218
IW -IV 1 J GRID CONNECTED INTEGRATED COMMUNITY ENERGY SYSTEM /Q.&S3 COO-4211-3/2 Final Report and Appendices, Volumes 1 and 2, Phase II August 9, 1977-March 22, 1978 MASTER Work Performed Under Contract No. EC-77-C-02-4211 Clark University Worcester, Massachusetts U. S. DEPARTMENT OF ENERGY Division of Buildings and Community Systems -TjacncworTHisDoct

Manual de Gestion

Embed Size (px)

Citation preview

  • IW-IV 1

    J

    GRID CONNECTED INTEGRATED COMMUNITYENERGY SYSTEM

    /Q.&S3COO-4211-3/2

    Final Report and Appendices, Volumes 1 and 2, Phase IIAugust 9, 1977-March 22, 1978

    MASTER

    Work Performed Under Contract No. EC-77-C-02-4211

    Clark UniversityWorcester, Massachusetts

    U. S. DEPARTMENT OF ENERGY

    Division of Buildings and Community Systems-TjacncworTHisDoct

  • DISCLAIMER

    This report was prepared as an account of work sponsored by an agency of the United States Government. Neither the United States Government nor any agency Thereof, nor any of their employees, makes any warranty, express or implied, or assumes any legal liability or responsibility for the accuracy, completeness, or usefulness of any information, apparatus, product, or process disclosed, or represents that its use would not infringe privately owned rights. Reference herein to any specific commercial product, process, or service by trade name, trademark, manufacturer, or otherwise does not necessarily constitute or imply its endorsement, recommendation, or favoring by the United States Government or any agency thereof. The views and opinions of authors expressed herein do not necessarily state or reflect those of the United States Government or any agency thereof.

  • DISCLAIMER

    Portions of this document may be illegible in electronic image products. Images are produced from the best available original document.

  • NOTICE

    This report was prepared as an account of work sponsored by the United StatesGovernment. Neither the United States nor the United States Department of Energy, norany of their employees, nor any of their contractors, subcontractors, or their employees,makes any warranty, express or implied, or assumes any legal liability or responsibility forthe accuracy, completeness or usefulness of any information, apparatus, product or processdisclosed, or represents that its use would not infringe privately owned rights.

    This report has been printed directly from copy supplied by the originating organization.Although the copy supplied may not in part or whole meet the standards for acceptablereproducible copy, it has been used for reproduction to expedite distribution andavailability of the information being reported.

    Available from the National Technical Information Service, U. S. Department ofCommerce, Springfield, Virginia 22161.

    Price: Paper Copy $9.25Microfiche $3.00

  • COO-4211-3/2 Distribution Category UC-97d

    GRID CONNECTED INTEGRATED

    COMMUNITY ENERGY SYSTEM

    FINAL REPORT AND APPENDICES,

    VOLUMES I AND I I

    PHASE I I

    FOR PERIOD

    AUGUST 9 , 1977 TO MARCH 2 2 , 1978

    CLARK UNIVERSITY

    950 MAIN STREET

    WORCESTER, MASSACHUSETTS 01610

    - NOTICE-This report was prepared as an account of work sponsored by the United States Government Neither the United States nor the United States Department of Energy nor any of their employees nor any of their contractors subcontractors or their employees makes any warranty express or implied or assumes any legal liability or responsibility for the accuracy completeness or usefulness of any information apparatus product or process disclosed or represents that its use would not infringe privately owned rights

    PREPARED FOR

    THE U . S . DEPARTMENT OF ENERGY

    UNDER CONTRACT NO. EC-77-C-02-4211.A001

    PREPARED BY

    CLARK UNIVERSITY

    THERMO ELECTRON CORP.

    FITZEMEYER AND TOCCI, INC.

    BOZENHARD COMPANY

    SHEPHERD ENGINEERING

    NEW ENGLAND ELECTRIC SYSTEM

    L. G. COPLEY ASSOCIATES

    * V DISTRIBUTION OF THIS DOCUMENT 13 L~" ::iTF?8'

  • CONTENTS

    Volume I; Final Report

    1. Introduction 12. Institutional Documentation 5

    2.0 Introduction 52.1 Corporate Power 52.2 Interchange Terms 52.3 Financing 62.4 Air Pollution Impact 82.5 Other Environmental Issues 112.6 Building Code, Zoning, and Fire 122.7 Labor Relations 12

    3. Preliminary Design Analysis 133.0 Introduction 133.1 Energy Load Profiles 133.2 Design Options and Final Choice of Engine 143.3 Update of Conceptual Design 20

    4. Design Package 224.0 Introduction 224.1 Mechanical 224.2 Electrical and Grid-Connection 224.3 Architectural 224.4 Utility Tie-in 244.5 Noise and Vibration 244.6 Monitoring 25

    5. Financial Analysis 275.0 Introduction 275.1 Capital Costs 275.2 Fuel and Maintenance Costs 285.3 Comparison with the Conventional System 295 .4 Evaluation of Investment 345.5 Generalization to Other Sites 36

    Volume II: Appendices

    2A Letters on Financing and Utility Tie-in 392B Utility Contract 462C Draft Environmental Impact Assessment 742D Letters on Environment and Codes 1093A Engine Operating Experience and Guarantees 1163B Plant Descriptions 1193C Performance of the Candidate Systems 1234A Design Descriptions for Steam, Fuel, and Fuel

    Treatment Systems 1324B Equipment and Instrument List 1474C Outline Specifications 1524D Electrical Specifications 1604E Architectural Design 1704F Utility Tie-in Specifications 1804G Noise and Vibration Analysis 1865A Project Effort and Capital Cost Analysis for

    Phases III-V Inclusive 1935B Operation and Maintenance Costs 205

    n

  • TABLES

    Volume I: Final

    2.4-1 Annual Air Pollution 9 2.4-2 Peak Air Pollution Rates 9 3.3-1 Performance Characteristics of Diesel Engines .21 4.6-1 Monitoring Equipment 26 5.1-1 Capital Cost Summary 28 5.2-1 Fuel Cost and Heat Credit 28 5.2-2 Maintenance Costs 29 5.3-1 Base Case Assumptions 30 5.3-2 Electricity and Thermal Outputs 31 5.3-3 First Year (1980) Base Case Calculation 32 5.3-4 Sensitivity Analysis 34

    Volume II: Appendices

    2C-1 Rate of Pollutants Produced by Diesel 82 2C-2 Worcester Air Pollution Measurements 90 2C-3 Noise Levels at Clark 91 2C-4 Baseline Sound Data at Clark 92 2C-5 Estimated Air Pollution Impact 99 2C-6 Estimated Peak Rates of Air Pollutants 100 4G-1 AcousticsDesign Criteria 190 4G-2 Noise Source Contributions 191 5A-1 Project Effort and Cost Analysis 196 5A-2 Capital Cost Summary 200 5A-3 Mechanical Capital Costs 201 5A-4 Cost Summary for Phases I-V 203 5A-5 Clark Base Cost and Replication Cost 204 5B-1 Lifetime of Engine Components 207 5B-2 Fuel ImpuritiesLimits and Treatment Costs 209 5B-3 Diesel Engine Operation and Maintenance Costs 210 5B-4 System Operation and Maintenance Costs ' 211

    FIGURES

    Volume I: Final Report

    3.1-1 Electrical and Thermal Outputs of Sulzer Engine....15 3.1-2 Yearly Energy Balance 16 3.1-3 Fuel Savings with Respect to the Displaced System..17 3.1-4 Fuel Use at Clark .'.' 18 4.3-1 Equipment Layout v. 23 5.3-1 Base Case Net Savings 33 5.3-2 Sensitivity of Savings, Sulzer Engine, #6 Oil 35

    Volume II: Appendices

    2C-1 Clark Campus Showing Location of Proposed ICES 77 2C-2 Exhaust Gas Emissions 78 2C-3 Soot Emissions 79 2C-4 Steam Distribution System at Clark. 84 2C-5 Energy Consumption at Clark 86

    (continued) iii

  • FIGURES

    Volume II;

    (continued)

    3C-1 Schematic for Diesel Heat Balance 125 3C-2 Heat Balance: Sulzer, 100% Load 128 3C-3 Heat Balance: Sulzer, 50% Load 129 3C-4 Heat Balance: Superior, 100% Load 130 3C-5 Heat Balance: Superior, 50% Load 131 4A-1 Equipment Layout 134 4A-2 Jacket Ebullient Cooling System 135 4A-3 Fuel Oil System 138 4A-4 Residual Fuel Oil Treatment SystemFlow Diagram...142 4A-5 Key to Flow Diagram Symbols 143 4D-1 Site PlanElectrical 162 4D-2 Floor PlanLighting 164 4D-3 Floor PlanPower 165 4D-4 Power Distribution and Control 166 4E-1 Site Plan 172 4E-2 Floor PlanLower Level 173 4E-3 Floor PlanUpper Level 174 4E-4 East Elevation 175 4E-5 North and South Elevat ions. . 176 4E-6 Building Cross-Sections, East-West 177 4E-7 Building Cross-Sections, North-South 178 4F-1 Site PlanEngineering 182 4F-2 Floor PlanEngineering 183 4F-3 Elevations 184 4G-1 Measured Ambient Noise Levels 189 5A-1 Organizational Chart 195 5A-2 Fuel Treatment Cost vs. Capacity 202

    TV

  • -1-

    1. INTRODUCTION

    Clark University represents an attractive site for demonstration of cogeneration. The principal features of the site are as follows.

    (1) Clark is located in New England, a region that depends on imported oil for most of its electric generation, and has some of the highest electric prices in the nation.

    (2) Clark, with a 1.5 MW peak electrical demand, offers a variety of demand patterns in its 20+ major buildings.

    (3) Clark already has an operating steam distribution system which serves its 12-acre campus.

