Mega Bridges Using Precast Technology SKD

  • Upload
    pvrk78

  • View
    227

  • Download
    0

Embed Size (px)

Citation preview

  • 7/28/2019 Mega Bridges Using Precast Technology SKD

    1/47

    Hindustan Construction Co Ltd

  • 7/28/2019 Mega Bridges Using Precast Technology SKD

    2/47

    Construction of

    Mega Bridges using Precast

    Segmental Methodology

    Mr S.K.DharmadhikariGroup Technical OfficerHCC Group of Companies

    December 14, 2012

  • 7/28/2019 Mega Bridges Using Precast Technology SKD

    3/47

    Mega Bridges

    Current Scenario

  • 7/28/2019 Mega Bridges Using Precast Technology SKD

    4/47

    Mega Bridges by nature have significant

    Design & Construction Challenges

    December 14, 20124 Precast Segmental Construction in Mega Bridges

  • 7/28/2019 Mega Bridges Using Precast Technology SKD

    5/47

    Mega Bridges by nature have significant

    Design & Construction Challenges

    December 14, 20125 Precast Segmental Construction in Mega Bridges

  • 7/28/2019 Mega Bridges Using Precast Technology SKD

    6/47

    Mega Bridges by nature have significant

    Design & Construction Challenges

    December 14, 20126 Precast Segmental Construction in Mega Bridges

  • 7/28/2019 Mega Bridges Using Precast Technology SKD

    7/47

    December 14, 2012 Precast Segmental Construction in Mega Bridges7

    Mega Bridges by nature have significant

    Design & Construction Challenges

  • 7/28/2019 Mega Bridges Using Precast Technology SKD

    8/47

    Requirements of Mega Bridge Projects

    Constructability Faster Construction Ease & flexibility inConstruction Cutting Edge Technologies Value Engineering Specialised skills & resources

    AestheticsMost Mega Bridges are Signature structuresThe Bridges dominate the local landscapeThe layout to be in harmony with Environment Innovative Design

    DurabilityHigh Construction Investments.High Quality & High precision Low maintenance costShould be strong & durable during its life

    time.SecurityHigh value projects - potential terrortargetsDesign to mitigate the security risks

    December 14, 20128 Precast Segmental Construction in Mega Bridges

  • 7/28/2019 Mega Bridges Using Precast Technology SKD

    9/47

    Precast Segmental construction provides solutions

    to these challenges and exceeds Project Requirements

    December 14, 20129 Precast Segmental Construction in Mega Bridges

  • 7/28/2019 Mega Bridges Using Precast Technology SKD

    10/47

    Precast Segmental Bridges are highly durable

    structures for a number of reasons

    Superstructure is Post-tensioned in both the Transverse and Longitudinal directions, placing

    the bridge deck in compression at all times

    This eliminates the possibility of cracking of the bridge deck and intrusion of corrosive agentsthat would damage the mild steel reinforcement and the post-tensioning in the deck

    These factors combined with low-maintenance detailing of the bearings and expansion joints

    enable the structure to easily achieve its design life with minimal maintenance by the owner

    When building over water, efficiency is achieved through the simplification of operation.

    Allows off-site casting that removes complicated casting procedures and unpredictableweather from the critical path.

    Once the segments are cast, they can easily be barged to the erection site, lifted onto theerection truss using a barge-mounted crane, and assembled

    December 14, 201210 Precast Segmental Construction in Mega Bridges

  • 7/28/2019 Mega Bridges Using Precast Technology SKD

    11/47

    This is the most suitable method for Long Span

    Bridges across River / Sea / Creeks

    ReducesIntermediatePiers & thusObstructions

    to flow

    Avoidsystem of

    staging fromriver bed

    level

    Faster &economical

    technique asit saves

    time.

    December 14, 201211 Precast Segmental Construction in Mega Bridges

  • 7/28/2019 Mega Bridges Using Precast Technology SKD

    12/47

    Construction Planning has to be Meticulous and needs

    lot of Care

    Delicate process and needs fine balance.

