Upload
wee-chek
View
528
Download
25
Embed Size (px)
Citation preview
7/25/2019 Method Statement of PDA test for bored pile
1/12
METHOD OF STATEMENT FOR PDA TESTING ON BORED PILE / MICRO PILE
DYNAMIC TESTING SERVICES (SINGAPORE)
METHOD OF STATEMENT
FOR PDA TESTING
ON BORED PILE / MICRO PIL
7/25/2019 Method Statement of PDA test for bored pile
2/12
Method of Statement for PDA Testing on Bored Pile / Micro Pile (Contd)
METHOD OF STATEMENT
FOR PDA TESTING ON BORED PILES / MICRO
1.0 INTRODUCTION
1.1 Dynamic Testing Service (Singapore) Pte Ltd (DTS) pr
specialist dynamic pile testing service. DTS own and opera
PDA/CAPWAP system of testing, which involves state-of-equipment and computer software. This system has been us
DTS for testing of piles in Australia, Singapore, Malaysia,
Kong and Thailand. DTS is an accredited laboratory by SAC-S
for PDA test.
1.2 The PDA field data acquisition and computer unit has its own i
self checking system and all force and acceleration transduce
fully calibrated in advance.
1.3 The PDA/CAPWAP system was developed by Pile Dynami
Ohio, USA and has been in use for more than 15 years. Details
system are attached in Appendix 1.
2.0 PILE MONITORING AND PREPARATION
2.1 Pile instrumentation and monitoring will be performed usi
PDA/CAPWAP system according to the ASTM standard D494
The system involves a Pile Driving Analyser (PDA), wh
manufactured by Pile Dynamic Incorporated, USA. Measurem
the force and velocity signal induced in the pile during pile d
are collected by strain and accelerometer transducers, which ar
near the pile head (at least 1.5 diameter away from pile top). Fo
blow struck to the pile the PDA signal processor conditio
output from these transducers and passes it to the processing sof the PDA. The PDA has an in-built program, which calculate
30 pile driving variables based on the data obtained from each
These variables include maximum pile top force, displaceme
velocity, estimates of pile static and dynamic capacity.
2 2 In order to conduct PDA testing transducers need to be attac
7/25/2019 Method Statement of PDA test for bored pile
3/12
Method of Statement for PDA Testing on Bored Pile / Micro Pile (Contd)
i. Build up section of pile should have higher strength co
preferably grade 40 or above. Minimum strength of co
before testing should be 30N/mm2or more.
ii. Bored pile to be tested to be encased with steel casing
top section (1m 2m from pile top) of pile in or
strengthen the concrete pile for hammer impact.
iii. Drop height of hammer proposed to be carefully calc
using dynamic Hiley formula by specialist testing prevent overstress during testing.
iv. Hammer to be aligned vertically to prevent eccentric
developed at hammer impact. Hammer guide is recomm
be used.
v. Proposed drop height will have to be ad
(revised/increased) on site if stress measured during tes
too high/low after first hammer blow. Note that desired
capacity may not be achieved if energy imparted onto
insufficient.
2.3 The PDA monitoring equipment will be set up in the veh
shaded protected area at certain distance from the pile. A main
connecting the PDA unit to the pile top transducers will be ru
the unit to the gauges.
2.4 The piles are recommended to be tested to 2 times working lo
working pile. This is to prevent any overstress in the pile hammer impact. The ultimate static capacity should be higher
times working load. The soil skin friction set-up effect may be
into consideration in the long term and therefore pile capaci
increase with time.
3.0 DATA PROCESSING AND CAPWAP ANALYSIS
3.1 Under each hammer blow, the analyser will be triggered an
acquisition will begin at this time. The PDA automatically pro
each blow recorded during monitoring and can display com
values of over 30 pile variables on command.
3.2 The PDA automatically checks each blow for pile integri
provides a warning of any damage detected along the length
7/25/2019 Method Statement of PDA test for bored pile
4/12
Method of Statement for PDA Testing on Bored Pile / Micro Pile (Contd)
3.4 After the completion of the CAPWAP analysis the PDA
estimates of static capacity can be refined and analyser data
calibrated to the CAPWAP analysis. This will effectively refi
real time PDA estimates of static capacity, which will be availa
subsequent piles monitored. CAPWAP will also give you th
friction distribution and end bearing resistance of pile and pre
load settlement curve under static loading.
