Star- S. Canton (3:41:35)

  • 8/12/2019 Major Power Grid Blackouts in North America and Europe

    11/32

    1539pkMPB- 10

    Sammis-Star(4:05:57.5)

  • 8/12/2019 Major Power Grid Blackouts in North America and Europe

    12/32

    1539pkMPB- 11

    ! Tripping of many additional 345 kV lines in Ohio andMichigan by Zone 3 (or Zone 2 set similar to Zone 3)

    relays

    ! Tripping of several generators in Ohio and Michigan! At 16:10:38, due to cascading loss of major lines in

    Ohio and Michigan, power transfer from Canada

    (Ontario) to the US on the Michigan border shifted

    " power started flowing counter clockwise fromPennsylvania through New York and Ontario

    into Michigan

    " 3700 MW of reverse power flow to serve loadsin Michigan and Ohio, which were severedfrom rest of interconnected system except

    Ontario

    ! Voltage collapsed due to extremely heavy loadingson transmission lines

    ! Cascading outages of several hundred lines andgenerators leading to blackout of the region

    Aug 14, 2003 US-Canada Blackout

  • 8/12/2019 Major Power Grid Blackouts in North America and Europe

    13/32

    1539pkMPB- 12

  • 8/12/2019 Major Power Grid Blackouts in North America and Europe

    14/32

    1539pkMPB- 13

  • 8/12/2019 Major Power Grid Blackouts in North America and Europe

    15/32

    1539pkMPB- 14

  • 8/12/2019 Major Power Grid Blackouts in North America and Europe

    16/32

    1539pkMPB- 15

  • 8/12/2019 Major Power Grid Blackouts in North America and Europe

    17/32

    1539pkMPB- 16

  • 8/12/2019 Major Power Grid Blackouts in North America and Europe

    18/32

    1539pkMPB- 17

    Areas Affected by the Blackout

    Service maintained

    in some area

    Some Local Load

    Interrupted

  • 8/12/2019 Major Power Grid Blackouts in North America and Europe

    19/32

    1539pkMPB- 18

    1. Inadequate understanding of the power systemrequirements:

    # First Energy (FE) failed to conduct rigorouslong-term planning studies and sufficient

    voltage stability analyses of Ohio control area

    # FE used operational criteria that did not reflectactual system behaviour and needs

    # ECAR (East Central Area Reliability Council)did not conduct an independent review or

    analysis of FE's voltage criteria and operatingneeds

    # Some NERC planning standards weresufficiently ambiguous that FE could interpret

    them in a way that resulted in inadequate

    reliability for system operation

    cont'd

  • 8/12/2019 Major Power Grid Blackouts in North America and Europe

    20/32

    1539pkMPB- 19

    2. Inadequate level of situation awareness:

    # FE failed to ensure security of its system aftersignificant unforeseen contingencies

    #FE lacked procedures to ensure that itsoperators were continually aware of the

    functional state of their critical monitoring

    tools

    # FE did not have adequate backup tools forsystem monitoring

    3. Inadequate level of vegetation management (treetrimming)

    # FE failed to adequately manage tree growthinto transmission rights-of-way

    $ resulted in the outage of three 345 kVlines and one 138 kV line

    cont'd

  • 8/12/2019 Major Power Grid Blackouts in North America and Europe

    21/32

    1539pkMPB- 20

    4. Inadequate level of support from the ReliabilityCoordinator

    # due to failure of state estimator, MISO did notbecome aware of FE's system problems early

    enough

    $ did not provide assistance to FE# MISO and PJM (Regional Transmission

    operator) did not have in place an adequate

    level of procedures and guidelines for dealing

    with security limit violations due to a

    contingency near their common boundary

  • 8/12/2019 Major Power Grid Blackouts in North America and Europe

    22/32

    1539pkMPB- 21

  • 8/12/2019 Major Power Grid Blackouts in North America and Europe

    23/32

    1539pkMPB- 22

  • 8/12/2019 Major Power Grid Blackouts in North America and Europe

    24/32

    1539pkMPB- 23

    ! Pre-disturbance conditions:" system moderately loaded" facilities out of services for maintenance:

    $400 kV lines in South Sweden$4 nuclear units in South Sweden$3 HVDC links to Germany and Poland

    ! The first contingency was loss of a 1200 MW nuclear unitin South Sweden at 12:30 due to problems with steam

    valves

    " increase of power transfer from the north" system security still acceptable

    ! Five minutes later (at 12:35) a disconnector damagecaused a double busbar fault at a location 300 km away

    from the first contingency

    " resulted in loss of a number of lines in thesouthwestern grid and two 900 MW nuclear units

    ! At 12:37, voltage collapse in the eastern grid sectionsouth of Stockholm area

    " isolated southern Sweden and eastern Denmarksystem from northern and central grid

    cont'd

  • 8/12/2019 Major Power Grid Blackouts in North America and Europe

    25/32

    1539pkMPB- 24

    At 12.30: Loss of a 1200 MWNuclear Unit

  • 8/12/2019 Major Power Grid Blackouts in North America and Europe

    26/32

    1539pkMPB- 25

    At 12.35: Double bus-bar fault leading to-Loss of two 900 MW Nuclear Units-Disrupture of the south-western grid

  • 8/12/2019 Major Power Grid Blackouts in North America and Europe

    27/32

    1539pkMPB- 26

    Voltage Collapse

    IsolatedSubsystem

  • 8/12/2019 Major Power Grid Blackouts in North America and Europe

    28/32

    1539pkMPB- 27

    The blacked-out area after the grid separation at 12.37

  • 8/12/2019 Major Power Grid Blackouts in North America and Europe

    29/32

    1539pkMPB- 28

    ! The isolated system had enough generation to coveronly about 30% of its demand

    " voltage and frequency collapsed within a fewseconds, blacking out the area

    ! Impact of the blackout:" loss of 4700 MW load in south Sweden

    $1.6 million people affected$City of Malmo and regional airports and rail

    transportation without power

    " loss of 1850 MW in eastern Denmark$2.4 million people affected$City of Copenhagen, airport and rail

    transportation without power

    ! Result of an (n-3) contingency, well beyond "designcontingencies"

  • 8/12/2019 Major Power Grid Blackouts in North America and Europe

    30/32

    1539pkMPB- 29

  • 8/12/2019 Major Power Grid Blackouts in North America and Europe

    31/32

    1539pkMPB- 30

    ! Predisturbance conditions (Sunday, 3:00 am):" total load in Italy was 27,700 MW, with 3638 MW

    pump load

    " total import from rest of Europe was 6651 MW! Sequence of events:

    " a tree flashover caused tripping of a major tie-linebetween Italy and Switzerland (Mettlen-Lavorgo

    380 kV line) at 03:01:22

    " Sychro-check relay prevented automatic and manualreclosure of line due to the large angle (42) across

    the breaker" resulted in an overload on a parallel path" attempts to reduce the overload by Swiss

    transmission operators by network change was not

    successful

    " at 03:21 import by Italy was reduced by 300 MW butwas not sufficient to mitigate the overload of a

    second 380 kV line (Sils-Soazza), which tripped at03:25:22 due to sag and tree contact

    cont'd

  • 8/12/2019 Major Power Grid Blackouts in North America and Europe

    32/32

    " the cascading trend continued and the powerdeficit in Italy was such that the ties to France,

    Austria and Slovania were tripped

    " the outages left the Italian system with a powershortage of 6400 MW

    " the frequency decay could not be controlledadequately by under-frequency load shedding

    " over the course of several minutes, the entireItalian System collapsed at 3:28:00

    ! The blackout affected about 60 million people" total energy not delivered 180 GWh" worst blackout in the history of Italy" power was restored after 3 hours in the

    northern area and during the same day for

    most of Italy