    Careful and Systematic Approach needed for

    Segment Casting as any Imbalance can causesevere damages

    Proper Sequencing of Key ConstructionOperations should be clearly established.

    December 14, 201212 Precast Segmental Construction in Mega Bridges

  • 7/28/2019 Mega Bridges Using Precast Technology SKD

    13/47

    HCC A brief profile

  • 7/28/2019 Mega Bridges Using Precast Technology SKD

    14/47

    Business Lines

    Hydro

    Dams & Barrages

    Tunnels

    Powerhouses

    Shafts & Penstocks

    Water Solution

    Storage Dams

    Barrages

    Bulk watertransmission canals

    Tunnels

    Pipelines

    Pumping Stations

    Treatment Plants

    Transportation

    Roads

    Bridges

    Tunnels

    MRTS

    Nuclear &

    Special Projects

    Nuclear Power

    Plants

    Ports

    UndergroundCaverns

    Utility buildings &

    industrial structures

    EPC

    Lump sum turnkey

    EPC

    Design Build

    Engineering Center

    December 14, 201214 Precast Segmental Construction in Mega Bridges

  • 7/28/2019 Mega Bridges Using Precast Technology SKD

    15/47

    Our track record in Bridge Construction

    Experience Expertise Diverse Capability Precast Segmentaltechniques

    Cable stayed /conventional bridges Pile / Well foundations River / Land bridges PSC / RCC / Steel /Composite bridges

    Design & Construction Complex projects involving

    difficult logistics Speedy construction Construction in urbanenvironment

    More than 5 decades 300 bridges

    34 bridges in Iraq 43 bridges in Nepal Over 50 km of bridge length

    Indias leading

    Mega BridgeConstructor

    December 14, 201215 Precast Segmental Construction in Mega Bridges

  • 7/28/2019 Mega Bridges Using Precast Technology SKD

    16/47

    Signature Bridges Built by HCC

    Mokameh

    Bridge [1959]

    Indias first road cum

    rail bridge

    Length - 1854 M

    Godavari Rail

    Bridge

    Indias first and only

    bow string arch

    bridge

    Length 2745 M

    Kaliabhomora

    Road Bridge

    3 km long bridgeover majestic river

    Brahmaputra, one of

    the largest river in

    Asia

    Varanasi Bridge

    Prestressed

    Concrete Road

    bridge across River

    ganga

    Length 1296.5 M

    Cable Stayed

    Bridge across

    Naini,

    Allahabad, UP

    Length 1510 M

    Badarpur

    Elevated Road

    Large scale elevatedhighway project built

    in congested urban

    environment

    Length 4.4 Km

    December 14, 201216 Precast Segmental Construction in Mega Bridges

  • 7/28/2019 Mega Bridges Using Precast Technology SKD

    17/47

    Construction of Mega Bridges withPrecast Segmental Construction

    HCCs experience

  • 7/28/2019 Mega Bridges Using Precast Technology SKD

    18/47

    Bandra Worli SealinkIndias Engineering marvel

    First bridge in India built on open sea

    Developed completely by Indian Engineers

    One of the most complex andadvanced

    construction projects ever to havebeen

    undertaken in India.

    December 14, 201218 Precast Segmental Construction in Mega Bridges

  • 7/28/2019 Mega Bridges Using Precast Technology SKD

    19/47

    Purpose

    Existing Route

    New Route

    To connect 2 suburbs ofMumbai Worli & Bandra

    Reduction in travel timebetween the two suburbs

    Reduction in traffic congestion

    December 14, 201219 Precast Segmental Construction in Mega Bridges

  • 7/28/2019 Mega Bridges Using Precast Technology SKD

    20/47

    Situation before Sealink :

    Distance from Lovegrove Jn toMahim Junction = 7.7 km

    Traffic Signals = 23 Nos

    Travel time:

    Morning peak hour = 35 min

    Evening peak hour = 38 min

    Average Journey Speed = 13 kmph

    Savings due to Sea Link

    Direct Cost savings = Rs 14.11 per car

    (fuel, tyre,wear & tear, lubricants,etc)

    Travel time savings = 29 min per car

    Time value @ Rs 100/ hr = Rs 48.43 / car

    Hence, total savings = Rs 62.59 / car

    Benefits

    December 14, 201220 Precast Segmental Construction in Mega Bridges

  • 7/28/2019 Mega Bridges Using Precast Technology SKD

    21/47

    Fuel savings worth Rs. 100 Crs per Annum

    Savings in travel time up to 20 - 30 minutes

    Reduction in Air, Noise & Sound Pollution

    Reduction of Nox by 43% & CO by more than 75%

    No adverse effect on Tides, Fisheries and livelihood ofFishermen

    Ease in driving with reduced mental tension and overallimprovement in the quality of life

    Reduced Accidents

    Proper Landscaping Measures along the Approaches andPromenade along Waterfront to enhance Environment of theArea

    Other Socio Economic Benefits

    December 14, 201221 Precast Segmental Construction in Mega Bridges

  • 7/28/2019 Mega Bridges Using Precast Technology SKD

    22/47

    Project Overview

    The entire project was originally conceived as one large

    project comprising, different components

    In order to accelerate the overall construction schedule, the

    project has been divided into five construction packages.

    Package I: Construction of flyover over Love Grove junction at

    Worli

    Packag e II: Construction of cloverleaf interchange at Mahim

    intersection

    Pack age III: Construction of solid approach road from the

    Mahim intersection up to the start

    of the Toll Plaza on the Bandra side and a public promenade

    Packag e IV: Construction of Cable-Stayed Bridges togetherwith viaduct approaches extending from Worli up to the Toll

    Plaza at Bandra end, Intelligent Bridge System (IBS).

    Package V: Improvement to Khan Abdul Gaffar Khan Road

    HCC built Package IV, which is the

    largest phase of Bandra - Worli

    Sea Link.

    December 14, 201222 Precast Segmental Construction in Mega Bridges

  • 7/28/2019 Mega Bridges Using Precast Technology SKD

    23/47

    MAHIM BAY

    APPROACH ROAD& TOLL PLAZA

    BANDRAAPPROACH

    600 m BANDRACABLE STAYED

    350M WORLICABLE STAYED

    WORLI APPROACH

    KAGK LINKBRIDGE

    WORLI

    BANDRA

    LAYOUT OF BANDRA WORLI SEALINK PROJECT

    December 14, 201223 Precast Segmental Construction in Mega Bridges

  • 7/28/2019 Mega Bridges Using Precast Technology SKD

    24/47

    Salient Features of the Project

    An 8-lane bridge with 2 lanes dedicated for buses.

    Unique bridge design for the Link Bridge

    Single tower supported 500 meters long Cable Stayed Bridge at Bandra

    Channel and Twin tower supported 350m Cable Stayed Bridge at Worli

    Channel for each carriageway.

    Modern toll plaza of 16 lanes with automated toll collection system.

    An intelligent bridge with state - of - art systems for traffic monitoring,surveillance, information and guidance, instrumentation, emergency support

    Development of promenade and landscaping to enhance the environment.

    December 14, 201224 Precast Segmental Construction in Mega Bridges

  • 7/28/2019 Mega Bridges Using Precast Technology SKD

    25/47

    Project Implementation Entities

    Project Owner : Maharashtra State Road Development Corporation

    Main Contractor : Hindustan Construction Co. Ltd [HCC]

    Design Consultants : Sverdrup Asia Ltd. (India)Stup Consultants India Pvt. LtdDar Consultants UK in JV with Dar Consultants India

    Proof Consultants : Construma ConsultancyMott Mc DonaldSchlaich BergermanTY Lin International