    (4) Clark is serviced by the Massachusetts Electric Company, an organization that has taken an active and creative interest in cogenera-tion.

    In Phase I of the ERDA Demonstration ICES Program, the team from Clark University, consisting of representatives from the University, Thermo-Electron Corporation, Fitzemeyer and Tocci, and Massachusetts Electric, reported the following results:

    (1) The system of choice for ICES demonstration at Clark is a diesel generator sized at about Clark's peak electric demand.

    (2) In order to avoid placing additional demand on scarce light-oil sources, such a generator should burn #6 oil if at all possible.

    (3) Through Massachusetts Electric's agreement to purchase excess power at about the cost of displaced fuel, the system can run at nearly full capacity the year round, sell 40% of its output to the utility, and receive backup as needed from the utility.

    (4) Under a variety of possible financing plans and reasonable projec-tions of fuel costs the system will deliver for Clark an internal rate of return of 15-20%.

    (5) There appear to be no institutional or environmental problems that would prevent operation of the system as planned.

    In this report we provide an update on a number of issues that were incompletely resolved in the Phase I report.

    In Section 2 we provide additional documentation on institutional

  • -2-

    issues involved in the proposed demonstration at Clark, particularly as follows. (1) We are assured through inquiries at the State Attorney General's Office

    that Clark, a non-profit institution, will be able to sell power to the utility without affecting its tax-exempt status. The principal reason for this finding is that the sale of power is considered "incidental" to the production of heat.

    (2) We now have an agreement with Massachusetts Electric that both we and the utility can support. The agreement provides for power on a standby

    basis to Clark when the ICES is not generating; it also describes terms for sale of power by Clark to the utility.

    (3) We are assured that we can obtain adequate financing through a 6-7% interest HEFA tax-exempt bond issue. This makes the proposed ICES financially viable for the University. In addition we are eligible for federal loan pro-grams at 3% interest rate, and are currently exploring these with help of Worcester's Congressman Early.

    (4) We have had new worries about air pollution because of the introduc-tion of short-term standards for nitrogen oxide concentrations; however, it now appears that the plant will not violate either new or existing federal and state regulations.

    (5) There are no other serious environmental problems. (6) There are, in addition, no problems with building codes, zoning and

    fire ordinances.

    In Section 3 we provide a preliminary design analysis that clearly defines our choice of engine and provides revised operating data in light of additional load profile studies. In particular we now find:

    (1) A Sulzer #6 oil burning 1405 KW diesel with ebullient cooling and exhaust gas heat recovery is the system of choice.

    (2) The engine and heat recovery system should be housed in a separate building in close proximity to the existing boiler and steam distribution center.

    (3) As a result of summer load studies we have determined that the engine as specified can be operated with a capacity factor of 90%, instead of the Phase I estimate of 85%.

    In Section 4 we present a summary of our preliminary design package. This includes sufficient detail to make a much more reliable estimate of capital and construction costs. Major items included here, but not previously, are a fuel treatment facility, preliminary design of a building, preliminary layouts of equipment, including a cooling tower on the roof of an existing building.

  • - 3 -

    In Section 5 we provide a financial analysis based on our design package. In comparison to Phase I , capi ta l costs have increased considerably due to the addition of a separate building, fuel treatment, and the use of a more expensive #6-oil-burning engine. These costs are in part cancelled by lower cost of #6

    o i l , and by the more favorable summer heat load picture that has emerged since Phase I . As a resu l t we find that the project continues to be f inancial ly viable . Specif ical ly, we project a 9.4 year payback period, on a t o t a l Clark investment of $1.5 mill ion. Total cost , including DOE-financed f eas ib i l i t y studies and demonstration aspects, i s projected at $2.2 mill ion. Replication cost for a f a c i l i t y l ike Cla rk ' s , but without f eas ib i l i t y and demonstration aspects, i s projected at close to Clark 's cost of $1.5 mill ion.

    Thus we find, as before, that the Clark ICES system i s a generally a t t r a c -t ive project . From a national point of view i t c lear ly demonstrates grid con-nected cogeneration through the sale of 40% of Clark's output and a net fuel saving of 30%. From Clark 's point of view i t serves as a sound investment and a useful hedge against inf la t ion and future changes in u t i l i t y ra te s t ruc ture .

    The resolution of the Clark Trustees on project continuation, as voted at a meeting of the Executive Committee on March 15, 1978, reads as follows.

    The Trustees have examined the results of the ICES study and are encouraged by its findings. In order to continue progress and to protect the interest of DOE and the University in this project, the Trustees take the following actions: VOTE #1; To authorize the Treasurer 1) to seek preliminary approval from HEFA

    to borrow up to $1,750,000 (includes reserve requirements and expenses of $250,000) in order to construct ICES servicing the Clark Campus, P) to make appropriate applications to the federal government for subsidized loans or grants, and 3) to negotiate with DOE for selection of the University as a demonstration site, for an ICES.

    VOTE #2: To authorize from unrestricted capital gift income $15,000 to be used as up-front planning money during the early stages of Phase III, until all pending issues are fully resolved. Expenditures shall'be approved by the President upon the recommendation of a special subcommittee which will include &ie co-chairmen of the Board of Trustees, Chairman of the Finance Committee, the University's Counsel, the Treasurer, and the Dean of Academic Affairs.

  • -4-To prepare for a final decision to go ahead with the project Ce-xpected

    late August, 1978), the University will apply this summer for financing under two federal energy conservation loan programs. Clark will also seek the necessary permits from the Massachusetts Department of Environmental Quality Engineering, and will begin those aspects of final design necessary to ensure that construction can begin June, 1979.

  • -5-2. INSTITUTIONAL DOCUMENTATION

    2.0 Introduction

    In Phase I we identified several institutional issues which had to be resolved. These critical issues were (1) whether the University has the power to sell electricity, (2) whether we could make suitable arrangements for interchange with Massachusetts Electric that would be approved by the Massachusetts Department of Public Utilities (DPU), (3) whether we could find a suitable mode of financing the system, and (4) whether the plant would meet environmental and zoning requirements. These issues are resolved (or nearly resolved).

    2.1 Corporate Power

    We had initially hoped to obtain a formal ruling from the Attorney General on whether the* University as a charitable institution has the power to sell electricity. However, since we are not a government agency, we are not entitled to a formal ruling. We have instead been given an informal opinion by the division in the Attorney General's office responsible for overseeing charitable institutions. In the opinion of Assistant Attorney General Reedy (letter in Appendix 2A), "the distribution of excess energy to a public utility would be incidental to the primary purposes [of the project], and would not affect the charitable status of the University." According to the University Counsel, Richard Mirick, since this is from the division of the state government charged with supervising the conduct of charitable institutions, it is sufficient assurance that the University's power to sell electricity will not be challenged (see Mirick's letter in Appendix 2A) .

    2.2 Interchange Terms

    Clark and the Massachusetts Electric Company have agreed on terms for interchange along the lines described in our Phase I report. Letters from William Cadigan, President of Massachusetts Electric, and Richard Mirick, University Counsel, appear in Appendix 2A. The agreement is given in Appendix 2B. We plan to submit the proposed contract to the DPU this summer. As the contract is acceptable to both Clark and Massachusetts Electric, we expect DPU approval within 30 days of our submission.

    Key features of the contract are as follows. The contract will be in effect for 20 years, the nominal life of the plant; Clark will have the option of switching to a future cogeneration rate if the terms seem prefer-

  • -6-able. The agreement empowers Clark to use directly as much of the ICES electricity output as Clark needs. Only when the ICES output is insufficient for the Clark demand will Clark purchase electricity from Massachusetts Electric. Clark has two options for purchases, but must choose one for the duration of the contract. One option is simply to use whatever auxil-iary service rate is in effect at the time. At present Clark would guarantee a minimum monthly payment based on its contracted demand and would make all purchases under one of the regular retail rates. Because Massachusetts Electric has informed us that they expect this auxiliary rate to change in the near future and because Clark wished for terms which would be defined over the twenty year life of the contract, Massachusetts Electric has offered Clark a second option. This option would require that Clark pay a monthly charge for distribution capacity based on contracted demand, and pay for all purchases under a retail energy rate, C-22, or the equivalent. The monthly charge would go from $1.00/kw to $2.00/kw in five years, then remain fixed at $2.00/kw.

    When Clark makes more electricity than it can use, the excess will be sold to the utility for a price closely approximating the cost of displaced fuel. This price depends on time of day; thus there will be two prices, one for weekdays from 7:00 A.M. to 11:00 P.M., the other for the remaining times. For convenience, the price will be factored into two pieces, a multiplier times the average wholesale fuel cost. There will be two multipliers, one for peak and the other for off-peak sales. For 1978 Massachusetts Electric has estimated the peak multiplier to be 1.45, and the off-peak multiplier to be 1.25. The multipliers will be reevaluated yearly to take account of changes in the mix of generating costs.

    2.3 Financing

    In Phase I we identified four alternative modes of financing the ICES. These were borrowing from the endowment, a commercial loan, a Health and Education Facilities Authority (HEFA) tax-exempt bond issue, and federal loan programs. We found that the last two possibilities were distinctly preferable, but we were not able to definitely determine their feasibility. At present we can report that we would have been eligible under last year's HUD loan program had we been ready to begin construction soon enough. The HUD program provides loans for investments for the purpose of conserving energy in dormitories and dining facilities. Since about half of Clark's heat and electricity go to dormitories and dining (see Phase I Report,

  • -7-

    Tables 1.2.4-2 and 1.2.4-3), this program could provide financing at 3% for half the project cost. The program has been funded again this year and final regulations should be published very soon. Another program covering all university buildings is administered by the Office of Education; it was not funded last year, but funds have been released for it this year. This program will also make some matching grants. We are prepared to submit applications for either program the moment final regulations are published, early this summer.