3.5 The PDA and subsequent CAPWAP analysis will indica
amount of static capacity that is actually mobilized during an
blow delivered to the pile during testing. In order to fully mobi
available pile static capacity a pile set in excess of 3 4 mm pe
is required. Should the pile set be less than 3 4 mm, or th
quakes be in excess of the normal 3 4 mm then not all of the
pile resistance will be mobilized during any one blow a
subsequent CAPWAP and PDA analysis will under predict
static capacity of the pile.
This provides some in-built conservatism to the capacities ind
by the PDA and CAPWAP system in the event of small set
recorded. If this is the case the PDA system is regarded as a
test, not a full load test.
4.0 REPORTING
4.1 On completion of all field work, a final report covering all asp
the pile monitoring and analysis work will be prepared. This
will incorporate results of the PDA monitoring, and results
CAPWAP computer analyses. The results of the CAPWAP an
will be compared to the PDA results and correlations will be
between the CAPWAP data and the PDA field monitoring r
Results from PDA test will be calibrated against the static loresults if results are available, to obtain a better correlatio
comparison with the static.
4.2 Results which can be obtained in report are as follows:-
4 2 1 Static capacity of piles (compression or tension) mobilized
7/25/2019 Method Statement of PDA test for bored pile
5/12
Method of Statement for PDA Testing on Bored Pile / Micro Pile (Contd)
5.0 COMPANY EXPERIENCE
5.1 Dynamic Testing Service (Singapore) Pte Ltd has been in op
in Singapore since early 1990 providing dynamic pile testing se
to the local construction industry. More than 500 over pile
piles, Steel Pipe piles and Bored piles) are dynamically teste
year as a supplement or substitute method of test to conven
static load test.
6.0 RECOGNITION OF PDA TEST
PDA test is well recognized in the following international standards:-
- ASTM (American Standard of Testing Materials) standard D4945-
- ICE Piling Specifications (UK)
- BS8004 (British Standard Foundation code 7.5.2)
- Canadian Foundation Engineering Manual (1992 Canadian GSociety).
=============================================================
7/25/2019 Method Statement of PDA test for bored pile
6/12
Method of Statement for PDA Testing on Bored Pile / Micro Pile (Contd)
APPENDIX 1
(PDA SYSTEM)
7/25/2019 Method Statement of PDA test for bored pile
7/12
1.5 dia
2.0m
G.L
Hammer
Steel guide
casing
Lift and drop by craneusing free fall
Built up section
with casing at 1 -
2 dia from pile top
to protect pile
from hammer
impact Gages installed by te
engineers
Windows of
to be cut
200(H)x200(
Bored pile
to be tested
Cushion
plywood
Rebar of
bored pile
Top of Pil
7/25/2019 Method Statement of PDA test for bored pile
8/12
Dynamic Testing Services (S) Pte Ltd
EXAMPLE OF DROP HEIGHT FOR PDA TEST ON PILES:
Project Name :
Client :
HILEY FORMULA FOR BORED PILE Pile reference : P199Dia. of pile (mm) 900 Test load 2.0 x WL (tons)
Dia. of rebar (mm) Length, L (mm)
No. of rebar (mm) EM of steel, E (t/cm2)
Set (mm) 1 EM of grout (t/cm2)
Efficiency (%) 0.35 SP of steel (t/m3)
Hammer weight (tons) 8.5 SP of concrete (t/m3)
Working load (tons) 390.0
Area of steel, A Area of concrete Area (Total)
(cm2) (cm
2) (cm
2)
0.0 6361.7 6361.7
Tc Wave Speed, c Drop Height
(mm) (m/s) (mm)
8.3 3800 1345.9
Proposed drop height = 1.4 m
Notes : -
Hiley formula : Ru = Energy /(set + Tc/2)
This formula obtained from simplified Hiley formula published by Prof.Bengt B Bromes
Energy = efficiency x drop height x weight hammer
Set = assumed permanent displacement (usually about 1 - 2mm/blow)
Temporary compression, Tc = can be calculated from P L / A E x k, where k = 1 (m
For bored pile test we ignore area of steel. EM of concrete = 353 - 400 t/cm2
Wave speed of concrete = 3800m/s (may varies from 3600 ~ 4600m/s,calculate from EM = SP x
Where, EM = Elastic Modulus , SP = Specific Density
Assume a certain efficiency o
Hammer weight
Drop Height
7/25/2019 Method Statement of PDA test for bored pile
9/12
7/25/2019 Method Statement of PDA test for bored pile
10/12
7/25/2019 Method Statement of PDA test for bored pile
11/12
7/25/2019 Method Statement of PDA test for bored pile
12/12