    Consultants to Main Contractor : VSL, Singapore

    December 14, 201225 Precast Segmental Construction in Mega Bridges

  • 7/28/2019 Mega Bridges Using Precast Technology SKD

    26/47

    Scope of Work in Package IV executed by HCC

    449m long embankment with 20m wide promenades for 16-lane toll plaza

    800m long Precast Segmental Approach Bridge on Bandra side

    600m long Cable Stayed Bridge with 125m high Towers including transition spans

    200m long Precast Segmental Approach Bridge between Bandra & Worli Cable

    Stayed Bridge

    350m long Cable Stayed Bridge on Worli Side with Pylons including transition spans

    1400m long Precast Segmental Approach Bridge on Worli Side

    811 m long link bridge to KAGK road comprising 510m Precast Segmental Bridge and301m Cast-in-Situ Bridge

    Setting up Traffic Monitoring, Surveillance, Information & Control Systems, Drainage, Street

    Lighting, Signage Marking, Landscaping & Arboriculture

    December 14, 201226 Precast Segmental Construction in Mega Bridges

    P t Y d

  • 7/28/2019 Mega Bridges Using Precast Technology SKD

    27/47

    Precast Yard

    Located on Reclaimed Land

    Total storage requirement 2342 Nos Original storage 470 Nos Precast Segments.

    As the area available is limited, the segments are to be stored in stacks of threelayers.

    The bearing capacity of existing ground was very poor and found to be less than2 T/Sqm.

    Limitation to storage capacity requirement of 2342 nos.

    Detailed Ground Stabilization was done to improve Bearing Capacityof Soil

    Excavation of the ground to a depth of ~ 2.5Mtrs.

    Strengthening the ground using rubble soling and filling the voids with sand The soling thus done was compacted layer by layer using vibratory rollers

    Total area of the Pre-cast Yard was covered with a layer of PCC

    RCC Footing done to facilitate storing of segments

    December 14, 201227 Precast Segmental Construction in Mega Bridges

  • 7/28/2019 Mega Bridges Using Precast Technology SKD

    28/47

    Precast Yard

    December 14, 201228 Precast Segmental Construction in Mega Bridges

  • 7/28/2019 Mega Bridges Using Precast Technology SKD

    29/47

    December 14, 201229 Precast Segmental Construction in Mega Bridges

  • 7/28/2019 Mega Bridges Using Precast Technology SKD

    30/47

    Super Structure Construction

    Precast Segmental Construction for

    the Prestressed girder :

    Superstructure construction in thisproject is very complex due tofollowing reasons :

    Construction across deep sea.

    The deck girder in this project is one

    amongst the heaviest.

    Deck girder cross section - Triple cell

    precast box girder

    Girder

    width

    M

    No. of

    spans

    Span

    lengths

    MBandra

    Approach

    Bridge

    18.10 17 50

    Cable stayed

    bridge 1

    22.70 1 500

    2nd approach

    bridge

    18.10 4 50

    Worli cable

    stayed bridge

    22.70 1 250

    Worli

    approach

    bridge

    18.10 28 50

    December 14, 201230 Precast Segmental Construction in Mega Bridges

  • 7/28/2019 Mega Bridges Using Precast Technology SKD

    31/47

    Segment ProductionCasting Yard

    December 14, 201231 Precast Segmental Construction in Mega Bridges

  • 7/28/2019 Mega Bridges Using Precast Technology SKD

    32/47

    Segment casting activities

    Method: - Short line match castMajor activities involved in the casting ofsegments

    Rebar cage tying.

    Alignment of cell.