    Because federal financing is not certain, we have spent considerable effort in seeking approval for a HEFA bond issue. We have retained an investment broker, Marsom Pratt of Adams, Harkness and Hill, to handle the bond issue. Mr. Pratt is investment counsel to HEFA. In 1976 he developed the successful bond issue for Clark's new Student Activities Center and he is confident that a HEFA bond issue can be developed for the ICES and that it will be approved by HEFA. He recommends that we place the bonds privately, instead of having a public issue. For a private issue, Clark will not need to tie up resources in securing the bonds, and approval and placement will be easier to obtain. We will, however, have to pay a higher interest rate than the 5% we paid on the public issue for the Student Activities Center. The interest charges will not exceed 7% in any event. HEFA approval for the bond issue must come in two stages. We have obtained preliminary approval for the bond issue. Preliminary approval authorizes the preparation of a prospectus for the bond issue. We expect to obtain final approval for the bond issue after a review of the proposed prospectus. The prospectus can, however, be completed only with the preliminary design results of Phase II; consequently, final approval of the bond issue can only be obtained after the completion of Phase II. At the same time Pratt assures us that, with the cost analysis presented in section 5 of this report, there will be no difficulty in obtaining final approval. (See letter from Marsom Pratt in Appendix 2A.)

    Pratt has also suggested the use of the leveraged lease as another mode of financing. This may offer even better terms than the HEFA bond issue. Under this plan an investor would own the facility and lease it to Clark. He

    would be able to offer good terms because he could take advantage of tax benefits, investment tax credit, accelerated depreciation, etc., which do not apply to the University. This mode of financing was used for the Harvard Hospitals' total energy plant.

  • -8-

    To summarize, we feel confident that we can obtain financing through a HEFA bond issue, and are taking the necessary steps to achieve this. We are continuing to pursue two alternative possibilities which might offer even better terms, namely federal loan programs and a leveraged lease. While we do not regard borrowing from the endowment as a satisfactory method of long-term financing, it is technically possible for us to borrow for this pur-pose, and this provides us with enough flexibility to meet unforeseen short-falls.

    2.4 Air pollution impact

    The net effect of the proposed Clark ICES is to increase air pollutant emission in the immediate neighborhood of the University, and to decrease emission at more distant utility power plants. Details are discussed in Appendix 2C, A summary of effects may be read from Tables 2.4-1 and 2.4-2 indicating annual and peak emission rates.

    With respect to published federal standards Worcester is currently a non-attainment area in three pollutants: particulates, CO, and oxidants. Worcester is an attainment area for two other pollutants: SO- and N02. (There are no standards for HC.) For a non-attainment area the Clean Air Act Amendments of 1977 require a permit from local authorities for new sources emitting over 100 tons per year of the non-attainment pollutant. Sources under 100 tons are unregulated. For an attainment area, federal legislation requires that new sources emitting over 250 tons of a given pollutant not affect ambient levels beyond a certain "significant increment of deteriora-tion." Sources under 250 tons are unregulated.

    A glance at Table 2.4-1 shows that under the present definition, all non-attainment pollutants emitted by the ICES are under 100 tons annually, and all attainment pollutants are under 250 tons annually. It is for this reason that we concluded in earlier reports that there is no problem in meeting air pollution standards.

    Very recently, however, it has become clear that the EPA is moving toward setting hourly maximum standards for N0_. It is possible that these could make Worcester non-attainment in N02. At that point our emission of 179 tons of N0_ per year would require us to show that ambient levels produced by the local plant do not materially aggravate N02 levels, especially at "sensitive targets" in the local neighborhood. Demonstration of this would require use

  • -9-

    Table 2.4-1: Annual Air Polluti on System

    Present system Utility boiler Clark boiler System impact

    ICES System Clark diesel Clark boiler Utility boiler System impact

    *may be overestimate

    System

    Present system

    Clark boiler ICES System

    Clark boiler Clark diesel Total

    Annual so2

    36 78 114

    57 56 -22 ii Tabl

    Peak so2

    4^ 0

    3.5 1.8 5.3

    emission

    N02

    25 54 79

    155 39 -15 179

    e 2.4-2:

    emission N02

    3.7*

    3.2* 5.0 8.2

    > in tons

    CO

    -

    24 --

    3A

    Peak

    HC

    0.5 1.0 1.5

    11.2 0.7 -0.3 11.6

    Air Pol

    rate in grams CO

    -

    -0.8 0.8

    HC

    -

    -0.4 0.4

    Particulates

    l.S 3.2 4.7

    0.5 2.3 -0.9 1.9

    Llution Rates

    /second Particulates

    '

    0.02

    0.02 -0.02

    'may be overestimate

  • -10-

    of certain EPA designated computer .modeIs, and interpretation of results ob-tained from these in light of existing hourly maxima.

    In anticipation of the forthcoming EPA hourly maximum standards we have been working with Ed Benoit, Chief of the Central Massachusetts Air Quality District. Benoit has in fact obtained preliminary computer results using the peak emission rates indicated in Table 2.4-2. From these he observed that our boiler plant has nearly as large an impact as the proposed ICES. We have subsequently measured NO emissions from our boilers and obtained values less than 1/4 those in Tables 2.4-1 and 2.4-2; however, these measurements were made while the boiler was burning gas and do not include NO production from bound nitrogen in residual oil. Maximum hourly effects of the combined Clark system on six sensitive targets in the near neighborhood ranged from 50 to 300

    3 3 /igms/m . The peak concentration from the diesel plume is nearly 200 /ug/m .

    3 If the forthcoming EPA standard i s set at 200 jug/ra the project appears to be in t rouble. According to Benoit, who has considerable modelling experience,

    3 200 Aigm/m would place in jeopardy nearly every new NO- source of 100+ tons in urban Massachusetts. Benoit has, however, assured us that we have no di f f icul ty with other a i r quali ty regulations (see l e t t e r dated April 5, 1978, in Appendix 2D).

    Further complicating the picture is the fact that recently, under intense community pressure, the Massachusetts Department of Environmental Quality Engineering (DEQE) has issued an order halting construction of a 22 MWe, six-diesel, total energy plant being built by Harvard University in downtown Boston. The impact of this project, which has total NO- emissions about 16 times our annual amounts, was estimated at 230jug/m hourly maximum for certain "sensitive" targets such as homes for the aged, and hospitals.

    3 Added to ambient hourly maxima of 300 to 400jug/m , the Harvard project was believed to be capable of producing hourly maxima in the range of 500-3 600 iUg/m at certain downtown Boston locations. The principal finding of DEQE Regional Environmental Quality Engineer McLoughlin in the Harvard University case is that existing federal NO- regulations are tqo lax, and allow the possibility of serious health effects. A proper interim safety level, 3 according to McLoughlin, is 200jug/m hourly maximum. It is for this reason that Harvard's project was disallowed.

    3 At present the Massachusetts DEQE interim standard 200 jugm/m will not apply to sources of less than 250 tons annually (see E. Benoit letter dated May 2, 1978, Appendix 2D) and hence the Clark project will not be affected by

  • -li-the interim standard. If Worcester is not in compliance with the forthcoming EPA standard (which will supercede the interim Massachusetts Standard), the Clark project will require review. Benoit believes (April 5, 1978 letter, Appendix 2D) that there will be no difficulty if the EPA standard falls in the

    3 range 470 - 940 jugm/m , now under consideration (March 27, 1978, Federal Register).

    A further change in air pollution regulations is the forthcoming EPA emission standards for diesel engines. These are the responsibility of the diesel manufacturer and so will not affect Clark except insofar as they limit the availability or performance of engines. The EPA draft proposed standard calls for a limit on NO emissions of 6 gms/bhp-hr, to go into effect 15 months after promulgation (Draft Summary of the Recommended Standard of Performance for Stationary Reciprocating Internal Combustion Engines, EPA, March 23, 1978). This can be compared with the emission of 8-9 gms/bhp-hr of the Superior and Sulzer engines and up to 18 gms/bhp-hr of certain diesels. The proposal has generated considerable controversy as very few present-day diesels can meet it without major impairment of performance that, together with the 15-month waiting period, makes it extremely unlikely that emissions standards will cause Clark any difficulty. Sulzer has stated that they could reduce emissions to 7 or 7.5 gms/bhp-hr with only a modest deterioration in engine performance.

    To summarize then, the most sensitive air pollution produced by the proposed ICES is NO . We have good indications that the ICES will comply with all applicable present and future air quality regulations, but we are continuing to watch closely as EPA develops standards for short term NO concentrations and standards for diesel emissions.

    2.5 Other Environmental Issues

    Other potentially deleterious environmental impacts of the ICES are water pollution from the fuel treatment, increased traffic due to increased oil deliveries, noise from the plant, traffic, noise, and air pollution during construction, and changes in the aesthetic character of the campus. It is our judgement that all of these problems are small or negligible.

    Water pollution. Oil treatment effluent will not exceed 18 gallons/ hour. This effluent will contain less than 80 ppm oil, 600 ppm sodium chloride, 70 ppm lead, 50 ppm calcium chloride, 5 ppm potassium, and 50-100 ppm magnesium. This is too small an effluent to affect the operation of the Blackstone Pollution Abatement District or water quality generally. (See letter from Michael Burke, Appendix 2D.)

  • -12-

    Noise. Noise from the plant will not change ambient levels as described in section 4.5 and Appendix 4G.

    Increased oil deliveries. The number of oil deliveries will be increased about 50% from the present 120/year. This will be noticeable on the Clark campus, but not in the adjacent heavily commercial Main Street area.

    Construction. We expect most construction to be concluded while the campus is largely unoccupied during the summer, so that adverse effects will be comparatively minor.

