PROJECT MANAGEMENT ● ENGINEERING ● CONTRACTING
Iv-Oil & Gas
www.iv-groep.nl
DEVELOPMENT OF A MARGINAL SATTELITE FIELD
PROJECT MANAGEMENT ● ENGINEERING ● CONTRACTING
INTRODUCTION
Iv-Oil & Gas
www.iv-groep.nl
PROJECT MANAGEMENT ● ENGINEERING ● CONTRACTING
INTRODUCTION
… is investigating the feasibility to utilize a low cost option to develop satellite fields located in the Dutch Sector of the North Sea where the water depth ranging from 20 to 35 meters.
PHILOSOPHY:
• The design shall allow for re-use after field depletion
• Lifecycle cost shall always be considered
• Simple installation/de-installation methodology
• An ergonomic acceptable lay out
• Free water knock out
• Renewable energy
Iv-Oil & Gas
www.iv-groep.nl
PROJECT MANAGEMENT ● ENGINEERING ● CONTRACTING
INTRODUCTIONSTUDY OBJECTIVES
• Define a concept,
• Define a generic topside,
• Estimate topside weight and space requirements,
• Recommend a transport, assembly and installation method,
• Cover implementation aspects of project execution,
• Estimate capital expenditure.
Iv-Oil & Gas
www.iv-groep.nl
PROJECT MANAGEMENT ● ENGINEERING ● CONTRACTING
INTRODUCTIONSTUDY PARAMETERS
• Site data (20 to 35m water depth)
• Base process data (2 producing wells, 1.8 mln m3/d)
• Materials of construction (Duplex stainless steel)
• Utilities (Emergency diesel, solar cells and wind turbines)
• Emergency overnight shelter (4 persons)
• Design and fatigue life (20 years, Fatigue: x5, x10)
• Other (wire line operations, no crane)Iv-Oil & Gas
www.iv-groep.nl
PROJECT MANAGEMENT ● ENGINEERING ● CONTRACTING
SUBSTRUCTURES
Iv-Oil & Gas
www.iv-groep.nl
PROJECT MANAGEMENT ● ENGINEERING ● CONTRACTING
SUBSTRUCTURESINSTALLATION OPTIONS
• Crane barge installed with driven piles
• Installed by jack-up rig or construction barge
• Self installing
SUBSTRUCTURES
• Conventional multi-legged jacket
• Minimal braced tower jacket
• Conductor supported modular structure
• Monotower
• Self installing platformsIv-Oil & Gas
www.iv-groep.nl
PROJECT MANAGEMENT ● ENGINEERING ● CONTRACTING
SUBSTRUCTURESCRANE/BARGE INSTALLED - MULTILEGGED JACKET
Advantages
• Proven concept
• Supports all marginal topsides
• Can support work-over units
Disadvantages
• Requires heavy lift vessel
• Main pile jackets require field welds
• High installation costsIv-Oil & Gas
www.iv-groep.nl
PROJECT MANAGEMENT ● ENGINEERING ● CONTRACTING
SUBSTRUCTURESCRANE/BARGE INSTALLED – MINIMAL BRACED
Advantages
• Low weight
Disadvantages
• Requires heavy lift vessel
• Limited future expansion
• Jack-up rig required for work-over
Iv-Oil & Gas
www.iv-groep.nl
PROJECT MANAGEMENT ● ENGINEERING ● CONTRACTING
SUBSTRUCTURESRIG/BARGE INSTALLED – CONDUCTOR SUPPORTED
Advantages
• Cost effective
Disadvantages
• Topsides limited to 200 tonnes
• Permitting
Not to be pursued
Iv-Oil & Gas
www.iv-groep.nl
PROJECT MANAGEMENT ● ENGINEERING ● CONTRACTING
SUBSTRUCTURESRIG/BARGE INSTALLED – MONOTOWER
Advantages
• Low weight
• Protected conductors and risers
Disadvantages
• Cannot pre-drill wells
• Work-over requires drilling rig
• Limited topside weight
• Sensitive to dynamic motions fatigue additional bracingsIv-Oil & Gas
www.iv-groep.nl
PROJECT MANAGEMENT ● ENGINEERING ● CONTRACTING
SUBSTRUCTURESSELF INSTALLING – SIP I
Advantages
• Transport floating on suction piles
Disadvantages
• Separately installed topsides
Iv-Oil & Gas
www.iv-groep.nl
PROJECT MANAGEMENT ● ENGINEERING ● CONTRACTING
SUBSTRUCTURESSELF INSTALLING – SIP II
Advantages
• No lifting required at location• Docking over pre-drilled wells• Re-usable• Maximized onshore commissioning