    Concreting

    TPT stressing

    Lifting & Storage

    December 14, 201232 Precast Segmental Construction in Mega Bridges

  • 7/28/2019 Mega Bridges Using Precast Technology SKD

    33/47

    Rebar Cage tying in the Jig

    December 14, 201233 Precast Segmental Construction in Mega Bridges

  • 7/28/2019 Mega Bridges Using Precast Technology SKD

    34/47

    Rebar cage lifting from the Jig

    December 14, 201234 Precast Segmental Construction in Mega Bridges

    Lif i f R b

  • 7/28/2019 Mega Bridges Using Precast Technology SKD

    35/47

    Lifting of Rebar cage

    December 14, 201235 Precast Segmental Construction in Mega Bridges

  • 7/28/2019 Mega Bridges Using Precast Technology SKD

    36/47

    Rebar cage Lowering in the Cell

    December 14, 201236 Precast Segmental Construction in Mega Bridges

  • 7/28/2019 Mega Bridges Using Precast Technology SKD

    37/47

    Concreting Pour Sequence

    CONCRETE PLACING SEQUENCE

    1

    5.33M

    22a

    3.17M 3.17M

    3a 3

    1.26M 1.26M

    44a

    1.66M1.66M

    5a 5

    1.26M 1.26M

    66a

    1.66M1.66M

    7a 7

    4.39M 2.52M

    8a 8

    2.69M 2.69M

    9a 9

    2.19M 2.19M

    10

    4.28M

    TOTAL CONCRETE QUANTITY = 44.30 CUM

    December 14, 201237 Precast Segmental Construction in Mega Bridges

  • 7/28/2019 Mega Bridges Using Precast Technology SKD

    38/47

    Match casting

    December 14, 201238 Precast Segmental Construction in Mega Bridges

  • 7/28/2019 Mega Bridges Using Precast Technology SKD

    39/47

    SITE PHOTOGRAPH SEGMENT LIFTING

    December 14, 201239 Precast Segmental Construction in Mega Bridges

  • 7/28/2019 Mega Bridges Using Precast Technology SKD

    40/47

    SEGMENT : TRANSPORTATION

    December 14, 201240 Precast Segmental Construction in Mega Bridges

  • 7/28/2019 Mega Bridges Using Precast Technology SKD

    41/47

    LAUNCHING TRUSS

    December 14, 201241 Precast Segmental Construction in Mega Bridges

  • 7/28/2019 Mega Bridges Using Precast Technology SKD

    42/47

    December 14, 201242 Precast Segmental Construction in Mega Bridges

  • 7/28/2019 Mega Bridges Using Precast Technology SKD

    43/47

    December 14, 201243 Precast Segmental Construction in Mega Bridges

    Relocation of Launching Trusses using 1600 MT

  • 7/28/2019 Mega Bridges Using Precast Technology SKD

    44/47

    Relocation of Launching Trusses using 1600 MT

    capacity Barge Mounted Crane Asian Hercules

    Various options examined :

    1. Dismantling of the trusses at present locations & reassembling them at new locations

    2. Lowering the trusses on a suitable floating craft & shift erect them.

    3. Shifting the total truss using a floating crane.

    Factors considered to decide on solution :

    i. Limited working period available to executed the work in sea,

    ii. Effect of open sea on dismantling & re-erection, etc

    iii. Relocation of the trusses in one piece using a floating crane was selected as the best

    option.

    December 14, 201244 Precast Segmental Construction in Mega Bridges

    Relocation of Launching Trusses using 1600 MT

  • 7/28/2019 Mega Bridges Using Precast Technology SKD

    45/47

    g gcapacity Barge Mounted Crane Asian Hercules

    December 14, 201245 Precast Segmental Construction in Mega Bridges

  • 7/28/2019 Mega Bridges Using Precast Technology SKD

    46/47

    Project Implementation is a collective responsibility

    Owner

    Developer

    Consultant

    RegulatoryEntities

    Contractors

    Vendors

    Value Engineering

    Meticulous planning

    ModernConstructionManagementTechniques

    Cutting EdgeTechnologies

    Risk Management

    World ClassProjectManagementpractices

    December 14, 201246 Precast Segmental Construction in Mega Bridges

  • 7/28/2019 Mega Bridges Using Precast Technology SKD

    47/47

    December 14, 201247 Precast Segmental Construction in Mega Bridges