    Aesthetics. As discussed in section 4.3, there has been considerable University concern about the aesthetic impact of adding a large structure to the center of the Clark campus. This concern has recently been resolved by the discovery that we can reduce the building volume by at least 40%; the Clark Trustees now believe that the building can be made to fit in well with the surrounding campus.

    2.6 Building Code, Zoning, and Fire

    We have been assured that the proposed ICES design can meet all building code, zoning, and fire regulations. Final permits can be issued only after submission of final working drawings. (See Appendix 2D.)

    2.7 Labor Relations

    Clark physical plant staff will operate the ICES. The staff have been closely involved in the planning for the ICES and we anticipate no labor-related difficulties in plant operation.

    For the construction of the plant, Bozenhard said that he foresees no problems with local unions. The job has been budgeted for union labor and would be bid by union-affiliated contractors. Present construction labor relations are good.

  • -13-

    3. PRELIMINARY DESIGN ANALYSIS

    3.0 Introduction

    Our preliminary design analysis incorporates a number of changes from Phase I. We have found that our summer thermal demand is not quite what we had estimated, and the correction will enable the ICES to generate some-what more heat and electricity. We have decided to locate the generating system in a new building outside Jonas Clark hall. Most important, we have found a diesel system which meets essentially all of the requirements we defined in the Phase I analysis. It is a Sulzer engine, Model 8 ASL 25/30; it is ebulliently cooled, burns //6 oil, and produces about 1400 KW of elec-tricity. With the #6-burning engine, we need one more subsystem for the conceptual design, a fuel treatment system.

    In the next section, 3.1, we present our new results on thermal demand, and describe the electrical and thermal outputs of the new diesel. In sec-tion 3.2 we review the Phase I choice of system and then give our reasons for selecting the Sulzer engine and the new location. In section 3.3 we describe the changes needed in the conceptual design to accomodate the new engine and location.

    3.1 Energy Load Profiles

    The electricity load profile presented in our Phase I report was based on several years of recorded data. Since our recent data is consistent with the previous records, we have not altered our estimated electricity load profile. The profile contains an estimated contribution from the new gym; the estimate is consistent with preliminary data from the first month the gym has been in use.

    The thermal load profile presented in the Phase I report used estimated summer thermal demands. We now have data on thermal demand for this summer and this changes somewhat our previous estimate. We have found that at present summer thermal demand is considerably more uniform than we had estimated. As with the electrical profile, we have estimated the contribution of the new gym and our estimate is consistent with preliminary data. The added demand in summer nights means that we will be able to operate the ICES, at part load, for many summer nights, and the overall output of the system will be somewhat greater than our previous estimate.

  • -14-

    We repeat the electric load profile and present our new thermal load profile in Fig. 3.1-1. Shown on these profiles are the electric and thermal outputs of the Sulzer 1405 kw engine. Except for summer nights and brief periods for maintenance, the engine operates at full load continuously. The overall fuel saving we expect is about 300,000 gals/yr oil saved by Clark and the electric utility. Notice that the grid-connection, in addition to its other benefits, gives rise to about 40% of those savings.

    We show fuel consumption and savings on an annual basis in Figs. 3.1-2, 3.1-3, and 3.1-4. Fig. 3.1-2 compares Clark's annual heat and electricity demands with the ICES output. Fig. 3.1-3 shows the total annual fuel savings produced by the ICES (approximately 8000 barrels/year). Fig. 3.1-4 shows the increase in fuel use at Clark (approximately 10,000 barrels/yr) illustrating why there is a local increase in air pollution, but a system-wide reduction in particulate and SO- emissions.

    3.2 Design Options and Final Choice of Engine

    We have decided to put the generating plant in a new building adjacent to the boiler room in the basement of Jonas Clark hall. This location is preferable to a location inside Jonas .Clark, because (1) it avoids major problems with noise and vibration insulation; (2) it does not eliminate classroom space; (3) it will be much easier to make the demonstration system accessible and attractive for public viewing. The disadvantage of the choice is that it adds significantly to the capital cost of the project (see section 5.1 and Appendix 5A). We believe that the advantages more than make up for the extra cost.

    In Phase I we concluded that the optimum ICES for Clark would use a single diesel engine, ebulliently cooled, burning residual oil, with a max-imum electricity output of about 1500 KW and a maximum recoverable heat out-put of about 4 million Btu/hr. We reached this conclusion after examining a variety of diesel engines in various configurations along with representa-tive steam turbine systems and gas turbine systems. We have reviewed that analysis for this report and found it still correct. Steam turbines small enough for Clark's heat demand simply do not make enough electricity to finance them. Gas turbines suited to our size burn distillate oil and have slightly poorer performance characteristics than comparable light-oil-burning diesels. Ebullient cooling is necessary because the University has

  • -15-

    Fig. 3.1-1: Electric and Thermal Output* of Sulzer Engine

    T

    . 1500

    1000T u o

    500 -

    2000 4000 6000 8000 Annual Hours at Power Level P or Greater

    Sfl 10 Heat Output of Boiler

    ' / / / / / / / / / A y f / / / / /Heat Output of p

    / / / / / / iesel

    2000 4000 6000 8000 Annual Hours at Thermal Level H or Greater

  • 0

    -16-

    ELECrRICtTy (Million Ku)h) SO 100 (SO ZOO ZfO 300

    1 1 1 1 ClourK electric dema.nd

    T T

    HEAT = \\o B B+u

    y ELecrRrciry = 6.9 MKU/K

    I 1 I HEAr = 77 B&tu -i

    K&f&tt

    t ^ ^ ^ ^ 2 ^ 4 eiecrfticfTy = //.4 Mkuk

    6.5* 4.5 Clark Heat demand Q.H

    \ \ \ \ \ \ \ \ I L 20 *ID 60 So 100

    HEAT (Billion Biro)

    CoVvENVOhJM ICES

    Fig. 3.1-2. Yearly Energy Balance

  • 17-

    o $* 1

    Ar aARK

    FUEL 10 \

    (THouSAMPS ts 1

    of BARRELS) ZO 2f i r

    Ar u r i u r y

    7/7 h 1

    : . . s. * * r

    77/7

    1 1

    31% FoL SAVING.

    1 ko 8o Ho

    FUBL (BBtu) ItO

    Fig. 3.1-3. Fuel Savings with Respect to the Displaced System

  • 0 FUBL (IOOO'
  • -19-

    a steam heating system and it would be prohibitively expensive to make the modifications needed for heating some buildings with hot water. There are two advantages to burning residual oil; it is significantly cheaper, and it is in the national and regional interest not to add to the pressure on the demand for light oil and gas. Grid-connection obviates the need for multiple engines,as we don't have to follow Clark's electrical demand and as we are not considering engines large enough to require extensive varia-tion of heat output. Finally, the size of the generating system is fixed by economic considerations. While it is profitable to sell excess electricity to the utility, it is not sufficiently profitable under the present terms to finance capacity which is solely for exports. Thus the optimum generator will produce approximately as much electricity as will meet Clark's peak electrical demand.

    In Phase I we made our analysis using a diesel generating system which met all of the above requirements except for one; the engine burned only distillate oil, not residual oil. Since then we have identified two candi-date diesels of the right size which can burn residual oil and be cooled ebulliently. These are a 1400 KW engine made by Sulzer, model 8 ASL 25/30, and a 1500 KW engine made by Cooper Bessimer, Superior model 40-X-16. The Sulzer engine is normally water cooled, not ebulliently cooled; however, the Sulzer Company assures us that the alterations are minor ones and that they are happy to maintain their standard one-year guarantee. The Superior engine normally burns distillate oil; the manufacturer, Cooper Energy Systems, is willing to modify the engine to burn residual oil. They too will maintain their one-year guarantee, with the proviso that the fuel entering the engine be carefully monitored to ensure strict limits on sodium and vanadium in the fuel.

    Since both manufacturers are confident that the modifications will not impair the performance of the engines and since they will guarantee the engines, we feel that both engines are viable options. Since they offer a significant economic advantage over the distillate-fired engine, we would prefer one of them as the generator for the grid-connected ICES. It is worth noting that, according to Thermo-Electron, both manufacturers have thoroughly competent field service representatives. Sulzer'^ U.S. service is performed byGolten Marine, Brooklyn, New York, who have worked many years on residual-burning marine diesels. Superior has its own field service team which also has much experience.

  • -20-

    We chose the Sulzer engine in preference to the Superior for the follow-ing reasons. (1) We believe that the burning of residual oil is a more sen-sitive modification than the change to ebullient cooling. Sulzer has both laboratory and field experience with burning #6 oil in that engine. That experience is summarized in Appendix 3A. (2) Sulzer places slightly less stringent limits on vanadium and sodium than Superior. (3) The Sulzer engine gives a slightly better return on investment (see section 5.3). (4) The Sulzer engine is smaller and will be easier to install.

    Each of these is a small consideration, but taken together they lead to a preference for the Sulzer engine. This preference could be reversed by a continuing decline of the dollar relative to the Swiss franc, which would make the Sulzer still more expensive than the Superior engine.

    3.3 Update of Conceptual Design

    The conceptual design section of the Phase I report has to be modified to take account of (1) the new choice of diesel engine, (2) the need for a fuel treatment system for //6 oil, and (3) the decision to place the system in a new location.

    In Appendix 3B we give a detailed description of the two candidate 116-burning engines, Sulzer and Superior. The #6 oil engines differ from the //2-burning engine described in Phase I in requiring a #6 fuel treatment system and a separate set of ill oil storage and day tanks for starting and stopping. The steam and electrical systems are the same for all engines. In Appendix 3C we present details of their performance, including heat balances at 100% and 50% loads. Engine performance deteriorates only slightly down to 50% load; it falls off rapidly for lower loads. Performance characteristics at 100% load are summarized in Table 3.3-1. Heat and electric outputs of both engines are similar. Because #6 oil is cheaper and is the fuel now used in the boiler system, the //6-burning engines have appreciably lower fuel costs, about 5.5 mills/kwh less than the //2-burning engine described in Phase I.