Disadvantages
• Too large to be considered marginal• Larger deck width
Iv-Oil & Gas
www.iv-groep.nl
PROJECT MANAGEMENT ● ENGINEERING ● CONTRACTING
SUBSTRUCTURESSELF INSTALLING – SIP III
Advantages
• No heavy lift vessel• Docking over pre-drilled wells• Re-usable• Maximized onshore commissioning
Disadvantages
• Topside weight limited• Temporary frame required on barge
Iv-Oil & Gas
www.iv-groep.nl
PROJECT MANAGEMENT ● ENGINEERING ● CONTRACTING
SUBSTRUCTURESSELF INSTALLING – SIP IV
Advantages
• No heavy lift vessel• Docking over pre-drilled wells• Re-usable• Maximized onshore commissioning
Disadvantages
• Deck and substructure weight too high for a marginal concept
Iv-Oil & Gas
www.iv-groep.nl
PROJECT MANAGEMENT ● ENGINEERING ● CONTRACTING
SUBSTRUCTURESCONCEPT SELECTION
Installable without a heavy lift vessel
• Ability to support a 3-well 400 tonnes topside
• Low weight
• Minimum decommissioning costs
The SIP 3 concept satisfies the criteria of the study and therefore it is selected as the preferred substructure for this study.
Self installable
400 tonnes topside
Pre-drilling Relative weight in
35 m water
Low cost removal
Jacket No Yes Yes High No Braced tower No Yes Yes Low No Conductor sup No No Yes Low No Monotower No Perhaps No 30 m max No SIP 1 Yes No No Low Yes SIP 2 Yes Yes Perhaps High Yes SIP 3 Yes Yes Yes Low Yes SIP 4 Yes Yes Perhaps High Yes
Iv-Oil & Gas
www.iv-groep.nl
PROJECT MANAGEMENT ● ENGINEERING ● CONTRACTING
SIP 3
Iv-Oil & Gas
www.iv-groep.nl
PROJECT MANAGEMENT ● ENGINEERING ● CONTRACTING
SIP 3SIP 3 CONCEPT
• SPT patent
• Barge installed, fully pre-installed and commissioned
Iv-Oil & Gas
www.iv-groep.nl
PROJECT MANAGEMENT ● ENGINEERING ● CONTRACTING
SIP 3SIP 3 SUBSTRUCTURE
• 3.5 m OD mono column, 3 suction piles
• Horizontal mono column orientation for fabrication
• Upending of the mono column from horizontal to vertical
• Vertical (lifted) load out with the suction piles attached
• Installation of topside (substructure at quay / harbour floor)
• Vertical transportation of the total platform
• Suitable transportation barge
• Docking over existing pre-drilled wells
• Future abandonment and re-installationIv-Oil & Gas
www.iv-groep.nl
PROJECT MANAGEMENT ● ENGINEERING ● CONTRACTING
TOPSIDES
Iv-Oil & Gas
www.iv-groep.nl
PROJECT MANAGEMENT ● ENGINEERING ● CONTRACTING
TOPSIDESSIP 3 TOPSIDES
• Main deck
• Intermediate deck
• Top deck (helideck)
PROCESS
• 1.8 mln Nm3/d capacity
• MOC: 900# Duplex
• Free water Knockout (3 phase separation)
• Oil skimmer tank
• Clean water (<30 ppmv oil) overboard
• 10” pipelineIv-Oil & Gas
www.iv-groep.nl
PROJECT MANAGEMENT ● ENGINEERING ● CONTRACTING
TOPSIDESCONTROL, SAFETY AND SHUT DOWN
• Unmanned autonomous operating classification
• Control via fibre optics by means of a DCS extension of the host platform
• Gas detection and intruder alarm
• Rig connected deluge system (dry)
• H60 wall (E/I facilities and refuge)
Iv-Oil & Gas
www.iv-groep.nl
PROJECT MANAGEMENT ● ENGINEERING ● CONTRACTING
TOPSIDESENERGY
• 2400 watt energy consumption (unmanned mode)
• Renewable energy sources (wind turbines and solar)
WEIGHT
• Topsides : 340 tonnes
• Substructure : 860 tonnes
• Total : 1200 tonnes
Iv-Oil & Gas
www.iv-groep.nl
PROJECT MANAGEMENT ● ENGINEERING ● CONTRACTING
FABRICATION, TRANSPORT AND INSTALLATION
Iv-Oil & Gas
www.iv-groep.nl
PROJECT MANAGEMENT ● ENGINEERING ● CONTRACTING
FABRICATION, TRANSPORT AND INSTALLATION
FABRICATION
Fabrication at a facility which has unrestricted access to the North Sea.