  • -21-

    Table 3.3-1: Performance Characteristics of Diesel Engines

    Sulzer Superior

    Fuel Maximum Electrical Output Thermal Output

    Low pressure steam High pressure steam

    Electrical Efficiencies Thermal Efficiencies Heat Pate Incremental Heat Rate with

    Heat Credit

    #6 1405 kw 4.0xl06 1.3xl06 2.7xl06 34% 39% 10,010

    6,110

    Btu/hr Btu/hr Btu/hr

    Btu/kw

    Btu/kw

    #6 1500 kw 5.3xl06 2.5xl06 2.8xl06 31% 43% 11,060

    6,260

    Btu/hr Btu/hr Btu/hr

    Btu/kw

    Btu/kw

  • -22-

    4. DESIGN PACKAGE

    4.0 Introduction

    The ICES has the following basic components: mechanical, including engine, generator, heat recovery, and fuel supply; electrical, including lights, motors, and grid connection; architectural; tie-in with utility system; noise and vibration control; and monitoring. We describe our preliminary design for each component briefly and refer to the appendices for more detail.

    4,1 Mechanical

    The major mechanical items are the diesel engine and generator, jacket heat recovery system, exhaust heat recovery system, fuel supply system, and fuel treatment system. Engine performance is described in Appendix 3 C The design, control and operation of the other mechanical systems are described in detail in Appendix 4A. Appendix 4A also gives key pressure drops showing that the system design is comfortably within manufacturers' tolerances.

    Equipment lists including design criteria form Appendix 4B. Appendix 4C gives outline specifications for all major mechanical equipment.

    4.2 Flectrical and Grid-Connection

    The electrical design has to meet the following demands: provision of adequate lighting to the new building under normal and emergency conditions, operation of motors for a large number of mechanical components, and com-pliance with Mass. Electric requirements for the grid-connection. The equip-ment needed to meet each of these demands is described, with outline specifi-cations, in Appendix 4D.

    4.3 Architectural

    The architectural design has been constrained in two ways. First of all, it has to provide adequate space for all ICES equipment. Our equipment layout is shown in Fig. 4.3-1. Second, since the building must be located near the focal point of the campus, it must not intrude too much on the open space that is available, and its design must be compatible with the neighbor-ing structures, including Jonas Clark Hall, the Goddard Library, and the new Goddard Memorial. We show a preliminary building design in Appendix 4E. A number of the Clark Trustees and other members of the Clark community felt that this building would not be satisfactory because of its mass, particularly

  • -its'.

    v-? o p ra O' o

    t j r^romMF M M

    I I noun

    1 t l

    4> My*ra*n, -

    _Lt-

    CBKMTM CI*TdX(*t*U.

    S ^ FT

    7 \ -+K-

    M3TOA COMTAOL PRMEL. 1

    -t^ EkKAU5T SHEKEL

    ",. T

    ecus re 3 ' I 3 " s ~ - f f / IJUST P-_*MTS

    t^TtT"

    7

    W

    ft=i-M>aiMMU

    0> INLET OJR QOCT

    ET rrr llm

    L337 JUCfttT VjtR IftU l 5 / l y HEAT ElCHMUD- I 1

    -ET SI 1 I JLCKE7 WTt

    / / REKHmT MOURE. I CL-x^OLJtc

    t-a.

    ^

    U

    =E*

    k- ZJf at i

    Figure 4.3-1 Equipment Layout

    -23-

    ^ ^ ? -JACKET ' - > OKtl*

    r - i ~ - ^ vaju=ti

    A-A

    wSSBTcTJJSricTrTCBJf C LARK UNKERSfTY. WOROCSTER.

    EQUMCHT ARRANGEMENT

    h r r- hsrf r i-

  • -24-

    its height. The height of the building had been determined by the need to provide adequate clearance over the exhaust gas run shown in Fig. 4.3-1. We have recently ascertained that a straight exhaust run would be possible from either the Sulzer or the Superior engine at little or no additional cost. By lowering the waste heat boiler a corresponding amount we can save about 10 feet in the height of the building. The new height would then be approximately 10' above grade on. the west side of the building and 20' above grade on the east side, an overall reduction in building volume of about 40%.

    Since the new height is at the top of the indentation shown in Figures 4E-.4 through 4E-7 in Appendix 4E, a new design for the building envelope is necessary. The Trustees feel, however, that a threshold has been crossed with the new dimension, and that it will be possible to make.a new design that fits well into that part of the campus.

    4.4 Utility Tie-In Since the proposed Clark ICES is a retrofit onto an existing heating

    plant we have to take account of the existing heating, fuel, and water lines, and, in some cases, alter routings for these. The basic requirements are the following: steam from the jacket cooler must be tied to.the existing 15 psig steam lines; steam from the waste heat boiler must be tied to the existing 125 psig lines; residual oil must be supplied to the diesel from the existing oil tanks. A new light oil fuel tank and distribution system must be supplied for starting and stopping the diesels. Details of the tie-ins are given.in Appendix 4F.

    4.5 Noise and Vibration

    Noise and vibration are critical issues for the Clark ICES since the facility is to be located in the center of the Clark campus and since it will be in a building attached to Jonas Clark Hall, a major four-story classroom building. There are some helpful circumstances. Jonas Clark is a 90-year-old building with 18" thick brick walls, and the existing heating plant in the basement has had adequate noise and vibration isola-tion. Appendix 4G gives an outline of our considerations on noise and vibration. The present ICES design will meet our design objective of making no significant increase in ambient noise levels anywhere the campus is used.

  • -25-

    4.6 Monitoring

    We have made a preliminary determination of the type of monitoring that

    would be desirable in Phase VI. Subject to the recommendation and consent of

    DOE, our objectives are as follows.

    (1) Monitor air pollution impact, Both the source emission of

    the boiler and ICES and ambient levels at Clark University are of interest. The

    Massachusetts DEQE currently samples

    ambient particulate and SO- levels at Clark. Complete information would

    require the addition of ambient CO and N0 2 sampling, as well as source measure-

    ments of particulates, S0_, CO, and NO-. (Though 0_ is an air pollution

    problem, it cannot be simply related to sources and is thus not proposed

    for monitoring.)

    (2) Monitor the heat of combustion of residual oil. The heat of combustion

    of residual oil varies widely. Accurate heat balance calculations require

    knowledge of this variation.

    (3) Monitor chemical impurities in residual oil. Diesel engines are ad-

    versely affected by sodium and vanadium impurities in oil. To check whether

    our fuel treatment plant is working properly and to obtain accurate information

    on residual oil operating costs, it is important to measure these impurities

    on a routine basis before and after fuel treatment.

    (4) Monitor performance of diesel engine. Long term system evaluation

    requires a continous record of useful heat and electrical output of the ICES.

    This may be done by metering fuel and water feed lines.

    (5) Monitor sector heat loads. Optimum load balancing between electric

    and heat loads requires knowledge of sector heat demand within the university.

    Sector heat demand may be measured by metering condensate return for six

    divisions of the University.

    The preliminary cost estimate is given in Jable 4.6-1.

  • -26-

    Table 4.6-1: Monitoring equipment

    Monitored variable Method Equipment Cost

    Annual opera-ting cost*

    Air pollution, ambient

    particulates

    so2 NO 2 CO

    Air pollution, source

    particulates

    so2

    N02 CO

    Heat of combustion

    Engine performance

    fuel use

    heat rate

    Sector heat load

    Fuel contaminants

    Sulfur content of fuel

    periodic sampling by State

    periodic sampling by State

    periodic sampling by Clark $11,000

    periodic sampling by Clark $2,000

    periodic sampling by Clark $3,000

    periodic measurement on fuel by Clark periodic sampling by Clark $ 8,000

    periodic sampling by Clark

    periodic measurement by Clark -

    Continuous metering of fuel '10,000

    Continuous metering of water| feed line.

    Continuous metering of condensate return from six heating sectors $17,000

    Monitoring: vanadium and sodium content in oil,. plus other heavy metals

    Monitor percent sulfur

    2,000

    $500

    $500

    $500

    $500

    $500

    $500

    $500

    $500

    $500

    500

    500

    Totals $53,000 $5,500

    Operating cost is based on hiring students of analytical chemistry and physics to work under faculty direction. .'.

  • -27-

    5. FINANCIAL ANALYSIS

    5.0 Introduction

    In their November evaluation of the proposed ICES, the Clark Trustees agreed to the following investment criteria:

    (1) The ICES should be 100% financed from savings, using an external source of capital.

    (2) The expected payback period, including principal and interest should be 10 years or less.

    (3) There should not be large risks associated with uncertainties in future economic conditions.

    In November 1977 we showed that the proposed ICES met these requirements. At this writing, after a considerably more detailed analysis, and despite significant changes in some economic parameters, we confirm this conclusion.

    We discuss capital and operating costs in the next two sections. In Section 5.3 we compare the ICES with the conventional system and show that the payback period is 9.4 years and the internal rate of return is between 14 and 15%. We also discuss the sensitivity of our model to various assumptions about key parameters, and conclude that the expected variations are acceptable: e.g. the extreme bounds of the payback period are 15 and 5 years, respectively. In Section 5.4 we discuss other features of the ICES which make it an attractive investment for Clark. In Section 5.5 we discuss the generalization of our results to other sites.

    5.1 Capital Costs

    Capital costs for two systems, the Sulzer 1405 KWg engine and the Superior 1500 KWe engine are summarized in Table 5.1-1. Detailed cost breakdowns are given in Appendix 5A. The total capital cost to Clark, beginning with phase III is $1,460,000 for the Sulzer based system. In addition we expect to request DOE to fund the following demonstration capital cost items.

    (1) Grid-connection at about $41,000, as per the original RFP. (2) Monitoring equipment at about $53,000, as per the original RFP. (3) Demonstration-related aspects of the power plant building, providing

    accessibility to the public, at about $28,000. (4) Fuel treatment system, at about $95,000.

  • -28-

    Table 5.1-1: Capital Cost Summary ($1000s)

    895 287 60

    223 1,465

    41 53 28 95 217

    823 287 60

    223 1,393

    41 53 28 95

    217

    Item Sulzer Engine Superior Engine Equipment and mechanical work Civil Work Electrical work without grid connection Engineering costs Total cost to Clark (proposed) Grid Connection equipment Monitoring equipment Demonstration civil costs Fuel treatment Cost to DOE (proposed)

    The first three are straightforward outgrowths of the present demonstra-tion program. The fourth is discussed in more detail in Appendix 5A. We believe that fuel treatment should be considered a demonstration cost, at least in part, because sodium (accounting for most of the capital cost) is a regional problem only, and because there will be major economics of scale when use of heavy oils in engines becomes widespread. For example, a fuel treatment facility of ten times the capacity would only cost about twice as much.

    5.2 Fuel and Maintenance Costs Fuel costs with heat credit for the two candidate engines are evaluated

    in Table 3.3-1 and Appendix 3C. They are summarized in Table 5.2-1: Table 5.2-1: Fuel cost and heat credit (mills/kwh)

    Engine Fuel cost Heat credit net fuel cost Sulzer 1405 KW 257o 9~77 T O Superior 1500 KW 27.7 12.0 15.7

    We constructed Table 5.2-1 assuming that the price of #6 oil to Clark 80 would be $2.50/106 Btu. Maintenance costs for the three engines are summarized in Table 5.2-2,

  • -29-

    Table 5.2-2: Maintenance Costs Item

    Diesel engine Fuel treatment Miscellaneous

    TOTAL

    Cost per kilowatthour

    Yearly Cost Sulzer $42,500 3,800 9,000

    $55,300

    5.6 mills

    Superior $41,400 7,100 9,000

    $57,500

    5.5 mills

    The derivation of these cost estimates is given in Appendix SB. The estimates include diesel manufacturer's recommended maintenance and cost experience, chemicals for fuel treatment, and safety margins. The miscellan-eous items include the generator, waste heat boiler, fuel treatment system, pumps, etc. A detailed discussion of fouling of the waste boiler is given in Appendix 5B.

    5. 3 Comparison with the Conventional System In Table 5.3-1 we list the base case assumptions we have made about costs

    which are used to compare the grid-connected ICES with the conventional system. We assume that the ICES is completed at the beginning of 1980, and that all costs including capital costs excalate at 6% per year from their values today. Because we assume a base cost of money of 6%, it does not matter when individual capital cost items are purchased.

    In Table 5.3-2 we list the energy output of the ICES, appropriately divided into Clark usage and Clark sales. These numbers are taken from the energy outputs described in Section 3.1. With this we may compare the costs of the ICES with conventional system costs, as shown in Table 5.3-3. It is seen that the Sulzer system has a first year operating savings of $162,000, and a net savings after payment of financing costs of $20,000. By the tenth year these savings project to approximately $240,000 and $100,000 respectively in constant 1980 dollars. The present estimates are little different from those obtained in November, as shown in Fig. 5.3-1.

    We have examined the sensitivity of the projected savings to the values of our base case parameters. In Table ; 5.3-4 we list the key parameters and the sample variations we have used to test the sensitivity of the savings. Figure

  • -30-

    Table 5 .3-1 :

    Variable

    Base case assumptions (1980 s tar t -up)

    Value -

    Rate of inflation Price of fuel (anticipated) #2 oil #6 oil

    Prices of electricity (anticipated) Purchased by Clark Sold by Clark, weekdays 7 A.M. - 11 P.M. Sold by Clark, other Distribution capacity charge: first year:

    after 5 years: Retail rate structure multiplier

    Plant lifetime Clark electric demand . Conventional boiler efficiency

    6%/VT

    $3.00/MBtu $2.50/MBtu

    4.7*/kwh 2.7*/kwh 2.4*/kwh $18,000 $36,000 1.2

    20 years 6.9xl06 kwh/yr

    75%

  • -31-

    Table 5.3-2: Electricity and Thermal Outputs

    ELECTRICITY 1. Clark total demand 2._ Clark demand supplied by diesel 3. Clark demand supplied by purchases 4. Diesel-produced energy sold to utility 5. Total production by diesel 6. Maximum possible production by diesel 7. Capacity factor 8. Outages for maintenance and certain

    summer nights 9. Operation at de-rated power level

    (average 65% full load) 8%

    FUEL SAVINGS 12. Savings at Clark plus savings at utility

    6.9xl06 6.5xl06 0.4xl06 4.6xl06 U.lxlO6 12.5X106

    90%

    6%

    kwh kwh kwh kwh kwh kwh

    HEAT 10 11. Clark demand supplied by diesel 3xl010 Btu 10. Clark total demand 11x10 Btu

    10 due to reduced generation 4x10 Btu

  • -32-

    Table 5.3-3 FIRST YEAR (1980) BASE CASE CALCULATION

    Sulzer Engine

    A. B. C. D. E. F. G. H. I. J. K. L. M. N. 0.

    Capital Cost Interest Rate Annual Capital Cost ($K) Annual Fuel Cost Annual 0 M Annual Heat Credit Operating Cost (D + E - F) Conventional Electricity Cost Clark Sales Purchases Total Credits (H + I - J) Net Operating Savings (K -Net Savings (L - C) Payback (years) Internal Rate of Return

    G)

    $1,650,000 6%

    141,000 278,000 70,000 108,000 240,000 326,000 114,000 38,000 402,000 162,000 21,000 9.4 14.5%

  • .-33-

    1988 VeAfl

    MO

    Fig. 5.3-1:Base case net savings expressed in constant and current dollars.

  • -34-

    5.3-2 shows the variation of the Sulzer engine savings with each of the changes. The total variation is taken to be the square root of the sum of the squares of each individual variation. The savings are always positive, even the total variation; hence the risk inherent in the ICES investment appears acceptable.

    Table 5.3-4: Sensitivity Analysis Key parameter Base value Variation tested

    Efficiency of Clark Boiler 0.75 0.85 Interest rate on loan 0.06/yr 0.03 - 0.07/yr Retail rate structure multiplier 1.2 1.35 rate of fuel price escalation 0.06/yr 0.0 - 0.12/yr Additional credit for import 0 0.3 $/kwh Mis-estimate of capital costs 0 $200,000 Inflation rate 0.06/yr 0.03 - 0.09/yr

    5.4 Evaluation of Investment

    The anticipated 15% internal rate of return with the reasonable assurance of positive net savings is enough to make the grid-connected ICES an attrac-tive investment for Clark. In addition, as pointed out by the University busines? officer, L. Landry, the investment in the ICES is a hedge against the inflation of energy costs. If about half of the electricity generation costs are fixed a s capital costs, only the remaining half are subject to inflation. Thus the costs using the ICES will rise much more slowly than costs for the conventional system as oil prices go up. Of course, costs would decline less rapidly if oil prices dropped, but we consider that much less likely. Furthermore, by generating most of its electricity, the University would be almost completely insulated from unfavorable changes in electricity rates. It is certain that electricity rates will change in the next year, as the DPU has required utilities to introduce time-of-day rates. It is not certain that the changes will be unfavorable to Clark, but it is likely. The University now benefits from sharply declining block rates and there is both state and federal pressure for flattening rate structures. Furthermore, the University does not have much flexibility for shifting more electric use to the nighttime and so it could be hurt by very high peak rates.

  • -35-

    200

    to u id O O oo C71

    G at J (A C o o 10 bo c

    H

    Cd CO

    0> z

    loo

    too-

    boiler efficiency

    increased credit for export of power

    0.3*/kW]

    interest rate

    rate struct, multiplier

    oil price escalation per year

    capital cost

    $200,000 ,' under ,'^ /'/. run "~*0 //

    overrun

    inflation rate

    total variation (r.r>.s) (excludes . rate struct*

    80 90/80 90/80 90/80 90 YEAR

    Fig. 5.32: Sensitivity of savings for the Sulzer engine burning #6 oil. Base case is shown as solid line, variation by dotted line. The variation used is defined in Table 5.34.

    a

  • -36-Thus we consider the ICES an attractive investment on two grounds. It

    offers a decent rate of return with only modest risk, and it helps protect the University from potential unfavorable changes in energy prices. Along with these benefits Clark would benefit significantly from being a demon-stration site. The demonstration would give Clark national visibility and would give a major boost to our research and teaching in energy studies.

    5.5 Generalization to other sites The analysis of the previous two sections shows that the proposed ICES

    is a reasonable investment for Clark University at this point. It is interesting to consider how important the DOE contribution is to this conclusion. There are two aspects to this question. (1) How big an effect d o e s the DOE contri-bution have on the economic evaluation of the proposed plant? (2) How significant has DOE sponsorship been in attacking and removing institutional barriers, and other first-of-kind costs?

    Our estimate, given in Appendix 5A, is that Clark's base capital cost is only $30,000 to $125,000 lower than the cost to a similar facility planning to duplicate the Clark system. Because of Clark's unusual architectural needs Clark's base capital cost is $100,000 to $200,000 less than it would cost Clark to design and build the plant without DOE participation. All of these numbers are within the range of uncertainty of capital costs considered in our sensi-tivity analysis.