• Delivery of mono column (rolled and pre-welded)
• Delivery of suction piles
• Fabrication substructure
• Integration of suction piles with the substructure
• Installation of sacrificial anodes
• Installation of SW pump, J-tube and riser inside columnIv-Oil & Gas
www.iv-groep.nl
PROJECT MANAGEMENT ● ENGINEERING ● CONTRACTING
FABRICATION, TRANSPORT AND INSTALLATION
TRANSPORT AND INSTALLATION
• Marine spread :
• Main tow tug 60-80 TBP• Assisting tug 40 TBP• Barge 300 – 400 ft
• Strand jacks (4 x 600 ton)
• Suction pumps (3 x)
• Hang-off frame (at stern of barge)
• Mooring winches (4 x allows for accurate manoeuvring)
• ROV spread (seabed survey and wellhead inspection)
• Survey & positioning spread (platform position monitoring)
Iv-Oil & Gas
www.iv-groep.nl
PROJECT MANAGEMENT ● ENGINEERING ● CONTRACTING
FABRICATION, TRANSPORT AND INSTALLATION
INSTALLATION OPTIONS
• Topside pre-installed at top of column, transport with barge SIP3, offshore lowered with strand jacks (1x jacking),
• Topside pre-installed at lower section of column, transport with barge SIP3, substructure lowered offshore using strand jacks, deck lifted with strand jacks (2x jacking),
• Topside installed at top of column, transport on barge, offshore single lift HLV/SSCV (1x lifting),
• Topside on barge, substructure on barge, offshore installation deck with sheerleg/HLV/SSCV (2x lifting),
• Transport topside on barge, substructure in hooks sheerleg (1x lowering, 1x lifting).Iv-Oil & Gas
www.iv-groep.nl
PROJECT MANAGEMENT ● ENGINEERING ● CONTRACTING
FABRICATION, TRANSPORT AND INSTALLATION
INSTALLATION
The installation of the platform consists of the following phases:
• Preparation phase
• Barge mooring
• Platform lowering
• Foundation installation
• Completion activities
Iv-Oil & Gas
www.iv-groep.nl
PROJECT MANAGEMENT ● ENGINEERING ● CONTRACTING
FABRICATION, TRANSPORT AND INSTALLATION
INSTALLATION
• Sea fastening of substructure to the barge using hydraulic pins for swift release of the substructure from the barge after mooring,
• Tow to the field using tugs,
• Transport positive range of stability more than 50 degrees (criterion > 36 degrees),
• Lowering stability (hydrostatic and hydrodynamic) provided by ballast on the suction piles,
• Lowering and lifting systems using strand jacks,
• Suction pumps for the installation and future removal of the suction pile foundation,
• No divers required for installation and removal of installation equipment.
Iv-Oil & Gas
www.iv-groep.nl
PROJECT MANAGEMENT ● ENGINEERING ● CONTRACTING
SCHEDULE
Iv-Oil & Gas
www.iv-groep.nl
PROJECT MANAGEMENT ● ENGINEERING ● CONTRACTING
SCHEDULEDEFINITION OF PROJECT PHASES
• Conceptual design
• Detail design
• Procurement
• Construction
• Onshore test/commissioning
• Transportation and installation
Iv-Oil & Gas
www.iv-groep.nl
PROJECT MANAGEMENT ● ENGINEERING ● CONTRACTING
SCHEDULECONCEPT PLANNING
Iv-Oil & Gas
www.iv-groep.nl
PROJECT MANAGEMENT ● ENGINEERING ● CONTRACTING
COST ESTIMATE
Iv-Oil & Gas
www.iv-groep.nl
PROJECT MANAGEMENT ● ENGINEERING ● CONTRACTING
COST ESTIMATEOVERVIEW
Iv-Oil & Gas
www.iv-groep.nl
Description FoB Fabrication Other Total
costs costs
(€·103) (€·103) (€·103) (€·103)
Substructure --- --- ---
Topsides structual steel --- --- ---
Helideck --- --- ---
Equipment (incl commisioning) --- --- --- ---
Design & Procurement --- ---
Fabrication and installation --- ---
Insurance --- ---
Certification --- ---
Overall contingency ~15% --- ---
Grand Total --- --- --- ---
PROJECT MANAGEMENT ● ENGINEERING ● CONTRACTING
END OF PRESENTATION
QUESTIONS?