    The answer to the second question is that DOE participation has been essential to Clark's resolution of most institutional issues, and hence Clark's willingness to continue the project. We have repeatedly found in dealing with Massachusetts Electric, with the Department of Public Utilities, with the Attorney General, and most recently with the Department of Environmental Quality Engineering that Clark's case represented a first-of-a-kind test case. It is quite clear that under these conditions the Clark trustees would soon have lost heart had it not been for the support of DOE. In addition it is unlikely that Clark would have been prepared to make extensive engineering comparisons of alternative systems before knowing that the project was feasible, yet these comparisons were essential in finding the most suitable configuration for a facility like Clark.

    Assuming, then, that the Clark ICES is built, we believe that a number of important precedents will have been established which will make the installation of subsequent facilities considerably easier. The technical comparison of

    ,

  • -37-

    system alternatives can be applied with, minor alterations to a large number of facilities resembling Clark, and Clark's experience in negotiating a contract with our electric utility, and coping with environmental and legal obstacles, will at least suggest a number of short cuts. We hope to make the Clark ICES even more useful by carefully documenting its performance, its impact on the utility and its environmental effects.

  • -38-

    /

    VOLUME I I

    APPENDICES

    h

  • -39-

    Appendix 2A

    Letter on Financing

    from

    Marsom B. Pratt

    Senior Vice President

    Adams, Harkness and Hill, Inc.

    and

    Letters on Utility Tie - In

    from

    Mary Joann Woods Reedy Assistent Attorney General Commonwealth of Massachusetts,

    Richard W. Mirick University Counsel

    (two letters)

    and William Cadigan

    President Massachusetts Electric Company

  • -40-

    sldfiins. Jlcirknoss 6Hill. inc. MEMBER NEW YORK ROsrC 'N t a n ASH mCA-4 'ASSOC STOCK r x C H A N C . l S

    5 5 COURT STREET B O S T O N , M A S S A C H U S E T T S O a i O S

    '617! 2 2 7 - 5 5 0 0 Tc i tx 340SIS ADAMS BSN

    April 6, 1978

    Mr. Lawrence L. Landry Vice President for Business & Finance Clark University 950 Main Street Worcester, Massachusetts 01610

    Dear Mr. Landry,

    At its meeting on April 4, 1978 the Massachusetts Health and Educational Facilities Authority gave preliminary approval to an approximately $1,750,000 Clark University Issue, Series B Revenue Bonds.

    The proceeds from the bond issue would be used to finance the co-generation plant for Clark University and related expenses including funding of a debt service reserve fund.

    The preliminary approval of the Authority is based on the condition that the bonds be privately placed with investors acceptable to the Authority. All terms of the bond issue are, of course, subject to final approval of (he Authority.

    Adams, Harkness & Hill, Inc. acting as financial consultants to the Authority has been authorized by Samuel C. Brown, Executive Director to issue this letter.

    Very truly yours,

    Marsom B. Pratt ypnior Vice President

    JUrv^ivnk c.': i\ip.s-(>-'n, "ri'-.xl and Winter

    i i

  • 41-

    T H E COMMONWEALTH OF MASSACHUSETTS

    DEPARTMENT OF THE ATTORNEY GENERAL

    JOHN W. MO OORMAOK STATE O F r i O I BUILDINQ ONE ABHBURTON PLACE. BOSTON 0210B

    rRAN cm x. a tLLom ATTORNEY 1 I N I M L

    October 21, 1977

    Richard W. Merick Merick, O'Connell, DeMallie and Lougee 1700 Mechanics National Tower Worcester, MA 01608 Dear Mr. Merick:

    You have requested the opinion of this office on the legal power of Clark University to engage in the construction and operation of an integrated community energy system (ICES).

    Upon review of your letter and the attached charter and feasibility study it is my conclusion that the primary purposes of the project will advance the charitable purposes of the University. The distribution of excess energy to a public utility would be incidental to the primary purposes, and would not affect the charitable status of the University. Conk1in v. John Howard Industrial Home, 224 Mass., 222 (1916): McKay v. Morgan Memorial Goodwill Industries, 272 Mass. 121 (1930).

    Sincerely,

    MJWR/kah

    (7uln %^-Aj^ Mary Joann Woods Reedy Assistant Attorney General Division of Public Charities

  • -42-

    MlRICK, 0 CONNELL, DEMALLIE 6C LOUGEE COUNSELORS AT LAW

    1700 MECHANICS NATIONAL TOWER

    W O R C E S T E R CENTER

    W O R C E S T E R , M A S S . OiGOS G I 7 7 9 9 - 0 5 4 1

    November A, 1977

    Lawrence L. Landry, Vice President for Business and Finance

    Clark University 950 Main Street Worcester, Massachusetts 01610

    Dear Mr. Landry:

    I suggested to you some time ago that if the University proceded with construction and operation of a grid-connected integrated community energy system, and sold any excess electricity to the local public utility, it might be argued that the University as an eleeymosynary institution did not have the legal power to manufacture and sell electricity.

    I am happy to report that discussion and correspondence with the Division of Public Charities of the Department of the Attorney General of the Commonwealth of Massachusetts has resulted in a response indicating that the project would not affect the charitable status of the University. I am attaching a copy of the letter from Assistant Attorney General Reedy.

    The Division of Public Charities is the agency which represents . the public interest in matters involving the charitable status of eleemosynary institutions. In view of her letter I do not anticipate any questions from any other state or local government source as to the University's legal power to proceed with the project as planned.

    Very truly yours,

    Richard W. Mirick

    RWM/pjb Enc.

  • - 4 3 -

    ^ Massachusetts Bedric

    William J. Cadigan Prttktonl

    February 16, 1978

    Dr. Frank W. Puffer Dean of Academic Affairs Clark University 950 Main Street Worcester, Massachusetts 01610 Dear Dr. Puffer:

    Clark-DOE Demonstration Program of a Grid-Connected Integrated Community Energy (Cogeneration) System

    I Have been advised of your recent meeting with Clark's Board of Trustees concerning the status of the subject program. Apparently, some of the members of the Board are unsure of Massachusetts Electric Company's posi-tion relative to its support of Clark's proposed Cogeneration project. Let me assure you that my Company's position toward this project has not changed since we agreed to become an active participant in your proposed program to DOE back in November of 1976. We have expended much time and effort in the development of the Phase I Report, as well as the soon to be completed Phase II Report; and, offer the same continued effort through the remaining Phases of work toward a successful completion of the demon-stration facility. It is important to note that our parent company, New England Electric System, has committed itself to the national energy conservation program. This has been demonstrated by undertaking various studies to evaluate the long range benefits of energy conservation programs. One such effort is our Solar Water Heating Experiment. This demonstration program was designed to test the suit-ability of solar water heater systems to help meet the energy needs of New England and their possible future integration with utility operations. Co-generation of heat and electricity at an industrial or institutional site offers a great potential for energy conservation through improved overall efficiency.

    However, many economic, technical and institutional factors will impact the future of cogeneration. These factors must be studied and carefully evalu-ated before the cost/benefit ratio of the cogeneration potential can be determined.

    A New England Electric System company

    Massachusetts Electric Company 839 Southbridge Street Worcester, Massachusetts 01610 Tel. (017) 701 -8511

  • -44-

    Dr. Frank W. Puffer, Clark University February 16, 1978

    In order to properly evaluate these factors, it is essential that my Company have some experimental installations in our service area to accumulate valu-able operating information. We have recently completed a survey, designed to assess the potential of cogeneration with a further attempt to identify a class of cogeneration customers. As a member of the Task Force, we have benefited greatly from the input of the other members. We have used this input in our work to develop a policy and cogeneration rate. The information gained in the following phases of work would be most valuable in assessing the cogeneration potential. We are now studying the long range potential economic benefits of the Co-generation capacity. The value of this cogeneration capacity will be greatly affected by its availability, its fuel economics, and the manner in which it is dispatched. The Clark Project will be valuable in terms of the information provided by the operating experience of the facility. We are hopeful that the Clark Cogeneration Demonstration Program will proceed on schedule; and, we continue to support its successful completion.

    Very truly yours,

  • -45 -

    PAUL.REVERE O C O N N E L L G A R D E N E R G. D t M A L L I E L A U R E N C E H. LOUGEE R I C H A R D W. M IR ICK ROBERT J MARTIN BAYARD T D t M A L L I E DAVID L LOUGEE PAUL R. O 'CONNELL . JR. R O B E R T V. DEIANA M I C H A E L J . M ICHAELES

    MIRICK. OCONNELL, DEMALLIE 6C LOUGEE C O U N S E L O R S AT LAW 1700 MECHANICS BANK TOWER

    WORCESTER CENTER

    W O R C E S T E R , M A S S . 016O8 B I 7 7 9 9 - 0 5 4 1

    March 20, 1978

    G E O R G E H. MIR ICK ( I 9 I O - I 9 S 3 )

    J O H N M. R I E D L J O H N O. MIR ICK R I C H A R D G. S M A L L

    Dr. Robert Goble Clark University 950 Main Street Worcester , Massachuse t t s 01610

    . Re: ERDA matter

    Dear Dr. Goble:

    I have reviewed the la tes t draft of the proposed agreement between the University and Massachuset t s Electric Company covering the sa le and purchase of electrici ty by the University to and from the ut i l i ty . Assuming that the sale and purchase rates produce a s a t i s -factory financial result for the University based on your ca lcula t ions , the overall content of the agreement appears to be reasonable .

    I suggest that consideration be given to the inclusion of language which would allow the University to terminate the arrange-ment on reasonable not ice , if a major change should occur In the Universi ty 's c i rcumstances .

    I am sti l l evaluating the question of whether and to what extent the University will be subject to the jurisdiction of the M a s s -achuset ts Department of Public Ut i l i t i es .

    RWM/abm

    Very truly yours ,

    Richard W. Mirick

  • -47-

    AGREEMENT dated as of by and between Clark

    University, a Massachusetts university of higher education, herein-

    after called "Clark", and Massachusetts Electric Company, a Mass-

    achusetts corporation, hereinafter called the "Company".

    ARTICLE I. BASIC UNDERSTANDINGS.

    The Company is currently in the process of formulating a

    Co-generation Policy and Rate for application to customers engaged

    in co-generation projects. The development of an appropriate co-

    generation policy and rate would be materially enhanced by infor-

    mation derived from the on-line experience of a co-generation

    project. Clark intends to construct, a co-generation plant (herein-

    after called the "Plant") with an electrical output which will at

    times exceed Clark's electric energy requirements. Since the

    operation of the Plant will provide the Company with valuable input

    to the development of its Co-generation Policy and Rate, the

    Company is willing, on the terms and conditions hereinafter set

    forth, to purchase all electric energy generated at the Plant in

    excess of Clark's requirements and provide Clark with electric

    service (hereinafter referred to as "Back-up Service"), up to an

    amount hereinafter set forth, whenever Clark's energy requirements

    cannot be fully satisfied by Plant generation.

    In accordance with the above, it is the purpose of this Agreement

    to provide terms and conditions on which Clark will sell and the Company

    will purchase electric energy generated at the Plant in excess of Clark's

    requirements and on wMch the Comapny will provide Back-up Service to Clark.

  • -48-

    Where not inconsistent with this Agreement, the Company's Terms and

    Conditions as on file and in effect from time to time shall apply. A

    copy of the Terms and Conditions in effect and on file with the

    Massachusetts Department of Public Utilities at the date of the execution

    of this Agreement is attached hereto and incorporated herein by reference.

    ARTICLE II. EFFECTIVE DATE AND TERM.

    The term of this Agreement shall commence as of 12:01 A.M. on the

    earlier to occur of (1) the commercial operation date of the Plant, as

    mutually agreed upon by the parties, or (2) sixty days following the date

    on which Clark shall first make delivery of electricity through the

    Interconnection Point, as hereinafter defined, (the "Commencement Date"),

    and shall extend, until terminated by either party giving the other six

    (6) months' written notice specifying the date of termination; provided,

    however, such date of termination shall not be earlier than twenty (20)

    years after the aforesaid Cjcmmencement Date.

    Notwitlistanding the foregoing, however, if at any time during the tenr. of

    this Agreement the Plant fails to operate for a period of more than ninety

    (90) days due to causes beyond Clark's immediate control and Clark deter-

    mines that it will no longer operate the Plant in the future to meet its

    electric energy requirements, then upon thirty (30) days written notice

    to the Company this Agreement shall terminate and Clark shall commence to

    take service from the Company under the Company's then effective Large

    Power Rate as on file with the Department of Public Utilities or such

    other rate as may then be most applicable.

  • -49-

    ARTICLE III. TERMS OF SALE.

    During the term of this Agreement Clark shall:

    (1) -Provide the Company prior to the first day of July

    of each year its best estimate of the generation of

    electricity at the Plant for the twelve (12) months

    next following such July 1st;

    (2) Provide the Company prior to the first day of each

    month its best estimate of the generation of electricity

    at the Plant for such month; and

    (3) Arrange its maintenance program so as to nunimize

    the possibilty of the Plant being out of service

    during the months of January, February, June, July,

    August and December of any calendar year.

    Clark shall sell and the Company shall buy all electricity generated

    at the Plant in excess of Clark's electric energy requirements. Electricity

    shall be delivered to the Company at the interconnection point between the

    Clark and Company systems, located two feet inside Clark's property line

    in the underground feeder off Downing Street in Worcester, Massachusetts

    (the "Interconnection Point"),in the form of three phase sixty-hertz

    alternating current at approximately 13,800 volts. The voltage shall

    not vary more than ten percent (10%) from said voltage momentary

    fluctuations excepted.

    Clark shall operate its electrical generating equipment at the

    Plant in parallel with the Company's system, and at such voltage as the

    Company may reasonably request.

  • -50-

    Whenever Clark's total electric energy requirements cannot be

    met by actual Plant generation, the Company agrees to supply Back-up

    Service in an amount not to excede fifteen hundred kilovolt amperes

    (1500 kVA); provided, however, that upon Clark's written application

    and the Company's written consent, the amount of Back-up Service may

    be increased to an amount not to excede sixteen hundred kilovolt amperes

    (1600 kVA). Such application shall be made not less than three months

    prior to the date on which the Company is requested to supply such

    increased level of Back-up Service. Clark's purchases from the Company

    shall not be at a Power Factor less than eighty percent (80%).

    ARTICLE IV. PRICE AND BTT.LTNG.

    (A) Commencing as of the effective date of this Agreement, the

    Company shall monthly pay Clark for electricity delivered by Clark

    hereunder, as determined in accordance with ARTICLE VT hereof, the

    sum of the following:

    (1) For all electricity delivered during the hours

    from 7:00 A.M. to 11:00 P.M. of each day Monday

    through Friday, excluding legal holidays in the

    Conironwealth of Massachusetts, a price in mills

    per kilowatthour equal to the Company's estimate

    of the incremental cost of fuel for these hours,

  • -51-

    PLUS

    (2) For all electricity delivered during hours other

    than those specified in (JL) above, a price in nulls

    per kilowatthour equal to the Company's estimate

    of the incremental cost of fuel for such other hours.

    For the purpose of (1) and (2) above the Company's incremental

    cost of fuel for the specified hours shall be determined by multiplying

    the average cost of fuel during the preceding month of the Company's

    wholesale supplier, New England Power Company (NEP), determined in

    accordance with NEP's FERC Electric Tariff as on file and as effective

    from time to time, times a multiplier reflecting the estimated relationship

    between NEP's average and incremental cost of fuel for the specified "

    hours during the current year as determined from incremental cost

    studies performed annually by New England Power Service Company, NEP's

    and the Company's service company affiliate. The Company shall make

    available for Clark's inspection records relating to the incremental

    cost studies utilized in determining the above referenced multiplier.

    (B) Commencing as of the effective date of this Agreement, Clark

    shall monthly pay the Company for electricity delivered by the Company

    hereunder, as determined in accordance with ARTICLE VT hereof,

    a price determined , at Clark's option, in accordance with:

  • -52-

    (1) The sum of a Distribution Capacity Charge

    plus an Energy Charge determined as follows:

    During the first year of the term of this

    Agreement, the Distribution Capacity Charge shall be

    one dollar ($1.00) per month per kVA of Distribution

    Capacity contracted for as a maximum service taking.

    During the second, third, fourth, and fifth and

    successive years of the term of this Agreement

    the distribution Capacity Charge shall be respectively,

    one dollar and twenty-five cents ($1.25); one

    dollar and fifty cents ($1.50); one dollar and

    seventy-five cents ($1.75);and two dollars ($2.00)

    per month per kVA of Distribution Capacity contracted

    for as maximum service taking. For the purposes of

    the above, the Distribution Capacity contracted for

    as maximum service taking shall be deemed to be

    fifteen hundred kilovolt amperes (1500 kVA); provided,

    however, that if at any time during the term of this

    Agreement Clark takes electricity from the Company

    at a rate exceeding fifteen hundred kilovolt amperes (1500 kVA)

    then the higher rate of taking sliall thenceforth be

    deemed to be the Distribution Capacity contracted

    for as a maximum service taking.

  • -53-

    The Energy Charge shall be determined in accordance \

    with the Company's General Rate C-22 as on file and in

    effect from time to time; provided, however, that the

    minimum charge provision contained in said rate shall not

    apply.

    If the Back-up Service provided to Clark is metered

    at the Company's supply line voltage, then the Company

    shall, prior to determining the Energy Charge as set forth

    above, deduct one percent (1%) from the meter registrations

    of kilowatthours. In addition, if Clark's highest rate

    of taking of electricity from the Company exceeds fifteen

    hundred kilovolt amperes (1500 kVA), then for the purposes

    of detentdning the Distribution Capacity contracted fcr as

    a maximum service taking for use in calculating the Distribution

    Capacity Charge as set forth above, the Company shall deduct one

    percent (1%) of the amount by which the kilovolt amperes

    meter registrations exceeds fifteen hundred kilovolt amperes.

    OR

    (2) A price determined in accordance with the Company's

    Auxilliary Service Provisions as on file and in effect from

    time to time. For purposes of the above, the Company's

    General Rate C-22, as on file and in effect from time to

    time, shall be the rate under which service is deemed to

    be supplied and contracted for.

  • -54-

    Simultaneously with execution of this Agreement, Clark

    shall specify, by circling the appropriate option on the execution

    page of this Agreement, which of the two pricing options set forth

    above it elects. The selected option shall apply throughout the term of

    this Agreement; provided, however, that if during the term of this

    Agreement the Company files a Co-generation Rate with the Massachusetts

    Department of Public Utilities, and if such rate is allowed to become

    effective, Clark shall have the right at any time thereafter to elect

    to pay a price determined in accordance with said Co-generation Rate

    as on file and in effect from time to time for electricity delivered by

    the Company hereunder. If Clark makes such an election, the Co-generation

    Rate as on file and in effect from time to time shall apply throughout the

    remainder of the term of this Agreement.

    (C) Bills for amounts due under this ARTICLE IV shall be rendered

    monthly to the respective parties and shall be due and payable upon

    receipt thereof. When all or any part of the bill shall remain

    unpaid for more than twenty-five days after the receipt thereof,

    interest at the simple rate of one and one half percent (1 1/2%)

    per month shall accrue from the date of receipt until the date

    of payment on either (1) such unpaid amount or (2) in the event

    the amount of the bill is disputed, the amount finally determined

    to be due and payable. For purposes of this paragraph the date of

    receipt of a bill shall be presumed to be three days following the

    date of mailing, unless the bill is delivered rather than mailed,

    in which case the date of receipt shall be the same as the date of

  • 55

    ARTICLE V. I^m!aO3NNECTI0N RESPONSIBILITIES.